37231-043-pak-iee.pdf
-
Upload
yousaf-shad-muhammad -
Category
Documents
-
view
217 -
download
3
Transcript of 37231-043-pak-iee.pdf
-
Initial Environmental Examination August 2012
PAK: Punjab Irrigated Agriculture Investment Program, Tranche 3 Pakpattan Canal and Suleimanki Barrage Improvement Project Prepared by Punjab Irrigation Department, Government of Pakistan for the Asian Development Bank.
-
Initial Environmental Examination
PAKPATTAN CANAL
INITIAL ENVIRONMENTAL EXAMINATION (IEE) REPORT
July 2012
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
PUNJAB IRRIGATED AGRICULTURE INVESTMENT PROGRAM INITIAL ENVIRONMENTAL EXAMINATION
Pakpattan Canal
TABLE OF CONTENTS EXECUTIVE SUMMARY
1. INTRODUCTION ........................................................................................................ 1-1 1.1 GENERAL ............................................................................................................ 1-1 1.2 PROJECT DETAILS ............................................................................................. 1-1 1.3 BACKGROUND ................................................................................................... 1-1 1.4 PROJECT OBJECTIVES ..................................................................................... 1-2 1.5 PROJECT LOCATION ......................................................................................... 1-2 1.6 PROJECT CATEGORIZATION ............................................................................ 1-3 1.7 OBJECTIVES OF THE REPORT ......................................................................... 1-5 1.8 STRUCTURE OF THE REPORT ......................................................................... 1-5 1.9 METHDOLOGY OF PERFORMING THE STUDY ................................................ 1-5 1.10 AREA OF RESPONSIBILITIES ........................................................................ 1-6
2. LEGAL AND ADMINISTRATIVE FRAMEWORK POLICY ......................................... 2-1 2.1 REGULATORY REQUIREMENTS IN PAKISTAN ................................................ 2-1 2.2 NATIONAL CONSERVATION STRATEGY .......................................................... 2-1 2.3 NATIONAL ENVIRONMENT POLICY .................................................................. 2-1 2.4 GUIDELINES FOR ENVIRONMENTAL ASSESSMENT ...................................... 2-2
2.4.1 Guidelines for the Preparation and Review of Environmental Reports, Pakistan Environmental Protection Agency, 1997 ..................................................................... 2-2 2.4.2 Guidelines of Public Consultation, Pakistan Environmental Protection Agency, May, 1997 ................................................................................................................... 2-2
2.5 ENVIRONMENTAL INSTITUTIONS AND THEIR RESPONSIBILITIES ................ 2-2 2.5.1 Provincial EPA ............................................................................................... 2-2 2.5.2 Provincial Departments of Forestry and Wildlife ............................................. 2-2 2.5.3 Local Government and Municipalities ............................................................. 2-2 2.5.4 Social & Environmental Management Unit (SEMU) ........................................ 2-3 2.5.5 Environment-Related Statutes ........................................................................ 2-3
2.6 ASIAN DEVELOPMENT BANK GUIDELINES ...................................................... 2-4 2.7 NATIONAL ENVIRONMENTAL QUALITY STANDARDS (NEQS) 2000 ............... 2-5 2.8 INTERNATIONAL CONVENTIONS ...................................................................... 2-7
3. THE PROJECT .......................................................................................................... 3-1 3.1 GENERAL ............................................................................................................ 3-1 3.2 CULTIVATED COMMAND AREA (CCA) .............................................................. 3-1 3.3 PAKPATTAN MAIN CANAL ................................................................................. 3-1 3.4 NEED OF THE PROJECT .................................................................................... 3-2 3.5 DESCRIPTION OF PROJECT ............................................................................. 3-2
3.5.1 Proposal for Rehabilitation & Up-grading Works ............................................. 3-2 3.6 WORK BASE AREA ............................................................................................. 3-6 3.7 BORROW AREA .................................................................................................. 3-6 3.8 MATERIAL REQUIREMENT / SOURCE .............................................................. 3-6
4. ENVIORNMENTAL BASE LINE CONDITION ............................................................ 4-1 4.1 GENERAL ............................................................................................................ 4-1 4.2 PROJECT AREA OF INFLUENCE (AOI) ............................................................. 4-1 4.3 PHYSICAL ENVIRONMENT ................................................................................ 4-3
4.3.1 Physiography and Soil .................................................................................... 4-3 4.3.2 Soil Types ...................................................................................................... 4-4
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
4.3.3 Surface Salinity .............................................................................................. 4-4 4.3.4 Seismicity Data .............................................................................................. 4-5
4.4 HYDROLOGY ...................................................................................................... 4-6 4.4.1 Surface Water ................................................................................................ 4-6 4.4.2 Flood Record ................................................................................................. 4-8 4.4.3 Groundwater ................................................................................................ 4-10
4.5 BIOLOGICAL ENVIRONMENT .......................................................................... 4-14 4.5.1 Flora ............................................................................................................. 4-14 4.5.2 Fauna ........................................................................................................... 4-15
4.6 SOCIO ECONOMIC CONDITION ...................................................................... 4-19 4.7 SOCIAL CHARACTERISTICS ........................................................................... 4-21 4.8 GENDER ISSUES AND ANALYSIS ................................................................... 4-31
5. STUDY OF PROJECT ALTERNATIVES .................................................................... 5-1 5.1 NO PROJECT OPTION (WORST CASE SCENARIO OPTION) ........................... 5-1 5.2 CONSTRUCTING NEW CANAL .......................................................................... 5-2 5.3 REHABILITATION OF EXISTING CANAL SYSTEM (SELECTED OPTION FOR DETAIL DESIGN) ........................................................................................................... 5-2 5.4 CONCLUSION ..................................................................................................... 5-2
6. PUBLIC CONSULTATION ......................................................................................... 6-1 6.1 GENERAL ............................................................................................................ 6-1 6.2 CONSULTATION METHODOLOGY .................................................................... 6-1
6.2.1 Stakeholder Identification ............................................................................... 6-1 6.2.2 Consultation Process and Technology ........................................................... 6-2
6.3 OBJECTIVES ACHIEVED WITH THE PUBLIC CONSULTATION ....................... 6-4 6.4 CONSULTATION AND DISCUSSION DURING IMPLEMENTATION................... 6-2
6.4.1 Public Hearing ................................................................................................ 6-2 6.5 INSTITUTIONAL ARRANGEMENT ...................................................................... 6-4
6.5.1 Management Responsibilities ......................................................................... 6-4 6.6 SOCIAL COMPLAINTS REGISTER ..................................................................... 6-7
7. IMPACT ASSESSMENT, MITIGATION AND ENHANCEMENT MEASURES ............ 7-8 7.1 POTENTIAL IMPACT SOURCES ........................................................................ 7-8 7.2 IMPACTS AND MITIGATION MEASURES DURING DESIGN PHASE .............. 7-11
