3g Optimization 1

53
January 2005 AIRCOM International 2005 3G RF Optimisation Basics Robert Joyce

Transcript of 3g Optimization 1

Page 1: 3g Optimization 1

January 2005

AIRCOM International 2005

3G RF Optimisation Basics

Robert Joyce

Page 2: 3g Optimization 1

January 2005

AIRCOM International 2005

WCDMA Basics

▪ Frequency Reuse▪ Scrambling Codes▪ Signal Strength/Quality Measurements in WCDMA▪ Soft/Softer Handover▪ Pilot Pollution▪ Missing Neighbours

Page 3: 3g Optimization 1

January 2005

AIRCOM International 2005

UK 3G Spectrum Allocations

From (MHz) To (MHz) From (MHz) To (MHz) From (MHz) To (MHz)A Hutchison 3G 1920.0 1934.9 2110.3 2124.9 1914.9 1920.0 2x15 + 5 = 35B Vodafone 1944.9 1959.7 2134.9 2149.7 N/A N/A 2x14.8 = 29.6C O2 1934.9 1944.9 2124.9 2134.9 1909.9 1914.9 2x10 + 5 = 25D T-Mobile 1959.7 1969.7 2149.7 2159.7 1899.9 1904.9 2x10 + 5 = 25E Orange 1969.7 1979.7 2159.7 2169.7 1904.9 1909.9 2x10 + 5 = 25

Total (MHz)TDD

Licence OperatorFDD DownlinkFDD Uplink

19051910 1960

FDD Uplink

Licence A - Hutchison 3GLicence B - Vodafone

1935

Licence C - O2

Licence D - T-Mobile

FDD Downlink

21502110

Licence E - Orange

19151920 1980 21251945 1970 2135 2160

TDD

Page 4: 3g Optimization 1

January 2005

AIRCOM International 2005

Frequency Reuse

▪ Initially operators have been launching with just a single carrier▪ Vodafone NZ Network will initially be FDD only▪ Vodafone will launch using only the FDD carrier (F1 =10588)▪ All launch cells will use F1 & therefore Vodafone NZ’s 3G network

will have a frequency reuse of 1

UARFCNFrequency

(MHz)FDD Uplink F1 9638 1927.6

F2F3

FDD Downlink F1 10588 2117.6F2F3

Page 5: 3g Optimization 1

January 2005

AIRCOM International 2005

Scrambling Codes & CPICH

▪ The Common Pilot Indication Channel (CPICH) is broadcast from every cell

▪ It carries no information and can be thought of as a “beacon”constantly transmitting the Scrambling Code of the cell

▪ It is this “beacon” that is used by the phone for its cell measurements for network acquisition and handover purposes (Ec, Ec/Io).

CPICH

Page 6: 3g Optimization 1

January 2005

AIRCOM International 2005

3G Coverage Measurements

▪ The majority of 3G coverage measurements are based upon measurements of the CPICH

▪ Golden Rule: If the UE can’t see the CPICH the UE can’t see the cell.

▪ Initial 3G network optimisation will be performed purely from CPICH measurements

▪ Three key related measurements for 3G optimisation are

▪ Ec - The Received Signal Level of a particular CPICH (dBm)▪ Io - The Total Received Power (dBm)▪ Ec/Io - The CPICH Quality (The ratio of the above two values)

Page 7: 3g Optimization 1

January 2005

AIRCOM International 2005

Total Received Power Io

▪ In a WCDMA network the User Equipment (UE) may receive signals from many cells whether in handover or not

▪ Io* = The sum total of all of these signals + any background noise (dBm)

▪ *Note: Sometimes Io is referred to as No, RSSI or ISSI

Io

Page 8: 3g Optimization 1

January 2005

AIRCOM International 2005

Received Power of a CPICH Ec

▪ Using the properties of SCs the UE is able to extract the respective CPICH levels from the sites received

▪ Ec* = The Received Power of a Particular CPICH (dBm)

▪ *Note: Sometimes Ec is referred to as RSCP

Ec1 Ec2

Page 9: 3g Optimization 1

January 2005

AIRCOM International 2005

The CPICH Quality (Ec/Io)

