41968173 01a Introduction to Process Plant Design

8
1 Introduction to Process Plant Design Copyright ©, 2009 William G. Beazley, PhD All Rights Reserved Photo: Air Products Process Plants • Characterized by Chemical Processes – Different from power (including nuclear), propulsion, etc. – Hazards from both energy and substance release – Substances and their temperature and pressure, etc., usually drives the selection of piping materials and design ratings • Petrochemical Plants have their own: – Design standards – Terminology – Practices and – Constraints Basic Components of a Typical Chemical Process (R. K. SINNOTT) Tanks, Warehouses, Hoppers, Piles, etc. Pumps, Compressors, Exchangers, Heaters, Crushers, Mixers, etc. Reactors, Furnaces, etc. Drums, Towers, Filters, Dryers, etc. Reflux, Strippers, Treaters, etc. Tanks, Warehouses, Baggers, etc. Raw Material Storage Tanks, Hoppers, Piles, etc. Feed Preparation (US Navy, Nasa, Transportation, Pumps, Compressors, Exchangers, Heaters, Crushers, Mixers, etc. http://www.npt.nuwc.navy.mil/facilities/QuietWater/default.htm http://www.tfhrc.gov///pubrds/05jan/02.htm http://www.ih.navy.mil/Departments/ord/che-ext-tec-div/index.asp Reaction (US Army, DOE, ) Reactors, Furnaces, etc. http://www.pmcd.apgea.army.mil/multimediaviewer.aspx?id=585 http://www.netl.doe.gov/technologies/coalpower/cctc/summaries/tampa/tampaedemo.html

Transcript of 41968173 01a Introduction to Process Plant Design

Page 1: 41968173 01a Introduction to Process Plant Design

1

Introduction toProcess Plant

Design

Copyright ©, 2009William G. Beazley, PhD

All Rights ReservedPhoto: Air Products

Process Plants• Characterized by Chemical Processes

– Different from power (including nuclear), propulsion,etc.

– Hazards from both energy and substance release

– Substances and their temperature and pressure, etc.,usually drives the selection of piping materials anddesign ratings

• Petrochemical Plants have their own:– Design standards

– Terminology

– Practices and

– Constraints

Basic Components of aTypical Chemical Process

(R. K. SINNOTT)

Tanks,Warehouses,Hoppers,Piles, etc.

Pumps,Compressors,Exchangers,Heaters,Crushers,Mixers, etc.

Reactors,Furnaces,etc.

Drums,Towers,Filters,Dryers, etc.

Reflux,Strippers,Treaters,etc.

Tanks,Warehouses,Baggers,etc.

Raw Material Storage

• Tanks, Hoppers, Piles, etc.

Feed Preparation(US Navy, Nasa, Transportation,

• Pumps, Compressors, Exchangers, Heaters,Crushers, Mixers, etc.

http://www.npt.nuwc.navy.mil/facilities/QuietWater/default.htm

http://www.tfhrc.gov///pubrds/05jan/02.htm

http://www.ih.navy.mil/Departments/ord/che-ext-tec-div/index.asp

Reaction(US Army, DOE, )

• Reactors, Furnaces, etc.

http://www.pmcd.apgea.army.mil/multimediaviewer.aspx?id=585

http://www.netl.doe.gov/technologies/coalpower/cctc/summaries/tampa/tampaedemo.html

Page 2: 41968173 01a Introduction to Process Plant Design

2

Product Separation(US DOE)

• Drums, Towers,Filters, Dryers, etc.

http://www.nrel.gov/data/pix/searchpix.cgi?

http://www.greensboro-nc.gov/departments/Water/watersystem/treatment.htm

Product Purification(US OSHA, DOT)

• Reflux, Strippers,Treaters, Sorters, etc.

http://iforms.osha-slc.gov/dts/osta/otm/otm_iv/otm_iv_2.html

Product Storage

• Tanks, Warehouses,

• Baggers,

• etc.

