5 Case Study Final
Transcript of 5 Case Study Final
8/14/2019 5 Case Study Final
http://slidepdf.com/reader/full/5-case-study-final 1/4
Case Study and Suggestions
Wastage of Dowel Bars:
• Case: These are to be provided as reinforcement for the supporting walls for the
LIFT (ELEVATOR). But the LIFT that has to beincorporated, its design is not yet finalized. The
dowel bars are long enough to provide reinforcement
for any size of the wall, but it will be used only as
per the requirement when the design will be finalized
and the remaining part will be removed as a waste,
or might be removed completely moreover it is
getting corroded, as left like that since long.
• Suggestion: The design of the LIFT must have been made prior to the construction
work, so that the wastage of the bars would have been checked. And if on a whole the
full site is considered, this wastage can be a big bother.
Unused Passenger Hoist:
• Case: A Passenger Hoist is installed in front of a Block for lifting man, small and
light weighed materials/tools/etc, is very costly and something more than the required
one. Operation of this lift a very expensive,
because power requirement is too high than
tradition of this segment. Presently at the site,
there is no means to provide such expensiveequipments.
• Suggestion: If the cost of the generator was
unaffordable, then such an expensive lift should
not have been bought. Now, it can be shifted to
any other project of the company where it can be
used efficiently.
Unused Spare Area:
•
Case: A considerable space is left beside flats of Block-1 and similar blocks as sparearea, while the same is not the case
with the other blocks. This space is
of no use as in particular.
• Suggestion: This would be
taken as an architectural
imperfection as of which can
be included in the boundary
area of the flat, which
thereby would haveincreased the carpet area of the flat.
8/14/2019 5 Case Study Final
http://slidepdf.com/reader/full/5-case-study-final 2/4
Facilities Provided to the Workers:
• Case: For any type of manual work to be carried out effectively and efficiently the
most important factor is ‘Mental strength’. Human mind become monotonous and
tedious doing a same work repeatedly and thus the efficiency decreases. This
definitely increases the tenure for completion of the project.
• Suggestion : When dealing in lakhs and crores, what a few thousands of rupees willmatter, which if invested in fact will be a blessing in disguise. What could have been
done is, a film projector can be provided which is not very costly, on which the
workers during night time can see movies/films and get freshen up. This can be very
beneficial for many aspects. Their efficiency will grow and the company will be
benefited. Moreover, with such a small facility, the company will be praised by their
workers.
Quality Control Lab:
• Case : Quality control at site is provided in order to maintain a desired degree of
quality of construction material together with the protection of environment. It
includes the quality of steel used, cement, bricks, aggregate, etc. which provides
stability to any structure. A quality control lab should have a garden in front of it,
which encourages and shows that the construction being done at site is environmental
friendly and creates a good working
environment.
There are certain tests that demand to be
conducted in a control temperature. So
the quality control must have a certaintemperature-controlling device so that the
tests are conducted in a proper manner.
• Suggestion : There should be a garden
in front of the lab and temperature-
controlling device.
Public Transport Accessibility and Transportation Route:
• Case : The mode of transport and the way of
transport to the construction site should be quick and easiest so that the work can be started at the
earliest without delays and is comfortable to the
engineers and working people and they remain fresh
and effective after coming at site.
The bus takes the engineers and workers from a
place name ‘Chingrihatta’. From this place there are
two possible routes to reach the site, the one is by
the by-pass (short-route) and the other is a normal
long route. The bus takes from the long route, as justafter the flyover there is a sharp turn and the road is
8/14/2019 5 Case Study Final
http://slidepdf.com/reader/full/5-case-study-final 3/4
muddy over there, which increases the chances of toppling of bus. This causes an
additional 20 minutes more to reach the construction site that’s means the work could
have started 20 minutes earlier besides this it causes a large inconvenience as there is
a single bus running to the site and almost 50% people goes standing in bus.
• Suggestion : Since the construction is a long-term work the company can repair the
shortest route so that the working people can reach by spending less time in busmoreover it will add to the company economy by saving the cost to petrol
consumption and attract the buyers by the mode of infrastructure to reach the place.
Also by increasing the number of vehicles company can provide comfort to its
workers so that their mind gives more productivity.
Water - Logging Problem Surrounding the Batching Plant:
• Case : It is always necessary to create a proper concrete base near the batching plant
so that the ingredients of concrete can be collected over that concrete base in a proper
quantity; a concrete base helps in providing a platform to these materials and helps in
proper utilization (less wastage) of the material.
At site although a concrete base was
prepared but it was not proper, the nearby
dirty sand come into the way of backhoe
which get mixed up in the material and is
carried up by the batching plant which led to
the side depression during rainy season. This
depression has creates the water logging
problem at the backside of the batching plant
and causes difficulty in movement of
backhoe. Now every time whenever there is a rain water gets collects over there and a
pump is used to remove the water which adds to the cost of construction project and
also use of an extra manpower which could have been used at some other work.
• Suggestion : The broken bricks, sand gravels and even the waste material generated
during pile caps can fill up the place where the depression has been created.
Protection of Reinforcement from Corrosion
• Case : Steel is the heart of any R.C.C. building. It is the most important, costlier, and
is very prone to rusting and hence proper
care of steel is very necessary. A proper
isolated place should be there to keep the
steel where there is no moisture, also
only the required quantity of steel should
be present on site so that its managing
could be done in a proper way. There
were two major problems at site: Firstly,
the steel was placed randomly at site in
an open atmosphere that caused rusting
of steel. Secondly, since phase 2 constructions have been stopped. The dowel bars that
8/14/2019 5 Case Study Final
http://slidepdf.com/reader/full/5-case-study-final 4/4
were protruded from columns are getting corroded in the open atmosphere. If such
condition persists further then the strength of steel will be reduced to great strength
and it couldn’t be used for further extension of building.
• Suggestion : There should be a proper isolated structure free from moisture for the
steel. The dowel bars should be coated with the anticorrosive material to prevent the
steel from being corroded further. The basement which has been prepared can be useda storage space for steel.