4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY
Stijn de Kruijf Data Center Facility Designer @Royal HaskoningDHV
DATA CENTER FACILITIES
Stijn de Kruijf
M: +31 6 51851476
E: [email protected] Certified TIA-942
![Page 2: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/2.jpg)
2016
Traditional data center practices
Data center development
2019
“Hidden”Revolution
2011
Data center revolution continues…
![Page 3: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/3.jpg)
Today
![Page 4: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/4.jpg)
For today…
• 4 Principles
• OCP San Jose summit – panel feedback
• OCP datacenter footprint reduction
![Page 5: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/5.jpg)
4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY
1
Simplify topology – Reduce costs
3
Time to “Think and Act”
4
OCP Integrated DC Operation & Communication
2
Integrated guidelines
DATA CENTER FACILITY
1 2
43
![Page 6: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/6.jpg)
Data center facility costs - Analysing
50% of the data center facility costs are for < 1% of the operation
Normal operation
Delivery
Capex & Opex
99%
80%
20% 100%
COP generators
Tier III Rated 4
2N+1Chillers
n=50 years
48 hours
Simplify topology – Reduce costs
How to get rid of the stuff used only less than 1% of the time?
![Page 7: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/7.jpg)
Really?
Do your still need to go 200 km/h with two flat tires?…. or get at a safe 50 km/h to the next garage.
![Page 8: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/8.jpg)
8
…..
What part of your data center IT environment is really critical?
Uncontrolled shutdown of IT equipment causes 20% to fail automatic restarting
The maximum power of a rack and a row a racks can be controlled already in OCP.
Why not use this possibility?
If you ramp down the your data storage access.
Your data is not lost!
Geo-redundancy can take care of local capacity limitations
…
Integrated guidelines
Can we define a “better questions”?
![Page 9: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/9.jpg)
Make better use time to respond(for example to scale down and or switch off less critical)
Data center IT is able to respond to
conditions outside the 99%.
UPS & UCS provides time to IT:
“To think and to act”!
Time to “Think and Act”
![Page 10: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/10.jpg)
OCP Integrated DC Operation & Communication
IT monitoring → Input for Controls Facility Facility monitoring → Input Controls IT
Source: OCP Intel/Baidu study on use of telemetry
![Page 11: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/11.jpg)
11
Open
facility
Open D
ata
cente
r
Com
munic
ation
Platform
OCP Data Center as ONE integrated machine
“by integration: balanced strategy between maximum uptime, performance and costs”1
![Page 12: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/12.jpg)
![Page 13: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/13.jpg)
1: OCP Environmental Conditions
Would it be acceptable for the design of your data center to have a maximum server inlet temperature condition of 35 degC (95 degF)?
• Why not? OPC gear can handle 40 degrees (ACS – liquid cooled can do more)• Not as standard working environment; too hot!• Air-management is key; recirculation occurring; Manage GPU and CPU temp• Okay for Scientific HPC; automatic managed lower clock speed; Not mission critical• Saves money (no compressor cooling) which can be spend on IT stack• No problem for OPENedge; can handle 45-55 degrees
DATA CENTER FACILITY
YES, NO PROBLEM NO, DON’T GO THERE
![Page 14: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/14.jpg)
2: Emergency Generator Capacity
Can you imagine operating a future data center with an emergency generator capacity < 80% of the normal operating load capacity?
• Why not? for locations which have high available grid at HV• Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key (five 9’s)• No allowance for the facility to fail ; should perform 100%• Scientific computing can work with power capping / geo-redundancy
DATA CENTER FACILITY
YES, NO PROBLEM NO, DON’T GO THERE
![Page 15: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/15.jpg)
3: OCP Data Center Facility
Would there be a market in the near future for OCP colocation facilities with in-rack UPS?
• Co- locators still provide centralized UPS / No solid market request to change• Dense IT solutions don’t want to spend 2 OU on in-rack UPS• Easy for maintenance on infrastructure because open transition allowed up
till rack level
DATA CENTER FACILITY
YES, NO PROBLEM NO, DON’T GO THERE
![Page 16: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/16.jpg)
4: OCP Principles Beyond the Rack
Are the power distribution paths to a row of racks of N acceptable in large scale deployments?
• Business to decide• Larger software stacks are design to resist failure on rack, row and even
data center level and are able to move applications around• Network availability is critical • Shift load during maintenance window is done already• Row of racks would be acceptable as increment
DATA CENTER FACILITY
YES, NO PROBLEM NO, DON’T GO THERE
![Page 17: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/17.jpg)
5: OCP and Industry Guidelines Gap
Do you reference industry standards or guidelines (S&G) in your design such as Uptime Institute, TIA-942, BICSI, …?
• Standards are based on the idea where Facility and IT are two separate worlds • Awareness of reasoning behind criteria e.g. 19”, input voltage• Avoid blindly use of standards and out-of-date versions• Challenging the industry guidelines by OCP is good• Different IT architecture require other data center facilities • Close connections in the industry between the different industry groups
DATA CENTER FACILITY
YES, NO PROBLEM NO, DON’T GO THERE
![Page 18: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/18.jpg)
6: Divide Between IT and Facility
In the data center communication between Software, IT hardware and Data Center facility to improve the total operation and environment?
• Political issues to overcome• Security to guarantee• IT owns the facility
DATA CENTER FACILITY
YES, NO PROBLEM NO
![Page 19: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/19.jpg)
Linking with other the groups is key
SERVER NETWORKINGSTORAGE RACK & POWER
DATA CENTER FACILITIES
TELCOMANAGEMENT HPC
SECURITY
OPEN SYSTEMS FIRMWARE
Also OpenEdge, OpenRMC, ACS
… especially for the facility
![Page 20: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/20.jpg)
Environment
… enables sustainability CHAIN responsibility
• Not spoiling energy, materials, water
• No waste → Circular approach
• Innovating on green energy
• Innovation on energy storage
OCP Data Center as ONE integrated machine…B
usin
ess
![Page 21: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/21.jpg)
21
Chain Responsibility
4 O
CP
PR
INC
IPLE
S F
OR
TH
E D
AT
A c
ente
r FA
CIL
ITY
The Open Integrated Domain Specific Data Center
![Page 22: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/22.jpg)
How do I get involved?Email Volunteer Leaders
Participate in Monthly MeetingTime: 3rd Wednesday at 10:30 Eastern/7:30 Pacific
Link: https://global.gotomeeting.com/join/490785413
Calendar: https://www.opencompute.org/projects/data-center-facility
Additional InformationProject Wiki: https://www.opencompute.org/wiki/Data_Center_Facility
Mailing List: https://ocp-all.groups.io/g/OCP-DCF
![Page 23: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/23.jpg)
![Page 24: 4 OCP PRINCIPLES FOR THE DATA CENTER FACILITY… · • Generators come with issues Capex$, Opex$, regulations, Emissions, Noise • Uptime and resilience of software stack is key](https://reader033.fdocuments.net/reader033/viewer/2022052519/5f1886c7fc317108611123e0/html5/thumbnails/24.jpg)
COMPETENCE center
MISSION CRITICAL FACILITIES
P.O. Box 151, 6500 AD Nijmegen,
Jonkerbosplein 52,
6534 AB Nijmegen
Stijn de Kruijf
Data center Developer
T: +31 88 348 66 43
M: +31 6 51851476
Certified TIA 942 Design Consultant – EPI
Uptime Institute Accredited Tier Specialist (ATS)
Prince2 Practitioner certified
Certified TIA-942 Design
Consultant