7.2.1 Weed in Canal Water ................................................................................... 7-11 7.2.2 Damage to Canal Banks .............................................................................. 7-11
7.3 IMPACTS AND MITIGATION MEASURES DURING CONSTRUCTION PHASE ... 7-12
7.3.1 Physical Environment ................................................................................... 7-12 7.4 BIOLOGICAL ENVIRONMENT .......................................................................... 7-21
7.4.1 Damage to Biological Resources and Disturbance of Wildlife ....................... 7-21 7.5 SOCIO-ECONOMIC IMPACTS .......................................................................... 7-22
7.5.1 Impacts of Land Acquisition.......................................................................... 7-22 7.5.2 Impacts on Local Population due to Migrating Labour from other Parts of the Country 7-23 7.5.3 HIV/AIDS and other Communicable Diseases .............................................. 7-23 7.5.4 Existing Services & Employment (Positive Social Impacts) .......................... 7-24
7.6 OPERATIONAL AND MANAGEMENT (O&M) PHASE ....................................... 7-24 8. ENVIRONMENTAL MANAGEMENT PLAN ............................................................... 8-1
8.1 MITIGATION PLAN .............................................................................................. 8-1 8.2 MITIGATION OF ADVERSE IMPACTS AT DESIGN PHASE ............................... 8-1 8.3 MITIGATION OF ADVERSE IMPACT AT CONSTRUCTION PHASE .................. 8-2 8.4 MONITORING PLAN ............................................................................................ 8-2 8.5 INSTITUTIONAL ARRANGEMENT ...................................................................... 8-3
8.5.1 Management Responsibilities ......................................................................... 8-3 8.6 COMMUNICATION AND DOCUMENTATION ...................................................... 8-7
8.6.1 Data Recording and Maintenance .................................................................. 8-7
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
8.6.2 Storage of Information .................................................................................... 8-8 8.6.3 Meetings ........................................................................................................ 8-8 8.6.4 Reports .......................................................................................................... 8-8 8.6.5 Photographic Record of the Project Area ..................................................... 8-10 8.6.6 Record Register ........................................................................................... 8-10
8.7 WASTE DISPOSAL PLAN ................................................................................. 8-11 8.7.1 Domestic Waste ........................................................................................... 8-11
8.8 Construction Waste ............................................................................................ 8-11 8.9 TRAFFIC MANAGEMENT PLAN ....................................................................... 8-13 8.10 Closure of Roads ............................................................................................ 8-13 8.11 Strengthening Embankments Works ............................................................... 8-14 8.12 Diversion Channels ......................................................................................... 8-14 8.13 OUTLINE OF EMERGENCY RESPONSE AND CONTINGENCY PLAN ........ 8-14 8.14 HEALTH, SAFETY & ENVIRONMENT (HSE) PLAN ...................................... 8-15 8.15 TREE PLANTATION PLAN............................................................................. 8-16 8.16 BORROW AREAS RESTORATION PLAN ..................................................... 8-18 8.17 LAND ACQUISITION PROCEDURE .............................................................. 8-18 8.18 RISK MANAGEMENT PLAN ........................................................................... 8-18 8.19 ENVIRONMENTAL MANAGEMENT COST .................................................... 8-20
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
LIST OF TABLES
Table 2.1: Effluent Discharge Standards Applicable to the Works
Table 2.2: Gaseous Emission Levels
Table 2.3: Noise Emission Levels
Table 3.1: Source of Raw Material
Table 4.1: Percentage Surface Salinity Statistics
Table 4.2: Water Quality Parameters (WAPDA STANDARD)
Table 4.3: Peak Discharge of Prominent Years in River Sutlej at Suleimanki Barrage
Table 4.4: Shallow Groundwater Quality
Table 4.5: Respondents Family Members
Table 4.6: Respondents Age Group
Table 4.7: Housing Characteristic of the Respondent
Table 4.8: Access to Education Facilities
Table 4.9: Social Amenities
Table 4.10: Profession/Business
Table 4.11: Household Income
Table 4.12 Household Expenditures
Table 4.13 Average Land Holding Size of the Family
Table 4.14 Cultivator Status
Table 4.15 Respondents age group
Table 4.16 Respondents language
Table 4.17 Marital Status
Table 4.18 Respondents Educational Level
Table 4.19 Source of Water for Domestic Use
Table 6.1 List of Officials Contacted
Table 6.2 Grievance Resolution Process
Table 7.1 Evaluation of Environmental & Social Impacts
Table 8.1 Environment & Management Cost
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
LIST OF FIGURES Figure 1.1: Pakpattan Canal Command Area Location Map
Figure 4.1: Overall Environmental Study Area Map
Figure 4.2: Physiography of Canal Command Area
Figure 4.3: Seismic Zones of Pakistan
Figure 4.4: Flood Inundated Area near the Canal Head Regulator
Figure 6.1: Cities and Towns along the Pakpattan Canal LIST OF PLATES Plate 4.1: Existing Livestock Pond along the Canal
Plate 4.2: Livestock Damage the Canal Banks
Plate 4.3: Occasional Finding of Fruit Trees (above is Mango Tree)
Plate 4.4: Fishing Contractor Catching Fish in Upper Pakpattan Canal
Plate 4.5: Meeting with the Officials of NGO in Vehari
Plate 4.6: A View of meeting with the cotton pickers
Plate 5.1: Public Consultation along Khadir Branch (near town Sahka)
Plate 5.2: Stakeholder Consultation at Water Management Office, Vehari
Plate 6.1: Public Consultation along Khadir Baranch (near town Sahka)
Plate 6.2: Stakeholder Consultation at Water Management Office Vehari
LIST OF APPENDICES Appendix 4.1: Environmental Test Results
Appendix 7.1: ABDs Rapid Environmental Assessment (REA) Checklist
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
vii
ABBREVIATION
ADB Asian Development Bank
AOI Area of Influence
BOD Biological Oxygen Demand
CCA Cultivable Command Area
CMS Conservation of Migratory Species
COD Chemical Oxygen Demand
COSHH Control of Substances Hazardous to Health
EC Electrical Conductivity
EMMP Environmental Management & Monitoring Plan
EMP Environmental Management Plan
EPA Environmental Protection Agency
EPAs Environmental Protection Agencies
EIA Environmental Impact Assessment
FAO Food and Agriculture Organization
GCA Gross Cultivated Area
GRC Grievance Redress Committee
IEE Initial Environmental Examination
IWT Indus Water Treaty
M&E Monitoring and Evaluation
NCS National Conservation Strategy
NEQS National Environmental Quality Standards
NOC No-Objection Certificate
O&M Operation and Maintenance
PCIP Pakpattan Canal Improvement Project
PEPA Pakistan Environmental Protection Act
PEPC
PHS
Pakistan Environmental Protections Council
Public Health and Safety
PID Punjab Irrigation Department
PMO Project Management Office
PMU Project Management Unit
PPE Personal Protective Equipment
RSC Residual Sodium Carbonate
SAR Sodium Adsorption Ratio
SCARP Salinity Control and Reclamation Project
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
viii
SEMU Social & Environmental Management Unit
SFA Social Frame Work Agreement
SMO SCARPS Monitoring Organization
SOP Survey of Pakistan
SSOP Soil Survey of Pakistan
TDS Total Dissolved Solids
US-EPA United States Environmental Protection Agency
WAPDA Water and Power Development Authority
WHO World Health Organization
WWF Worldwide Fund for Nature
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
S- i
EXECUTIVE SUMMARY Introduction For Pakpattan Canal Improvement Project (PCIP) an Environmental Assessment (EA)
Report has been prepared to ensure the following objectives:
ADBs Environment Safeguards Policy Statement
The applicable environmental administrative and legal frame work on the project
Environmental & social base line data of the project area of influence (AOI)
Assessment of potential environmental impacts and determining mitigation measures
of expected adverse impacts
A basic Environmental Management Plan (EMP) Framework (inclusive of all major
environmental aspects and risk based assessment plan) has been developed and the
envisaged EMP implementation cost estimated. The EMP will be revised, upgraded and
further details will be provided for each construction contract of the canal rehabilitation and
upgrading work.
