4- Project Cost Management

62
Project Cost Management Unit 7

description

PMP

Transcript of 4- Project Cost Management

Project Cost Management

Unit 7

Project cost management• Project cost management includes the processes involved in estimating,

budgeting, and controlling costs so that the project can be completed within the approved budget

• It is primarily concerned with the cost of the resources needed to complete schedule activities

• Should consider the information needs of the project stakeholders

• With proper planning, you can:

• Adjust the project plan to conform to the budget

• Track and manage cost once the project execution begins

• Compare actual cost to the original planned cost and analyze any variances between the two

2

Knowledge AreasInitiating Planning Executing Monitoring & Controlling Closing

Develop project charterDevelop project management plan

Direct and manage project execution

Monitor and control project work

Close project or phase

perform Integrated change control

Collect requirements Varify Scope

define scope Control Scope Create WBS

Define activities Control schedule

sequence Activity Estimate acitivity resources Estimate activity durations Develop schedule

Estimate costs Control costs Determine budget

Project Quality Management Plan quality Perform quality assurance Perform quality control

Develop human resource plan Acquire project team

Develop project teamManage project team

Identify stakeholdersPlan communications Distribute information Report performance

Manage stakeholder expectations Stakeholders

Plan risk management Monitor and control risks

Identify risks Perform qualitative risk analysisPerform Quantitative risk analysis

Project Management Process Groups

Project Integration Mangement

Project Scope Management

Project Time Management

Project Cost Management

Project Human Resource Management

Project Communications Management

Project Risk Management

Cost Management Plan• The planning effort of the processes of the Cost

Management Plan is a part of the develop project management plan

( Cost management plan can establish the following )• Precision level - The prescribed precision for rounding data related to schedule

activity cost estimates

• Units of measure - Define units of measurement for each of the resources

• Organizational procedure links - The WBS component used for the project cost accounting is called a control account (CA); each CA is assigned a code or account number

• Control thresholds - Variance thresholds for cost at designated time points in the project to indicate the agreed to amount allowable variance

4

• The planning effort of the processes of the Cost Management Plan is a part of the develop project management plan

( Cost management plan can establish the following )• Reporting formats - The format for various cost reports

• Process descriptions - Descriptions of each of the three cost management processes

5

Cost Management Plan

6

7.1 Estimate Costs

The process of developing an approximation (estimate) of the cost of the resources needed to complete each schedule activity

•Estimator must consider the possible causes of variation of cost estimates, including risks

•Includes identifying and considering various costing alternatives

•Costs for schedule activities are estimated for all resources that will be charged to the project

7

Scope Baseline

Project ScheduleThe type and quantity of resources and the amount of time

which those resources are applied to complete the work of the project are major factors in determining the project cost.

Human Resource PlanProject staffing attributes, personnel rates, and related

rewards/recognition

7.1 Estimate Costs(Inputs)

8

Risk RegisterThe risk register should be reviewed to consider risk mitigation costs.

Enterprise Environmental Factors• Market conditions.• Published commercial information.

Organizational Process Assets• Cost estimating policies,• Cost estimating templates,• Historical information, and• Lessons learned.

7.1 Estimate Costs(Inputs)

9

• Expert judgment

• Analogous Estimating

• Parametric Estimating

• Bottom-Up Estimating

• Three-Point Estimates

• Reserve Analysis

• Cost of Quality (COQ)

• Project Management Estimating software

• Vendor Bid Analysis

7.1 Estimate Costs(Tools & Techniques)

10

• Activity Cost Estimates

• Basis of Estimates

• Project Document Updates

7.1 Estimate Costs(Outputs)

11

Inputs

• Enterprise Environmental Factors

• Organizational Process Assets

• Scope baseline• Project schedule• Human resource plan• Risk register.

Inputs

• Enterprise Environmental Factors

• Organizational Process Assets

• Scope baseline• Project schedule• Human resource plan• Risk register.

Tools & Techniques

• Analogous estimating• Expert judgment• Bottom-up estimating• Parametric estimating • Project Management

Software• Vendor Bid Analysis• Reserve Analysis• Cost of Quality• Three-point estimate

Tools & Techniques

• Analogous estimating• Expert judgment• Bottom-up estimating• Parametric estimating • Project Management

Software• Vendor Bid Analysis• Reserve Analysis• Cost of Quality• Three-point estimate

Outputs

• Activity Cost estimates

• Basis of estimates• Project document

updates

Outputs

• Activity Cost estimates

• Basis of estimates• Project document

updates

7.1 Estimate Costs

12

7.1 Estimate Costs

13

• Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.

• This baseline includes all authorized budgets, but excludes management reserves.

• Project budgets constitute the funds authorized to execute the project.

• Project cost performance will be measured against the authorized budget.