▪ From the previous two measures we can calculate a signal quality for each CPICH (SC) received

▪ Ec/Io = Ec - Io (dB)

▪ *Note: Sometimes Ec/Io is referred to as Ec/No

Ec1 Ec2

Page 10: 3g Optimization 1

January 2005

AIRCOM International 2005

Example

▪ From the above three measurements we can calculate for each pilot the Ec level for that particular pilot

▪ Ec1 = -80 - 5 = -85dBm▪ Ec2 = -80 - 10 = -90dBm

Ec/Io1=-5dB Ec/Io2 =-10dB

Io=-80dBm

Page 11: 3g Optimization 1

January 2005

AIRCOM International 2005

Ec, Io and Ec/Io Measurement

▪ All commercial scanners and test UEs are capable of making Ec, Io and Ec/Io measurements

▪ It is these measurements that are used for cover analysis and basic optimisation

Page 12: 3g Optimization 1

January 2005

AIRCOM International 2005

3G Scanners

▪ Many types of 3G scanners on the market▪ Agilent’s 3G Scanner & Nitros Software▪ Anritsu’s ML8720B 3G scanner▪ DTI Seagull (Dual band 3G/2G) scanner

▪ From experience the Anritsu scanner is the better of the all three with a higher sampling rate and greater flexibility

▪ However DTI scanner has added benefit of 2G scanning, ideal for 3G-2G neighbour optimisation as well as 2G optimisation

Page 13: 3g Optimization 1

January 2005

AIRCOM International 2005

Handovers in WCDMA

▪ Various handover types exist in WCDMA

▪ Those between WCDMA sites (intra-system HO)▪ Those between WCDMA and GSM (inter-system HO)

Page 14: 3g Optimization 1

January 2005

AIRCOM International 2005

Handovers in WCDMA - Softer HO

▪ Softer handover occurs between sectors of the same site

Page 15: 3g Optimization 1

January 2005

AIRCOM International 2005

▪ Soft handover occurs between sectors of the different sites

▪ For both softer and soft it is the Ec/Io levels used to determine whether a cell should be added or removed from the active set

Handovers in WCDMA - Soft HO

Page 16: 3g Optimization 1

January 2005

AIRCOM International 2005

Handovers - Inter frequency HO

▪ Inter frequency handover occurs between two WCDMA carriers▪ Will be used once operator deploys its second carrier, for microcell

layer or capacity purposes

Page 17: 3g Optimization 1

January 2005

AIRCOM International 2005

Handovers - Inter system HO

▪ Inter system handover occurs between 3G and 2G sites▪ As with all handovers, accurate adjacencies will be required

3G 2G

Page 18: 3g Optimization 1

January 2005

AIRCOM International 2005

Optimisation Basics

▪ Coverage Optimisation▪ Neighbour Optimisation▪ Pilot Pollution Optimisation▪ SHO Optimisation

Page 19: 3g Optimization 1

January 2005

AIRCOM International 2005

Coverage Optimisation

▪ As with 2G if the coverage is inadequate then the call quality will be inadequate

▪ Therefore this first stage in 3G optimisation is ensuring adequate coverage

▪ Link budgets should be used to determine both the planning targets and the drive survey level targets

▪ Note that the planning and drive survey level targets will be different

Page 20: 3g Optimization 1

January 2005

AIRCOM International 2005

Coverage Optimisation

Dense Urban Urban/Suburban Rail Road Rural IndoorDeep Indoor - 95% Deep Indoor - 95% Indoor Window - 95% Indoor Window - 95% Outdoor - 90% 95%

12.2k Speech -71.0 -81.0 -88.0 -95.0 -102.0 -102.064k CSD -72.0 -82.0 -90.0 -96.0 -103.0 -102.064k PSD -73.0 -82.0 -90.0 -97.0 -103.0 -103.064k CSD Videophone -71.0 -80.0 -88.0 -94.0 -101.0 -101.0144k CSD -69.0 -79.0 -86.0 -93.0 -100.0 -99.0144k PSD -70.0 -79.0 -87.0 -94.0 -100.0 -100.0384k CSD -65.0 -75.0 -84.0 -90.0 -95.0 -95.0384k PSD -66.0 -76.0 -84.0 -90.0 -96.0 -96.0