The base line data was developed and analyzed to identify potential environmental impacts
of the project. An Environmental Assessment Checklist methodology was adopted to identify
the high risk activities and suggest their mitigation measures. Where possible, eliminating
the risk by altering the scope or method of execution of work was preferred rather than
minimizing the risk with control measures.
Legal and Administration Framework Policy
Pakistan Environmental Protection Act 1997 is the primary legislation which applies to
environmental assessment studies in Pakistan. Under section 12 of the Act, a project
falling under any category specified in Schedule II (SRO 339(1)/2000) requires the
proponent to file an Environmental Impact Assessment (EIA) with the concerned
Environmental Protection Agency (EPA), which in case of Pakpattan Canal is EPA
Punjab.
Pakpattan canal passes through mainly agricultural lands and does not pass through any
environmentally sensitive area along the canal in respect of the sensitive habitat, wildlife or
cultural heritage. The nature and scope of the construction works and the environmental
setting of the Project are such that no permanent adverse environmental impacts are
anticipated. According to ADB Environment Policy the project is categorized as category B
project. However, because the canal system serves more than 15,000 ha, the EIA (As per
section 12 of PEPA 1997) is mandatory for this project. All project activities should be compliant
with NEQS and should establish monitoring and evaluation systems.
Description of Project The project envisages mainly the raising and strengthening of banks, rehabilitation of
bridges and other hydraulic structures along the canal. This project is not a construction of
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
S- ii
new canal but a rehabilitation work leading to rehabilitation of Pakpattan Canal ultimately
leading to optional and judicious water supply to agricultural fields.
Description of the Environment
Baseline Conditions of the area of influence (AOI) have been established considering the
current and proposed development activities as well as the direct and indirect activities
connected with the AOI. The information utilized for the IEE was collected by using GIS
technology, collection of primary data (air, water and soil), stakeholder consultation including
Wildlife, Fishery, Forestry Departments, field visits carried out by the environment team and
review of environmental data of previous projects carried out in the area.
A strip of Punjab Irrigation Department (PID) land is available along both banks of the canal
which would be utilized for Contractors facilities (contractor camp, plant & equipment yard,
work base area etc). The ambient air quality was analyzed and is found to be reasonably
clean and no obvious source of the air pollution is identified during site visits. The climate of
the area is arid characterized by long hot summers and short mild winters.
Most of the canal banks length is planted with trees. Kiker (Acacia Nilotica) and Shesham
(Dalbergia Sissoo) are the main species of trees found along the canal. The canal command
area is famous for producing valuable crops (wheat, cotton etc) and fruits (mango, guava,
water melon etc).
The species of birds found in the area include pigeon, dove, egret, quail etc. Common wild
mammals of the area include jungle cat, mongoose, jackal, porcupine etc. some species of
reptiles and amphibians are found in the area e.g. snakes, variety of lizards, frogs, and
toads,
The Socio Economic Survey was conducted with the objectives to assess prevailing socio-
economic conditions of the related communities and to predict the effects of the proposed
different alternatives of rehabilitation works. The canal command area falls into four districts;
Okara, Pakpattan, Vehari and Lodhran. Approximately 80 % of Canal command area falls
into two districts; Pakpattan and Vehari. Total of 400 respondents i.e., 200 males for socio-
economic survey and 200 females for gender development study, were selected from
different project villages. The secondary data was collected from available documents i.e.
District Population Census Report 1998 of four districts of the project and maps related to
project area prepared by various Organizations / Departments. The occupational /
professional status of the respondents of the project area has been classified mainly into two
groups such as agricultural household and non-agricultural household. The members of non
farm community were generally doing labour work, shop keeping, government / private
employee, livestock, rearing business enterprises and receiving some remittances from
abroad.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
S- iii
The population of project area is totally based on rural setup. Average farm size in the canal
command is 2.7 ha (6.8 acres). The villages are formed of permanent settlements.
Habitation was classified according to the type of structure into three categories, i.e. Pacca
(concrete or brick structure), Kacha (Mud houses) Semi Pacca (mixed structure). A
significant majority of project households have electricity at their homes and only 2 percent
community has landline telephone facility. Use of mobile phones has greatly increased as a
way of communication. None of respondents was enjoying the facilities of Sui Gas and
drainage system in project area. Hand pumps are the major source of water in villages and
farmhouses, while the water supply systems are provided in cities.
The average literacy ratio in the project area analyzed from survey findings was 54% and the
literacy rate among the male members was higher (59 percent) than the females (41
percent) of the study area.
The PCIP will (i) ensure that the water supply to the distribution system in the entire canal
command area is secure; and the project will result in an 8.6% increase in farm income as a
result of the proposed intervention. A total of about 189,503 farm families or almost 2 million
people will benefit from the PCIP.
Environmental Impacts and Mitigation Measures
Most of the adverse environmental and social impacts of the Project will be associated with
the construction phase. Except for temporary resettlement during construction no permanent
resettlement is needed. Other impacts associated with the construction phase will be
temporary, reversible, phased over a period of time, localized and manageable.
Most of the length of canal bank (path along the canal) and access roads in the project area
are unpaved and may cause dust pollution during traffic movement. Air quality shall be
controlled by regular spraying of water on unpaved paths. All vehicles, machinery,
equipment and generators used during construction activities will be kept in good working
condition to minimize the exhaust emissions. Cutting & burning trees and shrubs as a fuel
shall be prohibited and clean source of energy would be provided at the contractors camp
e.g. gas cylinders etc. Noise, air quality and water sources shall be monitored periodically,
as specified in IEE report. All the work activities should be restricted within the allowed
working hours.
No designated environmentally protected or archaeological site falls within the direct project
area of influence or along the canal banks. The Project will not have any significant impact
on fish, fishermen communities, wildlife and wildlife habitat. However, monitoring measures
have been recommended to ensure that any unforeseen impacts can be identified,
compared with baseline and mitigated during the implementation stage. All forest, wildlife
and fisheries laws should be fully respected and abided by the contractor and his work force.
No fire arms should be carried out by the contractors work force.Tree cutting may require
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
S- iv
the construction of diversion channels or escape channels. Every tree cut on site for the
execution of work shall be replaced with plantation of minimum five new trees. The new
plantation would be protected during the contract implementation from animals and daily
routine activities. Public parks will be developed along the canal at suitable locations (away
from existing settlements, if any). This will raise the aesthetic value of the area and provide a
picnic spot to the local community.