7.2 Determine Budget

14

Activity Cost Estimates (Inputs)

Basis of Estimates (Inputs)

Scope Baseline (Inputs)

Project schedule (Inputs)

Resource Calendars (Inputs)

Contracts (Inputs)

Organizational Process Assets (Inputs)• Existing formal and informal cost budgeting-related

policies, procedures • Cost budgeting tools,

7.2 Determine Budget

15

Cost Aggregation (Tool)

•Schedule activity cost estimates are aggregated by work packages in accordance with the WBS

•Work package cost estimates are then aggregated for the higher component levels of the WBS, such as the control account, and ultimately for the entire project

Funding Limit Reconciliation (Tool)•The expenditure of funds should be reconciled with any funding limits on the commitment of funds for the project.

7.2 Determine Budget

16

1. Activity estimates

2. Work package estimates

3. Control Account estimates

4. Project estimates

5. Contingency reserves

6. Cost baseline

7. Management reserves

8. Cost budget

7.2 Determine Budget

17

Reserve Analysis (Tools)

Expert judgment (Tools)

Historical Relationships (Tools)

7.2 Determine Budget

18

Cost Performance Baseline (Output)•The cost performance baseline is an authorized time-phased budget at completion (BAC) used to measure, monitor, and control overall cost performance on the project. •It is developed as a summation of the approved budgets by time period and is typically displayed in the form of an S-curve

Project Funding Requirements (Output)•Total funding requirements and periodic funding requirements (e.g., quarterly, annually) are derived from the cost baseline. •The cost baseline will include projected expenditures plus anticipated liabilities. •Funding often occurs in incremental amounts that are not continuous, which appear as steps

7.2 Determine Budget

19

7.2 Determine Budget

20

Inputs

• Activity cost estimates

• Basis of estimates• Scope baseline• Project schedule• Resource calendars• Contracts• Organizational

process assets

Inputs

• Activity cost estimates

• Basis of estimates• Scope baseline• Project schedule• Resource calendars• Contracts• Organizational

process assets

Tools & Techniques

• Cost Aggregation• Reserve Analysis• Historical relationships• Expert judgment • Funding Limit

Reconciliation

Tools & Techniques

• Cost Aggregation• Reserve Analysis• Historical relationships• Expert judgment • Funding Limit

Reconciliation

Outputs

• Cost performance baseline

• Project Funding Requirements

• Project document updates

Outputs

• Cost performance baseline

• Project Funding Requirements

• Project document updates

7.2 Determine Budget

21

7.2 Determine Budget

22

7.3 Control Costs

Control Costs is the process of monitoring the status of the project to update the project budget and managing changes to the cost baseline.

Project cost control includes:

•Influencing the factors that create changes to the authorized cost baseline,

•Ensuring that all change requests are acted on in a timely manner,

•Managing the actual changes when and as they occur,

•Ensuring that cost expenditures do not exceed the authorized funding, by period and in total for the project,

•Monitoring work performance against funds expended,

23

Project Management Plan (Input)

The project management plan contains the following information that is used to control cost:

•Cost Performance Baseline.•Cost Management Plan.

Organizational Process Assets (Input)

•Existing formal and informal cost control-related policies, procedures,•Cost control tools; and•Monitoring and reporting methods to be used

Project Funding Requirements (Input)

Work Performance Information (Input)

7.3 Control Costs

24

• Earned Value Management (Tools)

• Forecasting (Tools)

• To-Complete Performance Index (TCPI) (Tools)

• Performance Reviews (Tools)

• Variance Analysis (Tools)

7.3 Control Costs

25

Inputs

• Project management plan

• Project Funding Requirements

• Work Performance Information

• Organizational process assets

Inputs

• Project management plan

• Project Funding Requirements

• Work Performance Information

• Organizational process assets

Tools & Techniques

• Earned value management• Performance measurement

Analysis• Forecasting• To-complete performance

index (TCPI)• Performance Reviews• Project Management

Software• Variance analysis

Tools & Techniques

• Earned value management• Performance measurement

Analysis• Forecasting• To-complete performance

index (TCPI)• Performance Reviews• Project Management

Software• Variance analysis

Outputs

• Work Performance Measurements

• Budget forecasts• Change requests • Recommended Corrective

action• Organizational Process

Assets (Updates)• Project management plan

(Updates) • Project document (Updates)

Outputs

• Work Performance Measurements

• Budget forecasts• Change requests • Recommended Corrective

action• Organizational Process

Assets (Updates)• Project management plan

(Updates) • Project document (Updates)

7.3 Control Costs

26

7.3 Control Costs

27

Earned Value Management Analysis

Earned value technique (EVT)

Compares the cumulative value of the budgeted cost of work Earned to both

1. The budgeted cost of work scheduled (planned)

2. The actual cost or work performed (actual)

An important part of Cost Control is to determine the cause of a variance, the magnitude of the variance, and to decide if the variance requires corrective action

EVT uses the Cost Baseline contained in the project management plan to assess project progress and the magnitude of any variations that occur

28

• Earned Value. (EV) Value of work performed expressed in terms of the approved budget

• Planned Value. (PV) Authorized budget assigned to the work to be accomplished for an activity or work breakdown structure component.

