5 project scheduling in agriculture of stabilization 300 hectares grape garden group 2
Transcript of 5 project scheduling in agriculture of stabilization 300 hectares grape garden group 2
PROJECT SCHEDULING IN AGRICULTURE OF STABILIZATION 300 HECTARES GRAPE GARDENHARYO M.WILLIAM ERIC MANONGGAVINDY T
PROBLEM ISSUESome activities must be done first before doing the next activity
Delay in some activity may cause delay in overall schedule
Need to Finish the project faster than normal time
METHODSCRITICAL PATH METHOD (CPM)
Was develop by Dupond Company in 1950’s
Algorithm for scheduling a set of project activities
Deterministic concept is used
Cost optimization is given prime importance
PROGRAM EVALUATION REVIEW TECHNIQUE (PERT)
Tool for planning
Probabilistic
Assumed cost varies directly with time model concept is used
Time is the controlling factor
ENVIRONMENTAL SCANNINGDelay time project
Some Critical activities
One activities connected with other activities
ALTERNATIVE COURSE OF ACTION
Minimum Project Completion Time (Using Normal Time)
Results by WinQsb software, there are 32 critical paths and project finished on 390 days
ALTERNATIVE COURSE OF ACTIONGant Chart
Results by WinQsb software
Activities 1,2,3,4,5,6,7 are critical activities and slack time is zero
ALTERNATIVE COURSE OF ACTIONCPM
Results by WinQsb software
Project completion in 365 days will cost additional 2,364,353 Rials
ALTERNATIVE COURSE OF ACTIONPERT
Results by WinQsb software
Project completion in 364.67 days is and have 384 critical paths
ALTERNATIVE COURSE OF ACTIONPERT
Results by WinQsb software
the maximum probability completion
365 days 53.49%
370 days 84.14%
380 days 99.80%
KEY SUCCESS OF FACTORRight planning (Critical activity crashing )
On time scheduling
Control of project
Money
SELECTION BEST OF ALTERNATIVES
CPM
RECOMMENDATIONIn doing CPM there will be some additional cost, makes sure that the budget is ready
PERT shows us the probability of achieving the target, make sure to choose one that is feasible