KHUSHI RAM BHARDWAJD.A.V.I.E.T(JALANDHAR)
JUNE 2011
KAPSONS INDUSTRIES LTD.
![Page 2: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/2.jpg)
Established in 1981
ESTABLISHED AS KRISHNA LAMINATIONS PRIVATE LTD. JALANDHAR
![Page 3: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/3.jpg)
KAPSONS TODAY
KAPSONS INDUSTRIES TODAY SPREADING IN 4 MAJOR PLANTS IN JALANDHAR AND PUNE.
![Page 4: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/4.jpg)
Quality
ISO 16949:2000, ISO 14001:1996, is/ISO 9001:2000, ISO 9001-2000 certified.
![Page 5: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/5.jpg)
Infrastructure
Covered Area-:: Unit I 62,568 Sq. Ft. Unit-II & III 72732 Sq. Ft. Unit IV 85000 Sq Ft(pune)
![Page 6: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/6.jpg)
Safety and Attendance
Safety Data2010
– Total Hours Worked 4018 hours– Minor First-Aid Cases
27– Cases Days Away
3
2011 YTD 5th june – Total Hours Worked 1668– Minor First-Aid Cases
13– Cases Days Away
0
ATT/TO Data2010
– Absenteeism Rate 0.04%
2011- YTD 5th june– Absenteeism Rate
0.016%
![Page 7: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/7.jpg)
Annual turnover
2007 rs. 350 crore 2008 rs. 395 crore 2009 rs. 432 crore 2010 rs. 500 crore
![Page 8: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/8.jpg)
Equipment List
Presses (1) Gauging Machine
(2) Sorting Machine
(3) Lapping Machine
(4) Roll Forming Machine
(5) Steel Ball Plant
(5) Wire Forming Machine
(6) Double Disk Grinding Machine
(7) Blade Grinding Machine
(8) Rough Grinding Machine
(9) Surface Grinding Machine
![Page 9: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/9.jpg)
Gauging & Sorting Machine
![Page 10: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/10.jpg)
Lapping Machine
![Page 11: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/11.jpg)
Rolling machine
![Page 12: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/12.jpg)
Products and services
![Page 13: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/13.jpg)
Clientele
M/S. Asea Brown Boveri Ltd. Faridabad.
M/S. Bharat Bijlee Ltd. , Thane. M/S. Alstom Ltd. (AEI Works),
Calcutta. M/S. Crompton Greaves Ltd M/S.
Alstom Ltd. (Paharpur Works), Calcutta.
![Page 14: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/14.jpg)
GENERATORS MAINTENANCE
![Page 15: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/15.jpg)
Typical Generator Maintenance
![Page 16: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/16.jpg)
![Page 17: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/17.jpg)
Generators
![Page 18: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/18.jpg)
![Page 19: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/19.jpg)
System controls
![Page 20: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/20.jpg)
![Page 21: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/21.jpg)
![Page 22: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/22.jpg)
![Page 23: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/23.jpg)
![Page 24: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/24.jpg)
![Page 25: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/25.jpg)
![Page 26: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/26.jpg)
![Page 27: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/27.jpg)
![Page 28: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/28.jpg)
![Page 29: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/29.jpg)
![Page 30: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/30.jpg)
![Page 31: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/31.jpg)
![Page 32: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/32.jpg)
![Page 33: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/33.jpg)
REASONS WHY GENERATORS FAIL
FOREIGN OBJECT DAMAGE Problem: Objects can come from
external sources or failure of internal components,
they can pick up energy from the spinning rotor and do
extensive damage Prevention: Inspect on a regular
basis all internal parts that are prone to failure or can be
dislodged. Inspection tests can be a
combination of visual inspection along with ultrasonic
or magnetic particle tests on rotating components
![Page 34: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/34.jpg)
STATOR WINDING VIBRATION
Problem: Primarily a design related problem that
affects large (>300Mw) generators which have
insufficient end winding bracing to limit the
movement of end turns. Prevention: Proper bracing of
the end winding is required to limit motion caused
by steady state and transient electromagnetic forces.
