45148-008: Greater Colombo Water and Wastewater …

68
Semi-Annual Social Monitoring Report Project number: 45148-008 Period: July December 2018 Submission Date: August 2019 SRI: Greater Colombo Water and Wastewater Management Improvement Investment Program Tranche 3 This report was prepared by Colombo Municipal Council, Government of Sri Lanka for the Asian Development Bank. This document is made publicly available in accordance with ADB’s Access to Information Policy and does not necessarily reflect the views of ADB. This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Transcript of 45148-008: Greater Colombo Water and Wastewater …

Page 1: 45148-008: Greater Colombo Water and Wastewater …

Semi-Annual Social Monitoring Report

Project number: 45148-008

Period: July – December 2018

Submission Date: August 2019

SRI: Greater Colombo Water and Wastewater Management Improvement Investment Program – Tranche 3

This report was prepared by Colombo Municipal Council, Government of Sri Lanka for the Asian Development Bank. This document is made publicly available in accordance with ADB’s Access to Information Policy and does not necessarily reflect the views of ADB.

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may

be preliminary in nature. Your attention is directed to the “terms of use” section of this website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: 45148-008: Greater Colombo Water and Wastewater …

1

Greater Colombo Water and Wastewater Management Investment

Improvement Program

Loan Number 3348/3349- SRI

Social Safeguards Report July to December 2018

Implementing agency

Colombo Municipal Council (CMC)

Executing Agency

Ministry of Internal & Home Affairs and Provincial Councils & Local

Government

Page 3: 45148-008: Greater Colombo Water and Wastewater …

2

Table of Contents

A. Executive Summary ……………………………………………………………………………………………………..4

B. Background of the Report and Project Description………………………………………………………..4

C. Scope of Impacts…………………………………………………………………………………………………………..6

c1. Contemporary status of the resettlement………………………………………………………………..6

c2. Entailment Matrix…………………………………………………………………………………………………..7

D. Compensation and Rehabilitation…………………………………………………………………………………9

E. Public participation and consultation…………………………………………………………………………..14

e1. Project Supervision………………………………………………………………………………………………..15

F. Grievance Redress Mechanism (GRM)………………………………………………………………………….20

G. Institutional Arrangement……………………………………………………………………………………………24

H. Monitoring Results – Findings………………………………………………………………………………………27

h1. Land Acquisition and Resettlement…………………………………………………………………………27

h2. Socio-Economic Development…………………………………………………………………………………28

I. Compliance Status………………………………………………………………………………………………………..29

J. Follow up Actions, Recommendation, and Disclosure……………………………………………………30

Appendix 1

i. List of Affected Persons and Entitlements

ii. Summary of RP/IPP with entitlement matrix

Appendix 2

i. Copies of AP’s certification of payment (signed by the APs)

ii. Summary of minutes of meetings during public consultations

iii. Summary of complaints received and solution status

Page 4: 45148-008: Greater Colombo Water and Wastewater …

3

ACRONYMS

ADB Asian Development Bank

Aps Affected Persons

CMC Colombo Municipal Council

CGR Ceylon Government Railways

DSIC Design, Supervision Institutional Development Consultants

DSD Divisional Secretariat Division

EA Executing Agency

GCWWMIIP Greater Colombo Water and Wastewater Management Investment

Improvement Program

GND Grama Niladhari Division

HH Households

IR Involuntary Resettlement

MIHA&PCLG Ministry of Internal & Home Affairs and Provincial Government & Local

Government

NIRP National Involuntary Resettlement Policy

PD Project Director

PMU Project Management Unit

RAP Resettlement Action Plan

RS Resettlement Specialist

SC Safeguards Committee

SIA Social Impact Assessment

SSO Social Safeguard Officer

SPS Safeguards Policy Statement

UDA Urban Development Authority

URP Urban Regeneration Project

WP Western Province

EMP Environment Monitoring Plan

SSC Social Safeguard Committee

GRM Grievances Redressal Mechanism

NHDA National Housing Development Authority

ADG Additional Director General

DS District Secretary

Page 5: 45148-008: Greater Colombo Water and Wastewater …

4

Social Safeguard Bi-Annual Report

July to December 2018

A. Executive Summary.

1. The expected impact of the Greater Colombo Water and Wastewater Management

Investment Improvement Program (GCWWMIIP) is an improved water supply and wastewater

service and management in Greater Colombo, aligned with Vision for a New Sri Lanka, 2010-2020.

The outcome will be improved system efficiency and financial sustainability of water supply and

wastewater services in Colombo.

2. The main component of the project consists of construction/rehabilitation of the new

sewerage system to the South part of the Colombo city. There are some resettlement and land

acquisition for laying sewerage pipe and construction two-pump station; not only that there may be

temporary disturbances to the people who are living close to the construction site hence project has

prepared Resettlement plan for addressing such resettlement issues and received concurrence from

ADB before starting the construction activities.

3. The contract for laying of sewer lines, force main and construction of pumping station of

Kirulapone catchment area has been awarded. Construction of Kalinga Mawatha Pump Station, pipe

laying using micro tunneling technology and pipe laying using open cut technology is in progress

under this contract.

B. Background of the Report and Project Description.

Project description

4. The Greater Colombo Water and Wastewater Management Improvement Investment

Program is financed by Asian Development Bank (ADB), together with the European Investment

Bank (EIB) and the Government of Sri Lanka to a total of $112.83 Million. Out of which ADB is

financing USD $ 92.67 Million USD $ 50 financed by EIB and balance USD $ 35.85 financed by

Sri Lanka Government. The project is effective from 03.11.2016 and was planned to be completed

by 31.12.2020. The Ministry of Internal & Home Affairs and Provincial Councils & Local Government

(MIHA&PCLG) is the executing agency of the Project. Colombo Municipal Council (CMC) and the

National Water Supply and Drainage Board (NWSDB) are the projects implementing agencies. This

report elaborates details of activities under the CMC component.

5. The expected project impact is an improved wastewater service and management in Greater

Colombo, aligned with Vision for a New Sri Lanka, 2010-2020. The outcome will be improved system

efficiency and financial sustainability of wastewater services in Colombo.

6. The expected outcome will be an improvement in water and wastewater services and its

management efficiency in Greater Colombo. The CMC component of the project has 3 components;

i) Wastewater system rehabilitated and expanded in the South Catchment area of the

Colombo city.

ii) Secondary Wastewater treatment plant constructed in the South catchment area of

Colombo city.

iii) Institutional structure and capacity of service provider strengthened.

7. All major civil works contracts are carried out under component 1 and 2 which directly

involves Environmental and Social Safeguard matters.

Page 6: 45148-008: Greater Colombo Water and Wastewater …

5

8. Project classification: This project is classified as category B for involuntary resettlement

and category C for indigenous people following ADB’s safeguard policy Statement 2009(SPS). The

project created a negative impact on 57 persons of 15 families (by laying of sewerage pipe and the

construction of 2 pump stations for the Kirulapoane area. Except for two families, all other families

have built houses at government lands.

9. Financing: All social safeguards and resettlement related activities are financed by the

Government of Sri Lanka as a part of the co-financing of the project.

10. Resettlement plan: A Resettlement Planning Document was prepared in 2016 being updated

and will be submitted to ADB for review. National Involuntary Resettlement Policy (NIRP 2001) and

the ADB’s Safeguard Policy Statement 2009 have been considered in the preparation of these

documents to avoid unnecessary disturbance to the people and the project implementation.

Table 1- Implementation progress of the construction activates of the project

Details Date of

award

Expected

Date of

completion

Contract

amount

Status Physic

al

progre

ss

Financial

progress

IR Impact

During

Impleme

ntation

Contrac

tor: M/s

Larson

and

Turbo

Pvt. Ltd.

18.05.2017

17.05.2020

Contract

amount:

LKR

7015.92

Million

1.Shaft

excavation

for micro

tunneling

at 6th lane

2.Manhole

constructio

n for pipe

laying using

an open cut

method

3.Construct

ion of guide

walls of

Kalinga

MW PS

19% 10% None

11. The scope of the project has not been changed up to now therefore there are no adjusted

safeguards measures required. However, during construction activities, there were adjusted

safeguards measures due to the emerging of the temporary impact as mention below and all the

impact and the Mitigation measures specified in appendix 2.

Table 2- Mitigation measures suggested addressing the difficulties of community

Impact Suggested mitigation measure

• Transportation and access

difficulties

• Difficulties faced by vehicle

users

• Road sections should be used stage by stage

(staggered construction) without excavating the

entire area at once for laying pipes.

• Construction work should be completed in a

speedy manner

• Exploring all the possibilities to use alternative

Page 7: 45148-008: Greater Colombo Water and Wastewater …

6

access roads

• Conducting construction activities during night

hours (only in suitable sub-project’s road sections).

• Explore possibilities to apply trenchless technology

in laying pipes (especially, in narrow roads).

• Effective management of the project site (clearing

the road, providing steel plates as temporary

entrances to houses during construction period)

• Providing safe vehicle parks during the

construction phase

12. Background of the Report

This Report aims to brief the progress of the resettlement and social safeguard activities of the

project from July to December 2018 consistent with updated/ revised figures which will be reported

in the updated resettlement plan. Section A of this report is the introduction which explains the

project background, received a loan from each donor agencies and the government of Sri Lanka.

Each section from section C up to section J will explain the scope of impact, Compensation and

Rehabilitation, public participation and consultation, GRM of the project, institutional arrangement,

and monitoring result and follow up action of the social safeguard activities of the project during the

reporting period.

C. Scope of Impacts

13. As per the updated resettlement plan for the project-3, there are 57 persons in 15 structures

including 14 households (three with small boutiques attached to the houses), and one business place

(garage) were identified as a project affected families by construction activities of two pump stations

sites at Kalinga Mawatha and Thalakotuwa Garden, and one pipe laying site at Colombage Mawatha

(Railway reservation)

Table 3 - C1. Contemporary Status of the resettlement of the project

S. No Location Loss of

land

Loss of

Structure

Loss of

Livelihood

(Permanent

)

Tempora

ry

income

loss

Remarks/Status of RP

Implementation

No. of Households and family members

1 Kalinga

Mawatha

PS site

None 19 members in

02 households

and 01 garage

01 01 All resettled with

required compensation

for the resettlement

2 Thalakotuw

a garden PS

Site

02 26 members in

06 households

01 None 03 families resettled

with all compensation.

03 families waiting for

relocation.

02 private lands are in

the land acquisition

process under the

ministry of land by the

line ministry.

01 leased land(NHDA) is

also in the land

acquisition process

under Ministry of land

by the line ministry

Page 8: 45148-008: Greater Colombo Water and Wastewater …

7

3 Colombage

Mawatha

(Railway

Reservatio

n)

None 12members in

05 houses

02 None 04 affected parties

resettled with all

compensation package

01 family is waiting for a

house

Total no. of affected families and persons - 57 affected persons in 15 families including

garage

Table 4- Type of structure loss

S.No. location Type of structure loss Total

structure

loss

01

Kalinga Mawatha PS

site

residential commercial Residential cum

commercial

02

own structures

01 tenant - 03

02 Thalakotuwa garden PS

Site

05

own structure

- 01

own structure

06

03 Colombage Mawatha

(Railway Reservation)

03

own structures

- 02

own structure

05

there are 02 families living in one house, therefore, the total affected structure is 06 and the number of affected

families are 07

14. As per the resettlement plan for the project following the Entitlements Matrix has been

proposed for project-affected people.

Table 5- c2. Entitlements Matrix for the project affected people as follows

Loss Magnitude Measures to mitigate Responsibility

Displacement from

present residences

built in public and

private land plots

Total 14 structures

displaced

03 structures at Kalinga

Mawatha PS site - 02

residential structures and

01 commercial structure

(garage)

05 structures at

Colombage Mawatha - 03

residential structures and

02 residential cum

commercial structures

06 structures at

Thalakotuwa Garden PS

site - 05 residential

structures and 01

residential cum

commercial structure

Resettlement in UDA built

condominiums ( a flat with 400

square feet floor area will be

offered for each affected family

If construction of condominium

get delayed affected families

will be assisted to stay in

rented -in houses temporary

until permanent resettlement

is completed, assistance will

also be offered to transport of

the household items to

temporary rented in houses

and then to the permanent

residences in condominiums,

The owners of 2 private land

will be proved with monitory

compensation at market price

of the affected land plots

CMC,

PMU/DSIDC,

and UDA

Loss of livelihood

activities performed

Kalinga Mawatha PS site -

1 Garage, 01 small

The 01 garage owners

compensated for the loss of

CMC,

PMU/DSIDC,

Page 9: 45148-008: Greater Colombo Water and Wastewater …

8

in the present

residences.

movable flower shop and

Also 01 cattle keeping a

yard

Colombage Mawatha pipe

laying site - 02 boutiques

attached to the

residences,

Talakotuwe Garden PS site

- 1 boutique attached to

a house.

income and compensation to

obtain alternative places to

continue business

The cattle-yard owner provided

land to keep cattle by UDA

Compensation for the flower

shop owner has been paid for

the temporary loss of income

during the transition period of

the present location to a new

house and AP continued his

business at the same place as

he wished.

