50 MW METRO WIND POWER PROJECT
-
Upload
tilal-ahmed -
Category
Documents
-
view
384 -
download
8
Transcript of 50 MW METRO WIND POWER PROJECT
![Page 1: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/1.jpg)
50 MW METRO WIND POWER PROJECT
![Page 2: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/2.jpg)
50 MW METRO WIND POWER PROJECT
Project Detail
Project Location = Jhimpir Sindh Pakistan
Client Name = Metro Power Company Limited.
EPC Contractor = Nordex Pakistan Pvt Ltd. Descon Engineering Ltd.
![Page 3: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/3.jpg)
50 MW METRO WIND POWER PROJECT
Project Brief Introduction Award of Contract = Sep 8, 2011.
First Amendment to Contract = July 1, 2013.
Second Amendment to Contract = May 15, 2014. PNTC (Preliminary Notice to Commence) = July 8, 2013
PCD (Project Commencement date) establishment = October 9, 2013
PNTC-II (Preliminary Notice to Commence-II) = May 16, 2014
NTC (Notice to Commence) = October 22, 2014
CD (Commencement Date) establishment = Expected March 20, 2015 Project Completion Date (TOC) = Expected June 20, 2016(15 Month from CD)
![Page 4: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/4.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-I (Off Shore & On Shore)
Micrositting Topography Survey for Access Road Design of Causeway for Naulla crossing Geological Survey for WTG Topography Survey for Metro Internal Road Design Initiation for E-BOP Project Management preparation
![Page 5: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/5.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-I Micrositing
![Page 6: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/6.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-I Geological Survey
![Page 7: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/7.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-I Topographical Survey
![Page 8: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/8.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II (Off Shore) Order Confirmation and Advance payment of E-BOP Equipment
Order Confirmation and Advance payment of Tower Plates
Order Confirmation and Advance payment of Anchor cage (10 nos)Tower Plates
Beside Above, PO has been issued for following and ready for shipment upon CD
1. Tower Flanges 11. Earthing conductor and accessories for WTG. 111. Tower internals (Weld shocked and oil proof plate farms)
![Page 9: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/9.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II (On Shore)
Construction of Causeways and Access Road
Temporary Site Facility (office and residence)
Lay down Area and Work shop
Civil works for Batch plat (60 & 30 Cu meter)
Batch Plant Installation and Calibration
Apart from above, civil works for Metro Internal roads has almost been completed
![Page 10: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/10.jpg)
50 MW METRO WIND POWER PROJECT
Project Progress
Overall Project Progress
Overall Project Progress = 31.93 %
![Page 11: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/11.jpg)
50 MW METRO WIND POWER PROJECT
Project Progress
Project Management Progress
Overall Project Progress = 0.25 %
Main Highlights Submission of project procedures (HSE, QA/QC, Progress monitoring, Project
Security, Document management Plans etc)Geotech Survey Topography Survey
![Page 12: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/12.jpg)
50 MW METRO WIND POWER PROJECT
Project Progress
Engineering works
Overall Engineering Works Progress = 62.40 (Discipline wise), 3.43 % (Overall)
Civil Engineering works = 53.87 %
E & I Engineering works = 8.808 %
![Page 13: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/13.jpg)
50 MW METRO WIND POWER PROJECT
Project Progress
Procurement works
Overall Procurement Works Progress = 50.8 % (Discipline wise), 23.65 % (Overalll)
Main Procurement Works Highlights PO issuance of complete E-BOP Equipment
PO issuance of Tower Plates PO issuance of Tower FlangesPO issuance of 10 nos Anchor cagesPO issuance of WTG earthing conductor and accessoriesPO issuance of Tower internal (weld socket and oil proof plate farms)
![Page 14: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/14.jpg)
50 MW METRO WIND POWER PROJECT
Project Progress
Construction works
Overall Construction Works Progress = 8.07 % (Discipline wise), 3.68 % (Overall)
Main Civil Works Highlights Completion of Access Road Completion of Causeways Internal Road in progress
![Page 15: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/15.jpg)
50 MW METRO WIND POWER PROJECT
Project Progress
Fabrication works
Overall Fabrication Works Progress = 2.58 % (Discipline wise), 1.17 % (overall)
Main Fabrication Highlights
Marking, Cutting, beveling & Rolling = 10 Bottom , 10 Mid 1 , 3 Mid II Sections Marking, Cutting, beveling = 13 Mid II SectionsTacking & Welding completed = 4 Bottom, 6 Mid I Sections Tacking & Welding in progress = 6 Bottom, 4 Mid I, 3 Mid II Sections
![Page 16: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/16.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Construction of Cause Way-I
![Page 17: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/17.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Construction of Cause Way-II
![Page 18: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/18.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Construction of Cause Way-III
![Page 19: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/19.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Access Road
![Page 20: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/20.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Access Road
![Page 21: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/21.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Access Road
![Page 22: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/22.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Temporary Site Facilities
![Page 23: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/23.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Temporary Site Facilities
![Page 24: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/24.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Temporary Site Facilities
![Page 25: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/25.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Temporary Site Facilities
![Page 26: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/26.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Temporary Site Facilities
![Page 27: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/27.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Temporary Site Facilities
![Page 28: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/28.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Batch Plant Installation
![Page 29: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/29.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Tower Fabrication
![Page 30: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/30.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Tower Fabrication
![Page 31: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/31.jpg)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Tower Fabrication
![Page 32: 50 MW METRO WIND POWER PROJECT](https://reader035.fdocuments.net/reader035/viewer/2022062223/588837bd1a28ab7a298b4f8b/html5/thumbnails/32.jpg)
50 MW METRO WIND POWER PROJECT
THANK YOU