During construction, the Contactors work force is expected to be largely available from the
local population, which will enhance the economic opportunities for the locals of working age
group. Socio-economic conditions of the project area will generally have positive impact due
to the project implementation entailing availability of jobs during construction phase.
The Project will also improve some of the social infrastructure as part of the repair and
rehabilitation of the irrigation structures and will reduce the exposure of local communities to
flooding events and the associated social and economic damages. The livelihoods of
farming communities will also improve through increased and equitable canal water
availability and improved agricultural productivity through improved agricultural practices and
road crossings. The representation of women and other vulnerable groups will be ensured in
the Project benefits.
The noticeable adverse impact of the Project will be temporary resettlement of affected
communities and relocation of some of the cultural sties that lie within the canal right of way
(ROW). Detailed resettlement action plans to mitigate these impacts will be prepared and
implemented before commencing the work on site. Resettlement Framework and
representative Resettlement Action Plans have been prepared as part of the feasibility study.
It is very important to protect the water sources during the construction phase from
accidental spills of diesel or any chemical, as any spill could percolate to the groundwater
through the sandy stratum at site. All the solid waste and wastewater generated from the
project activities and contractor camp are to be disposed of according to the waste disposal
plan, which would be a component of the EMP. If the groundwater is to be used for the water
supply in the contractors camp then it would be required to abstract water from sufficient
depth and confirm that it meets the WHO standards.
The EMP will also ensure reporting of all non-conformances and their rectification within a
specified period of time
The proposed project will bring about net-positive benefits in terms of improved water
resource management through assured water availability from the Pakpattan Main Canal
and will increase agricultural production from the project area.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
S- v
Continuous environmental monitoring will be carried out for the entire construction phase, to
ensure due diligence of environmental performance.
Conclusion It is anticipated that all environmental and social issues involved during the construction and
operational phase of the project are manageable, therefore it is concluded that the project is
environmentally friendly, financially viable, economically sustainable, generally neutral and
pro-poverty alleviation.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
1-1
1. INTRODUCTION
1.1 GENERAL The province of Punjab is only one fourth of the total area of Pakistan, yet its fertile land
yields are more than 50% of the total national agricultural produce. One of the reasons for
such high agricultural production is the efficient use of water resources through Punjabs
irrigation network. The Punjab irrigation network comprises 24 canals fed by 14
barrages/headworks and 9 major inter-river link canals, irrigating more than 21 million acres
of land. Pakpattan Canal off takes from Sutlej River at Suleimanki Barrage. There are two
barrages on Sutlej River; Suleimanki and Islam Barrage. Suleimanki is the first barrage on
Sutlej after it enters into Pakistan.
Asian Development Bank (ADB) is providing assistance to improve the management of
Punjab Water Resources and increase the agricultural productivity of the province under the
Punjab Irrigation Agriculture Investment Program (PIAIP).
1.2 PROJECT DETAILS Punjab Irrigation Department (PID) is the executing agency of the Punjab Irrigated
Agriculture Investment Program (PIAIP). Pakpattan Canal Rehabilitation & Up-grading
(R&U) will be carried out under PIAIP. The consultancy of the project including feasibility and
detailed design work was awarded to a joint venture of NESPAK, AAB and DMC in April
2009.
This report comprises the Initial Environmental Examination (IEE) study of the R&U of
Pakpattan Canal System. The IEE study takes into account the natural environment (air,
water, land, flora & fauna), human health and safety. This study evaluates the projects
potential environmental risks and impacts in its areas of influence and outlines planning,
designing and implementation by preventing, minimizing, mitigating or compensating for
adverse environmental impacts and enhancing positive impacts throughout project
implementation.
The Social Assessment (SA) has been conducted to evaluate the projects potential positive
and adverse effects on the affected people and to examine project alternatives where
adverse effects may be significant. The breadth, depth and type of analysis in the social
assessment are proportional to the nature of the project and scale of its potential effects,
positive or adverse, on the affected people.
1.3 BACKGROUND Pakpattan Canal and distribution network was completed in June 1926. The canals design
discharge is 6,594 cusecs at head regulator built on the right flank of Sulemanki Barrage.
Pakpattan Canal irrigates land in the districts of Okara, Pakpattan, Vehari, and Lohdran on
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
1-2
the right side of the river Sutlej. The main Pakpattan Canal is perennial and ceases to
operate for annual maintaining requirement during December/January. The total gross
command area is about 1.4 million acres.
In 1960, under the Indus Water Treaty, India was given the rights of the eastern rivers water,
including Ravi, Sutlej and Beas. Consequently upon the construction of Bhakra/Nangal Dam
on river Sutlej and Pandoh & Pong Dam on Beas, discharge in Sutlej was reduced
significantly. This entailed a significant work for conveying water from western rivers through
link canals to overcome the shortfall in the eastern rivers. Balloki-Suleimanki Link canal (B.S
Link) brings about 25,000 cusecs from Balloki barrage to feed the canals off taking from the
Suleimanki Barrage.
With the construction of Sidhni Mailsi Bahawal Link (SMB Link) canal Pakpattan main canal
was split into two parts i.e. Pakpattan Canal Upper (PC (U)) from RD 0-567 and Pakpattan
Canal Lower (PC (L)) from RD 568 to 667. Due to bifurcation, PC (L) now draws its supplies
from SMB Link with a new head regulator at RD 195+171/R of SMB Link.
1.4 PROJECT OBJECTIVES The system at present is facing many maintenance problems like deteriorated condition of
80 years old structures with upstream and downstream erosion, bermless reaches with
eroded banks and reduced free board. The system cannot take its authorized discharge
safely and is being run by adopting a rotational program.
The project aims to upgrade water resources and irrigation infrastructure of Pakpattan Canal
System and address the following main problems in this project:
The decks of most of the road bridges on the canal have deteriorated and are risky for
present traffic requirements.
Repair of regulation machinery and other hydraulic structure for smooth operation of
the canals.
Raising & strengthening of banks.
Improve the efficiency of canal system ensuring fulfillment of water requirement at the
tail end area.
1.5 PROJECT LOCATION Pakpattan canal off takes from river Sutlej at right side of Suleimanki Headworks. Its
command area lies between 29o51 to 30o27 latitudes north and 72o12 to 73o38 longitudes
east. The canal command area is bounded by river Sutlej in the south-east, boundary of
Lower Bari Doab Canal in the north and river Chenab in the west. Approximately one million
acres of the canal command area falls in south-eastern part of Punjab Province as shown in
Figure 1.1.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
1-3
1.6 PROJECT CATEGORIZATION According to ADB Safeguard Policy Statement 2009 and Environment Policy 2002
guidelines, projects are to be categorized into three environmental categories; A, B, or C. All
the anticipated adverse environmental impacts of the project are mitigable, temporary,
nature and localized. Also there is no environmentally sensitive or archeological site falling
within project area of influence; therefore the project is classified as Category B. This report
comprises the Initial Environmental Examination (IEE) of the proposed project to fulfill the
requirements according to ADBs, Safeguard Policy Statement 2009.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
1-4
Figure 1.1: Pakpattan Canal Command Area Location Map
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
1-5
1.7 OBJECTIVES OF THE REPORT The main objectives of the report are as follows:
The application of environmental administrative and legal frame work on the project
Develop Environmental Baseline Data for the project Area of Influence (AOI), derive
land use and environmental maps.