The owners of two boutiques

provided compensation for loss

of income and ground floor

house in high rise building to

continue business (Since these 2

boutiques are attached to

housing structures, therefore,

they are not entitled to receive

compensation for the

structures)

The owner of the boutique

provided compensation for loss

of income and ground floor

house in high rise building to

continue business (Since these 2

boutiques are attached to

housing structures, therefore,

they are not entitled to receive

compensation for the

structure)

and UDA

Loss of land Except for two lands

other, all lands in three

subproject sites are

government lands.

(Colombage Mawatha

pipe laying land belongs to

Department of Railway

(CGR),

Talakotuwe Garden land

belongs to the National

Housing Development

Authority (NHDA) and

privet parties.

Kalinga Mawatha land

belong to UDA)

The privet lands owners will be

paid compensation based on

the government Chief Valuer

valuation and other

compensation related to the

resettlement.

CMC,

DSIDC/PMU

Page 10: 45148-008: Greater Colombo Water and Wastewater …

9

D. Compensation and Rehabilitation

15. 15 families are living in 14 structures need to be relocated to get the land cleared for the

construction activities at Kalinga Mawatha PS site, Thalakotuwa garden PS site and Colombage

Mawatha pipe laying site.

16. Kalinga Mawatha PS site: The affected people at Kalinga Mawatha PS site has been

resettled with all compensation that was mentioned in the resettlement plan and construction of

Pump station is in progress.

17. Thalakotuwa Garden PS site: As described in table 5 above there are seven families1 have

to be relocated to get land clear for construction of wastewater Pump station at Thalakotuwa

garden. Out of seven three families have been resettled with all compensation related to the

resettlement which was mentioned in the resettlement plan for the Kirulapone contract. There are

two private lands required to be acquired for the construction of Thalakotuwa PS. Hence, as

requested by MIHA&PCLG, the land acquisition process is in progress by the ministry of land.

Besides, the subfamily, living in house number 154/12 which is built on leased land belongs to NHDA

has claimed for an additional house for them. According to the government policy and legal

framework project unable to provide two houses for one house, therefore, it was decided to follow

the land acquisition process to clear the land by the higher management of the EA and IA.

18. Colombage Mawatha Pipe laying site: As mentioned in table 5 above there are 5 families

have to be resettled to get land clear for the construction activities. Out of 5 two families have been

resettled at a newly built apartment at Kollonnawa with providing all compensation package what

was mention in the resettlement plan.

19. However, as reported in the last SSMR for January to June 2018 the resettlement work has

to be postponed due to the finalization of the proposed Kaleni Valley railway line expansion design.

Therefore, project has Series of discussion with the officials of the Ministry of Transport and the

Colombo Suburban Railway Project (CSRP) to finalize the decision; CSRP has finalized design of

expansion of the railway line gave concurrence or pipe laying works at Railway reservation and

relocation of the remaining households (three families) of the site has been restarted accordingly.

During the reporting period out of the remaining three families, two families have been resettled

with all compensation. Still, one family are remaining for relocation.

20. The compensation package was paid to the affected people as mentioned in the

resettlement plan as bellow.

Table 6 - Compensations delivered to affected families at Kalinga Mawatha PS site

No of

affected

families

entitlements as per approved resettlement plan

No. of Affected Families compensated till December 2018

No. APs compensated during the reporting period,

No. of APs yet to receive compensation

04 Demolition of

structure - All

payments at

replacement cost

in material, cash,

or a combination

of both

according to the

actual loss to

repair or rebuild

04

-

-

1 There are Seven families living in six structures (two families living in one structure)

Page 11: 45148-008: Greater Colombo Water and Wastewater …

10

the structure to

an original or

better condition

when remaining

land sufficient to

rebuild upon

Permanent

impact on

livelihood - All

(cash) payments

for loss of income

will be made.

APs will be

provided

compensation for

loss of income

and provide

assistant to find a

suitable place to

original or better

condition when

remaining to

continue income

generation

activities.

03

-

-

Table 7- Compensations delivered to affected families at Thalakotuwa garden PS site

No of

affected

families

entitlements as per approved resettlement plan

No. of Affected Families compensated till December 2018

No. APs compensated during the reporting period,

No. of APs yet to receive compensation

07 Demolition of

structure - All

payments at

replacement cost

in material, cash,

or a combination

of both

according to the

actual loss to

repair or rebuild

the structure to

an original or

better condition

when remaining

land sufficient to

rebuild upon

Permanent

impact on

03

01

- - 04

Page 12: 45148-008: Greater Colombo Water and Wastewater …

11

livelihood - All

(cash) payments

for loss of income

will be made.

APs will be

provided

compensation for

loss of income

and provide

assistant to find a

suitable place to

original or better

condition when

remaining to

continue income

generation

activities.

Table 8 - Compensations delivered to affected families at Colombage Mawatha pipe laying site

No of

affected

families

entitlements as per approved resettlement plan

No. of Affected Families compensated till December 2018

No. APs compensated during the reporting period,

No. of APs yet to receive compensation

05 Demolition of

structure - All

payments at

replacement cost

in material, cash,

or a combination

of both

according to the

actual loss to

repair or rebuild

the structure to

an original or

better condition

when remaining

land sufficient to

rebuild upon

Permanent

impact on

livelihood - All

(cash) payments

for loss of income

will be made.

APs will be

provided

compensation for

loss of income

and provide

02

02

02 01

Page 13: 45148-008: Greater Colombo Water and Wastewater …

12

assistant to find a

suitable place to

original or better

condition when

remaining to

continue income

generation

activities.

Table 9-Resettlement Budget

No Compensation for the type

of loss

Quantity Duration The total amount of Rs.

01 Unauthorized Residential Structure

Fully affected structure 12 Permanent 3.5 Million per house for 10

4 Million per 01 for 02 house

02 Private land acquisition

Fully affected

Lands with structure

02 Permanent 5 Million/perch for 4.08

Perches

Compensation to build a

new house

02 Permanent 1.50 Million per house

Rent a house 02 12 months 25,000.00 per house

Livelihood assistant for AP

families

02 06 months 1000.00 per day , 7000.00

for a week

Transport cost for transport

household items to rent a

house and a new house

02 Lump-sum

for (two

times)

0.1 Million per house

Labor charges for loading

and unloading household

items

02 Lump-sum 5000.00 per person for 2

laborers

03 Relocation

Transport cost: to transport

household goods from

present houses to new

housing units

14 Lump-sum 5000 per truck

Livelihood assistance for AP

families

14 7 days 1000 per day

Page 14: 45148-008: Greater Colombo Water and Wastewater …

13

04 Loss of livelihood –permanent

Permeant disruption of

income

01 garage 12 months 30,000.00 per month

Permeant disruption of

income

02 small

shops

12 months 20,000 per month each

Permeant disruption of

income

01 small

shop

12 months 25,000.00 per month

Permeant disruption of

income

01 mobile

vendor(flo

wer seller)

14 days 1000.00 per day

Transport cost for the

transport garage items

01 garage Lump-sum 5000.00

21. Status of the land acquisition for construction of wastewater Pumping station

Table 10- Status of the Land Acquisition

Component Compensation package Status of payment

Thalakotuwa garden PS site All (cash) payments for

Private land and structure will

be paid

EA and IA of the project decided

to purchase lands due to

delays2 in the land acquisition

process.

22. Social Safeguard team of the project has given fullest support to the resettled 38 personnel

in 10 families at three locations named Kalinga Mawatha pumping station site, Thalakotuwa garden

PS sites and Colombage Mawatha (Railway reservation) pipe laying site to come across following

facilities.

1. Electricity connection to the new house

2. Water connection

3. Find schools for the children

Communicating with other organizations and URP-UDA. Affected people are very happy with their

new houses and new living environment and appreciated for providing greater houses better than

the houses which they lived in.

23. The project has met the host community to introduce newly resettled people who were

affected by the project. The awareness session for the Aps has also been done before resettled them

at new houses. The following topics were discussed in the session.

1. challenges and benefits of the new life at a new house / high rice apartment

2. lifestyle of the high rise apartment /new community

2 Land equation process is very long procedure and take time to get land acquisition but project need to hand

over land to contractor as soon as possible therefore EA and IA of the project decided to perches land to handed over to contractor minimize delay.

Page 15: 45148-008: Greater Colombo Water and Wastewater …

14

3. changing the behavior of the APs following rules and regulation of the high rise apartment and

the host community

E. Public participation and consultation

24. Finalized resettlement plan, which was prepared by consultation with various stockholders

and the Aps has been disclosed on the ADB web site.

25. The household survey and focus group discussion methodologies have been used for

collecting socio-economic information for the preparation of Resettlement and social impact

assessment. Also, many consultation sessions have been held for the affected people at

Thalakotuwa Garden, Kalinga Mawatha PS sites and Colombage Mawatha pipe laying sites with

support from relevant stakeholders to get people for relocation.

26. Door to door awareness campaigns, and public meeting awareness sessions have also been

conducted before starting the construction activities by Safeguard Team of the PMU with the

support of Contractor’s safeguard team and the construction crew.

The following topics were discussed in this session.

1. present situation without sewerage system and health and environmental problems and

how it affects the residents

2. Health and sanitation benefits for the residents and their children and how it affects

their livelihood activities and the economy.

3. Resident’s responsibilities of a clean environment

4. the complexity of the sewerage system and the expenditure

5. construction activities and construction methodology

AP signing document related to the new

house

DSIDC –TL handing over keys of new house to

one of affected women at Colombage

Mawatha pipe laying site

Page 16: 45148-008: Greater Colombo Water and Wastewater …

15

6. public participation of the project activities

7. GRM of the project and the contractor

8. Details of contact persons 9. the communication procedure 10. Probable impacts due to construction activities

27. However, construction induced impact, environmental hazards and traffic congesting are the

most concerning problems of the people.

Table 11- Major activities and actors responsible for the implementation of the RP

Activity Responsible actor Status

Review of the RP The team leader of the DSIDC

Sociologist of PMU and the PD

Done

Submission to ADB PMU Done

Revision of the RP ( if required) Resettlement specialist of DSIDC After comments from ADB, it has

been done

Awareness of contractors on

resettlement issues in the sub-

project areas

Resettlement specialist of DSIDC

and Sociologist of PMU

Awareness has been done for

the contractor before starting

the construction works.

Awareness programs for the

general public also conducted by

PMU Sociologist together with

the contractor, and door to door

awareness session has been

done Just before the start the

construction activities.

Awareness of the Affected

population

Resettlement specialist of DSIDC

and Sociologist of PMU and UDA

Has been done for the resettled

people and awareness program

by PMU Sociologist, and for the

remaining affected people will

also be aware before resettled

Implementation of RP UDA, PMU In progress by PMU

Monitoring of the RP

implementation process

Sociologist of PMU with inputs

from Resettlement specialist of

DSIDC

PMU Sociologist has doing

monitoring woks of the RP

implementation and

construction-related impact.

e 1. Project supervision

28. The following table describes activities conducted during the reporting period for public

consultation and participation of the project activities.

