4-Q[1].C.-final

download 4-Q[1].C.-final

of 5

Transcript of 4-Q[1].C.-final

  • 8/14/2019 4-Q[1].C.-final

    1/5

    Quality Control

    Introduction:

    Testing the quality of building material is very necessary at the site before it is ready to be

    used as a construction material. The material which is used on site suffers from manydifferent environmental conditions (moisture conditions and temperature conditions) then the

    material tested in the laboratory as compared to the control conditions of laboratory. The

    material available near the site for example the water has to be tested for its construction

    requirements as it may affect the quality of construction. The water used must not have high

    chlorine content.

    Since the moisture content of sand varies continuously depending upon different weather

    conditions so its moisture content has to be check regularly and necessary correction has to

    be implanted and proper quantity of sand and aggregate can be used to achieve the desired

    standard of strength.

    Admixtures are substances used in small quantity to increase the workability of the concrete

    for the given water cement ratio without affecting the strength of the concrete. Admixtures

    used at the site are Sikament170PL4.

    Water proofing of walls and floors are necessary to prevent them from dampness and

    destruction of steel in reinforcement due to rusting and to prevent subsequent leakages and

    even in worst cases failure of complete structure.

    According to the material available at the site before starting of the construction proper mixdesign is done and is estimated that what moisture content will amount to what strength in

    concrete and a regular check is made by testing the concrete while construction and proper

    correction is made if necessary.

    Fundamentals of Quality Controls:

    Water proofing of walls and floors are done by layering the walls and floors by water

    proofing compound DR. FIXIT PIDECRETE MPB in 1:1 ratio by cement of

    thickness about 1 mm.

    The steel used for construction purpose is Fe 500 TMT (Thermo-MechanicallyTreated) bars.

    The grade of concrete used for construction purpose varies from M-25 to M-40 grade

    concrete.

    Flakiness and elongation index of aggregate should be below 35%.

    Aggregate are tested for their strength by aggregate crushing and aggregate impact

    test on site. Maximum size of aggregate used at site is 20 mm and minimum is 10

    mm. The test are made according to IS 2386 Part (I-VIII).

  • 8/14/2019 4-Q[1].C.-final

    2/5

    Cubes are casted and check for their strength by checking their 7 days and 20 days

    compressive strength.

    Non-destructive tests (like ultrasonic test etc.) are done on concrete if the concrete

    fails to achieve the desired strength after 28 days to determine the cause of such weak

    strength (due to honey-bee structure, etc.)

    Admixture used is 0.6% by weight of cement.

    Quality Control at Site:

    Quality of the various materials utilized in the field is tested at the site itself. A separate

    room for the testing of the various materials has been provided at the site office. A cube

    testing machine, a hot-air oven and a sieve shaker is present in the quality control room. At

    present only the cube test and the slump test are being conducted, as no other material except

    for concrete is being used at the site. Though the cube test is not of much significance here, it

    is being conducted at the site to assure the quality of the mix. Since the concrete is being

    supplied by the company the cube test of the concrete becomes all the more significant.

    Usually 6 cubes are tested when light concreting is being carried out and a minimum of 12cubes are tested when heavy concreting is being carried out. The samples of concrete are

    randomly taken from the trucks that bring in the ready mix concrete. The number of cubes

    that are tested depends upon the client also. The cube test is usually conducted in the

    presence of the client. The slump test is conducted in the field itself. It is carried out to

    determine the workability of the mix. The acceptability limits of the slump of the concrete is

    slightly increased after taking into consideration the weather conditions prevalent in the

    region i.e. hot and humid weather conditions. The various other tests will be conducted once

    the brickwork, plastering, etc. starts. Bricks, sand, etc. will not be supplied by the client hence

    the testing of these materials becomes a necessity as the usage of low of the failure will have

    to be borne by the company. Quality materials may lead to failure and the whole

    responsibility. The bricks will be tested using the hot-air oven. The sieve analysis will be

    conducted to test the quality of the sand that is being used. The quality of cement that is being

    used is determined by finding the initial setting time and the final setting time of the cement.

    Tests Conducted on Soil:

    Sand Replacement Method.

