4. Flow-Time Analysis Problem 4.1 The Traffic Court of King James County operates 9 am-1 pm. Each...
-
Upload
julio-marrow -
Category
Documents
-
view
215 -
download
2
Transcript of 4. Flow-Time Analysis Problem 4.1 The Traffic Court of King James County operates 9 am-1 pm. Each...
4. Flow-Time Analysis
Problem 4.1
The Traffic Court of King James County operates 9 am-1 pm. Each morning, roughly at 9 p. m., 200 defendants show up for trial involving traffic violations. On a Monday, a sample of 10 defendants were selected at random. For each defendant, the actual time spent in discussion with the judge and the time paying the fine ( not including waiting) were recorded. Also recorded were the times the defendant arrived and left the court.
November 11, 2011 1Ardavan Asef-Vaziri
4. Flow-Time Analysis
Problem 4.1
a) Estimate the flow time. (9:30-8:45) + (9:45-8:45) + …… + (12:55-9:00) + (9:20-
9:00) = 1200.Average Flow Time = 1200/10 = 120 min.
b) Estimate the theoretical flow time. Average time with judge = (1+1.5+…..+ 1+1.5)/10 =
1.55 min. The average time to pay fine = (5+2+…..+ 2+3)/10 =
2.4 min.Theoretical flow time: 1.55 + 2.4 = 3.95 min.
c) What is the flow- time efficiency?3.95/120 = 3.3% November 11, 2011 2Ardavan Asef-Vaziri
4. Flow-Time Analysis
Problem 4.2
Wonder Shed Inc. ( Example 4.3) produces, in addition to the standard model, a deluxe version for the discriminating customer. The production process for the two models are identical and depicted in Figure 4.1. The activity times for deluxe models is listed below. All the times mentioned represent flow time at the various activities and include the effects of waiting.
November 11, 2011 3Ardavan Asef-Vaziri
Activity Activity Time (Work Content)
1 Separate 202 Punch the base 353 Punch the roof 454 Form the base 105 Form the roof 456 Subassemble the base 307 Assemble 258 Inspect 40
4. Flow-Time Analysis
Problem 4.2
a) Compute the process flow time for producing a deluxe
shed.
Path 1 (roof) : = 20+ 45 +45 +25+ 40 = 175 min.
Path 2 (base): = 20+35+10 +30+ 25+ 40= 160 min.
The critical path is path 1, and the flow time is 175 min.
b) What is the impact on flow time of the process if the
flow time of Activity 2 is increased to 40 minutes?
Activity 2 is on path 2 ( not the critical path). Increasing
the time of this activity by 5 minutes does not make
path 2 critical. c) What is the impact on flow time of the process if the
flow time of Activity 3 is reduced to 40 minutes?The flow time will be reduced to 170 minutes. (170 still
>160)
November 11, 2011 4Ardavan Asef-Vaziri
4. Flow-Time Analysis
Problem 4.3
When a guest calls room service, the room-service manager takes down the order. She submits an order ticket to the kitchen to begin preparing the food, and an order to the wine waiter to prepare alcoholic beverages . Finally, she assigns the order to a waiter. It takes 4 minutes to take down the order and to assign the work. It takes the kitchen 18 minutes to prepare the typical order, and the sommelier 6 minutes to prepare the drinks for the order. While the kitchen and the sommelier are doing their tasks, the waiter prepares the cart. This takes 10 minutes per order. Once the food, wine, and cart are ready, it takes the waiter 12 minutes to deliver the meal to the customer. It takes the waiter additional 4 minutes to return to the station and debit the guest’s account. All the times mentioned represent flow time at the various activities, and include the waiting times.
November 11, 2011 5Ardavan Asef-Vaziri
4. Flow-Time Analysis
Problem 4.3
a) Draw a process map from receipt of order to delivery
of food
Activity 2 is not on the critical pathc. The lead time will be reduced to 170 minutes. 4.3. a.
b) What is the flow time of the process?