Table 12 – Summary of the Consultation

Event Date of the Event Name of the subproject Reason

Meeting with

Thibirigasyaya

District Secretary

on Colombage MW

RS issue

01.08.2018 Colombage Mawatha

pipe laying site-

Kirulapone

To clear ownership

of the affected

house

Site visit 02.08.2018 Keerakotuwa pipe laying

site and Kalinga

mawatha PS site

Site monitoring

Meeting with public 06.08.2018 Kirulapone To discuss pipe

laying at privet road

Page 17: 45148-008: Greater Colombo Water and Wastewater …

16

Meeting with public 31.08.2018 Thalakotuwa garden pipe

laying site

To discuss traffic

issues during

construction

Site visit 03.10.2018 All sites of the kirulapone

contract

Site monitoring

Site visit 10.10.2018 All sites of the kirulapone

contract

Site monitoring

ADB review mission 05.11.2018 Project 3 Progress review

Construction site

visit with ADB

mission

07.11.2018 All sites at Kirulapone

and WWTP at

Wallawatta

To progress

monitoring

Progress review

meeting

12.11.2018 Kirulapone contract To Progress review

Meet Additional

Secretary Land –land

Ministry

12.11.2018 Thalakotuwa PS site To discuss land

acquisition

EIB review mission 19.11.2018 Kirula –Narahenpita

contract

Progress review

Site visit with EIB

review mission

20.11.2018 Kirula –Narahenpita All

sites and Wallawatta

WWTP site

Site monitoring

EIB review mission 21.11.2018 Kirula –Narahenpita

contract

Document review

site meeting 28.11.2018 Kirulapone contract To review of the

Construction

progress

Meeting with

project-affected

people

04.12.2018 Colambage Mawatha PS

site

To hand over the

key of the new

house

Meeting with public

and contractor

06.11.2018 Kirulapone contract To discuss

construction-

related social issue

Monthly progress

meeting

20.12.2018 Kirulapone contract To review

construction

progress and issues

Meeting with Project

Director to the

Colombo Suburban

Railway Project

21.12.2018 Colombage Mawatha

pipe laying site

To discuss the

resettlement issue

of one of rent

family of the site

Site visit with

Deputy Project

Director (ESS) to the

Colombo Suburban

Railway Project

28.12.2018 Colombage Mawatha

pipe laying site

To collect

information on the

one of rent family

of the site

29. The Social safeguard team of the project is rapidly doing compliance monitoring during the

implementation of the construction activities. Table 11 illustrates the events planned for the next

half of the year for compliance monitoring of the site activities.

Table 13- Event planned next Quarter

Page 18: 45148-008: Greater Colombo Water and Wastewater …

17

Contraction site Event

Meeting with TL-DSIDC To discuss Kirula- Narahenpita RP

Meeting Land office –Thibirigasyaya AGA

office

To discuss Thalakotuwa Garden PS land

acquisition

Avarihena pipe laying site –Kirulapone

contract

To discuss people objection of the pipe laying

works

Meeting with AGM- NHDA To discuss the resettlement issue of the NHDA

land leaseholder at Thalakotuwa garden PS site

Discussion with National Housing

commissioner

To collect Thalakotuwa garden survey plan

Meeting with APs To hand over compensation claques for

resettlement

Meeting with AP –colombage Mawatha On resettlement issue

Thalakotuwa garden site visite with

government valuer

To prepare a survey plan

Meeting with GM-NHDA To solve NHDA leased land at Thalakotuwa

garden

Visit new house with AP- Thalakotuwa

garden

To check house condition before resettled APs

Monthly progress review meeting To review the construction progress

Meeting with AP(rent family)- Colombage

Mawatha

To collect information

Thalakotuwa garden site visit with

Government valuer

To collect information to prepare a valuation

for privet lands

GRM meeting To discuss a compensation package for

Colombage Mawatha APs

Meeting at Kirulapone To discuss the public issue

Colombage Mw 4th lane trial pit excavation

site

Site visit, awareness programs

Railway avenue pipe laying works Site visit, awareness programs

Kalinga Mw micro tunneling site Site visit, awareness programs

Poorwarama site Site visit, awareness programs

Kalinga Mawatha PS site Site visit, awareness programs

Thalakotuwa garden PS site i. monitoring of resettled families

ii. follow up the land acquisition of remaining

three lands

iii. awareness programs

Railway reservation (Colombage Mw) relocation of remaining families

30. Project progress has also been reviewed by ADB mid-term review mission on 05.11.2018,

and the mission has visited following construction sites on 07.11.2018.

• Kalinga Mawatha PS site

• 6th lane micro tunneling pipe laying site

• Andarawatta pipe laying site

• Thalakotuwa garden pipe laying site and proposed PS construction land

• Wellawatta WWTP land

Page 19: 45148-008: Greater Colombo Water and Wastewater …

18

ADB mission at Kalinga Mawatha PS site and discussion on construction related issues

ADB mission meeting with PMU staff and the consultant at Project

Page 20: 45148-008: Greater Colombo Water and Wastewater …

19

ADB mission at proposed Wallawatta WWTP site

ADB mission at land of Thalakotuwa garden PS

ADB mission at Andarawatta Rd pipe laying site

ADB mission at land of Thalakotuwa garden pipe laying site

Page 21: 45148-008: Greater Colombo Water and Wastewater …

20

F. Grievance Redress Mechanism (GRM)

31. The contractor shall attend to the complaint with the agreeable solution with the

consultation of the Engineer’s site staff within about three days and inform of the solution to the

APs/Engineer’s site staff/PMU in writing with an agreeable time frame to solve the issue. If the

agreed period is more than a month contractor should update the complainant periodically. If the

fresh complaint reaches the contractor PMU SGRO shall follow up each of these complaints

periodically. If the Contractor fails to solve the complaint within the agreed time frame or lagging to

adhere to the proposed millstones, the complaint shall now be informed the PMU- PD level for

further action. PD shall provide an agreeable solution to the complaint within one week. During this

period the PMU SGRO shall be responsible to update the complainant on the same procedure as

mentioned above. If PMU PD fails to solve the complaint within the agreed time frame or lagging

schedule, the complainant can take up this to the Safeguard Committee (SC) the same procedure

shall precede to an agreeable solution within two weeks, all these statuses shall be informed to the

APs at the appropriate times. If the SC fails to provide an agreeable solution, a complainant may seek

legal action.

Figure 1- GRM procedure

Page 22: 45148-008: Greater Colombo Water and Wastewater …

21

Public complaints

32. Numerous complainants were received regarding environment hazards such as Noise, Dust

Flooding, etc. during construction activities from people who are living around the construction sites

details of the complaints received are in Appendix 2. According to the Project GRM contractor

together with the PMU safeguard team solved all the inconveniencies with the support of relevant

stockholders.

33. As reported in the last SSMR there was a public complaint against to pipe laying in

Allenmathiniyarama Road by residents due to the road being private property. According to the

project scope, the project has the responsibility to lay a pipeline to facilitate to get connected to the

main sewer line of the area to provide a healthy living environment to the residents of the area to

provide a healthy living environment to the people of the area. Therefore, the project had numerous

Residents, Project Director, TL-DSIDC and contractor at the discussion

Page 23: 45148-008: Greater Colombo Water and Wastewater …

22

discussions with residents living along this road with the participation of residents, PMU staff,

consultant and the contractor to explain the importance of having a sewer connection. But residents

requested to fulfill the following requirements to give their agreement on pipe laying on the road. If

the project cannot fulfill the requirements, they demand that they will not be willing to allow to lay

pipe in this road.

34. Inspection of impact on the stability of the roadway and/ or embankment by a reputed third

party before starting the excavation work on the road

Requested ensure all structure for 10 years after construction

Proper traffic management during construction works

Requested to install three Submersible pumps for three houses due to the revers problem the

houses cannot connect to the sewer line.

35. As mentioned in the last SSMR the issue at Allan Methiniaramaya pipe laying site has been

discussed with the higher management of the project in the various technical meeting at EA and IA.

As per the requested by the EA and IA the project has sent a letter including all requirements to the

residents of the said location to get their agreement for the pipe laying works on the road. However,

the residents refused to have a sewer line on their private road. Hence the project decided to delete

this section with the agreement from higher management of the EA and IA accordingly.

36. The residents of the Thalakotuwa garden complained of traffic congestion due to shaft

construction works on the Thalakotuwa garden road during School hours. Therefore, a meeting was

held at Asian International School with the participation of Residents, principals of both Ilma and

Asian international schools, OIC of the traffic Division-kirulapone Police and PMU officials on

31.08.2018 to discuss the issue. Following decisions were made:

Table-14- Summary of the Discussion

Issue Decision

Reduce school dropping vehicle and use

common transport up to school

Both schools agreed

Requested to get service from traffic police to

control traffic during school hours

Traffic police of Kirulapne and contractor agreed

To use proper signboard Contractor agreed

37. The public who are living at Thalakotuwa garden by roads has also logged complaints on

construction-related disturbances to the contractor and in parallel to the Project Director. Hence,

Residents, principals of both Ilma and Asian international schools, OIC of the traffic Division-

kirulapone PMU officials and contractor’s team at the meeting

Page 24: 45148-008: Greater Colombo Water and Wastewater …

23

the Project Director has requested the contractor to fix the meeting with the public & solve the

issue. Accordingly, the meeting was held on 06.12.2018 at Resident Engineer’s field office at

Kirulaopne.

38.

The

contractor

advised to

use proper

construction methodology to minimize construction induce impact such as noise dust vibration and

also advised to solve all complaints on construction induce impact as soon as possible and

complainants agreed.

Table 15- Summary of the grievances recorded and status: 3

Category Grievances

recorded

Number of

complaints

received

Status Decision was

taken

proposed for

resolution of

pending

grievances

Solved pending

Safety Damage to

culvert

01 01 - Prepared

consultation

with

complainants

-

Other

problem

related to

the

constructio

n

Road blocked

during

construction

03

03 - Arranged

proper traffic

management.

Barricade and

signboards at

the proper

locations

-

Public object

to excavation

work

07

07 - Aware people

on the project

construction

-

3 Summary of the all complaint received attached as an annex 02 of the report

Page 25: 45148-008: Greater Colombo Water and Wastewater …

24

activities and

the benefit of

the project

Public

objection on

private road

excavation

04 02 02 Obtained

consent letter

on excavation

after having

consolation

with residence

Send letter and

conducted an

awareness

program on the

project and the

benefit of the

project to get

consent for the

excavation

Public

health

Dust 02 02 - Reduced

generating

dust from

watering and

covering

trucks during

material

transportation

-

Derain block 01 √ -

Noise 01 √ -

Other

problem

Disturb to

exam

02 √ - Discussion with

the management

of the university

is ongoing to

solve the problem

Utility

interruptio

n

Damage to

water,

electricity

lines

24

23

01

Damaged line

rehabilitated

with

coordination

with all utility

agencies

Planed to

rehabilitated with

coordination of

all utility agencies

Traffic

congestion

01 √

-

Structure

damage

House

damage

01

√ -

G. Institutional Arrangement

39. The Ministry of Internal & Home Affairs and Provincial Council & Local Government

(MIHA&PCLG) is the Executing Agency (EA). The Colombo Municipal Council (CMC) is acting as

implementing Agency (IA) of the project. The Project Management Unit (PMU) is supporting to

implementing the project activities with the support of CMC. A project steering committee (PSC) has

been established to oversee the Project.

Diagram 1- Institutional Arrangement

Page 26: 45148-008: Greater Colombo Water and Wastewater …

25

40. Monitoring and Evaluation Unit of the PMU deals with safeguards functions and

resettlement issues and safeguard issues during project implementation period are manage and

coordinated by a Sociologist of the PMU with the support of safeguard team of the PMU and the

safeguarding team of the contractor.

Ministry of Internal & Home Affairs and

Provincial Councils & Local Government

Engineer DMC-

CMC

Employer Representative

Project Director

Consultant DSIDC Project

Management

Unit PMU

Contactor

Country Representative

Design and

Supervision

staff Including

Site Staff Monitoring &

Evaluation (M&E)

Finance Engineering

M&E Officer

Environment

officer

SGRO

Site monitoring

staff

Contractor

implementation

staff including

Environment Officer

Public Relation

Officer

Social Safeguards Team of the project at Kalinga

mw PS site

Social Safeguards Team of the project at 6th

lane Micro Tunnelling site

Page 27: 45148-008: Greater Colombo Water and Wastewater …

26

41. However, as per to the Project Grievances Redress Mechanism Grievances redress

committee has been established to engage construction-related complaint which was not addressed

by the contractor; and some resettlement related issues have also been addressed by the

committee.

Table 16- The GRM committee

Designation Institute Position of

the

committee

Contact

Engineer Drainage District 4 Chairman of

the

committee

Robert Gunawardhana Mw,

Kirulapone, Col. 05

0112512596

Assistant

Director

(Planning)

Ministry of Internal &

Home Affairs and

Provincial Councils &

Local Government

Committee

member

No. 330, Union Place

Colombo 02

0113135188

Sociologist and

Grievance

Redressal Officer

Project Management

Unit

Committee

member

Greater Colombo Water and

Wastewater Management

Improvement Investment

Program,

No. 86, Ananda

Coomaraswamy Mw,

Colombo 07

0112665331

[email protected]

CBO Leader Affected Community (if

any)

Committee

member

-

42. As cited in the resettlement plan and the EMP following safeguard team has been employed

by the contractor to minimize social safeguard issues during construction activities.