    Core Cutter Method.

    Proctor Test.

    Vicats apparatus Test.

    Pycnometer Test.

    Test on Aggregate:

    Sieve analyses.

    Flakiness and elongation test.

    Aggregate Impact test.

    Aggregate Crushing test.

    Test on Concrete:

    Compressive strength test.

  • 8/14/2019 4-Q[1].C.-final

    3/5

    Field Quality Control:

    Sl.

    No.Material

    Tests to

    be conducted

    IS/ Job

    Specification

    Ref. No.

    FrequencyTest conducted

    By

    1.Fine

    Aggregate

    a. Totaldeleterious

    material content

    IS 2386

    Part IITwice per source Approved Lab

    b. Silt clay

    content

    IS 2386

    Part II

    To be done every day before

    start of work for 1st 7 days.

    Later 1 test in every 100 m3

    of sand.

    Simplex Field

    Lab

    c. Particle size

    distribution

    IS 2386

    Part I/ IS 383

    1 testing daily for 1st 7 days.

    Later 1 every 100 m3 of

    sand/ change of source if any

    Simplex Field

    Lab

    d. Moisture

    content

    IS 2386 PartII/ IS 456/ IS

    383

    1 per 100 m3

    except duringmonsoon when it has to be

    done every day before start

    of work.

    Simplex Field

    Lab

  • 8/14/2019 4-Q[1].C.-final

    4/5

    2.Coarse

    Aggregate

    a. Particle size

    distribution

    IS 2386I/ IS

    383

    1 testing daily for 1st 7 days.

    Later 1 every 100 m3 of

    stone aggregate/ change of

    source if any

    Simplex Field

    Lab

    b. Percentage of

    soft deleterious

    material

    IS 2386

    Part IIITwice per source

    Simplex Field

    Lab

    c. Moisture

    content

    IS 2386 Part

    II/ IS 456/ IS

    383

    1 per 100 m3 except during

    monsoon when it has to be

    done every day before start

    of work.

    Simplex Field

    Lab

    d. Flakiness

    Index

    IS 2386

    Part I

    Once initially and then

    change with source.

    Simplex Field

    Lab

    e. Elongation

    Index

    IS 2386

    Part I

    Once initially and then

    change with source.

    Simplex Field

    Lab

    f. Impact ValueIS 2386

    Part IV

    Once initially and then once

    every month.

    Simplex Field

    Lab

    g. Los Angeles

    Abrasion value

    IS 2386

    Part IV

    Once initially and then once

    every month.

    Simplex Field

    Lab

    h. SoundnessIS 2386

    Part V

    Once initially and then once

    every month.Approved Lab

    i. AlkaliAggregate

    Reactivity

    IS 2386

    Part VII

    Once initially and then onceevery month.

    Simplex Fieldlab

    3. Water

    a. Chemical &

    Physical

    Properties

    IS 3025

    Water from each source to

    be tested before start of work

    and then every 6 months.

    Approved Lab

    b. pH value IS 456Once initially thereafter

    every month.

    Simplex Field

    Lab

    4. Cement

    a. Initial & Final

    setting time

    IS 4031

    Part V

    Every 3000 bags and at least

    once monthly.

    Simplex Field

    Lab

    b. Compressive

    strength

    IS 4031

    Part VI

    Every 3000 bags and at least

    once monthly.

    Simplex Field

    Lab

    c. Chemical

    Analysis

    IS 4032/ IS

    4031 Part II

    a. Each lot

    b. Once for every type of

    cement

    a. Manufacturer

    Test Certificate

    b. Approved Lab

    d. Fineness &

    SoundnessIS 4031 Each lot

    Simplex Field

    Lab

  • 8/14/2019 4-Q[1].C.-final

    5/5

    5. AdmixtureAll tests as per

    IS 9103IS 9103

    a. Lot wise

    b. Once per source

    a. Manufacturer

    Test Certificate

    b. Approved

    Lab

    6. ConcreteAll tests as per

    IS 516-1959IS 516-1959

    1 set of 6 cubes per 28 m3 or

    part thereof concrete poured

    Simplex Field

    Lab