ServiceEnvironment

▪ These levels are the levels that should be achieved at the roof of the vehicle

▪ If these levels are not achieved then inbuilding coverage will be poor▪ Further optimisation with lower coverage levels is very difficult▪ Solutions: Downtilt, Azimuth, New Site

▪ Given below are example target drive survey Ec levels for the different 3G services

Page 21: 3g Optimization 1

January 2005

AIRCOM International 2005

Neighbour Optimisation

▪ Missing Neighbours was and still is the biggest cause of poor performance in most commercial 3G networks

▪ The majority of call drops in early cluster are due to missing neighbours.

▪ It is therefore essential that the initial neighbour list is thorough, ideally with neighbours ranked in order of importance

▪ In 3G the UE must be on the best cell at all times … otherwise it will drop the call – this is not the case in 2G

▪ 3G/2G neighbour lists must also be comprehensive, incorrect 3G/2G neighbour lists will lead to dropped calls when moving from 3G to 2G and poor 3G re-selection performance when on 2G

Page 22: 3g Optimization 1

January 2005

AIRCOM International 2005

3G/3G Neighbour Optimisation

▪ We declare a 3G missing neighbour as a a cell not declared as neighbour of the best active cell although it is eligible to be added in the active set.

▪ A practical margin of 5dB is recommended as an initial window …anything bigger and the neighbour lists become too large

▪ Solution: 3G Scanner Survey, Actix Analysis, Neighbours Added

NMISSINGBESTNMISSING inMEcNoEcNo __ arg−≥

Page 23: 3g Optimization 1

January 2005

AIRCOM International 2005

2G/3G Neighbour Optimisation

▪ 2G/3G neighbour optimisation will require the use of both 3G and 2G drive survey equipment

▪ Dualband scanner files can quickly be processed to pair up the best 3G cells with the best 2G cells for every sample along the drivesurvey.

Page 24: 3g Optimization 1

January 2005

AIRCOM International 2005

Pilot Pollution Optimisation

▪ As more and more 3G sites are integrated, the pilot pollution within the network will increase

▪ With >4 pilots of a similar level it can be very difficult to establish even a voice call

▪ The higher the data rate the more susceptible the service is to pilot pollution (bad Ec/Io).

▪ Whilst 3G voice requires an Ec/Io of above -15dB, 384kbps will required Ec/Io levels of -9dB or higher !!

▪ Pilot pollution should not be confused with poor coverage, where there is poor coverage, there is generally pilot pollution/bad Ec/Io

Page 25: 3g Optimization 1

January 2005

AIRCOM International 2005

PS384 - Pilot Pollution Areas

▪ DL_PS384 is much more sensitive to pilot pollution or overlaps than lower bit-rates. Optimising pilot pollution for PS128 is already a challenge, for 384 might be an unrealistic target.

▪ Comparison of required EcIo:

Service Voice PS64 PS128 PS384Min EcIo -15 -13 -13 -9.5

▪ Even with good Ec levels, some areas will never provide reliablePS384 simply due to cell overlaps. It seems unclear whether a mature network may ever provide a full 384 footprint.

Conclusion: 384 requires an optimised network

Page 26: 3g Optimization 1

January 2005

AIRCOM International 2005

Required EcIo

GPRS Attach Success Rate vs Serving CPICH Ec/Io

-20%

0%

20%

40%

60%

80%

100%

120%

-19 -18 -17 -16 -15 -14 -13 -12 -11 -10 -9 -8 -7 -6 -5

Serving Cell CPICH Ec/Io (dB)

GPRS Attach Success Rate

Page 27: 3g Optimization 1

January 2005

AIRCOM International 2005

PS384 - required EcIo

DL Application Throughput vs. Serving Cell CPICH Ec/Io

0

50

100

150

200

250

300

-14 -12 -10 -8 -6 -4 -2 0Serving Cell CPICH Ec/Io (dB)D

L A

pplic

atio

n Th

roug

hput

(kbp

s)