![Page 35: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/35.jpg)
ROTOR WINDING DISTORTION
Problem: Rotor winding distortion caused by poor end
turn blocking support design or by foreshortening of
the rotor coils. Foreshortening is caused by thermal
forces which compress rotor coils. Prevention: Proper design of
rotor coils and bracing to support the coils under axial load
is essential. Rotors should be tested for turn
to turn shorts at operating speed.
![Page 36: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/36.jpg)
STATOR WINDING VIBRATION
Problem: Primarily a design related problem that
affects large (>300Mw) generators which have
insufficient end winding bracing to limit the
movement of end turns. Prevention: Proper bracing of
the end winding is required to limit motion caused
by steady state and transient electromagnetic forces.
![Page 37: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/37.jpg)
OVERHEATING
Problem: Overheating of the rotor or stator can lead to
insulation failure, shorting of turns and ground
faults. Overheating can result from blocked
ventilation passages caused by shifting insulation
components or slot wedges. Prevention: Inspect on a regular
basis to ensure all rotor wedges are "locked" in place
preventing migration and thus blocking of cooling
passages.
![Page 38: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/38.jpg)
CONTAMINATION
Problem: For air cooled machines, dirt and dust cause
tracking which can lead to electrical ground faults.
Prevention: Inspect air filterson a regular basis , the
filters must be checked and cleaned regularly.
Polarization index (PI) tests give a good indication of
overall cleanliness of the rotor winding.
![Page 39: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/39.jpg)
ROTOR VIBRATION
Problem: There are many causes, turn-to-turn shorts,
rotor coil foreshortening, electrical grounds,
mechanical imbalances, overheating, etc.
Prevention: Comprehensive vibration measuring is effective
combined with a regular maintenance program.
![Page 40: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/40.jpg)
STATOR WEDGE LOOSENESS
Problem: When stator wedges become loose, coils can
vibrate causing insulation wear leading to ground
faults or turn-to-turn shorts. Prevention: Inspect on a regular
basis tightness of wedge blocks.
![Page 41: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/41.jpg)
STATOR CORE DAMAGE
Problem: Stator core looseness can occur over time as
pre-tensioned through bolts relax. A loose core
results in insulation wear to coils and laminations
resulting in hot spots and core-to-coil failures.
Prevention: Inspect bolt tightness on a regular basis.
![Page 42: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/42.jpg)
GENERATOR MAINTENANCE
The following tests which should be carried out annually in addition to vendor recommended maintenance.
![Page 43: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/43.jpg)
A) INITIAL GENERATOR TEST
• “Megger” rotor winding • “Megger” exciter armature
winding • “Megger” exciter field winding • Complete polarization index (pi)
on main stator • Check bearing insulation
![Page 44: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/44.jpg)
B) INSPECTION ON STATIC EXCITER
• Remove exciter end cover • Examine condition of diode
carrier • Examine exciter
armature/stator for contamination
• Examine exciter armature/stator for winding wear
• Check pmg magnets for contamination
![Page 45: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/45.jpg)
C) ELECTRICAL CONTROL/PROTECTION PANEL • Visually inspect external
surfaces of panel • Complete insulation
resistance checks of panel wiring
• Check function of all relays • Check all fuses • Check all lamps • Check operation of all
switches • Check operation of panel
heaters • Run generator; recalibrate
avr • Secondary inject all
protective relays
![Page 46: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/46.jpg)
E) ROTOR EARTH FAULT PROTECTOR
• Carry out static checks to confirm operation of
detector • Carry out functional check
to confirm operation of detector
![Page 47: 6 MONTHS INDUSTRIAL TRAINING PPT EE BY KHUSHI RAM BHARDWAJ(DAVIET JALANDHAR)](https://reader034.fdocuments.net/reader034/viewer/2022052506/557d48fdd8b42a9c148b4a0f/html5/thumbnails/47.jpg)
F) SLIP-RINGS AND BRUSH-GEAR (IF FITTED) • Check all brushes for grade
and length • Check condition of brush
holders/mountings • Check that spring tensions
are correct • Check conditions of slip-
rings • Check mechanical run-out of
slip-rings • Check cooler and leakage
alarms