Assessment of potential environmental Impacts and development of mitigation
measures to cater for adverse impacts.
Preparation of framework of Environmental Management Plan (EMP) and envisaged
EMP implementation cost for this project.
1.8 STRUCTURE OF THE REPORT This report is divided into following chapters:
Chapter 1 Introduction
Chapter 2 Legal and Administrative Framework Policy
Chapter 3 The Project
Chapter 4 Environmental Baseline Conditions
Chapter 5 Study of Project Alternatives
Chapter 6 Public Consultation
Chapter 7 Impact Assessment, Mitigation and Enhancement Measures
Chapter 8 Environmental Management Plan
Appendices
1.9 METHDOLOGY OF PERFORMING THE STUDY The environmental and social data were collected and analyzed for the overall
environmental study area. Data was collected during site visits and stakeholder consultation
works. The concerned departments and institutions consulted are Wildlife, Forestry &
Fishery Department, Water Management Office, Irrigation, SMO, SEMU and Land
Reclamation Directorate of PID etc.
The base line data was developed and analyzed to identify potential environmental impacts
of the Project. A risk based methodology was adopted to identify the high risk activities and
suggest their mitigation measures. Where possible, eliminating the risk by altering the scope
or method of execution of work was preferred rather than minimizing the risk with control
measures. Public consultations were also undertaken including a gender study to take into
account the public point of view about the project.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
1-6
1.10 AREA OF RESPONSIBILITIES The following experts were involved for the preparation of this Initial Environmental
Examination Report:
Project Manager Tariq Altaf
Deputy Team Leader (Canals) Ehsan Ullah Sardar
Sub-Team Leader Mukhtar Ahmad
Environmental Specialist Ahsan Bela
Rural Sociologist Abdul Hameed
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
2-1
2. LEGAL AND ADMINISTRATIVE FRAMEWORK POLICY This chapter provides an overview of the policy framework and national legislation that
applies to the proposed Project. The Project is expected to comply with all national
legislations and Asian Bank Guidelines relating to environmental and social issues, and all
the required regulatory clearances will be obtained.
The environmental study includes primarily Pakistan Environmental Protection Act 1997
(PEPA 1997), Pakistan IEE and EIA review regulations (2000) and Asian Development Bank
SPS. All other laws and guidelines relevant to the project have also been reviewed.
Synopses of relevant laws and guidelines are provided in this chapter.
2.1 REGULATORY REQUIREMENTS IN PAKISTAN Under section 12 (with subsequent amendment) of the 1997 Act, a project falling under any
category specified in Schedule I (SRO 339(1)/2000), requires the proponent to file an IEE with
concerned federal agency (Pak-EPA). Projects falling under any category specified in schedule
II require the proponent to file an EIA with the federal agency. Within ten working days of the
lodging of IEE or EIA, the federal agency will confirm that the document submitted is complete
for the purpose of review.
2.2 NATIONAL CONSERVATION STRATEGY The Pakistan National Conservation Strategy (NCS) was approved by federal cabinet in March
1992 and is the principal policy document on environmental issues in the country. The NCS
outlines the countrys primary approaches towards encouraging sustainable development,
conserving natural resources and managing resources. The NCS has 68 specific programs in
14 core areas in which policy intervention is considered crucial for the preservation of
Pakistans natural and physical environment. The core areas that are relevant in the context of
the proposed Project are pollution prevention and abatement, conserving biodiversity and
preservation of cultural heritage.
2.3 NATIONAL ENVIRONMENT POLICY The National Environmental Policy provides an overarching framework for addressing the
environmental issues facing Pakistan, particularly pollution of fresh water bodies and coastal
waters, air pollution, lack of proper waste management, deforestation, loss of biodiversity,
desertification, natural disasters and climate change. It also gives directions for addressing the
cross sectoral issues elaborating the underlying causes of environmental degradation and
international obligations. The policy provides broad guidelines to the Federal Government,
Provincial Government, Federally Administrated Territories and Local Government for
addressing environmental concerns and ensuring effective management of their environmental
resources.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
2-2
2.4 GUIDELINES FOR ENVIRONMENTAL ASSESSMENT The Pak-EPA has published set of environmental guideline for conducting environmental
assessment and the environmental management of different types of development projects.
The guidelines relevant to the proposed Project are listed below.
2.4.1 Guidelines for the Preparation and Review of Environmental Reports, Pakistan Environmental Protection Agency, 1997
The guidelines, targeted at project proponents, specify:
The nature of the information to be included in environmental reports
The minimum qualification of the IEE/EIA conductors appointed
The need to incorporate suitable mitigation measures during project implementation
The need to specify monitoring procedures
The report must contain baseline data relating to the project area, an interpretation of the data
and mitigation measures.
2.4.2 Guidelines of Public Consultation, Pakistan Environmental Protection Agency, May, 1997
These guidelines deal with possible approaches to public consultation and techniques for
designing an effective program of consultation that reaches out to all major stakeholders and
ensure that their concerns are incorporated in any impact assessment study.
2.5 ENVIRONMENTAL INSTITUTIONS AND THEIR RESPONSIBILITIES
2.5.1 Provincial EPA The Punjab Irrigation Department (PID) will be responsible for providing the complete
environmental documentation required by the provincial EPA and remain committed to the
approved project design. No deviation is permitted during project implementation without the
prior and explicit permission of the EPA.
2.5.2 Provincial Departments of Forestry and Wildlife The rehabilitation works are expected to involve some clearing of vegetation that exists on
government land where labour camp and batching plants are to be installed. Widening and
strengthening of the embankments may also involve some uprooting of trees. All the trees
along the canal belong to Forest department. Plantation at the irrigation rest houses and at the
barrages belongs to irrigation department. Wildlife department nominates any sensitive wildlife
area as game reserve or highly sensitive area as wildlife sanctuary. A competent person should
manage the work activities in wildlife sensitive areas to minimize any adverse impacts on
wildlife habitat. However no environmentally sensitive area has been identified within the direct
influence of the project activities.
2.5.3 Local Government and Municipalities The PID and its contractors must ensure that the project meets the criteria of district
governments as related to the establishment of construction camps and plants, and the safe
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
2-3
disposal of wastewater, solid waste and toxic materials. The PID will coordinate and monitor
environment-related issues.
2.5.4 Social & Environmental Management Unit (SEMU) Punjab Irrigation Department (PID), under Punjab Irrigation and Drainage Authority (PIDA),
established the Social and Environmental Management Unit (SEMU) in December 2006 to
enable it to address the environmental and social issues in a timely and effective manner during
operation, maintenance, rehabilitation, construction of new canals and drains etc. SEMU has
developed checklists for canal rehabilitation works covering construction or remodeling of J-
Head Spur / Dike / Flood Bund / Training Works, new canals, new distributaries or lining of any
channel. SEMU may also be involved as an independent environmental monitoring
organization during construction phase of this Project.