Mean DL Application Throughput

Mode DL Application Throughput

DL Application Throughput (Last Value)

Page 28: 3g Optimization 1

January 2005

AIRCOM International 2005

Pilot Pollution Optimisation

▪ To avoid confusing areas of poor coverage with areas of pilot pollution we can define an area of pilot pollution as somewhere where

▪ The Ec target is the target coverage = -100dBm▪ The current recommended Ec/Io target = -10dB▪ Actix is able to identify areas of pilot pollution and display the locations

on a map

Best server CPICH_Ec >= Ec target (dBm)

And

Best server CPICH EcNo < Ec/Io target (dB)

Page 29: 3g Optimization 1

January 2005

AIRCOM International 2005

Pilot Pollution Optimisation

▪ There are various means of reducing pilot pollution▪ New Sites: Additional sites may reduce pilot pollution by bringing

dominance to an area (before optimising for pilot pollution, always check that a new site is not about to be brought on air in the locality)

▪ Antenna Downtilts: By adjusting tilts on the best servers, or worst interferers, pilot pollution can be removed

▪ Solution: 3G Scanner Survey, Analysis, Downtilts, New Sites?

Page 30: 3g Optimization 1

January 2005

AIRCOM International 2005

Handover Optimisation

▪ Softer, Soft, Inter-frequency & system HOs have all been optimised on Nokia’s trial and other customers networks

▪ Therefore initial HO Optimisation should not require any changes to the UTRAN parameters ….

▪ Instead initial HO optimisation will involve studying how much HO occurs in the network and where this HO occurs.

▪ For 3G/3G HO, Actix is able to display areas where Softer & Soft HO is occurring and calculate the percentage of a drive route in SHO

▪ Typically we should be aiming for a SHO area of less that 40%▪ Optimisation of SHO area should be performed using downtilt and

azimuth changes▪ Solution: 3G Scanner Survey, Analysis, Downtilt and Azimuth

changes

Page 31: 3g Optimization 1

January 2005

AIRCOM International 2005

Optimisation Basics

▪ Coverage Optimisation▪ Neighbour Optimisation▪ Pilot Pollution Optimisation▪ SHO Optimisation

▪ Everything is based around Ec/Io, to improve this we need to

▫ Increase Ec (improve the best server(s))▫ Reduce Io (reduce pilots not eligible for the active set)▫ Get all neighbours optimised

▪ In call drive runs should only take place once Radio Optimisation is complete

Page 32: 3g Optimization 1

January 2005

AIRCOM International 2005

Overview of Vodafone New Zealand Optimisation Process

Page 33: 3g Optimization 1

January 2005

AIRCOM International 2005

OrangeUK 3G Optimisation Process

▪ This section will cover the following;

▪ Overview of Vodafone New Zealand 3G Optimisation Process▪ Key Performance Indicators▪ Analysis Tools & Processes▪ Next Steps

Page 34: 3g Optimization 1

January 2005

AIRCOM International 2005

Overview of Vodafone NZ’s 3G Optimisation Process

▪ Based upon the 3G Optimisation Process flowcharts agreed between Aircom/Nokia and Vodafone New Zealand

1 hour prior to every cluster Drive test 3G Opt eng must

obtain CDF dump from OSS eng

CDF file obtainable ?

3G Opt eng obtains Alarm report and cell availability

report from OSS eng

Yes

No

CDF = Cell Definition File

Yes

Check with Nokia Opt manager

High number of alarm ?

Can drive testproceed ?

Yes

No

Can drive testproceed ?

Check with Nokia Opt manager

Yes

High cell availability ?

No Check with Nokia Opt manager

Yes Yes Can drive teststart ?

Can OMC solve the problem < 4

hours?

Yes

OMC works onsolving the alarm

Is the problem solved ?

No

Optimization Stage 1(Optimize RF condition)

Optimization Stage 2(Optimize Neighbour list)

Optimization Stage 3(Optimize Call Performance)

Postpone the drive testto next day or until

Problem solved

Can OMC solve the problem < 4

hours?

Yes

OMC works onIncreasing cell

availability

Is the problem solved ?