• Actual Cost. (AC) Total cost actually incurred and recorded in accomplishing work performed for an activity or work breakdown structure component.

• Schedule Variance (SV) is a measure of schedule performance on a project.

SV = ( EV – PV )• Cost Variance (CV)

is a measure of cost performance on a project.

CV = ( EV – AC )

Earned Value Management Analysis

29

• Schedule performance index (SPI) Is a measure of progress achieved compared to progress planned on a the project.

SPI = ( EV / PV )

• Cost performance index (CPI) Is a measure of the value of work completed compared to the actual cost on the project.

CPI = ( EV / AC )

Earned Value Management Analysis

30

ExampleWe are about to produce 20 tables in 20 days cost is $20 for each.

How much BAC = ???BAC = $20 * 20 tables = $400

Today is day 4 How much is the PV ?PV = $20 x 4 tables = $80

At day 4 i earned only 3 tables, how much is the EV ?EV = $20 x 3 tables = $60AC = $90SV = EV – PV = 60 – 80 = -$20 CV =EV – AC = 60 – 90 = -$30SPI = EV / PV = 60 / 80 = 0.75CPI = EV / AC = 60 / 90 = 0.666

Earned Value Management Analysis

31

Forecasting

Estimate At Completion (EAC) actual costs incurred for work completed, plus an estimate to complete (ETC) the remaining work.

EAC = ( AC + ETC )

EAC forecast for ETC work performed at the budgeted rate

EAC = AC + ( BAC – EV ) = 90 + ( 400 – 60 ) = $430

EAC forecast for work performed at the percent CPI

EAC = BAC / CPI = 400 / .66 = $606.6

EAC forecast for ETC work considering both SPI and CPI factors

EAC = AC + [ ( BAC – EV ) / ( CPI * SPI ) ] = 90 + [ (400 – 60 ) / ( 0.75 * 0.66 ) ] = $868.68

32

To-Complete Performance Index (TCPI)

33

Project Performance Management

Time

Cost

BAC

EACData date

PV

AC

EVSV= EV - PV

CV= EV - AC

Exercise.

34

35

Example - Wall Construction

Wall Construction

Time = 1 week per wall

Cost = $ 1,000 per wall, materials and labor

Total Schedule = 4 weeks

Total Cost = $ 4,000

Working days 5 day per week starting on Sunday and finish on Thursday by 5 PM

Assume production is liner

36

Wall 1 100% = $ 1,000

Wall 2 80% = $ 800

Wall 3 0% = 0

Wall 4 0% = 0

PV = $ 1,800

How much work should have been completed -PV?

5 pm Wednesday, Week 2

PLANNED

37

Wall 1 100% = $ 1,000

Wall 2 50% = $ 500

Wall 3 10% = $100

Wall 4 0% = 0

Total = $1,600

5 pm Wednesday, Week 2

What is the budgeted value of actual work - EV?

10 %

50 %

EARNED

38

5 pm Wednesday, Week 2

Total Cost to date –

AC = $ 2,250

39

5 pm Wednesday, Week 2 Earned Value

PV $1,800

EV $1,600

AC $2,250

Schedule Variance = EV - PV

= $1,600 - $1,800

= ($200)

Cost Variance = EV - AC

= $1,600 - $2,250

= ($650)

40

5 pm Wednesday, Week 2 Performance Indices

PV $1,800

EV $1,600

AC $2,250

SPI = EV / PV

= $1,600 / $1,800

= .9

CPI = EV / AC

= $1,600 / $2,250

= .7

Questions

41

1- Half way through the executing processes of your project, a team member alerts you to a potential cost overrun for a specific deliverable. What do you do first?

A ) Determine the projected actual cost.

B ) Implement a change control process to track the change

C ) Inform the customer.

D ) Determine the cause of the overage

42

1- Half way through the executing processes of your project, a team member alerts you to a potential cost overrun for a specific deliverable. What do you do first?

A ) Determine the projected actual cost.

B ) Implement a change control process to track the change

C ) Inform the customer.

D ) Determine the cause of the overage

43

2 - Which type of costs is team training?

A ) Direct

B ) E V

C ) Indirect

D ) fixed

44

2 - Which type of costs is team training?

