55 Eglinton Washroom and Hallways
8th floor Men’s Washroom -Paint Main Door and Frame (Rado)
-Paint Stalls (Rado)-Repair wall tiles (Dave)
8th floor Women’s Washroom -Paint Main Door and Frame (Rado)
8th floor Women’s Washroom -Replace Vanity (Cabinet Co.)
8th floor Hallway Door and Frames-Paint Staircase doors and frames -North/South (Rado)
-Paint Elevator door/frames and HVAC door/Frame
7TH Floor Men’s.- Paint washroom stalls (Rado)
-Paint Main door and frame (Rado)-Repair Wall tiles (Dave)
7TH Floor Women’s.- Replace cabinet and vanity (Cabinet Co.)
Close up of cabinet door
7th floor Women’s Washroom -Paint Stall Doors (Rado)
- Paint main door and frame
7th floor Hallway Faux Door-Build faux door over damaged wall paper (remove fountain)
(Complete Solutions Inc.) (647)293-7697
Photo of 4th floor panels for reference
Photo of 8th floor faux door as reference
6th floor Men’s Washroom-Replace Vanity and Cabinet (Cabinet Co.)
6th floor Men’s Washroom-Paint Main Door/Frame (Rado)-Paint Stalls and Doors (Rado)
6th floor Women’s Washroom- Paint Stalls and Main Door/Frame (Rado)
6th WW Stall Doors
5th floor Accesible (HC) Washroom- Remove Wall Paper / Plaster / Paint (Rado)
5th floor Women Washroom (Completed)- Remove Wall Paper / Plaster / Paint (Rado)
- Paint Main door/frame and stall doors (Rado)
5th floor Men’s Washroom- Remove Wall Paper / Plaster / Paint (Rado)
- Paint Main door/frame and stall doors (Rado)
5th floor Men’s Washroom- Vanity is in good condition (Remains)
5th floor men’s
4th floor Women Washroom (Completed)- Remove Wall Paper / Plaster / Paint (Rado)
- Paint Main door/frame and stall doors (Rado)
4th floor Men’s Washroom- Remove wall paper / plaster / paint (Rado)
- -Paint Stall doors (Rado)
5th floor men’s
3rd floor Men’s Washroom- Remove wall paper / plaster / paint (Rado)
- -Paint Stall doors (Rado)
Wall Paper Vandalism
Wall Paper Vandalism3rd FL Men’s
3rd floor Women’s Washroom- Remove wall paper / plaster / paint (Rado)
-Paint Stall doors (Rado)-Paint Main door/frame
3rd Floor WW Wallpaper
3rd floor Women’s Washroom- Replace stained/chipped counter top
- Replace 1 cracked basin- Replace Rusted faucet
3rd floor Hallway Door and Frames-Paint Staircase doors and frames -North/South (Rado)
-Paint all utility room door/frames and washroom doors/frames
2nd floor Men’s Washroom-Remove Wallpaper/ Plaster / Paint (Rado)
-Paint Main Door and Frames (Rado)-Paint Stalls and Doors (Rado)
Rusting Stall Wall 2nd Floor Men’s
2nd floor Men’s Washroom-Replace Counter Top (Counter Co.)
Rusting Stall Wall 2nd Floor Men’s
2nd floor Women’s Washroom-Remove Wall Paper / Plaster / Paint (Rado)
-Paint Stall doors (Rado)-Paint Main door/frame (Rado)-Replace lifting floor tile (Dave)
2nd floor Hallway Door and Frames-Paint Staircase doors and frames -North/South (Rado)
-Paint all utility room door/frames and washroom doors/frames