No

Stage 1 completed?

Stage 2 completed?

Stage 3 completed?

KPI measurementand reporting

Postpone the drive testto next day or until

Problem solved

No

No

No

Yes

Yes

Yes

No

No

NoNo

Yes

Yes

A

A

A

A

D

C

B

Drive test starts

A.1

A.3A.2

A.4

A.5

A.6 A.7

A.8A.9

A.10

A.11A.12

A.13A.14

A.15

A.16A.17

A.19

A.21

A.22

A.20

A.23

A.24

A.18

Page 35: 3g Optimization 1

January 2005

AIRCOM International 2005

Overview of Vodafone NZ’s 3G Optimisation Process

▪ Based upon the 3G Optimisation Process flowcharts agreed between Aircom/Nokia and Vodafone New Zealand

▪ Stage 1 & 2 cover the basic RF Optimisation steps described earlier

▪ Only once these steps are completed is it worth moving onto Stage 3 – Call Performance Optimisation

Yes

Optimization Stage 1(Optimize RF condition)

Optimization Stage 2(Optimize Neighbour list)

Optimization Stage 3(Optimize Call Performance)

Stage 1 completed?

Stage 2 completed?

Stage 3 completed?

KPI measurement

No

No

No

Yes

Yes

Yes

A

A

A

D

C

B

Drive test starts A.8

A.10

A.14

A.17

A.22

A.20

A.23

A.24

Page 36: 3g Optimization 1

January 2005

AIRCOM International 2005

Key Performance Indicators (KPI)

▪ In order to benchmark the performance of a 3G network a basic set of KPI targets are required

▪ The Vodafone NZ 3G KPI targets fall into two categories, RF KPIs and in-call KPIs

▪ The Vodafone RF KPIs are very simple and concise but focus on the key RF requirements of Ec (RSCP), Ec/Io and SHO area

▪ The In Call or End To End (E2E) KPIs are somewhat more complex

Page 37: 3g Optimization 1

January 2005

AIRCOM International 2005

Vodafone RF KPIs▪ The RF targets are defined in terms of: -

▫ RSCP of the Common Pilot Channel▪ -89 dBm in >= 95% of bins for dense urban▪ -94 dBm >= 95% of bins for urban▪ -99 dBm >= 95% of bins for suburban▪ -104 dBm >= 90% of bins for rural

▫ Ec/Io of Common Pilot Channel in unloaded network▪ Ec/Io >= –10 dB in >= 95% of bins for DU, U, SU▪ Ec/Io >= –10 dB in >= 90% of bins for Rural

▫ Ec/Io of Common Pilot Channel in loaded network▪ Ec/Io >= –14 dB in >= 95% of bins for DU, U, SU▪ Ec/Io >= –14 dB in >= 90% of bins for Rural▪ Test case to be agreed

▫ SHO Overhead: 30-40%▪ This Kpi will be measured according to the formula below:

SetActiveinCellsBinsSetActiveinCellsBinsSetActiveinCellBinsSetActiveinCellsBinsSetActiveinCellsBinsSetActiveinCellBins

____3__#____2__#____1__#3____3__#2____2__#1____1__#

++×+×+×

Page 38: 3g Optimization 1

January 2005

AIRCOM International 2005

RF Optimisation

▪ Basic RF analysis checking the following

▪ Coverage Optimisation▪ Neighbour Optimisation▪ Pilot Pollution Optimisation▪ SHO Optimisation.

▪ First stage is to run the KPI reports, then follows this with more detailed analysis.

▪ If the route meets the RF KPIs there’s no point doing further analysis

Page 39: 3g Optimization 1

January 2005

AIRCOM International 2005

Actix RF KPI Report

▪ Run the basic RF KPI report – check the KPIs

Page 40: 3g Optimization 1

January 2005

AIRCOM International 2005

Basic “Sites on air” analysis

▪ For each cell in the cluster check that coverage is seen for the sites expected to be on air

▪ Check correct SC is radiating in the expected direction (crossed feeders?)

▪ Highlight those sites not seen on air and any suspected crossed feeders

▪ But make sure your cell refs data is accurate !!!