The critical path time is 4+18 + 12 +4 = 34 min
November 11, 2011 6Ardavan Asef-Vaziri
Order
Food
Alcohol BillDeliver
Cart
4
18
10
12 46
4. Flow-Time Analysis
Problem 4.3
Activity 2 is not on the critical pathc. The lead time will be reduced to 170 minutes. 4.3. a.
c) What is the effect on the process flow time if the
waiter could prepare the cart in 8 minutes, instead of
10?
Cart preparation is not on the critical path.
d) What is the effect on the process flow time if the
waiter could deliver the order in 10 minutes, instead
of 12?
The critical path (flow time) is reduced by 2 min.
November 11, 2011 7Ardavan Asef-Vaziri
4. Flow-Time Analysis
Problem 4.4
A home insurance application consists of two forms: F1 and F2 . On receipt, each application is processed and separated into F1 and F2; 10 min. F1 requires Activity A for 15 min and then Activity B for 10 min. F2 requires Activity C for 20 min. F1 and F2 are then combined and further processed by a loan officer for 15 min. All the times mentioned represent flow time at the various activities, and include the effects of waiting.a) Draw a process flowchart for the processes.
November 11, 2011 8Ardavan Asef-Vaziri
F1
F2
Process And Separate
Activity C
Loan Officer
Activity B
Activity
A
10
15
20
15
10
4. Flow-Time Analysis
Problem 4.4
b) What is the flow time?
The flow time is 50 minutes. The critical path is the one
of F1.
c) What is the effect on flow time if 50% of F1 forms
must repeat Activity A one more time due to quality
problems?
Since 50% of F1 forms return to A, then 100% of F1
forms spend 15 minutes in A and the other 50% spend
15 more minutes at A. On average an F1 form spends
15+ 0.5(15) = 22.5.
Therefore activity A takes 7.5 minutes more.
Since activity A is on the critical path, the flow time will
increase 7.5 minutes, to 57.5 minutes.
November 11, 2011 9Ardavan Asef-Vaziri
4. Flow-Time Analysis
Problem 4.5
A single security line in Vancouver International Airport comprising an X- ray scanner for carry on items and a screening station for passengers. Passengers first prepare themselves for the inspection by removing belts, coats and shoes, emptying their pockets, etc. and deposit all the bags in the trays on the scanner. They then proceed and pass through the screening station . They then retrieve their belongings. The X- ray scanner takes 40 seconds per tray, and the average passenger utilizes 1.5 trays. The personal screening station requires 30 seconds per person. Finally, retrieving of belongings and getting reorganized takes 60 seconds. All the times mentioned represent activity time at the various activities and do not include the effects of waiting. November 11, 2011 10Ardavan Asef-Vaziri
4. Flow-Time Analysis
Problem 4.5
a) Draw a process map for the security check process.
November 11, 2011 11Ardavan Asef-Vaziri
b) What is theoretical flow time of the security check
process? The critical path is the one through the X-ray
scanner.
The flow time is 30 + 40*1.5 + 60 = 150 seconds.
4. Flow-Time Analysis
Problem 4.5
c) A sample of 20 passengers were selected at random
and the time required for each to clear the security
check was recorded. The average of the individual times
was 530 seconds. What is the process flow-time
efficiency?
The flow time efficiency is 150/530 = 28%
d. What is the impact on theoretical flow time of the
process if the personal screening activity is expedited to
20 seconds?
The personal scanner is not on the critical path.November 11, 2011 12Ardavan Asef-Vaziri
4. Flow-Time Analysis
A temp work service maintains an “inventory” of 200
computer specialists who are assigned to various
customers on a short term basis. The typical tour of
duty lasts for 7 weeks, and the period between
assignments typically lasts for 3 weeks. Assume 50
weeks per year.
a) On average, how many specialists start on a new
assignment each week?
Critical Path Example of Flow Time
November 11, 2011 13Ardavan Asef-Vaziri
4. Flow-Time Analysis
Lets assume each job is composed of 7 weeks of activity
A (working on a job) and activity B (doing nothing).