• public Relation Officer

• environment Manager

• safety Manager

• Traffic Manager

Page 28: 45148-008: Greater Colombo Water and Wastewater …

27

This team has played a key role to mitigate construction-related safeguard issues with the support

of other stockholders.

H. Monitoring Results – Findings

43. The grievance Redress Committee was established for in project area and the contractor

advised to record and attend all complaints, suggestions, and requests of the public and other

stakeholders of the construction area. Complaint register has been kept at all sites and contact detail

of the relevant officials has also been published at all sites.

44. Following milestone have been encountered during the implementation of the safeguarding

work as mention in the resettlement plan.

Table 17- Milestone of the safeguarding work

Monitoring indicators Remarks

Funds for resettlement released on schedule Resettlement funds allocated by the GOSL

component and available and released on

schedule.

Sites prepared on time for the start of

construction

• Kalinga Mawatha PS site

• pipe laying sites

• pipe laying site at Railway Reservation

• Thalakotuwa Garden PS site

This site has been prepared on time and handed

over to the contractor on time to start

construction of PS

All sites except Railway reservation have been

handed over to the contractor to start pipe

laying works.

Due to Kaleni wally Railway line, there was

some delay to hand over railway reservation to

the contractor

Due delay of the land acquisition there are

some delay of the land hand over to the

contractor to start construction of PS

APs received entitlements according to

amounts and program specified in RP

All compensation have been paid before

resettled AP form the site

Compensation provided before loss incurred All compensation have been paid before

resettled AP form the site

Arrangements for livelihood provided to

vulnerable APs

All compensation have been paid before

resettled AP form the site

Public meetings held to disclose impacts and

entitlements

Affected people have been aware of impact and

entitlement before start resettlement

Meetings with individual APs to agree with the

compensation

Affected people have been aware of impact and

entitlement before start resettlement

h1. Land acquisition and resettlement

45. As mentioned in section D of this report all compensation package including new houses

were given to the affected people before resettling them at the new place. It is observed that all

affected people are very much happy with their new house and the new lifestyle comparing their

Page 29: 45148-008: Greater Colombo Water and Wastewater …

28

previous houses and lifestyle. Currently, they are fully settled with a new lifestyle with the support

of UDA management and the project. The project safeguard team still in line with relocated peoples

to assistance their new life in a new location.

h2. Socio-Economic Development of the Project area

46. The project is not only doing construction works

but also facilitate social and cultural activities of the

area.

Table 18 - Progress of the resettlement activities

Activities Planned Actual Pending

Resettlement of

the Aps

Kalinga MW PS site

02 and 1 garage

(August – Sep.

2017)

03 Nil

Thalakotuwa garden PS

site

06 (August

2017)

03

(March 2018)

03

Railway reservation site 4 (August 2017) 04(December

2018)

Nil

Payment for

business losses

Kalinga MW PS site

03 03

Nil

Thalakotuwa garden PS

site

01 01 Nil

Railway reservation site 02 01 Nil

Private Land

acquisition

Thalakotuwa garden PS

site

03 - 03

I. Compliance Status

47. The status of compliance with loan covenants concerning social safeguards as at 31st

December 2018 summarized as bellow

Table 19- Compliance with loan covenants

Reference Description Status as at 1st July to 31st

December 2018

Happy life in the new house- Mr Asithambi and his family at the new house

Page 30: 45148-008: Greater Colombo Water and Wastewater …

29

Schedule 5 para, 10 Land acquisition and involuntary

resettlement

All land acquisition and resettlement

activities are implemented in

compliance with (a) all applicable laws

and regulations of the Borrower

relating to land acquisition and

involuntary resettlement; (b) the

involuntary resettlement safeguard; (c)

the RF; and (d) all maters and

requirements outlined in the

respective RP. and any corrective or

preventive actions outlined in a

Safeguard Monitoring Report

Resettlement of Kalinga Mw

PS completed, Thalakotuwa

garden PS and railway

reservation resettlement in

progress; Land acquisition of

Thalakotuwa garden PS in

progress

Schedule 5; para 5 Grievance Redress Mechanism

The Borrower shall have a grievance

redress mechanism for the projects

under the investment program.

acceptable to the ADB, to receive and

resolve complaints/ grievances or act

upon the report from stakeholders on

misuse of funds and other

irregularities, including grievance due

to resettlement. the Borrower shall (a)

make public of the existence of this

grievance redress mechanism;(b)

review and address grievance of

stockholders of the projects under the

investment program, concerning either

the project, any of the service

providers; or any person responsible

carrying out any aspect of the

subproject; and (c) proactively and

constructively responding them.

The GRM has been

established for all packages

Awareness meetings have

been conducted for

Stockholders and the public.

During the reporting period,

no complaints had been

received to GRM. the

contractor has attained all

complaints and requests

Schedule 5 para 7 Involuntary resettlement

All land and right of way under the

schedule agreed under the related

works contract required for a

subproject are made available to the

works contractor and all land

acquisition and resettlement activities

are implemented in compliance with

(a)all applicable laws and regulations of

the borrower relating to land

acquisition and involuntary

resettlement; (b)the involuntary

resettlement safeguards; and (c) all

measures and requirements outlined in

the RP and a corrective or preventive

actions outlined in the Safeguards

Monitoring Report

Resettlement of Kalinga Mw

PS completed Thalakotuwa

garden PS and railway

reservation resettlement in

progress; Land acquisition of

Thalakotuwa garden PS in

progress.

Schedule 5 para 14 Safeguards Monitoring and Reporting

(a) Submit semiannual safeguards

Semiannual safeguards report

has been submitted to the

Page 31: 45148-008: Greater Colombo Water and Wastewater …

30

monitoring reports to ADB for

discloser on ADB’s website,

and disclose relevant

information from such reports

to affected persons promptly

upon submission.

(b) if any anticipated

environmental and/or social

risk s and impacts arise during

construction, implementation

or operation of the project that

were not considered in the IEE,

the EMP or the RP as

applicable, promptly inform

ADB of the occurrence of such

risks or impacts, with detailed

description of the event and

proposed corrective action

plan; and

(c) report any actual or potential

breach of compliance with the

measures and requirements

outlined in the EMP or the RP

promptly after becoming

aware of the breach

ADB and disclosed on ADB

website

Up to now, there are no

anticipated environmental

and/or social risks and

impacts arisen during

construction hence there no

corrective plan.

There no any breach of

compliance

J. Follow up Actions, Recommendation, and Disclosure

48. Resettlement activities of the Kalinga Mawatha PS site 100% completed all compensation

and houses were provided for the affected people. Resettlement works at Thalakotuwa garden PS

site and railway reservation (Colombage Mw) site 50% completed compensation and the houses

were provided to resettled people. Two lands acquisition of the Thalakotuwa PS site is in progress by

line Ministry.

49. GRM has been established for the project and engaging grievances if any during construction

activities. GRM mechanism and the committee as an appendix 3. As per the contract agreement the

contractor, bound to attended construction-related complaints and up to now contractor safeguard

team has handled complaints satisfactorily.

Appendix 1

i. List of Affected Persons and Entitlements

Site name Name of the AP Address Entitlements Status

Kalinga

Mawatha PS

site

S. Selladore No.30/40, Kalinga

Mw, Polhengoda

House from UDA flat

Transport cost

Livelihood assistant

Payment for loss of

income

Resettled

Page 32: 45148-008: Greater Colombo Water and Wastewater …

31

W.A. Thilak

Rohana

No 30/40 1,

Kalinga Mawatha,

Polhengoda,

House from UDA flat

Transport cost

Livelihood assistant

Resettled

R.G.B.A. Kumara

Siriwardhana

30/40/C Kalinga

Mawatha,

Polhengoda

Replacement cost

Transport cost

Compensation for Loss of

income

Resettled

J.P.H. Padmasiri

Mahinda

30/41/22, Kalinga

Mawatha,

Polhengoda,

Colombo-5

Alternative land for cattle

yard

Provided

Thalakotuwa

garden PS

site

K.V. Asaithambi 154/11/A

Sri Saddarma Mw

Kirulapone

House from UDA flat

Transport cost

Livelihood assistant

Resettled

R. Pryadharshani 154/11

Sri Sddarma Mw

Kirulapone

House from UDA flat

Transport cost

Livelihood assistant

Resettled

R.A. Prasanna

Perera

152 Sri Sddarma

Mw

Kirulapone

House from UDA flat

Transport cost

Livelihood assistant

Loss of income

Resettled

V. VadiwellAchchi 154, Sri

Siddhartha Road,

KIrulapone,

Colombo 5

Compensation for land

and house

Under the

land

acquisitio

n process

Suppiya Welu 154/12, Sri

Siddhartha Road,

KIrulapone,

Colombo 5

Compensation for house Under the

land

acquisitio

n process

W. R. Grace 114G Sri

Siddhartha Road,

KIrulapone,

Colombo 5

Compensation for land

and house

Under the

land

acquisitio

n process

Railway

Reservation

(Colombage

Mawatha)

M.D. Sriyani 29/53 F D.M.

Colambage Mw

Kirulapone

House from UDA flat

Transport cost

Livelihood assistant

Loss of income

Resettled

K.A. Kasun Gayan 29/53 D.M.

Colambage Mw

Kirulapone

House from UDA flat

Transport cost

Livelihood assistant

Loss of income

Resettled

Chandrawathi 29/57 D.M.

Colambage Mw

Kirulapone

House from UDA flat

Transport cost

Livelihood assistant

Resettled

S. Saraswathi

Kandhaiyah

29/53A D.M.

Colambage Mw

Kirulapone

House from UDA flat

Transport cost

Livelihood assistant

Resettled

ii. Summary of RP/IPP with entitlement matrix

Page 33: 45148-008: Greater Colombo Water and Wastewater …

32

Summary of the Resettlement Plan

Laying and construction of Gravity Sewers, Force Mains and Pump Stations of Kirulapone

Catchment Area within Colombo Municipality

Greater Colombo Water and Wastewater Management Improvement Investment Program

Project 3 (GCWWMIIP-P3)

Loan Number: 3348/3349 SRI

Project Number: 45148-008

CONTENT

I.Project Discription ................................................................................................................... 36

ii.Scope of Land Aquisition ..................................................................................................... 4237

iii.Socio Economic Imfrmation and Profile ............................................................................... 4537

iv. Information Discloser……………………………………………………………………………………………………………..40

v. Grievance Redress Mechanism………………………………………………………………………………………………..41

vi. Legal Framework…………………………………………………………………………………………………………………….42

vii. Entitlement, Assistance and Benefit……………………………………………………………………………………….42

viii. Compensation Mechanism……………………………………………………………………………………………………45

ix. Resettlement Budget and Financing Plan………………………………………………………………………………..46

x. Monitoring and Reporting ……………………………………………………………………………………………………….48

Abbreviations

ADB - Asian Development Bank AP - Affected person CMC - Colombo Municipal Council DSC - Design and Construction Supervision Consultants DSC-RS -Design and Construction Supervision Consultants - Resettlement Specialist DSIDC - Design, Supervision and Institutional Development Consultant EA - Executing agency GCWWMIIP-P2 - Greater Colombo Wastewater Management Improvement Investment Programme - Project 2

Page 34: 45148-008: Greater Colombo Water and Wastewater …

33

PD - Project Director RP - Resettlement Plan SC - Safeguard committee SIE - Social Impact Evaluation UDA - Urban Development Authority

i. Project Description.

1. Background of the Project: The Greater Colombo Water and Wastewater Management

Improvement Investment Program – Project 3 (the Investment Program) will complement the efforts

of the Government of Sri Lanka to improve water supply and wastewater services to the residents of

Greater Colombo. It will also assist the Government in introducing institutional and regulatory

reforms in the sector, particularly in Greater Colombo.

2. The Greater Colombo Water and Wastewater Management Improvement Investment Program-P3

(GCWWMIIP-P3) aims at delivering efficient and reliable urban water supply and sewerage services

in the Greater Colombo area. The impact of the Investment Program will be improved quality of life

for the residents of Greater Colombo. This RP focuses only on the Waste Water component of the

GCWWMIIP-P3. The expected outcome of the Waste Water Component of the overall project will be

improvement wastewater service and management efficiency in Greater Colombo. The expected

outputs this component of the overall project are: (i) rehabilitated and expanded wastewater

network in South and North Catchment Area of Colombo City; (ii) construction of secondary

wastewater treatment plant in the South Catchment Area of Colombo City at Wellawatta and (iii)

strengthened institutional structure and capacity of service provider. The project is to be

implemented over four (4) years, from 2016-2020.

