Transcript of 5A. The Drilling Riser.ppt

1
TAMU - PemexOffshore Drilling
Lesson 5A
The Drilling Riser

2
Lesson 5A - The Drilling Riser
Riser Components Riser Tensioning Fatigue Kill/Choke Lines Inspection & Maintenance Reentry

3
Riser system for a floating drilling rig
BOP
RISER JOINTSKILL AND CHOICE LINES
SLIP JOINT OUTER BARREL
UPPER BALL JOINT
SLIP JOINT INNER BARREL
RISER TENSION
LOWER BALL JOINT
Mudline
Marine riser = drilling riser, get returns to surface, well control, communications link

4
Integral Marine Riser JointsChoke and kill lines are integral with the marine riser , flanged connections; clamp, etc

5
Integral Marine Riser Connector
Flanged connection - 6 bolts
NOTE: Choke and Kill Lines
O-ring type seals- inspect when running

6
Integral Marine Riser Connector

7
Marine Riser
Flexible Joint
Flexible joint, binding from high tensile forces, inject lubricant, up to 1,500,000 lbf!

8
Upper Section Marine Riser System.
MARINE RISER DIVERTER ASSEMBLY
RISER TENSIONING
LINESTELESCOPIC JOINT
KILL AND CHOKE LINES
FLEXIBLE JOINT

9
Control valve
Vent line
Mud returns
L.P. Annular
A diverter system.Re-directs flow from rig floor to blooey line (10”+), downwind, do not shut in, erosion -108

10
Figure 6-6.
Subsea BOP Stack
Vertical steel loops used for kill / choke line transition around the ball joint.

11
The Drilling Riser
Schematic diagram of riser with imposed forces
MEAN WATER LEVEL
RISER ELEMENT
Optimum riser tension to minimize damage to riser and wear-and-tear on tensioners, sag

12
Str
ess
in r
iser
, ki
ps
Applied tension in riser, kips
Maximum stress
Minimum stress
Tension in riser must be not too low and not too high. Set at 118 kips - will fluctuate 100-136 kips ~ 15%
Mean tension
Insufficient Tension
(too much sag)

13
Combined Effect of Mean Stress and Alternating Stress
Consider: Max Stress of 40 ksi
Alternating Stress: 10 or 20 ksi
Mean Stress: ?
Life: ?

14
Mean stress, ksi
Modified Goodman diagram
Alt
ern
atin
g s
tres
s, k
si
30 10 (20-40 ksi) => 106; 20 20 (0-40 ksi) => 105 cycles. If Mean stress is high, alt. low
Yield strength

15
Vessel offset, % of water depth
Max
. ris
er s
tres
s, k
si
Need adequate tension: Tensioned to 225 kips for 6% offset: at 3%, 11 ksi; at 10%, 30 ksi.

16
The effects of losing one-sixth tensioning capacity on the riser system of previous slide
Max
. ris
er s
tres
s, k
si(196 * 5/6 = 163)
Need adequate tension: Tensioning to 296 kips looks the most advantageous.
(225 * 5/6 = 188)

17
Estimating Pressure Dropin Choke Lines
It is important to be able to determine if the pressure drop in the choke line will be a problem (excessive).
Most drilling fluids are Non-Newtonian.
The Bingham Plastic or Power-Law models may be used. More about this later.

18
Riser Considerations
Riser Metallurgy is very important. Correct heat treatment is
essential. 80,000 psi min. yield strength and
good toughness is preferred. Preheating, welding & normalizing
after welding is critical for riser integrity & long life.

19
Riser Considerations – cont’d
No Field Welding on Riser!
Fatigue of riser cannot be measured prior to some indication of failure.
Routine inspection required.

20
Riser Considerations – cont’d
Fatigue is an embrittlement of the metal. It often starts in the vicinity of welds or other places of high stress concentration.
Fatigue is caused by cyclic loading.

21
Riser Inspection
Visual Inspection of the riser should occur every time the riser is run.
Check all the sealsCheck all the sealing areas

22
Riser Inspection – cont’d
A complete inspection should be made annually.
Dyes: Will detect cracks. To use dyes, paint must be removed.
Magnetic Particle Inspection: Sand blast areas around welds prior to magnetic particle inspection.

23
Riser Inspection – cont’d
Ultra-Sonic Inspection: May detect cracks below the surface. This test is run inside pipe. Paint removal is not necessary.
X-Ray Inspection: Is for cracks inside the metal. It may miss surface cracks.
No one technique will find all the cracks.

24
Riser Instrumentation
Heave Gauge: Pointer attached to guide line moving in front of graduated board.
Riser Angle Indicator (at ball joint):
2/1y
2x
21
2/12y
2x
tantantan

25
Riser Instrumentation – cont’d
Accurate Positioning System:
For detecting and monitoring vessel position.

26
Ball Joint
A Ball Joint Angle > 4 degrees is an indication that something is wrong!
Vessel has excessive offset
Riser tension is inadequate

27
Ball Joint – cont’d
Must decrease ball joint angle before operations are resumed.
Remedial Action:Decrease OffsetIncrease Riser Tension

28
Vessel to Seafloor Guidance System
Guidelines are used for guiding equipment from the vessel to the seafloor (except in deepwater)
Selection and care of guidelines is critical

29
Vessel to Seafloor Guidance System – cont’d
Guidelines should not be tensioned beyond 1/3 of breaking capacity
But…inadequate tension is the most common cause of failure in guidelines

30
Vessel to Seafloor Guidance System - cont’d
Tension should be maximum when landing the BOP stack, or when landing the riser onto the stack.
When the guidelines are not being used to run equipment, tension may be slacked off to ~ twice the weight of the line in seawater.

31
Table 6-1. Recommendations for
Conventionally Used Guidelines
As water depth increases, larger diameter guidelines must be used.
Higher tensioning is required.
Don’t forget to limit tension to < 1/3 of breaking strength.