Waste Storage(DOE, EPA, USGS)

http://www.fedcenter.gov/_storage/Photos/176.jpg

http://www.tobyhanna.army.mil/about/certifications/environmental/rcra%20cleanup.htm

http://pubs.usgs.gov/gip/gw_ruralhomeowner/gw_ruralhomeowner_new.html

Sales

http://www.msc.navy.mil/sealift/2005/September/katrina.htm

The Manufacture of Cement by thePortland Process

(US CDC)

http://www.cdc.gov/elcosh/docs/d0200/d000279/ilochap93.html

Limestone,Clay, etc.

Page 3: 41968173 01a Introduction to Process Plant Design

3

Parties to PlantDesign

(The 'PIPING GUIDE')

• Client wants a finishedplant– Business Case Primary

Concern

– Everyone Else isTemporary

• Design Engineersproduce highly qualityassured productdefinition data

• Construction RealizesDesign

Source:The 'PIPING GUIDE'http://www.pipingguide.com

Process Plant Client• Funds the engineering and construction of the plant

• Generally supplies or approves the processes to be used

• Accepts the work performed

The Project Engineer

• Formal point of contact with the client

– Voice of the client inside the engineering organization

– Usually “seals” design as professional engineer

• Responsible for completeness and correctness of workhttp://www.nps.gov/hfc/products/imi/imi-ser-class.htm

The Project Engineer

• Reviews the DesignBasis of Plant

• Enforces ClientRequirements

http://www.osha.gov/dcsp/partnerships/regional/region2/453_signing.html

The Project Engineer

• Plans and SchedulesWork

http://www.osha.gov/dcsp/partnerships/regional/region2/459_signing.html

Procured Materials and Services

• Items that has been obtained from vendor orsupplier

• Assistance or advice provided by a vendoror supplier

• Obtained through a procurement process

• Result in a list of vendors andsubcontractors

Page 4: 41968173 01a Introduction to Process Plant Design

4

Project Organization

Source: The 'PIPING GUIDE'http://www.pipingguide.com

ProjectDesign

Groups andInformation

Flow(Source: The

'PIPING GUIDE')

http://www.pipingguide.com

Design Organizational Roles

DesignSupervisor

Designer

Designer

Designer

Designer

Checker

ProjectData

Design supervisor/Group leader

• Manages the documentation of in processand approved engineering data

• Contacts the Project Engineer for anyapprovals required

• Assigns work to designers at the appropriatetime

• Assures all data needed for work isavailable to designers

The Piping Designer

• Responsible for correctness of hiswork

• Inform supervisor if questions arise

• Recognize need for data required tocomplete work

• Never contact the client directly

Engineering Design Specifications

• Established basis for final plant design

• Includes:

– start-up procedures,

– initial site selection information,

– general pre-commissioning guidelines,

– equipment testing procedures and acceptancemethods

– final process topology,

– material and energy balance information

Page 5: 41968173 01a Introduction to Process Plant Design

5

Functional Equipment Characteristics

• Describe or specify:

–Functional requirements for theequipment

–Service provided to the process bythe equipment

–What equipment is supposed to do

Vendor-Proprietary Equipment

• Equipment whose performance isguaranteed by the vendor.

• Specified by equipment datasheet inprocess design specificationspackage.

• Usually designed by first selecting avendor who performs testing andsizing of the item

Supplier/Vendor Relationship

• Request the required information only

• Disclosing only necessary information toget the right data

• Avoid:

–Disclosing competition

–Telling vendor he’ll get the order

–Gratuities and never demand them (lunch)

–Ordering to get information then cancel

Documentation

• All project management, design,contractual, regulatory, and disposaldocuments produced during the lifecycle of a process plant.

• Has versions and releases that mustbe managed.

