PREVENTIVE MAINTENANCE OF WATER CHILLER
1. Chiller use/sequencing (daily)
Turn off/sequence unnecessary chillers
2. Overall visual inspection (daily)
Complete overall visual inspection to be sure all equipment is operating and safety
systems are in place
3. Check set-points (daily)
Check all set-points for proper setting and function
4. Evaporator and condenser (weekly)
Assess evaporator and condenser coil fouling as required
5. Compressor motor temperature (weekly)
Check temperature per manufacturer’s specifications
6. Perform water quality test (weekly)
Check water quality for proper chemical balance
7. Leak testing (weekly)
Conduct leak testing on all compressor fittings, oil pump joints and fittings, and relief
valves
8. Check all insulation (weekly)
Check insulation for condition and appropriateness
9. Control operation (weekly)
Verify proper control function including:
• Hot gas bypass
• Liquid injection
10. Check vane control settings (semiannual)
Check settings per manufacturer’s specification
11. Verify motor load limit control (semiannual)
Check settings per manufacturer’s specification
![Page 2: (4) CHILLER PREVENTIVE MAINTENANCE written by Arnold](https://reader035.fdocuments.net/reader035/viewer/2022073120/55d0157dbb61eb6e238b45c4/html5/thumbnails/2.jpg)
12. Verify load balance operation (semiannual)
Check settings per manufacturer’s specification
13. Check chilled water reset settings and function (semiannual)
Check settings per manufacturer’s specification
14. Check chiller lockout set point (annually)
Check settings per manufacturer’s specification
15. Clean condenser tubes (annually)
Clean tubes at least annually as part of shutdown procedure
16. Eddy current test condenser tubes (annually)
As required, conduct eddy current test to assess tube wall thickness
17. Clean evaporator tubes (annually)
Clean tubes at least annually as part of shutdown procedure
18. Eddy current test evaporator tubes (annually)
As required, conduct eddy current test to assess tube wall thickness
19. Compressor motor and assembly (annually)
• Check all alignments to specification
• Check all seals, provide lubrication where necessary
20. Compressor oil system (annually)
• Conduct analysis on oil and filter
• Change as required
• Check oil pump and seals
• Check oil heater and thermostat
• Check all strainers, valves, etc.
21. Electrical connections (annually)
Check all electrical connections/ terminals for contact and tightness
22. Water flows (annually)
Assess proper water flow in evaporator and condenser
23. Check refrigerant level and condition (annually)
Add refrigerant as required. Record amounts and address leakage issues.