Therefore we always have 200 of these jobs. Some
specialist are working on
The flow time of entire process is 3+7 = 10 weeks
Inventory is 200
RT = I R= I/T = 200/10 = 20 per week
Alternatively, each job takes 10 weeks. Each specialist
will be assigned 1/10 of a new job per week. There are
200 specialists, they will be assigned 200(1/10) = 20
new jobs per week. R = 20.
Critical Path Example of Flow Time
November 11, 2011 14Ardavan Asef-Vaziri
4. Flow-Time Analysis
b) On average, how many specialists are idle (between
assignments)?
The flow time of “idle” is 3 weeks R=3
R = The throughput is 20 per week
RT = I 20(3) = 60
Alternative way % of idle time 3/10= 30%. Thus 30% of
staff will be idle on average, ( 30% of 200 = 60)
Critical Path Example of Flow Time
November 11, 2011 15Ardavan Asef-Vaziri
4. Flow-Time Analysis
Practice: Draw the Network of Activities
Task Pred. Dur. Task Pred. Dur.
a -- 4 g c,d 1
b -- 3 h e 4
c a 3 i f 5
d a 2 j e,g 6
e b 6 k h,i 1
f b 4
For each task, compute ES, EF, LF, LS, slack
November 11, 2011 16Ardavan Asef-Vaziri
4. Flow-Time Analysis
Practice: Compute the Theoretical Flow Time
Start Finish
a=4slack=
b=3slack=
c=3slack=
d=2slack=
e=6slack=
f=4slack=
g=1slack=
h=4slack=
i=5slack=
j=6slack=
k=1slack=
Task=durslack=xxx
LST LFT
EFTEST
November 11, 2011 17Ardavan Asef-Vaziri
4. Flow-Time Analysis
Practice: Compute the Theoretical Flow Time
Start Finish
a=4slack=
b=3slack=
c=3slack=
d=2slack=
e=6slack=
f=4slack=
g=1slack=
h=4slack=
i=5slack=
j=6slack=
k=1slack=
Task=durslack=xxx
LST LFT
EFTEST
November 11, 2011 18Ardavan Asef-Vaziri
4. Flow-Time Analysis
Practice: Compute the Theoretical Flow Time
Start Finish
a=4slack=
b=3slack=
c=3slack=
d=2slack=
e=6slack=
f=4slack=
g=1slack=
h=4slack=
i=5slack=
j=6slack=
k=1slack=
Task=durslack=xxx
LST LFT
EFTEST
November 11, 2011 19Ardavan Asef-Vaziri
4. Flow-Time Analysis
Practice: Compute the Theoretical Flow Time
Start Finish
a=4slack=
b=3slack=
c=3slack=
d=2slack=
e=6slack=
f=4slack=
g=1slack=
h=4slack=
i=5slack=
j=6slack=
k=1slack=
Task=durslack=xxx
LST LFT
EFTEST
November 11, 2011 20Ardavan Asef-Vaziri
4. Flow-Time Analysis
Practice: Compute the Theoretical Flow Time
Start Finish
a=4slack=
b=3slack=
c=3slack=
d=2slack=
e=6slack=
f=4slack=
g=1slack=
h=4slack=
i=5slack=
j=6slack=
k=1slack=
Task=durslack=xxx
LST LFT
EFTEST
November 11, 2011 21Ardavan Asef-Vaziri
4. Flow-Time Analysis
EZS is a small fast food outlet serving mainly the corporate clientele. EZS’ main fare is a freshly prepared, customizable line of sandwiches. It is supplemented with an assortment of drinks, light salads, seasonal fruit and snacks. The restaurant is open 10:00AM to 10:00PM, but the peak demand is during lunch hours, 11:30 to 2:00PM. A customer joining the line makes a sandwich selection by consulting the billboard, marks her selection on a customized form, and hands the form to one of several assemblers who produce the sandwich. The customer does not wait for the sandwich to be assembled, but proceeds directly down the line to select additional items onto her tray. Next, the customer proceeds to pay at the cash register. Finally, (after the payment is completed) she collects her prepared sandwich at a designated location. Selecting the sandwich and marking the form takes 45 seconds. Assembling the sandwich requires 90 seconds. Selecting additional items takes 60 seconds. Paying at the cash register requires 40 seconds. Collecting the prepared sandwich requires 20 seconds. The restaurant employs 2 cash registers and 6 sandwich assemblers, and one person to disburse the prepared sandwiches.
