  • TITLE

    Prepared by:

    PART 4: IMPLEMENTATION & OPERATION

    4.2 Hazard Identification, Risk

    Assessment and Risk Control (HIRARC)

  • Learning Objectives

    To define what is risk

    assessment.

    To assess the hazard

    identification, risk

    assessment and risk

    control process.

    To describe the

    method of identifying

    hazard.

    To construct the risk

    assessment matrix.

  • What is Risk assessment??:

    The process of evaluating the risks to safety and

    health arising from hazards at work.

    Risk assessment results is documented and used for:

    1. Risk control in OSH management

    2. Future reference and review

    Risk Assessment

  • 1. Integrate Risk Management as part of planning

    at all levels of business

    2. Accept all risks

    3. Make risk decisions appropriately (depending on

    level of risk)

    4. Manage the risk

    Basic Principles Of Risk Management

  • Before Operation

    During Operation

    After Operation

    When To Carry Out Risk Assessment

  • Review whenever there are

    changes:

    Internal

    Before modification, changes

    or introduction of new

    Materials, machinery or

    processes, working

    procedures.

    External

    Amendments of national laws

    and regulations

    Developments in OSH

    knowledge and technology

    When To Review Risk Assessment

  • Hazard Identification

    Risk Assessment

    Risk Control

    Review

    Basic Components Of Risk Management

  • Risk Assessment

  • Severity in terms of:

    Harm to health

    Damage to property

    Damage to environment

    Or the combination of the

    above

    Determining Severity

  • Severity

    Determine severity categories:

    Catastrophic (Major fatality & irrecoverable damage)

    Fatal (normally irreversible injury or damage to health)

    Serious (Non-fatal injury, permanent disability.)

    Minor (Disabling but not permanent injury)

    Negligible injuries (first aid type injury)

  • Most likely - could happen

    frequently

    Possible has a good chance

    of occurring & not unusual.

    Conceivable occurred

    sometime in future.

    Remote not been known

    to occur many times.

    Inconceivable impossible

    & never occured

    Likelihood

  • Severity

    Likelihood

    Most Likely

    (5)

    Possible

    (4)

    Conceivable

    (3)

    Remote

    (2)

    Inconceivable

    (1)

    Catastrophic

    (5) High-25 High-20 High-15 Medium-10 Medium-5

    Fatal

    (4) High-20 High-16 Medium-12 Medium-8 Low-4

    Serious

    (3) High-15 Medium-12 Medium-9 Medium-6 Low-3

    Minor

    (2) Medium-10 Medium-8 Medium-6 Low-4 Low-2

    Negligible

    (1) Medium-5 Medium-4 Low-3 Low-2 Low-1

    A. Qualitative Risk Table

  • Status of Risk

    RISK DESCRIPTION ACTION

    15 25 HIGH

    A HIGH risk requires immediate action to control

    the hazard as detailed in the hierarchy of control.

    Actions taken must be documented on the risk

    assessment form including date for completion.

    5 12 MEDIUM

    A MEDIUM risk requires a planned approach to

    controlling the hazard and applies temporary measure if

    required. Actions taken must be documented on the risk

    assessment form including date for completion.

    1 4 LOW

    A risk identified as LOW may be considered as

    acceptable and further reduction may not be necessary.

    However, if the risk can be resolved quickly and

    efficiently, control measures should be implemented and

    recorded.

  • Determine severity categories:

    4: Fatality & Permanent Disability

    3: More than 4 days MC

    2: Less than or 4 days MC

    1: First aid and near misses

    B. Semi Quantitative Risk Assessment

  • Determining Likelihood of Occurrence of

    Hazard

    4: Daily

    3: Weekly

    2: Monthly

    1: Yearly

    Semi Quantitative Risk Assessment

  • LIKELIHOOD

    SE

    VE

    RIT

    Y

    Yearly Monthly Weekly Daily

    1 2 3 4

    First Aid and Near Misses

    1 1 2 3 4

    Less than or 4 days

    MC 2 2 4 6 8

    More than 4 days MC

    3 3 6 9 12

    Fatality & Permanent Disability

    4 4 8 12 16

    Semi Quantitative Risk Assessment

  • Activities / process /

    facilities/ equipment Hazard Effect

    Current Risk

    Control

    Legal

    Reqmt

    Risk Action &

    Recommendations Severity. Likelihood Risk

    Rating

    Arc Welding

    Physical:

    -Radiation

    Eyes

    Face shield FMA,

    OSHA 2 3 6

    PPE-goggles, eye

    wash station, job

    rotation

    Chemical:

    -Fumes

    Breathing ..

    - FMA,

    OSHA 2 3 6

    Exhaust fan,

    respirator, job

    rotation

    Physical:

    - Spark

    Skin blister

    Gloves,

    overall, kasut

    FMA,

    OSHA 2 3 6

    Fire resistance

    coverall , glove, fire

    extinguisher,

    emergency shower

    Risk Assessment Form

  • Risk Control

  • Substitution

    Modify process

    Enclosure

    Local exhaust

    Fugitive

    emission control

    Isolation

    Housekeeping

    General

    ventilation

    Continuous area

    monitoring

    Dilution

    ventilation

    Automation or

    remote control

    Training and

    education

    Worker rotation

    Enclosure of

    worker

    Personal

    monitoring

    Personal

    protective devices

    Principle of Control

  • Hierarchy Of Control

    MOST EFFECTIVE

    Elimination - remove the hazard.

    FAIRLY EFFECTIVE

    Substitution - use less hazardous

    one.

    Isolation isolate the work area i.e.

    X-ray machine in restricted room

    Engineering Control design,

    isolation at source, barricade,

    guarding,

    LEAST EFFECTIVE

    Administrative Control safe work

    procedure, isolation i.e. reduce

    exposure time and limit, training,

    signage etc

    PPE - last resort.