3. The executing agency of the project is the Ministry of Internal & Home Affairs and Provincial

Councils & Local Government (MIHA&PCLG). The implementing agency is the Colombo Municipal

Council (CMC). Project Management Unit (PMU) has been already established by the implementing

agency (CMC).

4. The sub-project: The Kirulapone sub-project spans in Kirulapone, Pamankada East and in part of

Kirula- Narahenpita area, the administrative wards of Colombo Municipality. The project work

comprises of laying 29.40 km of sewer pipelines and construction of two pump stations and

connected force mains. Pipe-laying is limited to 49 sub-project road sections and the lanes linked to

these main 49 sub-project road sections. Two pumping stations have been planned to establish near

Kalinga Mawatha and the other in Talakotuwe Garden at the Kirulapone area.

Table 1: 49 sub-project road sections

Index Number

(assigned by

sociologist)

Road Name

Index Number

(assigned by

sociologist)

Road Name

1 Edmonton Road

26 High-level Road

2 Kirillapone Avenue

27 Balahenmulla Lane

3 Polhengoda Gardens

28 Nagaspura Mawatha Road

4 Idama Mawatha

29 Balapokuna Road

5 Athula Place

30 Balapokuna Place

6 Arnold Place 31 1st

Lane – High-level Road

Page 35: 45148-008: Greater Colombo Water and Wastewater …

34

Index Number

(assigned by

sociologist)

Road Name

Index Number

(assigned by

sociologist)

Road Name

7 Thalakotuwa Gardens

(One of the pumping stations

proposed)

32 Railway Avenue

8 Somadevi Place

33 Robert Gunawardena

Mawatha

9 Sri Siddhartha Path 34 De Costa Garden

10 Sri Siddhartha Passage

35 Gajaba Place

11 Temple Road

36 Mahawela Place

12 Vijaya Kumaratunga

Mawatha

37 Luxman Place

13 Andarawatta Road

38 Mahinda Place

14 Averihena Road

39 Mugalan Road

15 Allen Methiniyarama Road

40 Nandimitra Place

16 Polhengoda Terrace

41 Suranimala Place

17 Devika Gardens

42 Purana Vihara Road

18 Lionel Edirisinghe Mawatha

43 Jayasinghe Road

19 D. M. Colambage Mawatha (

One of the places where

resettlement issues would

emerge)

44 Kavinda Place

20 Kalinga Mawatha ( one of the

Pumping stations located)

45 Halgaswatte Lane

21 6th

Lane – D. M. Colombage

Mawatha

46 Stratford Avenue

22 Siebel Avenue 47 Sri Siddartha Road

23 Rajawatta Terrace

48 Aramaya Road

24 Poorwarama Mawatha

49 Baseline Road

25 Sangabo Place

- -

5. Resettlement Plan. The laying of sewer line and construction of two pump stations for the

Kirulapone area is one of the major components of the project 3 for which feasibility report has been

prepared. This RP is an updated version of the RP prepared during the feasibility study. The RP is

prepared following the requirement of ADB’s Safeguard Policy Statement 2009, and the Government

of Sri Lanka laws (NIRP 2001).

6. Population in the sub-project roads’ vicinity: the area is the density of the population and

during peak hours roads are full of traffic but off time there are less traffic and houses and privet and

public institutes located about 5 to 8 meter away from the road center. Most of the lands of the area

are privet with freehold title and other lands belonging to the government (CMC, NHDA, and UDA)

Page 36: 45148-008: Greater Colombo Water and Wastewater …

35

7. Existing sewerage disposal system in the sub-project area: The area under this sub-project

is not served by the Municipal council provided sewerage system. The residents have their systems

established for the disposal of sewerage. An insignificant number of home gardens the existing

sewerage pits overflow during rainy days. Some householders discharge the overflowing wastewater

from the sewerage pits to the nearby stormwater canals. Not only discharging overflowing

wastewater to the common water bodies but also some householders have directly connected their

sewerage lines to the stormwater canals. This has created critical health issues in the area. The

environment becomes polluted and odor problems are common during rainy days. The stormwater

ditches located in the interior areas of the Under Served Settlements (USS) in the Kirulapone area

are contaminated with wastewater and solid waste and odor are not confined only to rainy days.

8. Resettlement issues: Implementation activities in Kalinga Mawatha pumping station will

create IR impacts 4 families ( 2 residential structures and 1 building exclusively used for a garage,1

family keep cattle in small piece of land within sub-project land, the house of the cattle owner will

not be affected), Pipe laying activities in D.M. Colombage Mawatha near Kirulapone rail station will

result to displace 5 families ( 3 residential structures and 2 housing structures used for residential

cum business activities) and Talakotuwe Pumping station at Talakotuwe Garden road area will result

to displace 7 families in 6 housing structures ( 5 residential structures and 1 residential cum business

structure). The UDA has expressed its willingness to accommodate the evacuated families in sub-

project road areas (Kalinga Mawatha, railroad reservation and Talakotuwe Garden area) in their

newly established Condominium. Therefore, the GCWWMIIP develops this RP and commits to

providing necessary funding and other supports to resettle the sub-project affected families in UDA

built condominium. The PMU of GCWWMIIP will monitor the resettlement and post resettlement

process during the project period.

9. The command areas in some of the sub-project roads are densely populated. There will be

serious access difficulties in such roads during the construction period. Similarly, some other roads

are significantly congested with high traffic. Nearly 13 of 49 sub-project roads are narrow and access

difficulties are presently experienced during peak hours.

Location of the resettlement

Figure 1: Map of the pumping station in Kalinga Mawatha

Page 37: 45148-008: Greater Colombo Water and Wastewater …

36

Figure 2: Map showing the Thalakotuwa Garden with 6 affected houses

Figure 3: Map showing the Railway Reservation 4 affected houses

C. Scope of Land Acquisition and Resettlement

10. The scope of the land acquisition and the resettlement impact identified based on the field

visit during the design stage and project implementation stage. Proposed involvements and

potential IR impacts are attached in Appendix- 01 of this report sub-component-wise.

11. During the design stage, all efforts have been made to avoid or minimize resettlement

impact through careful design of pipe alignments through available government land and the

existing public road. Therefore, The Project's physical construction works in 49 road sections do not

require land acquisition. Land acquisition is required for two pumping stations at Thalakotuwa

Garden and Kalinga Mawatha, and one pipe laying road section in D.M. Colombage Mawatha. All the

lands except two private plots of lands in Talakotuwa Garden pumping station are government lands

Page 38: 45148-008: Greater Colombo Water and Wastewater …

37

(land in D.M. Colombage Mawatha belong to Department of Railway, Kalinga Mawatha PS land

belongs to UDA and Thalkotuwa garden land belong to NHDA).

12. At the project design stage, it was identified resettlement issues in 3 locations at Kalinga

Mawatha & Thalakotuwa garden PS sites and on D.M. Colombage Mawatha pipe laying site. The land

at Kalinga Mawatha PS site was occupied by two households one business place and one cattle-yard,

Thalakotuwa garden land occupied by seven families in six households (two families in one house)

and D.M. Colombage Mawatha pipe laying site occupied by five householders.

D. Socio-Economic Information

Table 2-Socio economic features of families to be evacuated for Kalinga Mawatha Pumping station

Socio-economic

features Family 1 (House 1)

Family 2 ( Garage

only)

Family 3 ( Cattle

shed owner) Family 4

Name of the

chief

householder

(CHH)

W.A. Thilak

Rohana

R.G.B.A. Kumara

Siriwardhana

J.P.H. Padmasiri

Mahinda

S. Selladore

Family size 5 5 4 5

Monthly income

of the family

Rs 70,000 (Chief

householder Rs

40,000 and

income from

renting out of a

Garage-Rs30,000 )

Rs. 30,000 (only

from employment

of chief

householder)

Rs 29500

(Husband

25,000+wife

4500)

Chief householder

Rs 20,00+ First

Son Rs 15,000

Per capita

monthly income

Rs14,000 Rs. 6000 Rs. 7375 Rs7000

Address & other

identification

details

No 30/40 1,

Kalinga Mawatha,

Polhengoda,

Telephone

number-

0725378232 (NIC

No 693150930 V )

30/40/C Kalinga

Mawatha,

Polhengoda,

Telephone No

0711438398 (NIC-

No 770461812V)

30/41/22, Kalinga

Mawatha,

Polhengoda,

Colombo-5

30/40, Kalinga

Mawatha,

Polhengoda

Type of Land Public Public Public Public

Type of affected

property

The entire house

and entire Garage

Entire house cum

Business center

Piece of public

used to keep

cattle

House only

Use of affected

property

Residence houses

and rented out

Garage

Residence and

Business

Residence not

affected

Residence

Table 3.Socio economic profile of affected 4 families at Railroad reservation on D.M. Colombage

Mawatha

Socio-

economic

features

Family 1

(House 1)

Family 2 Family 3 Family 4 Family 5

Name of the

chief

W.A.Chnadraw K.A.Kasungayan S.Saraswathie M.D.Sriyani I.D.Chathurika

Page 39: 45148-008: Greater Colombo Water and Wastewater …

38

Socio-

economic

features

Family 1

(House 1)

Family 2 Family 3 Family 4 Family 5

householder

(CHH)

athie Kandaiyah Sandamali

Family size 1 1 5 2 2

Monthly

income

Rs 20,000/=

(from chief

householder’s

boutique

Rs.21,000 Rs. 26,000 (Rs

8000 from Chief

householder

and 18, 000

from Grand Son

Rs 40,000

(20,000 from

Chief

householder

and 20,000

from Son)

Rs.25,000 (

Spouse Male)

Per capita

family income

Rs.20,000 Rs. 21,000 Rs.5,200 Rs.20,000 Rs.12,500

Address &

other

identification

details

29/57, D.M.

Colombage

Mawatha,

Colombo 5,

Telephone

0778157575,

NIC No

537860065V

29/53, D.M.

Colombage

Mawatha,

Colombo 5,

Telephone

0725903906,

NIC No

872484647V

29/53 A (

railway station

Mawatha), D.M.

Colombage

Mawatha,

Colombo 5,

Telephone

0715870463,

NIC No

465672951X

29/53 F, D.M.

Colombage

Mawatha,

Colombo 5,

Telephone

0115756260,

NIC No

657750956 V

29/57 B,

Colombage

Mawatha,

Colombo 5,

Telephone

0727447653

Type of land

they live

Public

(reservation of

railroad)

Public

(reservation of

railroad)

Public

(reservation of

railroad)

Public

(reservation of

railroad)

Public

(reservation of

railroad)

Use of the

house

Residence cum

Business

Residence Public

(reservation of

railroad)

Residence

cum Business

Residence

Table 4- Socio-economic profile of affected 6 families at Thalakotuwa garden PS site

Socio-

economic

features

Family 1

(House 1) Family 2 Family 3 Family 4 Family 5 Family 6

Family 7

Name of the

chief

householder

(CHH)

V.Vadiwel

Achchi

K.V.Asaitham

bi (female)

R.Priyadarsha

ni

Suppaiya

Welu

W.R.Grace R.A. Prasanna

Perera

Shasikala

Welu

Family size 4 6 2 7 2 6 04

Monthly

income

Rs 6000/= Rs.35,000 Rs 42,000 Rs 148,000/= Rs 25,000/= Rs 40,000/= Rs 130,000/=

Per capita

family income

Rs1500/= Rs.5833 Rs.21,000 Rs21142 Rs12,500 Rs.6660 Rs.32,500

Address &

other

identification

details

154, Sri

Siddharth

a Road,

KIrulapon

Sri Siddhartha

Road,

KIrulapone,

Colombo 5

154/11,

Siddhartha

Road,

Kirulapone

154/12,

Siddhartha

Road,

Kirulapone

114 G, Sri

Siddhartha

Road,

Kirulopone,

152, Sri

Siddhartha

Road,

Kirulapone,

154/12,

Siddhartha

Road,

Kirulapone(

Page 40: 45148-008: Greater Colombo Water and Wastewater …

39

Socio-

economic

features

Family 1

(House 1) Family 2 Family 3 Family 4 Family 5 Family 6

Family 7

e,

Colombo

5

Colombo-5 Colombo-5 living with

parents as a

subfamily)

Type of

community

Legal

resident

Squatters Squatters Squatters Legal

Resident

Squatters Squatters

Type of land

they live

Private Public Public Public Private Public Public

Use of the

house

Residence Residence Residence Residence Residence Residence

cum Business

Residence

13. The Mitigatory measures planned to implement: project-affected total families 15 will be

resettled with compensation under the resettlement policies of the country and the ADB. One of the

other 2 families is involved in running a business venture, garage in a building structure and one

person using a small piece of UDA owned project land as cattle keeping yard but, not living in the

proposed project land even there is no structure in the land. The operational activities of the Garage

(three wheeler repair place) are carried out by a person, a Bachelor on informal mutual agreement

between the owner and the present operator. The Owner of the Garage is living in UDA provided

house at Dematagoda. Therefore, the owner will only be paid compensation for the loss of structure

and business activities and they will not be resettled in the UDA condominium. UDA agreed to

provide alternative land to the cattle yard owner to keep cattle before start the construction

activities. The GCWWMIIP will have the Urban Development Authority’s (UDA) support to resettle

the affected 15 families in their newly built condominiums. Two families privet lands owners of 6 in

Talakotuwe Garden will be given the option to select either to get resettled in UDA built

condominium or to resettle in an area which they prefer.