• Includes all documentation retainedpast the end of the plant life cycle

Operations Documents

• Covers all the many different phases andaspects of plant operation

• Documentation necessary to run theplant safely:

–Procedure to start up and shut down theplant

–Parameters and settings for processequipment and controls

Handover

• Transfer of responsibility for the plant

–Construction team to commissioning team

–Commissioning team to operating team

• Involves transfer of all supportingdocumentation

Page 6: 41968173 01a Introduction to Process Plant Design

6

Activity Model of the Oil and GasProduction Facility Life-cycle

(ISO 15926)

Produce ConceptualProcess Design

Produce DetailedProcess Design

Produce ConceptualEngineering Design

(Front End)

Produce DetailedEngineering Design

CommissionPlant

Construct PlantPre-Commission

Operate PlantDecommission

Plant

Maintain Plantand Equipment

Demolish Plantand Restore Site

Procure and Control Equipment, Material and ServicesSuppliers andFabricators

http://www.tc184-sc4.org/About_TC184-SC4/About_SC4_Standards/

Common Status Terms

• As-built: Process plant's actual physicaland functional aspects at a specific pointin timeAs-approved: Product data provide toand approved by clientAs-specified: Approved data provide toengineer by clientAs-released: Product data officiallyprovided to anyone

Construction Release

• All data needed to realize the plant– Build,

– Commission,

– Train to operate, maintain

• Approved for release by engineering forconstruction

• Stamped by a registered professionalengineer

Finalized Construction Documents

• All documentation related to the erection,commissioning and operation

• Includes:– As-built reports,

– Equipment certification,

– Nameplate information of installed equipment,

– Operating manuals,

– Testing procedures,

– Field changes, and

– Photos of as-built units, modules and plant

Plant Commissioning• Required before

client handover

• Proven operationalthrough specificprocedures

– Confirm StaffSkills

– Verify productdata

– Test equipment

• EquipmentCommissioningProcedures - Step-by-step explanationof start-up actionsrequired tocommissionequipment in theplanthttp://www.usaid.gov/iraq/photogallery/gallery_8/capconstr1_06.html

Maintenance

http://flickr.com/photos/coolnewspics/244371213/in/dateposted/

Page 7: 41968173 01a Introduction to Process Plant Design

7

Maintenance

http://www.eere.energy.gov/industry/bestpractices/energymatters/full_issue.cfm/volume=37

http://www.srs.gov/general/busiops/tech-transfer/plant.htm

http://www1.usaid.gov/iraq/photogallery/gallery_39/photo18.html

http://splash.metrokc.gov/wtd/southplant/index.htm

Shutdown/Decommissioning

• Shutting down theplant

• Preserving it forlatercommissioning ordemolition

• May not includesite remediation

http://www-als.lbl.gov/als/als_news/news_archive/vol.240_042804.html

http://www.lm.doe.gov/land/sites/oh/fernald_orig/VImages/PhotoTour/1998/Dec98/Plt6c.htm

http://www.nrc.gov/reading-rm/doc-collections/fact-sheets/decommissioning.html

Project Schedule

• Duration

• Start Date

• Critical Path

– Sequence of Taskssuch that if any is latethe project is late.

– Can be more than one

http://www.coconino.az.gov/cji.aspx?id=383

Questions

Production Output• Materials or energy to be sold or

traded

• Result of processing raw material(s)(Production Input)

• Produced according to a scheduleddelivery time, grade, and quantity ofproduct to be produced

Source: EPISTLE Process Industries Data Handover Guide - Part 1http://www.uspi.nl/projects/Joint_Projects/fr_joint_projects.html

PISTEP Process Plant Engineering Processes

Page 8: 41968173 01a Introduction to Process Plant Design

8

Course Outline

• Part 1 Pipe Lifecycle

• Part 2 Pipe Fluid Flow & Control

• Part 3 Plant Equipment

• Part 4 Pipe Structural Design

• Part 5 Project Practices & Management

• Part 6 Project