Page 41: 3g Optimization 1

January 2005

AIRCOM International 2005

Coverage (Ec) Analysis

▪ If KPI Report indicates good Ec - no further Ec analysis required !▪ Otherwise analyse !!▪ Solution: Tilts, azimuths, new sites

Page 42: 3g Optimization 1

January 2005

AIRCOM International 2005

Neighbour Optimisation

▪ If downtilts are to be made to any sectors, then additional neighbours should not be added to/or for these cells as they may not be necessary after downtilts

▪ Actix should be used to generate Missing Neighbour Report from Scanner data

▪ Remember until the cluster is complete, additional neighbours will come and go

Page 43: 3g Optimization 1

January 2005

AIRCOM International 2005

3G/3G Neighbour Optimisation (2)

▪ 3G Neighbour lists can be generated automatically by the Actix

▪ The tool runs through every point in the survey comparing the Ec/Io values of the SCs seen generating a neighbour list like the one given

▪ The number of missing neighbours found will be dependent on the quality of the initial neighbour list

▪ Don’t be scared of adding neighbours !!

sc neighbour count8 9 1658 232 528 496 408 344 348 154 188 386 128 10 118 362 118 145 108 114 88 256 58 488 58 360 48 376 48 346 38 50 18 218 18 490 18 66 18 152 18 48 18 378 18 401 19 8 1149 362 379 10 10

Page 44: 3g Optimization 1

January 2005

AIRCOM International 2005

Pilot Pollution (Ec/Io) Analysis

▪ Run Pilot Pollution query to display areas of pilot pollution on map

Page 45: 3g Optimization 1

January 2005

AIRCOM International 2005

Pilot Pollution (Ec/Io) Analysis

▪ Identify worst “Pilot Polluters” on map▪ Solution: tilts, azimuths, new site?

Page 46: 3g Optimization 1

January 2005

AIRCOM International 2005

SHO Analysis

▪ KPI report will indicate % of route in SHO▪ Aim for SHO < 40%▪ Run RE SHO query to display areas on a map - is this due to distant

sites, is it in important high traffic areas?▪ Solution: Tilts, Azimuths

Page 47: 3g Optimization 1

January 2005

AIRCOM International 2005

Cell Adjacency Planner - CAP3G – 2G Adjacencies

Page 48: 3g Optimization 1

January 2005

AIRCOM International 2005

Cell Adjacency Planner - CAP3G – 3G adjacencies

Page 49: 3g Optimization 1

January 2005

AIRCOM International 2005

3G/3G Neighbour Optimisation (3)

Page 50: 3g Optimization 1

January 2005

AIRCOM International 2005

Stage 3: In Call Optimisation

▪ Only once the RF Optimisation is complete should In Call analysis be undertaken

▪ In call analysis will also pick up▫ Coverage Problems▫ Pilot Pollution Problems▫ Missing Neighbours▫ SHO problems

▪ However if the RF Optimisation has been done correctly, none of the above should be seen at Stage 3 !

▪ In Call Optimisation will be similar to RF Optimisation▫ Run In Call KPI report▫ Analyse any problems seen

Page 51: 3g Optimization 1

January 2005

AIRCOM International 2005

Stage 3: Run Call KPIs Report

▪ Run RE Call KPI report▪ Identify problem areas, Call Setup Success, Call Drop etc.

Page 52: 3g Optimization 1

January 2005

AIRCOM International 2005

Stage 3: Detailed In call analysis

▪ Detailed in call analysis▪ Look for the basics first, Ec, Ec/Io, missing neighbours etc.▪ Only then delve into the detailed L3 message flows.

Page 53: 3g Optimization 1

January 2005

AIRCOM International 2005

Process Summary

▪ Stage 0 Cluster Preparation - plots, site checks, neighbour checks etc.

▪ Stage 1&2 RF optimisation, Ec, Ec/Io, Missing Neighbours, SHO Area

▪ Stage 3 In Call Analysis (Speech, Video, PS, ISHO etc) – will be the subject of a further training session once Actix Reports in place.

▪ CLUSTER ACCEPTANCE !!

▪ Any questions: [email protected]