14. The entitlement matrix has been developed and included in this RP following the policies of

the ADB (2009) and the Sri Lankan government on resettlement (NIRP-2001). The compensation will

be paid for the affected persons before the commencement of the sub-project implementation

activities in their areas. If the resettlement will get delay rental allowances will be paid for affected

families to stay temporary in rented in houses until they are resettled in UDA condominium.

15. Measures will be implemented to address the problems of impact on street vendors and

three-wheel operators and privet and public institute during the project implementation period.

Steps will be taken to minimize the likely negative impacts on road-based livelihood activities and

other disturbances. And also project will take necessary action to mitigate negative impact during

construction activities such as environmental issues, traffic and access difficulties with the support of

the contractor.

16. The construction contractors will be made legally responsible to repair any damages caused

to the structures located in the construction sites due to their activities. This will indirectly influence

the construction contractors to carry out their activities with extreme care to the properties in the

construction sites

17. There will not any negative impacts on poor, indigenous and /or ethnic minorities, and other

vulnerable groups.

E. Information disclosure, consultation, and participation

Page 41: 45148-008: Greater Colombo Water and Wastewater …

40

18. Information and dissemination and disclosure have been a continuous process of the

project. The Social safeguard team of the project will continue consultation, information

dissemination disclosure with support to DSIDC consultant and the contractor’s safeguard team. The

finalized RP will be disclosed in ADB’s web site and available Ministry and the project office. Project

information will be continually disseminated through the discloser of the resettlement planning

document and then update the document. Information on compensation, entitlement and

resettlement planning, management principals and monitoring will be available in the local language

and distribute to the affected parties.

Table 5- Mitigation measures suggested addressing the difficulties of community

Impact Suggested mitigation measure

• Transportation and access

difficulties

• Difficulties faced by vehicle users

• Road sections should be used stage by stage

(staggered construction) without excavating the entire

area at once for laying pipes.

• Construction work should be completed in a speedy

manner

• Exploring all the possibilities to use alternative access

roads

• Conducting construction activities during night hours

(only in suitable sub-project’s road sections).

• Explore possibilities to apply trenchless technology in

laying pipes (especially, in narrow roads).

• Effective management of the project site (clearing the

road, providing steel plates as temporary entrances to

houses during construction period)

• Providing safe vehicle parks during the construction

phase

Table 6- Actions to mitigate potential impacts on Economic centers

Impact Suggested mitigation measure

• Customers will not be able to park their

vehicles

• Road congestion

• Providing temporary access roads to the

establishments

• Conducting construction work during night

hours

• Adaption of advanced technology to install

sewer lines without huge damages to roads

• Effective traffic management during the

construction phase

• Completion of project work in a speedy

manner

Page 42: 45148-008: Greater Colombo Water and Wastewater …

41

F. Grievance Redress Mechanisms

19. The GRM aims to provide a time-bound transparent mechanism to resolve project-related social

and environmental issues. All grievances linked to the project will be registered.

20. Affected parties at the project site can complain about the grievances to the contractor’s Public

Relation Officer and if not addressed such issues can be forwarded to the PMU Sociologist. If

Grievances are not addressed at the project sociologist level or if the solution is not agreed by the

AP, such issues can be referred by the Project Director to the Safeguards Committee of the project.

GRM process is depicted in FIG.3. The GRM process will not remove the right of the APs to the

recourse of legal action to address issues related to resettlement.

Diagram 1- Complaint handling process

Page 43: 45148-008: Greater Colombo Water and Wastewater …

42

G. Legal Framework

21. The Resettlement Plan of the sub-project is developed based on the principles and legal

provisions laid down in The Land Acquisition Act, 1950 (LAA, amended from time to time) and the

National Involuntary Resettlement Policy, 2001 (NIRP). The principles of the NIRP are largely

consistent with ADB’s Policy on social safeguard, ADB SPS 2009.

22. Laws and Policies on the resettlement of Government of Sri Lanka. According to the

National Resettlement Policy (NIRP); involuntary resettlement addresses social and economic

impacts on permanent or temporary and (i) caused by acquisition of land and other fixed assets, (ii)

by change in the use of land, or (iii) restrictions imposed on land as a result of the Project.

H. Entitlements, Assistance and Benefits

23. According to the context of ADB SPS 2009 and the NIRP, all affected persons (APs) are

physically relocated who are living at three locations of the area both Kalinga Mawatha,

Thalakotuwa garden PS sites and Colombage Mawatha pipe laying site. In the absence of formal and

legal title to the land affected person does not receive compensation for the land but they are

entitled to receive compensation for the structure and other compensation relevant to the

resettlement. If there are any vulnerable Aps eligible for the additional compensation and

assistance and also if they interested they are given priority in employment in project-related

construction activities. Type of losses and Entitlement summarized based on both government and

ADB policies and resettlement principals.

Table 7- Entitlement Matrix

Type of Loss

Definition of

Entitled

Person

Provision / entitlement Compensation

Policy

Implementation

Issues /

Responsible

Agency

Demolition of

structures

Title owners

or the users of

the structures

( who have

built them)

All (cash) payments for

Private land and

structure will be made at

replacement costs.

All payments at

replacement cost in

material, cash, or a

combination of both

according to the actual

loss to repair or rebuild

the structure to an

original or better

condition when

remaining land sufficient

to rebuild upon;

Involuntary

Resettlement,

2001- ADB SPS

2009,

Payment for

lost assets,

assistance to

reorganize on

existing land

or relocate on

alternate land

and support

for a transition

period.

CMC with

guidance from

the Ministry of

local

government

and PMU will

implement the

recommended

actions in the

RP.

permanent

impact on the

livelihood

Business

owners who

are losing

business

All (cash) payments for

loss of income will be

made.

APs will be provided

compensation for loss of

income and provided

assistance to find a

Involuntary

Resettlement,

2001- ADB SPS

2009,

Payment for

loss of income

or livelihood

With the

guidance from

the Ministry of

Local

Government

and PMU will

implement the

Page 44: 45148-008: Greater Colombo Water and Wastewater …

43

Type of Loss

Definition of

Entitled

Person

Provision / entitlement Compensation

Policy

Implementation

Issues /

Responsible

Agency

suitable place to original

or better condition when

remaining to continue

income generation

activities.

source at full

replacement

cost.

recommended

actions in the

RP.

Evacuation/displac

ement of families

from their

residences

House owners

stay in the

affected

houses

Relocation of the

affected families in

suitable alternative

houses

Payment of all

the required

cost for

evacuation

and

resettlement,

Renters will be

paid shifting

allowance to

shift their

household

items to other

locations

CMC with

guidance from

the Ministry of

local

government

and PMU will

implement the

recommended

actions in the

RP with support

from UDA.

Temporary loss of

secure parking

space

Residents and

business

owners losing

access to

private

parking

spaces, and

vehicle

owners losing

access to

secure parking

lots.

Assistance to access to

secure parking lots

30 days

advance

notice

regarding

construction

activities,

including

duration and

type of

disruption.

Where

Contractor's

actions cannot

address the

loss, affected

persons (APs)

will be

provided

secure parking

space

(sufficiently

cordoned and

provided with

security

guards) in

sections of the

road which

will be closed

during

construction.

Identification of

sufficient space

for an

alternative

parking facility.

APs will be

determined by

the PMU

through the

survey and will

be provided

with

identification

cards which will

allow access to

the temporary

parking facility.

The temporary

parking facility

will identify ID

numbers

eligible to park

based on the

section where

construction is

being

undertaken.

Temporary Legal 30 days advance notice Same as above

Page 45: 45148-008: Greater Colombo Water and Wastewater …

44

Type of Loss

Definition of

Entitled

Person

Provision / entitlement Compensation

Policy

Implementation

Issues /

Responsible

Agency

disruption of

livelihoods

titleholders,

non-titled

mobile

hawkers and

three-wheel

operators

parked their

vehicles in the

sub-project

area

regarding construction

activities, including

duration and type of

disruption.

Where Contractor’s

actions cannot ensure

there is no

income/access loss4, APs

will be assisted to

temporarily shift for

continued economic

activity.5 Identification of

alternative temporary

sites to continue an

economic activity.

PMU will

determine

hawkers

entitled to

assistance

through the

survey and will

be provided

with

identification

cards.

Temporary

disruption of

livelihood

Legal

titleholders,

non-titled

immovable

business

owners/opera

tors

30 days advance notice

regarding construction

activities, including

duration and type of

disruption.

Where Contractor’s

actions cannot ensure

there is no

income/access, APs will

be provided

compensation for lost

income or a transitional

allowance for the period

of disruption whichever

is greater.

Same as above APs will be

determined by

the PMU

through the

survey and will

be provided

with

identification

cards. The

survey will

determine

income loss.

Temporary impacts

on common

resources

Common

resources

(Communities

)

Replacement or

restoration of the

affected community

facilities – including

public water stand posts,

public utility posts,

shrines, etc.

Same as above PMU and

Contractor.

Impacts on

vulnerable Aps

Vulnerable

APs (All

impacts)

Vulnerable households

will be informed of all

project construction

employment

opportunities, The PMU

Same as

above.

PMU will

determine

vulnerable APs

and provide

information on

4 This includes: (i) leaving spaces for access between mounds of soil, (ii) providing walkways and metal

sheets to maintain access across trenches for people and vehicles where required, (iii) increasing the workforce in front of critical areas such as institutions, (iv) consulting business and institutions regarding operating hours and factoring this in work schedules, (v) providing advance information on works to be undertaken including appropriate signages, and (vi) coordination with CMC traffic authorities for necessary rerouting of traffic and traffic management, and ensuring appropriate signages and policing of traffic. 5 For example assistance to shift to a side of the road where there is no construction or to the location

where traffic will be diverted.

Page 46: 45148-008: Greater Colombo Water and Wastewater …

45

Type of Loss

Definition of

Entitled

Person

Provision / entitlement Compensation

Policy

Implementation

Issues /

Responsible

Agency

and UDA will consider

them as a special group

to be entitled to special

assistance during

resettlement ( e.g.

Providing alternative

housing units in the

ground floors of

condominium to the

disable; APs),

all project

construction

employment

opportunities.

VIII. COMPENSATION MECHANISM

24. Affected unauthorized structures at both Kalinga Mw and Thalakotuwa garden PS sites will

be given houses at newly built condominium by URP-UDA. Affected two plots of private land will be

paid replacement cost.

25. The project will also ensure if there are damages private property will pay replacement/

rehabilitation cost. Compensation for the in movable property includes i) Land: compensation at

replacement cost for private land based on the valuation given by Government Chief valuer’s

valuation ii) Structures: newly built houses from condominium as per the compensation for the loss

of structure and other relevant replacement cost based on the market value and recommendation

given by the GRC.

I. Resettlement Budget and Financing Plan

Table 8- Resettlement Budget

No Compensation

for the type of

loss

Quantity Duration Total amount

Rs. Million

The total

cost of Rs.