A ) Direct

B ) E V

C ) Indirect

D ) fixed

45

3- A project manager has completed a detailed WBS and cost estimates for each work package. To create a cost baseline from this data, the project manager would :

A ) Use the highest level of the WBS to estimate analogously

B ) Sum up the work package and risk contingency reserve estimates.

C ) Roll up work package estimates into a project total and add managements reserves.

D ) Gain expert opinions of the project costs. 46

3- A project manager has completed a detailed WBS and cost estimates for each work package. To create a cost baseline from this data, the project manager would :

A ) Use the highest level of the WBS to estimate analogously

B ) Sum up the work package and risk contingency reserve estimates.

C ) Roll up work package estimates into a project total and add managements reserves.

D ) Gain expert opinions of the project costs. 47

4- You are having difficulty estimating the cost of your project. Which of the following BEST describes the most probable cause of your difficulty?

A ) Inadequate scope definition

B ) Unavailability of desired resources

C ) Lack of historical records from previous projects

D ) Lack of company processes

48

4- You are having difficulty estimating the cost of your project. Whish of the following BEST describes the most probable cause of your difficulty?

A ) Inadequate scope definition

B ) Unavailability of desired resources

C ) Lack of historical records from previous projects

D ) Lack of company processes49

5- Which of the following represents the value of work we have actually completed?

A ) Earned value

B ) Planned value

C ) Actual cost

D ) Estimate to complete

50

5- Which of the following represents the value of work we have actually completed?

A ) Earned value

B ) Planned value

C ) Actual cost

D ) Estimate to complete

51

6- While completing your project, you realized that you need to decrease the project costs. After researching your options, you came up with the following choices. Which choice would DECREASE project costs?

A ) Change to component A from component B. component A costs more to purchase, but has a lower life cycle cost than B.

B ) Change activity A to be completed by resource B instead of resource c. resource B is more experienced worker.

C ) Move activities B and H to occur concurrently, and accept a 30 percent increase in the risk that five more resources will be needed later.

D ) Remove a test from the project management plan. 52

6- While completing your project, you realized that you need to decrease the project costs. After researching your options, you came up with the following choices. Which choice would DECREASE project costs?

A ) Change to component A from component B. component A costs more to purchase, but has a lower life cycle cost than B.

B ) Change activity A to be completed by resource B instead of resource c. resource B is more experienced worker.

C ) Move activities B and H to occur concurrently, and accept a 30 percent increase in the risk that five more resources will be needed later.

D ) Remove a test from the project management plan.

53

7- If earned value (EV) is U.S.$300000, actual cost (AC) is U.S.$350000, and planned value (PV) is U.S. $375000, what does the schedule performance index (SPI) indicate?A ) You are progressing at 86% of the rate originally

planned.B ) You are progressing at 125% of the rate originally

planned.C ) You are progressing at 116% of the rate originally

planned.D ) You are progressing at 80% of the rate originally

planned. 54

7- If earned value (EV) is U.S.$300000, actual cost (AC) is U.S.$350000, and planned value (PV) is U.S. $375000, what does the schedule performance index (SPI) indicate?A ) You are progressing at 86% of the rate originally

planned.B ) You are progressing at 125% of the rate originally

planned.C ) You are progressing at 116% of the rate originally

planned.D ) You are progressing at 80% of the rate originally

planned. 55

8- The formula, EAC = BAC/CPI, assumes that:

A ) All subsequent work will be completed at the planned expenditures.

B ) All subsequent work will be completed at the planned expenditures, excluding the work packages currently under way

C ) All subsequent work will be completed based upon the cost performance to-date

D ) The cost performance cannot change during the project

56

8- The formula, EAC = BAC/CPI, assumes that:

A ) All subsequent work will be completed at the planned expenditures.

B ) All subsequent work will be completed at the planned expenditures, excluding the work packages currently under way

C ) All subsequent work will be completed based upon the cost performance to-date

D ) The cost performance cannot change during the project

57

9- Feasibility study answers the question “can we do it?” cost benefit analysis answer the question---------

A ) Should we do it?

B ) Are the safety risks acceptable?

C ) Is it beneficial to have a high level sponsor?

D ) Does the technology exist? 58

9- Feasibility study answers the question “can we do it?” cost benefit analysis answer the question---------

A ) Should we do it?

B ) Are the safety risks acceptable?

C ) Is it beneficial to have a high level sponsor?

D ) Does the technology exist? 59

10- What tool must project managers rely upon to accurately identify the costs associated with the project?

A ) A bill of materials

B ) A Gantt chart

C ) A precedence diagram network

D ) A work breakdown structure60

10- What tool must project managers rely upon to accurately identify the costs associated with the project?

A ) A bill of materials

B ) A Gantt chart

C ) A precedence diagram network

D ) A work breakdown structure61

Thank you

.