2.5.5 Environment-Related Statutes This section outlines statutes apart from the Pakistan Environmental Protection Act, 1997,
which are relevant to the project.
The Forest Act, 1927 (and Provincial Acts and Rules)
The Act, inter alia, deals with the matters related with protection and conservation of natural
vegetation/habitats. It empowers the concerned agency to declare protected and reserved
forest areas and their maintaining. In spite of the fact that it recognizes the right of people for
access to the natural resources for their household use, it prohibits unlawful cutting of trees and
other vegetation from forest reserve area. The permission is required prior to undertake any
tree cutting from the Forest Department of Punjab province. The contractor will inform formally
to the Punjab Forest Department and PID at-least 1 month before cutting any tree on site.
Provincial Wildlife (Protection, Preservation, Conservation and Management) Act,
Ordinances and Rules
In addition to empowering provincial wildlife department to establish game reserves, parks, and
wildlife sanctuaries, these acts regulate the hunting and disturbance of wildlife. This law will
help in eliminating any trespassing into protected areas.
Antiquities Act, 1975
The Antiquities Act relates to the protection, preservation and conservation of
archaeological/historical sites and monuments. There are no archeological site(s) or cultural
heritage site inside or in the AOI of the project. Nevertheless if there is chance find during the
construction phase this law would provide due guidance.
Provincial Local Government Ordinances, 2001
These ordinances, issued following the devolution process, establish regulations for land use,
conservation of natural vegetation, air, water, and land pollution, the disposal of solid waste and
wastewater effluents, as well as matters related to public health and safety. This law will help as
and when participatory management of irrigation system becomes the order of the day.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
2-4
Factories Act, 1934
The clauses relevant to the project are those that are related with the health, safety and welfare
of workers, disposal of solid waste and effluent, and damage to private and public property.
The Factories Act also provides regulations for handling and disposing of toxic and hazardous
materials. There are no factories / industries inside the project area.
Land Acquisition Act 1894
Land Acquisition Act (LAA), 1894 is the primary law governing land acquisition in Pakistan. For
the acquisition of land, the above-mentioned Act, rules and regulations are followed whether
the acquisition is for Government of Punjab or any other agency. Up to this stage no permanent
land acquisition has been anticipated in the design of the project. Should there be a need for
temporary acquisition, this law would be helpful.
2.6 ASIAN DEVELOPMENT BANK GUIDELINES The Asian Development Banks Safeguard Policy Statement (SPS) 2009 and Environmental
Policy 2002 require that environmental considerations be incorporated in to ADBs funded
project to ensure that the project will have minimal environmental impact and be
environmentally sound. Occupational health & safety of the local population should also be
addressed as well as the project workers as stated in SPS. A Grievance Redress
Mechanism to receive application and facilitate resolution of affected peoples concerns,
complaints, and grievances about the projects environmental performance is also
established and provided in chapter-6.
Environmental Category
According to ADB guidelines, projects are to be categorized in to the following environmental
categories; A, B, or C as given in the table below. Once the project has been categorized,
the chief compliance officer must confirm it at the management review meeting. At any stage
the category can be changed with the approval of the chief compliance officer if further
studies and investigations reveal that the projects potential impacts are worse, minimal or
negligible.
ADB Environmental Categories
Category A:
Criterion
Projects with potential for significant adverse environmental impacts.
This is applicable in case of mega projects causing global or at least regional impacts.
This types of project require a first class EIA to be produced and implemented.
It is not applicable on this project.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
2-5
Category B:
Criterion
Projects judged to have some adverse environmental impacts, but of lesser degree
and/or significance than those for category A projects.
This is applicable in case of projects with localized and mitigable impacts. Rehabilitation
& Upgrading of Pakpattan Canal is a Category B project. The project involves
rehabilitation and repair of an already existing structure without causing any permanent
change in the surrounding environment. All impacts shall be localised, limited and
mitigable. Such projects according to ADB require an IEE and EMP only.
Category C:
Criterion
Projects unlikely to have adverse environmental impacts. It is not applicable on this
project
2.7 NATIONAL ENVIRONMENTAL QUALITY STANDARDS (NEQS) 2000 The NEQS 2000 specify the following standards:
1. Maximum allowable concentration of the Pollutants, (32 parameters) in emission and
liquid industrial effluents discharged to inland water.
2. Maximum allowable concentration of pollutants (two parameters) in gaseous
emission from vehicle exhaust and noise emission from vehicles.
3. Maximum allowable noise level from vehicles
4. Maximum allowable limits for Drinking Water
5. Maximum allowable limit for Ambient Air Quality
These standards apply to the gaseous emission and liquid effluents discharged by campsite
and construction machinery. The standards for vehicles will apply during the construction as
well as operation phase of the project. Precise standards for air quality are not available
under NEQS, 2000. The National Environmental Quality Standards (NEQS) 2000 specify the
following standards:
1. Discharge to inland waters:
The standard prescribes the maximum allowable concentration for 32 contaminants in the
municipal and liquid industrial effluents being discharged to the environment.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
2-6
Determinants which will be relevant to the contractors activity and discharges into inland
waters and their limits are listed in the following Table 2.1.
Table 2.1: Effluent Discharge Standards Applicable to the Works
Determinant Limit
Temperature 40oC =
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
2-7
There are no prescribed limits for the concentrations of microbiological determinants which
will be required to be met by any wastewater discharged from the contractors work camps.
Appropriate international standards will be considered in the Environmental Management
Plan.
2. Gaseous emission from industrial sources:
Maximum allowable concentrations of air based pollutants at construction site are given in
Table 2.2:
Table 2.2: Gaseous Emission Levels
Determinant Limit
Carbon Monoxide (CO) 9 ppm (8 hours)
35 ppm (1 hour)
Sulphur Dioxide (SO2) 140 ug/m3
Nitrogen Dioxide (NO2) 100 ug/m3
3. Environmental Noise Levels
While no environmental noise levels are currently in place, values have been submitted to
the Expert Advisory Committee on NEQS for consideration. The levels which are being
proposed are summarized in Table 2.3.
Table 2.3: Noise Emission Levels
Category Daytime dB(A) (06:00 21:00) Night-time dB(A) (21:00 06:00)
Residential Area 55 45
Commercial Area 65 55
Industrial Area 75 70
Silence Zone 50 40
The Standard prescribed for maximum allowable noise levels for road vehicles and
construction machinery is 85 dB (measured 7.5m from vehicle/machinery).
2.8 INTERNATIONAL CONVENTIONS Pakistan is signatory to a number of International Conventions, Protocols and
Understandings relating to the environment. Those relevant to the project are described in
the following paragraphs.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
2-8
Convention on Biological Diversity
The Convention of Biological Diversity was the outcome of the Earth Summit held in Rio-
de-Janeiro in 1992. The Convention binds the signatories to respect, protect and conserve
the earth environment and bio-diversity through sustainable use of natural resources. In all
development projects in Pakistan the protocols of this convention are respected in letter and
spirit.