Million

Remarks

01 Unauthorized Residential Structure

Fully affected

structure

12 Permanent 3.5 Million per

structure for 10

4 Million per

structure for 02

35

8

Appendix 07 &

08

02 Private land acquisition

Fully affected

Lands with

structure

02 Permanent Million/perch

for 4.08 perchs

20.4 Appendix 09

Page 47: 45148-008: Greater Colombo Water and Wastewater …

46

Transport cost to

transport

household goods

from present

houses to new

housing units

02 Lump-sum 5000 per one

truck

0.010 refer

Methodology

applied in

calculating

compensations

Livelihood

assistance for AP

families

02 7 days 1000 per day 0.014 refer

Methodology

applied in

calculating

compensations

03 Relocation

Transport cost to

transport

household goods

from present

houses to new

housing units

14 Lump-sum 5000 per one

truck

00.070 refer

Methodology

applied in

calculating

compensations

Livelihood

assistance for AP

families

14 7 days 1000 per day 00.098 refer

Methodology

applied in

calculating

compensations

04 Loss of livelihood –permanent

Permeant

disruption of

income

01 garage 12 months 30,000.00 per

month

00.360 Please refer

Methodology

applied in

calculating

compensations

Permeant

disruption of

income

02 small

shops

12 months 20,000 per

month

0.480 refer

Methodology

applied in

calculating

compensations

Permeant

disruption of

income

01 small

shop

12 months 25,000.00 per

month

0.3 refer

Methodology

applied in

calculating

compensations

Permeant

disruption of

income

01 mobile

vendor(flo

wer seller)

14 days 1000.00 per day 0.014 refer

Methodology

applied in

calculating

compensations

Page 48: 45148-008: Greater Colombo Water and Wastewater …

47

Transport cost for

the transport of

garage items

01 garage Lump-sum 5000.00 00.005 refer

Methodology

applied in

calculating

compensations

05 Other

Grievance redress item Lump sum 300,000 00.3 Do

Consultation with

APs

item Lump sum 250,000 0.25 Do

Awareness

generation

item Lump sum 300,000 0.3 Do

Monitoring

program of RP

implementation

item Lump sum 300,000 0.3 Do

Cost for long term

use of rail

reservation to

install pipeline

(administrative

cost and tax)

item Lump-sum 535,474 0.54

Sub Total 71.041

Contingency 10% 7.1041

Total 78.1451

The methodology applied in calculating compensations

• Cost for alternative housing units- The UDA has requested Rs.3.5 Million per housing unit in

newly built condominiums to recover their capital cost of 2017 (Appendix 07 ). And in 2019

r the UDA has increased capital cost of the house up to 4 Million per housing unit (

Appendix 08)

• Cost for private land acquisition: the finalized amount of the negotiation with landowners.

The valuation based on the Government Chief Valuer’s valuation (Appendix 09)

• Cost for Livelihood Assistance for privet lands owner based on their daily income

• Labor charges for loading and unloading household items based on the current labor

charges of the area

• Cost for Livelihood Assistance: for APs for 7 days equivalent actual income during an initial

period of resettlement- Rs. 1000 per person is the daily income from their employments.

• Cost for transport household items from present houses to new houses: Rs 5000 one-off

payment considering the distance, daily charges of the small truck. This amount was agreed

by the APs and they indicated that it is adequate to transport their household items in small

houses (they also mentioned that group transportation will be possible in some cases).

Page 49: 45148-008: Greater Colombo Water and Wastewater …

48

• Cost for the loss of income: based on monthly income from the garage as per the garage

owner and market rate

• Cost for income loss of small scale business: based on the monthly income of the shop

owners

• Cost for Awareness training and other information disclosure program, Monitoring

program of RP implementation Facilitation for livelihood re-establishment in the post-

resettlement phase based on the government rate on training program

• Cost for management of GRM- including to payment of attendance allowance for the GRC

members who are not PMU staff based on the monthly salary of the relevant officer

• Cost for long term use of rail reservation to install pipeline (administrative cost and tax):

based on the CGR land lease Valuation (Appendix 10)

J. Monitoring and Reporting

26. RP implementation will be monitor by PMU SGRO using following monitoring indicators to

ensure that to provide effective sustenance to the resettlement process and identifying potential

difficulties and problems which are faced during the resettlement process. Table 9: Potential

Monitoring Indicators

Table 9- RP Monitoring Indicators

Monitoring Issues Monitoring Indicators

Management, budget, and program • PMU strengthened and trained; management &

monitoring systems established and functioning

• PMU Sociologist appointed and in post

• DSIDC Resettlement Specialist appointed and in post

• DMS conducted as planned, completed on time

• Updated RP prepared according to schedule

• Funds for resettlement released on schedule

• Sites prepared on time for the start of construction

Delivery of AP entitlements • APs received entitlements according to amounts and

program specified in RP

• Compensation provided before loss incurred

• Arrangements for livelihood provided to vulnerable APs

Consultation, grievance, and other

issues

• Public meetings held to disclose impacts and

entitlements

• Meetings with individual APs to agree on compensation

• APs aware of entitlements and grievance procedure

• SC meetings held and grievances resolved

Benefit monitoring • Post-impact meetings held with APs to check receipt of

entitlements and satisfaction

• Check off any disproportionate impacts on vulnerable

households

27. Status of resettlement will be sent to the ADB through the semi-annual report by the PMU

SGRO with the assistance of RS expert of DSIDC and data will be reserved from the construction

supervision staff, contractor and the Aps. A sample monitoring template is given by appendix 12 and

appendix 13 presented area of the affected households by the project activities.

Page 50: 45148-008: Greater Colombo Water and Wastewater …

49

Appendix 2

i. Copies of AP’s certification of payment (signed by the APs

Page 51: 45148-008: Greater Colombo Water and Wastewater …

50

Page 52: 45148-008: Greater Colombo Water and Wastewater …

51

Page 53: 45148-008: Greater Colombo Water and Wastewater …

52

Page 54: 45148-008: Greater Colombo Water and Wastewater …

53

Page 55: 45148-008: Greater Colombo Water and Wastewater …

54

English translation of the AP’s certification of payment

Dear Madam,

GREATER COLOMBO WATER AND WASTEWATER MANAGEMENT IMPROVEMENT INVESTMENT

PROGAM

PROVISION OF NEW GRAVITY SEWERS, FORCE MAINS, AND PUMPING STATION FR KIRULAPONE

CATCHMENT AREA

SUB: key hand over to resettled families at proposed pipe laying site at Colombage Mawatha

(Railway reservation)

The Greater Colombo Water and Wastewater Management Improvement Investment Program-P3

(GCWWMIIP-P3) aims at delivering efficient and reliable urban water supply and sewerage services

in the Greater Colombo area. The impact of the Investment Program will be improved quality of life

for the residents of Greater Colombo.

The project has planned to lay pipe along to the railway track reservation at Colambage Mawatha

belongs to Railway Department and you (Mr/Mrs…………………….. ID……………….. ) have built a house

on this land and register under No. 29/53A needs to be removed to get land clear for the pipe laying

works.

It is pleased to inform you that the project delivers house no. ………………………..at Kollonnawa,

“Laksada Sewana” Housing scheme built by Urban Regeneration Project (URP) on

……………………………….. as reimbursement of your loss house at the above address.

After receiving all compensation for relocation you are kindly requested to move out from the house

before …………………………. to land hand over to the contractor.

As per the URP resettlement procedure, you will not be authorized to enter the land for any reason

without permission from the project team.

Your cooperation in this regards highly appreciate.

Thank you

Yours Sincerely

Project Director

Greater Colombo Water and Wastewater Management Investment Improvement Programme

Page 56: 45148-008: Greater Colombo Water and Wastewater …

55

i. Summary of minutes of meetings during public consultations

Event Reason for the

meeting

Date Issues discussed Quires

/suggestions

Action

taken

Number of

participants

Male Female

Meeting

with GA -

Thibirigasy

aya

Discuss on

ownership of

the one affected

house at

Colombage

Mawatha pipe

laying site

01.08.2018 To meet all

parties who are

a struggle for

the house and

check legal

ownership of

the house

Meeting

with public

Pipe laying at

privet road

06.08.2018 impotency of

the wastewater

system and its

connection and

to increase land

value how to

increase land

value after

getting a

connection to

wastewater

system

neediness of the

involvement of

the city

development

impotency of

connection

to the

sewerage

system

Explaine

d

08 15

Meeting

with public

Traffic

contingency

during

construction

activities

31.08.2018 It was agreed

to provide

police

personnel to

control

traffic during

peak

hours(School

time)

Explaine

d

11 03

introduction

and impotency

of the

wastewater

system and

public

participation for

the project

activities

and Public

complaint

handling

procedure of

impotency of

connection

to the

sewerage

system

Explaine

d

Page 57: 45148-008: Greater Colombo Water and Wastewater …

56

the project

Construction

methodology

construction

induce

impact to

their

property and

compensatio

n

Explaine

d GRM

Environmental

hazard and

prevention

during

construction

activities

environment

hazards

Agreed

to

minimiz

e

Public complaint

handling

procedure of

the contractor

traffic

constancy

Explaine

d traffic

manage

ment

Traffic

Management

quickly finish

construction

to minimize

disturbances

to day to day

activities

Agreed

discussion on

access road

issue at Kalinga

Mawatha PS site

09.03.2018 Construction of

by road for the

public who are

lost access road

via PS site

People

agreed to

construct a 3

m width

road.

PMU

advised

the

contract

or to

construc

t

concret

e by

road for

the

public

05 10

the

contract

or

agreed

to

construc

t the

road as

soon as

possible

Meeting

with

project-

affected

people

To hand over

the keys of the

new house

04.12.2018 - Requested to

assist

resettlement

at the new

apartment

Agreed

Hand

over the

keys

and

03 03

Page 58: 45148-008: Greater Colombo Water and Wastewater …

57

and get

services

connection

(water,

electricity,

etc.)