Critical Path Example of Flow Time
November 11, 2011 22Ardavan Asef-Vaziri
4. Flow-Time Analysis
a) Draw a process map
Critical Path Example of Flow Time
November 11, 2011 23Ardavan Asef-Vaziri
b) What is the theoretical flow time of the process?
The critical path is the top one, = 45 +60 + 40 +20 =
165 sec
4. Flow-Time Analysis
Capacity and Buttleneck
November 11, 2011 24Ardavan Asef-Vaziri
c) What is the capacity of the process?
Assembly Capacity = 6*60/90 = 4 per min.
Cash register Capacity = 2*60/40 = 3 per min.
Disburse capacity = 1*60/20= 3 per min (assuming
time to collect = time to disburse).
d) During rush hour, demand exceeds capacity and long
lines form. Does it make sense to add a sandwich
assembler
No. Assembler is not a bottleneck
4. Flow-Time Analysis
Honda's he "American Classic Edition" (ACE) motorcycle is assembled in the US from four
major subassemblies. The first subassembly produces the engine: (i) The left and right
part of the engine block come out of the automatic mold every 2 min. (ii) These parts are
welded together, requiring 1 min of welding machine. (iii) It takes the engine assembler 3
min to insert the two pistons and four valves. The second subassembly produces the
frame in two steps: (i) Heavy metal bars are bent in the 10K-pound press in 1 min. (ii) It
takes 3 min to weld the multiple bars together with the welding machine to produce the
frame. The third subassembly consists of the front and rear fenders, both of which are
formed using the same 10K-pound press for 1 min each. The fourth subassembly makes
the seat. It takes an assembler 7 min to cut the padding, pit it on a performed piece of
sheet metal and wrap the two with synthetic leather. In final assembly, first the four
subassemblies are put together. It takes 30 min to finish assembly of one motorcycle.
Currently, Honda ACE staffing is as follows there is 1 molding machine operator, 1 welder
1 press operator, 1 engine assembler, 2 seats assemblers, and 10 final assemblers.
a) Draw a process flowchart identifying resources, activity times, and any potential
storage buffers
Problem 4.4 from Second Edition. Four major subassemblies; Engine, Frame, Fenders, Seats.
4. Flow-Time AnalysisProblem 4.4 from Second Edition. Four major subassemblies; Engine, Frame, Fenders, Seats.
molding eng. ass.
seat ass.
stamping
welding
FA
aut. molding machine
1 molding operator
10K lbs press
1 press operator
welding machine
1 welder
2 seat assemblers
1 engine assembler
10 final assemblers
startend
2 min 1 min 3 min
1 min 3 min
2 min
7 min
30 minstamping welding
November 11, 2011 26Ardavan Asef-Vaziri
4. Flow-Time Analysis
Problem 4.4 from Second Edition.
b) What is the theoretical flow time of the ACE
production process?
We have 4 paths, the critical path is the longest path =
37 minutes (going through seat assembly). Therefore,
the theoretical flow time = 37 minutes.
c) Knowing the benefits of flow-time reduction, Honda
would like to decrease the theoretical flow time of the
ACE process. Which specific action(s) do you
recommend?
November 11, 2011 27Ardavan Asef-Vaziri
4. Flow-Time Analysis
Problem 4.4 from Second Edition.
We can decrease the theoretical flow time only by
decreasing the length of the critical path. Thus we
need to decrease the theoretical flow times of seat
assembly and/or final assembly: try to change the
design and process so that we can perform subtasks
parallel.
Easiest is to do final assembly of the first three
subassemblies first and seat assembly at the end.
November 11, 2011 28Ardavan Asef-Vaziri
4. Flow-Time Analysis
Cross-traning
Cross training may not reduce flow time if the activities
cannot be subdivided into smaller activities that could
be done in parallel.
November 11, 2011 29Ardavan Asef-Vaziri
5
1
3 2
5
1
3 2
3
1
3 22