Ramsar Convention
The Convention on Wetland of International Importance, especially on Waterfowl Habitats
held in Iran in 1972 at village Ramsar in Iran, places an obligation on the signatories to
protect habitats of migratory waterfowl. There is no Ramsar site within the canal command
area and AOI of the project.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
3-1
3. THE PROJECT
3.1 GENERAL Pakpattan canal off takes from right side of Suleimanki Barrage with design discharge of
6594 cusec. With the construction of Sidhnai-Mailsi Bahawal Link (SMB Link), the main
canal was split into two parts viz Pakpattan Canal Upper from RD 0+000 to 567+372 and
Pakpattan Canal Lower from RD 568+000 to RD 667+000. Pakpattan canal lower draws its
supplies from Sidhnai Mailsi Bahawal (SMB) link with a new head regulator at RD 195+171 /
R of SMB Link. Gross Command Area (GCA) of Pakpattan canal is 1.4 lac acres whereas
Cultivated Command Area (CCA) is 1.29 lac acres which fall, mainly in Pakpattan and
Vehari districts.
3.2 CULTIVATED COMMAND AREA (CCA) The Pakpattan Canal command is located between River Sutlej on its south and Old Sukh
Beas Nallah running along boundary of Lower Bari Doab Canal in its north. In the eastern
side it starts from the edge of the eastern border of Pakistan with India at Suleimanki
Barrage. The total length is approximately 134 miles extending up to Lodhran district from
the Suleimanki Barrage. The command area width varies and at places reaches up to 26
miles. The 90% command area falls in districts Pakpattan and Vehari. The remaining 10 %
area is in Okara and Lodhra districts.
3.3 PAKPATTAN MAIN CANAL The whole main canal is divided into two parts viz Pakpattan Canal Upper from RD 0 to 568
and Pakpattan Canal Lower from RD 568 to 667. The upper canal and its associated
distribution system feed from Suleimanki Barrage and Lower section draws its supplies from
SMB Link with a new head regulator at RD 195 of SMB Link. The design discharge of
Pakpattan canal lower is 940 cusecs. Due to addition of additional area the canal was
allowed to run with a discharge of 1160 cusecs.
Khadir branch is the main branch off taking from Pakpattan upper at RD 112 with design
discharge of 2230 cusecs and irrigates area falling namely in Pakpattan and Vehari districts.
Two Link Canals are connected with Pakpattan Upper Canal. MP (Motgomery Pakpattan)
Link was constructed to deliver 1000 cusecs of supplies from LBDC (Lower Bari Doab
Canal) to Pakpattan Canal at RD 266. Water is run up to RD 406 Pakpattan Canal Upper,
from where it passes into Pakpattan-Islam Link for use at Islam Barrage i.e. non-perennial
feeding to Upper Bahawal Canal and Qaim Canal.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
3-2
3.4 NEED OF THE PROJECT The system at present is facing many maintenance problems like deteriorated condition of
80 years old structures with upstream and downstream erosion, bermless reaches, eroded
banks, insufficient free board, vulnerability to breaches, accumulation of silt and debris and
water storage at tails etc. The damages mainly occurred due to the event of 1988 flood. The
flood caused breaching in RMB at Suleimanki Barrage and flows routed back to the river
through breaches in Pakpattan Canal, which resulted in uncontrolled supplies in the canal.
Due to this excessive discharge, serious damages mainly downstream of all the
falls/regulators and other structures have taken place. No major rehabilitation works were
carried out during the life time, consequently the main canal has become less efficient.
Pakpattan Main Canal is unable to run with its authorized discharge safely and is being run
by adopting a rotational program.
It is proposed under PIAIP Project to rehabilitate and upgrade the Pakpattan Canal System.
3.5 DESCRIPTION OF PROJECT The project envisages mainly the raising and strengthening of banks, rehabilitation of
bridges and other hydraulic structures along the canal. This project is not a construction of
new canal but a rehabilitation work leading to rehabilitation of Pakpattan Canal ultimately
leading to optional and judicious water supply to agricultural fields.
3.5.1 Proposal for Rehabilitation & Up-grading Works
- Structures in dilapidated condition to be reconstructed, while others to be
rehabilitated.
- Stilling basin for fall structures to be reconstructed to dissipate energy properly.
- To restore PC (U) section, studs/spurs are to be constructed where channel
banks are eroded and section widened.
- New VR Bridges to facilitate local peoples of the area when required.
- Foot Bridges will be constructed when required.
- Outlets in bad condition to be reconstructed/ rehabilitated.
- Banks of channels to be raised to cater for required free board.
- Cattle Ghats to be rehabilitated in order to protect channel section in the area
having substantive number of cattle.
- To minimize embayment near structures brick masonry protection to be provided
u/s & d/s of structures.
- Defective and worn out gates and hoisting arrangement to be replaced.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
3-3
- Gates will be provided at Head of distributaries and minors where they do not
exist.
- New distribution complex to be constructed at the tail of PC upper for efficient
feeding of the tail distributaries.
- The analysis accommodation facilities along the canal for the irrigation staff and
Rest Houses need renovation.
- Operator / Gauge Reader Huts need renovation or rehabilitation.
The works include civil, mechanical and electrical works. The possible components of the
works are as follow: -
Hydraulic Design of Main Canal
Pakpattan Canal Upper was originally designed for a discharge of 6594 cusecs by Kennedy
Theory with bed width 180 ft, FSD 12 ft which was revised in 1972, and designed by lacey
theory having bed width 195 ft, FSD 10 ft using Lacey silt factor of 0.86. It is proposed to
tighten the section of the canal from last design 195 ft bed width to its original bed width 180
ft, and an increase in water depth by 2 ft. It will help to remove the silt bed to its original
level.
Falls and Cross Regulators on Pakpattan Canal
In order to reduce the D/S embayment and erosions consultants will check the structure
hydraulically and modify according to the design requirements during detail design stage. All
fall / x-regulator will be redesigned to control the flow conditions. Step drop structures are
proposed to be replaced with glacis type fall structure and stilling basin.
Embayment Down Stream of Structure
Bank erosion and embayment downstream of structures is a common problem of Pakpattan
Canal System. Previously stone pitching was provided on the eroded bank to restrict further
embayment. However bank erosion shifted to the end of stone pitching and canal
embayment moved further. In order to restrict turbulent wave formation, proper transition is
being proposed to protect canal banks from erosion.
Cattle Ghats on Pakpattan Main Canal
Mostly banks are eroded due to trespassing where there is populated area near the canal.
Previously to protect banks from erosion, cattle ghats were constructed which are in bad
shape. Therefore, to protect banks from erosion it is proposed to rehabilitate the existing
cattle ghats.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
3-4
Head Regulators of Distributaries
Gates and hoisting arrangement need to be repaired for the proper functioning of the canal
system. Therefore it is proposed to construct/rehabilitate the head regulators and where ever
required gates and hoisting arrangement will be replaced.
Bank Strengthening
Bank strengthening is required in various reaches of Pakpattan Canal. Most of the channels
in the distribution system have insufficient free board. Therefore, it is proposed to attain
proper shape of the channel prism and strengthening of channel banks.
Protection Down Stream and Upstream of Structures
During condition survey it was found that embayment exists upstream and downstream of
structures in main canal as well as in distributaries and minors. It is proposed to provide
brick side protection works in the canal prism near structures as per requirements.