aware

people

on

challeng

es and

benefits

of the

new life

at a new

house /

high rice

apartme

nt

the

lifestyle

of the

high rise

apartme

nt /new

commu

nity

changin

g

behavio

r of the

APs

followin

g rules

and

regulati

on of

the high

rise

apartme

nt and

the host

commu

nity

Meeting

wit

h

pu

blic

To discuss

construction-

related issues

06.12.2018 Disturbances

during pipe

laying works

and excavation

Aware and

requested to

minimize

construction-

related

disturbances

Agreed 05 08

Meeting

with

Project

Director to

the

Colombo

Suburban

To discuss

resettlement at

Colombage

21.12.2019 possibility of

providing house

to a rented

person who is

affected at

Colombage Mw

site

Agreed 04 01

Page 59: 45148-008: Greater Colombo Water and Wastewater …

58

Railway

Project

Site visit

with

Deputy

Project

Director

(ESS) to the

Colombo

Suburban

Railway

Project

To collect

information

about the

affected rented

person at

Colombage Mw

28.12.2019 Collect

information

about the family

Aware of

relocation

and their

DPD

agreed

to check

the

possibili

ty of

providin

g house

to AP

under

CSRP

resettle

ment

program

01 03

discuss pipe

laying works in

Allenmathiniyar

ama privet road

– Kirulapone

01.06.2018 inspection of

impact on

the stability

of the

roadway

and/ or

embankment

by a reputed

third party

before

starting the

excavation

work on the

road

Request

ed to

send

latter

includin

g all

queries

13 04

requested

insure all

structure for

10 years

after

construction

Request

ed to

send

latter

includin

g all

queries

proper traffic

management

during

construction

works

Agreed

and

explaine

d the

traffic

manage

ment

plan

requested to

installing

three

Submersible

pump for

three houses

due to revers

Request

ed to

send

latter

includin

g all

queries

Page 60: 45148-008: Greater Colombo Water and Wastewater …

59

problem the

hoses cannot

connect to

the system

ii. Summary of complaints received and solution status

Construction

site

Category Description

of the

complaint

Number

of

complai

nts

received

Date of

complaint

received

Date of

resolution

Status

Solved Ongoi

ng

Purwarama

by lane

Safety Damage to

culvert

01 26.02.2018 25.03.2018 √

Other

problem

related to

the

constructi

on

Road blocked

during

construction

03

23.01.2018

02.02.2018

23.01.2018

02.02.2018

Public object

to excavation

work

02

18.02.2018

14.03.2018

18.02.2018

14.03.2018

Kalinga Mw

PS

Public

health

Material

transport

01 03.07.2018 03.07.2018 √

Derain block 01 07.08.2018 07.08.2018 √

Noise Generating

noise during

excavation

01 28.07.2018 28.07.2018 √

Disturb to

exam

02 19,31.07.2

018

19,31.07.20

18

Other

problem

Problem

with material

transport

01

28.07.2018

17.08.2018

28.07.2018

17.08.2018

Site Access

blocked

01 11.10.2018 √

Object to

excavation

by OUSL

01

19.10.2018

25.08.2018

Handunge

Mw

Utility

interrupti

on

Damage to

the waterline

01

06.07.2018

06.07.2018

Danger to

public

Excavation in

front of the

gate

01 18.07.2018 18.07.2018 √

Kalinga Mw

micro

tunneling site

Danger to

public

Shaft

excavation

without

proper

01 08.07.2018 08.07.2018 √

Page 61: 45148-008: Greater Colombo Water and Wastewater …

60

barricade

Structure

damage

House

damage

01

01.09.2018 - √

Utility

interrupti

on

Damage to

water lines

02 21.07.2018

19.08.2018

21.07.2018

19.08.2018

Damage TP

line

01 17.08.2018 17.08.2018 √

Damage CEB

line

01 22.09.2018 22.09.2018 √

Reduced

quality and

quantity of

water

02 13.09.2018 - - √

Noise Excavation at

night

01 19.10.2018 19.10.2018 √

Thalakotuwa

garden pipe

laying site

Danger to

public

Unsafe

excavation

01 11.07.2018 11.07.2018 √

Traffic

congestio

n

Traffic 03 17.07.2018

02.082018

27.08.2018

17.07.2018

02.082018

27.08.2018

Utility

interrupti

on

Damage to

water line

02 26.07.2018

22.08.2018

26.07.2018

22.08.2018

Other Public

objection on

privet road

excavation

02 23.07.2018

06.08.2018

- - √

Keerakotuwa

Rd

Utility

interrupti

on

Damage to

water line

02 08.09.2018

05.10.2018

08.09.2018

05.10.2018

Siddartha adi

para

Utility

interrupti

on

Water

damage

02 16.10.2018

07.11.2018

16.10.2018

07.11.2018

Other Public

objection

02 25.10.2018

03.11.2018

25.10.2018

03.11.2018

Vijaya

Kumarathung

a Mw

Utility Damage to

CEB cable

01 02.10.2018 02.10.2018 √

damage to

underground

power cable

01 30.10.2018 30.10.2018 √

Damage to

water line

02 05.11.2018

06.11.2018

05.11.2018

06.11.2018

Traffic Road blocked 01 27.10.2018 27.10.2018 √

Other Unsafe

excavation

01 16.10.2018 16.10.2018 √

Road

instatement

01 25.10.2018 25.10.2018 √

People

objection to

excavation

01 06.11.2018 06.11.2018 √

Page 62: 45148-008: Greater Colombo Water and Wastewater …

61

Other Public

objection on

excavation

03 16.10.2018

23.10.2018

26.10.2018

16.10.2018

23.10.2018

26.10.2018

Sewer

overflow

01 26.10.2018 26.10.2018 √

Costha

gardens

Other Public

objection on

excavation

02 17.10.2018

18.10.2018

17.10.2018

18.10.2018

Awarihena

Rd

Utility

interrupti

on

Damage to

water line

01 19.10.2018 19.10.2018 √

Damage to

Darin

01 06.11.2018 07.11.2018 √

Robot

goonawardh

ana Rd

Utility

interrupti

on

Damage to

water line

02 17.03.2018

18.03.2018

17.03.2018

18.03.2018

Other Poor Road

restatement

02 27.10.2018

31.10.2018

27.10.2018

03.11.2018

Halgaswatta

Rd

Other

Road blocked 01 23.10.2018

26.10.2018

23.10.2018

26.10.2018

Polhengoda

Rd

Utility

interrupti

on

Damage to

water line

01 02.11.2018 02.11.2018 √

Total 61 56 05

Page 63: 45148-008: Greater Colombo Water and Wastewater …

62

Appendix-3

Grievances Redressal Mechanism (GRM)

Greater Colombo Water and Wastewater Management Investment Improvement Program

Loan Number 3348/3349- SRI

Implementing agency

Colombo Municipal Council (CMC)

Executing Agency

Ministry of Internal & Home Affairs and Provincial Councils & Local Government

Page 64: 45148-008: Greater Colombo Water and Wastewater …

63

Content

A sequence of Redressal Mechanism

Duty of Safeguards Committee (SC)

Project Information Document (PID)

Social and Environmental Safe Guard Division

Communication and Contact Details

Schematic Diagram for GRM

Procedure for Registration of Complaints

Awareness Program

Duties and the Responsibilities of the Safeguard Officers

ACRONYMS

GRM Grievances Redressal Mechanism

AP Affected persons

CMC Colombo Municipal Council

PD Project Director

PMU Project Management Unit

MPAHA&CLG Ministry of Public Administrate, Home Affairs, Provincial Councils and

Local Government

ADB Asian Development Bank

SGRO Sociologist and Grievance Redressal Officer

SC Duty of Safeguards Committee

NSC National Steering Committee

PID Project Information Document

DSC Design Supervision Consultant

Page 65: 45148-008: Greater Colombo Water and Wastewater …

64

Grievances Redressal Mechanism (GRM)

Greater Colombo Water and Wastewater Management Investment Improvement Program in

Colombo Municipal Area

1) A sequence of Redressal Mechanism

The sequence of the activities and the persons responsible in each stage of the Grievance

Redressal Mechanism are as follows:

I. Reporting the grievances to the site staff of the Contractor and the

Engineer by the affected persons (APs). The complaints received by other parties such as

CMC, PD or other relevant officers shall also be channeled through this process. The

Contractor (Contractor’s Public Relations Officer) should then acknowledge in writing the

receipt of the complaint to the APs and report the incident to the Engineer’s site staff and

the PMU immediately. The contractor shall attend to the complaint with the agreeable

solution with the consultation of the Engineer’s site staff within about three days and inform

of the solution to the APs/Engineer’s site staff/PMU in writing with an agreeable time frame

to solve the issue. If the agreed period is more than a month contractor should update the

complainant periodically. If the fresh complaint reaches the level above contractor such as

PMU, CMC, MPAHA&CLG or ADB it should be sent to the contractor and acknowledge the

complainant. The PMU SGRO shall follow up on each of these complaints periodically.

II. If the Contractor fails to solve the complaint within the agreed time frame or lagging to

adhere to the proposed millstones, the complaint shall now be informed the PMU- PD level

for further action. PD shall provide an agreeable solution to the complaint within one week.

During this period the PMU SGRO shall be responsible to update the complainant on the

same procedure as mentioned above.

III. If PMU PD fails to solve the complaint within the agreed time frame or lagging schedule, the

complainant can take up this to the Safeguard Committee (SC) the same procedure shall

precede to an agreeable solution within two weeks, the SC may consult the National

Steering Committee (NSC) in resolving any issue. All these status shall be informed to the

APs at the appropriate times.

IV. If the SC fails to provide an agreeable solution, a complainant may seek legal action.

2) Duty of Safeguards Committee

The SC shall comprise the Senior Officer of the Ministry of Public Administration, Home Affairs

Provincial Councils and Local Government. The level of this officer must be agreed at NSC, CMC

District Engineer of the relevant District will be the chairperson however if a senior officer of

MPAHA&CLG joint this, then this set up need to be changed, hence the PMU PD will need to

appoint the chairperson of the SC as per the need. The PMU SGRO and a representative from the

affected parties such as GS, Community Leader or clergy. The PMU SGRO or any clerical staff of

PMU shall take the minutes of the proceedings.

The SC shall be formed and the first meeting shall be called for before a complaint is received

Page 66: 45148-008: Greater Colombo Water and Wastewater …

65

The SC shall meet when grievances are put forward by the Project Director for settlement. SC

shall determine the merit of the grievances and resolve them within a month of the date of

receipt of the complaint. Further grievances will be referred by APs to the Project Steering

Committee as well. Records will be kept of all grievances received including contact details of the

complainant, date of receipt of the complaint, nature of the grievance, agreed corrective actions

and the date of occurrence of the grievances and outcome. The grievance redress mechanisms

will continue to function for all components of the project.

3) Project Information Document (PID)

A Project Information Document including a brief description of the Project, sub-projects,

benefits of the project, likely negative impacts and institutions to be contacted and their

locations to seek solutions to the problems and constraints which could face during the

construction phase shall be prepared. This document will be distributed among APs just before

mobilizing and civil works.

4) Social and Environmental SafeGuard Division

The affected people should make their complaints to the Contractor or the Engineer’s Site staff

at their respective work sites. However, they can also make their complaints to the SGRO at the

Social and Environmental SafeGuard Division of PMU. The SGRO of this division is responsible for

taking action to solve the problems with the help of other parties. The PMU SGRO together with

DSC Resettlement Expert will make frequent visits to the sub-project sites.

5) Communication and Contact Details

The communities can use the following contact details for reporting their grievances. These are

centrally located areas with well-established transport facilities. They also can post their written

complaints to the PMU office to the address mentioned below through posts or e-mails.

• SGRO:

Office: 86, Millennium center, Ananda Coomaraswamy Mawatha,

Colombo 07.

Telephone: 011 2 665331

E-mail: [email protected]

• District Engineer:

Office: Robert Gunawardena Mawatha, Kirulapone, Colombo 06

Telephone: 0112512596

• Contractor: Larsen & Toubro Limited Construction

• Engineer’s Staff:

Public Relation Officer:

Telephone: 0770430719

Email: [email protected]

Environment manager:

Telephone: 0715350721

Email: [email protected]

These details shall be provided to the communities in the sub-project sites through suitable

awareness programs such as distribution of handouts.

Page 67: 45148-008: Greater Colombo Water and Wastewater …

66

6) Schematic Diagram for GRM

The following diagram shows schematically the sequence of activities of the GRM.

7) Procedure for Registration of Complaints

The following procedure shall be followed for the registration of the complaints from the

communities.

i. A form shall be prepared by the PMU SGRO in Consultation with the Consultant

Resettlements Expert and the CMC for recording the complaints from the APs.

ii. Finalize this form after obtaining the views of the Contractor.

iii. The copies of this finalized form shall be provided to the Contractor’s site staff and the

Engineer’s site staff at the sub-project offices to be used for registration of the

complaints in the project implementation areas.

iv. The PMU SGRO will also use this form for registration of complaints received by him/her

directly.

AP’s complaint to contractor/ Engineer’s

site staff about the grievances faced by

them.

1. If the Contractor/site Engineer

cannot solve the problem in 3

days, forward the same to PMU

Sociologist/Consultant re-

settlement Expert to solve in 1

week.

2. Failing which, inform PD for

solution in 2 weeks.

3. Failing which PD will refer it to

Safeguards Committee for

solution in one month.

If the Safeguard Committee cannot

solve the problem, APs have the option

to resort to legal action.

Step 1

Step 2

Step 3

Acknowledge the AP

in writing / inform the

solution to AP

Inform the

solution to AP

Inform the

solution to AP

Inform the

solution to AP

Page 68: 45148-008: Greater Colombo Water and Wastewater …

67

v. The Contractor should report each complaint to the Engineer’s site staff and the SGRO in

this form along with the actions taken by him. The contractor shall also update the

information on each complaint and maintain files regularly. This updated information

shall be provided to the SGRO and the Engineer’s site staff as well.

vi. The SGRO shall take the appropriate actions to solve the problems timely and follow the

GRM procedure described above in consultation with the Consultant Resettlement

Expert.

vii. PMU SGRO and the Engineer’s site staff shall also maintain records on these complaints

systematically and update them regularly.

8) Awareness Program

Before mobilizing for any physical works at sites, information about the intended work and likely

impacts due to the implementation of the work shall be conveyed to the community. Periodic

updates shall be provided among all users of the subproject sites regularly. Detailed handouts

shall be distributed to the surrounding communities before the commencement of civil work

with specific details such as:

• Description of about the sub-project

• GRM arrangements

• Details of contact persons

• the communication procedure

• Contractor’s construction program

• Type of activities to be carried out

• Probable impacts due to construction activities

• Benefits of the projects to the communities

The PMU SGRO together with the Consultant Resettlement expert shall conduct awareness

meetings to the communities, the construction crews of the Contractor and the Engineer’s site

supervision staff in each sub-project site to explain the GRM arrangements.

9) Duties and the Responsibilities of the Safeguard Officers

The PMU SGRO and the Consultant Resettlement Expert shall play key roles in monitoring GRM

of all sub-project sites during the construction period. These two Safeguard Officers shall

educate the APs, community leaders and other stakeholders on the GRM to be adopted. The

Contractor’s construction crew and the Engineer’s supervision staff shall also be made aware of

the GRM by these two Safeguard Officers. They shall be responsible for monitor the social

safeguard related activities in the sub-project sites during the implementation period. The

information on the social safeguard implementation will be included in the bi-annual progress

reports submitted to the ADB.

The committee:

1. Eng. A.L.M. Nihar, CMC District 4 drainage Engineer – Chairman of the committee

2. Mr. D.P.K. Ranasinghe, Assistant Director Planning) – Member

3. Ms. D.W.U. Anuruddika Kumarihami, SGRO-PMU - Member

4. Mr. Duminda Perera, CBO Leader –Member