4th Quarter Contractor Business Meeting

12
4th Quarter Contractor Business Meeting December 14, 2012 Mike Kehoe Plant Engineering Facilities Session

description

4th Quarter Contractor Business Meeting. Facilities Session. December 14, 2012. Mike Kehoe. Plant Engineering. Agenda. Product use in sensitive areas Access to Life Saving stations No parking or material in crane paths Hydrostatic testing IAW Ch. 8 of Health and Safety Manual - PowerPoint PPT Presentation

Transcript of 4th Quarter Contractor Business Meeting

Page 1: 4th  Quarter  Contractor Business Meeting

4th Quarter Contractor Business Meeting

December 14, 2012

Mike KehoePlant Engineering

Facilities Session

Page 2: 4th  Quarter  Contractor Business Meeting

2

Agenda

– Product use in sensitive areas– Access to Life Saving stations– No parking or material in crane paths– Hydrostatic testing IAW Ch. 8 of Health and Safety Manual– Scheduling of shutdown work

• LOTO or 3rd rail tagging from O43 during shutdown– FMEDs– SAFETY

• Cutting/sawing/core drilling into concrete decks• Contractor’s not using their LOTO tags with NNS tags. Second

leading finding in monthly audits.• H&S Audit findings

Page 3: 4th  Quarter  Contractor Business Meeting

3

Product Use in Sensitive Areas

• All products must be approved for use in the plant– MSDS approval required by 027 Environmental Health & Safety

• Avoid opportunity for generation of mixed waste

• Review with your coordinator before using products

Page 4: 4th  Quarter  Contractor Business Meeting

4

Access to Life Saving Station

• During construction, be aware of locations of the life saving stations on water front areas

• Maintain clear access to the life saving stations

Page 5: 4th  Quarter  Contractor Business Meeting

5

Crane Path

REMINDER• Do not park vehicles in crane path

• Do not obstruct crane path with material

Page 6: 4th  Quarter  Contractor Business Meeting

6

Unplanned Event – B4636 River Water Pump House Leak

• October 16, 2012 - B4636 river water pump house

• River water system was being modified

• System was pressurized

• Hydrostatic testing failed

• Test was not conducted in accordance with Chapter 8 of H&S Manual

Page 7: 4th  Quarter  Contractor Business Meeting

7

Scheduling of shutdown work

• On, or before December 17, provide information to your coordinator if you are planning to work between December 21 and January 2. Need location and point of contact.

• If any work requires technical support for LOTO or 3rd rail tagging from O43, PLAN AHEAD. We have a lot of work that will occur during shutdown. We do not want to slow 043 work by emergent LOTO issues.

Page 8: 4th  Quarter  Contractor Business Meeting

8

FMED’s

• FMED - Foreign Material Exclusion Device

• Use from the start of the project

• Maintain cleanliness of pipe systems – Tape, cuttings, and dirt were found in our pipe systems

• Foreign material in process gas piping is dangerous to the user

Page 9: 4th  Quarter  Contractor Business Meeting

9

O27 - Safety

• Cutting/sawing/core drilling into concrete decks

• Contractors are not using their LOTO tags with NNS tags. Second leading finding in monthly audits

Page 10: 4th  Quarter  Contractor Business Meeting

10

O27 - Safety

2012 H&S Audit Findings

• 20% of hot work operations requiring fire watches did not have fire watches on duty

• 47% of fire watch trained employees were not able to identify the different classes of fire, extinguishing agents, the stages of fires and methods for extinguishing fires

• 53% of employees failed to recognize that CO2 can displace oxygen in a confined space

• 20% of hot workers observed did not have the required 8-inch boots or spats

Page 11: 4th  Quarter  Contractor Business Meeting

11

Comments?

Page 12: 4th  Quarter  Contractor Business Meeting

12

QUESTIONS????

• If you have questions regarding this presentation, please contact your Contract Coordinator or: