Proceedings of Projects and Works Committee Meeting -08/2014 -15 dated 30.09.2014
Meeting of Projects and Works Committee was held on 30.09.2014 under the Chairmanship of Sh. Shikhar
Agarwal, Jaipur Development Commissioner in "Manthan" at 1.00 PM. After discussion on the agendas, the decisions made by the committee are as under:-
Agenda Item No.
OIC Subject/Agenda Details Decision taken Action to
be taken by
1 MS PWC Confirmation of proceeding of
07/2014-15 PWC meeting held on 28.08.2014
The proceedings of PWC meeting 07/2014-15 held on 28.08.2014 were confirmed.
MS PWC
2 MS PWC Compliance report of decision taken in PWC Meeting of 07 /2014-15
Compliance report was perused and found complied.
MS PWC
3 f, pwc ,. :::::!:ng Agenda r`LPRoads
4 DC-13
s.,-N1 'ff0 850,822 4 *let The Agenda was presented by DC-13. After discussions and deliberation, the committee decided to defer the Agenda
DC-13 '/, q 'Ire liffi cDRIcill 064cf 31.* 4 ft-8 31-1447
t TkET 4
5 DC-5
f41;(T v( ITT 4 aTTITiftzi
ill-A7T 4 11731Trd ,(c) -7 3 A1-11-A7 'T-i Ztift31179. tir4Tff
The Agenda was presented by DC-5. After discussions and
deliberation the committee approved the part plan submitted by DC-5.
ft.-a 1-0117
-7/3 Th-T
DC-5
41167 ITirr 4-9 :1r4 3T-19)-4-ff Glieslci I
6 EE
Project-II
Revision of A&F for the work of "Strengthening and widening of B-2 Byepass, Tonk
Road to New Sanganer Road, Jaipur"
The Agenda was presented by EE Project-II. After discussions and deliberations the committee approved the Revision of A&F for the work of Strengthening and widening f B-2 byepass Tonk Road to New
Sanganer Road, Jaipur from Rs. 1360.95 lacs to 1597.44 lacs.
EE Project-II
7 DC-10
300 Itre 1 rF 1 1 '1177371 The Agenda was presented by DC-10. After discussions and deliberations, the committee
approved the revised map of
Govindpura Ropada Group Housing Scheme.
The Agenda was presented by DC- 10. After discussions and deliberation, the committee decided to approve the revised map of JDA scheme on the land of Animal Husbandary in village Jamdoli
DC-10
DC- 10
tlT5T TT 6I\iRi 1 1 3T-19A-ff WftIT T41791. 41 I' 1l tiatiq .-7 31- 4- -9. cileicl I
8 DC-10
WITWPI-44F- . 1--i----------eTff tiV-Ilei-f ftliFT 'et VI 4 SAT 31-11:41tff thW9T 11111." Th-F \'46-1 'f Th7 3711349. 611" I
9 EE-
Drainagei
Construction of Drain from Ajmeri Pulia ( Parivahan Marg) to Gandah Nalla ( Via Civil
The Agenda was presented by EE-Drainage. After discussions and deliberations, the
EE-
Drainage
)
Lines Phatak) to 22 Godwan
Pulia to Sahakar Marg
committee approved the
proposal for Construction of
Drain from Ajmer Pulia
(Parivahan Marg) to Gandah
Nalla ( Via Civil Lines Phatak) to
22 Godam Pulia to Sahakar
Marg. Amounting Rs.
9,50,72,955.00
10 EE-
Drainage
Proposal for sanction of
Project and A&F for the work
"Construction of drain & other
related work from
Powerhouse Chouraha to
Kabeer Marg via Collectorate
Circle"
The Agenda was presented by
EE-Drainage. After discussions
and deliberations, the
committee approved the
proposal A&F sanction for the
work "Construction or drain and
other related work from Power
House Chouraha to Kabeer
iviarg via conectorate Circle"
amounting Rs.10,92,95,615.00
EE-
Drainage
11 EE-
Drainage
Revision in the scope of work
of construction of drain and
other related work as follows:
Original route-From Indira
Circle to Rambagh circle to Lal
kothi to Sahakar Marg and
upto Ganda Nalla- Proposed
Route- In addtion to existing
proposal of Tonk road
construction of drain from
Rambagh circle to Ambedkar
circle and upto Ganda Nallah
and from High Court to
Ambedkar Circle
The Agenda was presented by
EE-Drainage. After discussions
and deliberations, the
committee approved the
Revision in the scope of work of
construction of drain and other
related work as follows: Original
route-From Indira Circle to
Rambagh circle to Lal kothi to
Sahakar Marg and upto Ganda
Nalla- Proposed Route- In
addtion to existing proposal of
Tonk road construction of drain
from Rambagh circle to
Ambedkar circle and upto
Ganda Nallah and from High
Court to Ambedkar Circle
EE-
Drainage
12 EE Pr.4
(Electrical)
A&F Proposal for
Electrification of JDA Marriage
Resort Hub Scheme at village
Govindpura Ropada Tehsil
Sanganer, Jaipur
The Agenda was presented by EE P-4 Electrical. After
discussions and deliberations,
the committee approved the
A&F proposal for Electrification
of JDA Marriage Resort Hub
scheme at village Govindpura
Ropada Tehsil Sanganer, Jaipur
amounting Rs.8,98,86,955.00
EE P.4 Electrical
S-1 EE-
Drainage
"Construction of drain from
Ajmer Pulia to Amanishah
Nalla via Sodala Tiraha'", JDA,
Jaipur
The Agenda was presented by
EE-Drainage. After discussions
and deliberations, the
committee approved the A&F
proposal for "Construction of
drain from Ajmer Pulia to
Amanishah Nall? via Sodala
EE-
Drainage
Tiraha", JDA, Jaipur amounting
Rs. 14,63,34,667.00
S-2 EE-7
Proposal for Revised A&F
sanction for the work "Repair
of Sirsi Road from Queens
Road to C-Zone Byepass, Zone-
7 area, JDA
The Agenda was presented by
EE-7. After discussions and
deliberatins, the committee
decided to approve the Proposal
for revised A&F sanction for the
work "Repair of Sirsi Road from
Queens Road to C-Zone
Byepass, Zone-7 area, JDA from
Rs. 387.16 lacs to Rs. 408.66 lacs
EE-7
S-3 ROLVRUE;
EE- ::
Proposal for approval of GAD
for the work of "Construction
of six lane High Level Bridge
connecting Riddi Sidhi junction
to Mansarovar link road on
Amanishah Nallah"
The Agenda was presented by
EE-ROB/RUB-II. After discussions
and deliberatins, the committee
approved the Proposal for
approval of GAD for the work of
"Construction of six lane High
Level Bridge connecting Riddi
Sidhi junction to Mansarovar
link road on Amanishah Nallah"
EE
ROB/RUB-
II
S-4 EE-Garden
Revision of A&F sanction for
Development work of Ram
Niwas Garden and approval
for execution of works
suggested by Hon'ble
Empowered Committee
The Agenda was presented by
EE-Garden. After discussions
and deliberations, the
committee decided to approve
the Revision of A&F sanction for
Development work of Ram
Niwas Garden and approval for
execution of works suggested by
Hon'ble Empowered Committee
from Rs. 1092.00 lacs to Rs.
1282.60 lac
EE-
Garden
S-5 EE-Pr.4
Electrical
A&F Proposal for construction
of 33/11 KV GSS for various
Affordable Housing Schemes
in JDA Region, Jaipur
The Agenda was presented by
EE P.4 Electrical. After
discussions and deliberations,
the committee approved the
A&F Proposal for construction
of 33/11 KV GSS for various
Affordable Housing Schemes in
JDA Region, Jaipur amounting
Rs.10,69,17,672.00
EE P.4
Electrical
5-6 EE-10A
Repair & Renewal of road
from Agra road to Ring Road
via Lakheshra Viilage in Zone
10A area, JDA, Jak, ,ur
The Agenda was presented by
EE-10A. After discussions and
deliberatins, the committee
:=nnrr,...,. ,=ri the A&f Sanction for
Repair & Renewal of road from
Agra road to Ring Road via
Lakheshra Viilage in Zone 10A
area, JDA, Jaipur amounting Rs.
2,40,60,939.00
EE-10A
I
5-7 EE PRN
16,17,18,19
The Agenda was presented by
EE- PRN-16,17,18,19. After
disyssiszns and deliberations,
EE PRN
16,17,18,
19
1124 -PH th-A-9T li f=44- -IF 1WiiT •f-16(1, 1 Tifilfff Th---9-rdr A -i-A 1=41:Our INd I
the committee approved the A&F Sanction for construction of Drains in various GNSS in PRN amounting Rs. 156.94 crore.
S-8 EE-9
Proposal for sanction of A&F for Rs. 3,88,73,608.00 for work of construction of 100 feet wide sector road in front of Chakrol JDA scheme Zone-9, Jaipur
The Agenda was presented by EE-9. After discussions and deliberations, the committee decided to approve the proposal for sanction of A&F for work "Construction of 100 feet wide sector road in front of chakrol JDA scheme Zone-9, Jaipur amounting Rs. 3,88,73,608.00
EE-9
S-9 EE-9
Proposal for sanction of A&F for Rs. 3,11,46,131.00 for work of Construction Of 100 feet & 80 feet wide sector rodd in Sector-37 zone-9 DA, Jaipur
The Agenaa was presented by EE-9. After discussions and deliberations, the committee decided to deter the Agenda
EE-9
S-10 DC-13
(riiii 44(4 zi %Al1 MR WiSt .4 The Agenda was presented by DC-13. After discussions and deliberations, the committee deferred the Agenda
D13 eqcf 4 %All 911 1 4 4 7114
'0 `4A4 01464 t 4Atri. a1-4-. - C°3 V r4tthul ir4tT 41
5-11 EE-PHE-III
A&F sanction for the work of "Providing,Laying and commissioning of sewer system for proposed PRN JDA area of Jaipur City Phase-I amounting Rs. 1,71,60,84,567.00
The Agenda was presented by EE-PHE-Ill. After discussions and deliberations the committee approved the A&F sanction for the work of "Providing,Laying and commissioning of sewer system for proposed PRN JDA area of Jaipur City Phase-I amounting Rs. 1,71,60,84,567.00
EE-PHE-III
S-12 EE-11
Proposal for approval of A&F sanction for Construction of Missing Links of various Sectokr roads in JDA, Jaipur
The Agenda was presented by EE-11. After discussions and deliberations, the committee approved the proposal of A&F sanction for Construction of Missing Links of various Sectokr roads in JDA, Jaipur amounting Rs. 6503.73 lacs
EE-11
S-13 EE-7
Proposal of A&F sanction for "Construction of CC road and Drain at Girdharipura Katchi Basti and Sanjay Nagar Katchi Basti, Zone-7, JDA, Jaipur
The Agenda was presented by EE-7. After discussions and deliberation, the committee decided to approve the A&F sanction for "Construction of CC road and Drain at Girdharipura Katchi Basti and Sanjay Nagar Katchi Basti, Zone-7, JDA, Jaipur amounting Rs.379.99 lacs
EE-7
S-14 EE-7
Proposal for A&F sanction for
the work "Construction of
road at JDA approved colonies
near Ajmer Road in Zone-7
area, JDA, Jaipur"
The Agenda was presented by
EE-7. After discussions and
deliberations, the committee
approved the A&F sanction for
the work "Construction of road
at JDA approved colonies near
Ajmer Road in Zone-7 area, JDA,
Jaipur" amounting Rs. 263.43
lacs
EE-7
S-15 EE-
Electrical-1
S-16
S-17
S-18
EE-
Electrical-1
EE-
Electrical-1
DC-13
Shifting and Dismantling of
existing HT/LT lines including
street light work in PRN Area,
Jaipur
Providing and fixing of street
light of Service road (Both
side) of C-Zone bye pass from
Ajmer road to Sikar road,
Jaipur
Providing and fixing of Street
Light on various sector roads
in PRN Area, JDA, Jaipur
,G ■311-4 UN flef
bi 34 31-ft t
.art tH
tq*NI 90 859/ 2370
•coelf 0.04 to 860/2370 isoca 0.
03 to 861 /2374 •4(1)611 0.03 *0,
862 / 2576 0.01
*,864/2207 '(chef( 0.09
*0,864/2208 ,N).541 0.04 to 865
.(4).511 5.81 *0865/2375 cbcif 0.
27 tO, 865/ 2586 •?ctmlf 0.30 *0,
1001/ 2407 .c.b611 0.02 to
1002 / 2408 •M)61f 0.04
*0,1004 / 2411 ,(ct)(11T 0.07
tO,f -dT —12 cr2,c4 ,meiT 6.75 *0
q 7tiztrf4- 3r174-4-9
t-qt
The Agenda was presented by
EE-Electrical-1. After discussions
and deliberations, the
committee decided to approve
the A&F sanction for Shifting
and Dismantling of existing
HT/LT lines including street light in PRN Area, Jaipur
amounting Rs.27,79,19,012.00
The Agenda was presented by
EE-Electrical-1 After discussions
and deliberations, the
committee approved the A&F
sanction for Providing and fixing
of street light of Service road
(Both side) of C-Zone bye pass
from Ajmer road to Sikar road,
Jaipur amounting
Rs.5,17,19,543.00
The Agenda was presented by
EE-Electrical-I. After discussions
and deliberations, the
committee approved the A&F
sanction for Providing and fixing
of Street Light on various sector
roads in PRN Area, JDA, Jaipur
amounting Rs.5,07,17,220.00
The Agenda was presented by
DC-13. After discussions and
deliberatins, the committee
decided to approve the
Residential Scheme at Village
Jaitpura, Tehsil Chomu on Sikar
Highway to 1T1 Road
EE-
Electrical-
1
EE-
Electrical-
1
EE-
Electrical-
1
DC-13
S-19 S-19
EE-
ctr ical-1
Shifting and dismantling of
existing ENV/132 line from 132 KV GSS Vaishali to C-Zone
byepass, Jaipur
The Agenda was presented by
EE-Elect.l. After discussions and
deliberations, the committee
approved the A&F proposal
amounting Rs. 1040.00 lacs but with condition that cabling be
done instead of shifting.
EE-
Electrical-
I
S-20 EE-12
Proposal for permission of
additional work i.e
construction of road from
olafarm road to Natlalpura village via Harnath baba jat ki Dhani Gram Panchayat
Mundiyaramsar Zone 12 JDA
Jaipur under the on going
original work "Construction of
roads in Gram Panchayat Mundiyaramsar Zone 12 JDA,
Jaipur.
The Agenda was presented by EE-12. After discussions and
deliberations, the committee granted permission to take up additional work construction of
road from olafarm road to NatlaIrrA village via Harnath
baba jat ki Dhani Gram
Panchayat Mundiyaramsar Zone 12 JnA Jaipur under the on going original work
"Construction of roads in Gram Panchayat Mundiyaramsar Zone
12 JDA, Jaipur.
EE-12
The meeting ended with vote of thanks to the chair.
Addl. Chief Engineer-IV & MS PWC, JDA, Jaipur.
Dated: hot No. JDA/EE-5/D- 4 S. Copy to following for kind perusal and necessary action:
1. P.S. To JDC, Jaipur Development Authority, Jaipur. 2.P.S. to Collector, Jaipur. 3. P.S. to Secretary, Jaipur Development Authority, Jaipur. 4. Chief Town Planner, Rajasthan, Jaipur. 5. Director (Engineering-I), Jaipur Development Authority, Jaipur. 6. Director (Engineering-II), Jaipur Development Authority, Jaipur. 7. Director (Finance),Jaipur Development Authority, Jaipur. 8.Director (T.P.),Jaipur Development Authority, Jaipur. 9. Addl. Chief Engineer, 1/11/IIIN/Electrical, JDA, Jaipur 10.The Conservator of Forest, JDA, Jaipur 10.Addl. Commissioner (East/West/LPC/ Land/Admn, JDA, Jaipur. 1 VNINII/VIII/IX/X, Rural JDA, Jaipur.
12. Addl. Chief Town Planner, (MP) JDA, Jaipur. 13.Advisor (RRP)JDA, Jaipur 14.Sr. Town Planner ( ),JDA, Jaipur 15. OSD (R.M.), Jaipur Development Authority, Jaipur. 16.Deputy Commissioner ( ), Jaipur Development Authority, Jaipur. 17.Executive Engineer ( ), Jaipur Development Authority, Jaipur. 18.Sr. Horticulturist, JDA, Jaipur 18.PRO, Jaipur Development Authority, Jaipur./PMIS Cell 19.System Analyst, JDA, Jaipur.
Ex tia~Engineer-5 JDA, Jaipur