Platforms for Regulation at Head Regulators
Most of the channels head regulators need deck platforms with railing and stairs; platforms
will be constructed of appropriate width and height where required. Slab widths at some
head regulators of the distributaries with already are to be increased for proper regulation.
Killa Bushing
Killa bushing will be provided to convert the channel section to its design parameters. Berms
developed by the Killa bushing will also increase the safety of canal.
Removal of Sarkanda
Sarkanda growth is common along the main canal and causes obstruction to flow. For
altering smooth flow in channel, sarkanda is proposed to be removed.
Tail Reach of Pakpattan Canal (Upper)
Due to split-up of PC discharge is reduced in tail reach of PC(U) and the channel is
meandering in wider section. To attain proper shape of the channel section it is proposed to
be redesigned and straightened for the actual flow.
Tail Distribution Complex
Four distributaries 9L, 7R, 6R and 10L off-take from PC(U) at RD 546+830, 547+475,
547+581 and 567+382 respectively. As per discussion with field supervisory staff and
concerned officials, regulation problems exist there. It is proposed to construct a combined
distribution complex at RD 546+830 on PC (U) to regulate flows into distributaries.
Discharge D/S of RD 546+830 is reduced to 12.04 cusecs, it is proposed that the tail of the
PC (U) be curtailed at this point and a distributor complex be constructed and it may be
renamed as 10L Disty instead of PC (U)
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
3-5
Proposed Plan for Tail Distributor Complex to Cater Regulation Problem at Tail of PC (U)
Village Road Bridges
Village Road Bridges, which are damaged or in dilapidated condition on Pakpattan Main
Canal and will be reconstructed/rehabilitated. New Village Road Bridges are also proposed
to be constructed to facilitate local people and avoid damage to the canal system.
Rehabilitation of Gauge Reader Huts
In order to increase the work efficiency and facilitate the irrigation staff, Gauge Reader Huts
are proposed to be reconstructed / rehabilitated. Presently most of the huts are not in livable
condition.
Renovation of Rest Houses and Residences of Field Staff
Most of the Rest Houses and residences for the field staff were constructed during 1st and
2nd quarter of 20th century. No major rehabilitation work has been undertaken since then.
Most of these rest houses are not in satisfaction condition. To facilitate the supervisory staff
these rest houses/residences are proposed to be rehabilitated under PIAIP Project. These
rest houses can be used as FOs headquarter or meeting point in future. Boundary walls are
proposed to be constructed to ensure security as most of the rest houses do not have
boundary walls.
Diversion Channels
Diversion channels will be constructed (where required) to maintain the routine canal flows.
PID land is available along the canal and no private land will be acquired for this activity. The
excavated material will be back filled at the completion of project and land will be restored to
its original condition.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
3-6
3.6 WORK BASE AREA The work base area and all the access roads will be located within the PIDs land. Therefore
no private land acquisition is required to establish the work base area and access roads.
Modification and maintenance of the surface of the bunds and access roads will be
undertaken to ensure dust free environment of the area.
3.7 BORROW AREA PID owned and private land may be required for the contractors facilities (offices, residential
areas, material/plant/equipment yard, batching plant (if required) etc). The locations of these
facilities will be suggested during detail design stage according to environmental point of
view. A strip of land, approximately 50 ft. wide, along the canal belongs to PID. This land
should be preferred for developing contractors facilities. Irrigation rest houses are located
along the canal, which could be developed and utilized by the contractor.
It is envisaged that private land may also be required to obtain some fill material. Most of the
land found along the canal is agricultural land and may be used borrow area, if required,
after obtain Engineers approval. However the land would be restored for agricultural or other
desirable purpose at the completion of the project.
3.8 MATERIAL REQUIREMENT / SOURCE The civil works will require the following materials
Cement, Crush, Sand, Plastisizer, Air Entraining Agents, Steel Reinforcement, Epoxy and
Grouting material, and earth work.
The material associated with Mechanical Works of the Project is Gates, Hoisting System, Cables, Motors, Gear Box and Welding Materials
Table 3.1: Source of Raw Material
Sr. No. Raw Material Availability Source
1 Earth Material (soil) Available locally, borrowed from the lands temporarily acquired for the purpose.
2 Aggregate (crush) Available at many sources, such as: Quarries at Sakhi Sarwar (160 miles), Margalla Hills (320* miles) and Sikhanwali (220* miles), Sargodha (230* miles). The choice will however will depend upon the quality and suitability of the rock material of the construction of the hydraulic structures.
3 Rip-rap material Available from the three locations indicated above.
4 Sand Though available locally, the construction grade would need to be acquired from Chenab River bed (100* miles) or other approved site.
5 Water for preparation of Ample useable (at most of the locations)
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
3-7
Sr. No. Raw Material Availability Source
concrete groundwater aquifer is available along the canal. The contractor will install tube well within PID land at the agreed location with consultants environmentalist and Project Management Staff.
6 Water for compaction of embankments
Canal water can be used for this purpose with the permission of regulating authorities and supervision consultants
7 Cement Portland cement is locally available from the two factories situated at Daud Khel (250* miles). However, the cement of other grades is available within the country for the factories at D.G.Khan (260* miles), Karachi (800* miles), Chakwal (300* miles), Islamabad (281* miles), Wah (365* mile) etc.
8 Reinforcement steel Available from re-rolling mills at Lahore (94* miles).
9 Mechanical parts of the Gates
Could be manufactured at Heavy Mechanical Complex at Taxilla (365* miles), Factories at Lahore (94* miles) and Gujranwala (160* miles) and /or imported from abroad.
* All distances are given from Pakpattan Canal Head Regulator.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
4-1
4. ENVIORNMENTAL BASE LINE CONDITION
4.1 GENERAL The data were collected regarding the physical environment, biological environment and
social aspects of the study area during stakeholder consultation and technical visits
conducted by the environment team.
4.2 PROJECT AREA OF INFLUENCE (AOI) The area of project influence referred as Area of Influence (AOI) is the area likely to be
affected by the project, including all its ancillary aspects such as canals, sites for proposed
diversion channel(s), escape channel(s), relocation and access roads, borrow and waste
disposal areas and labour camps as well as unplanned developments induced by the
project.
Although the major construction activities remain restricted to the construction site which is
along the canal and its distributaries, yet the situation in which construction related activities
could extend beyond the construction site include:
a) The Labour camp site, batching plant, material storage depots, equipment
and machinery yards
b) Borrow areas for soil materials
c) Construction of haul tracks in order to transport construction material
d) Impact of accidental canal closure on canal command area
The canal command area falls in four districts; Okara, Pakpattan, Vehari and Lodhran out of
which the major part is covered in districts Pakpattan and Vehari. Other main cities/towns
located along the canal are Arifwala, Burewala, Mailsi, Luddan, Tibba Sultanpur, Gaggo,
Sahuka, Machiwal, Karampur, Shaikh Fazal and Thingi.
Overall environmental study area map is given in Figure 4.1.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
4-2
Figure 4.1: Overall Environmental Study Area Map
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
4-3
4.3 PHYSICAL ENVIRONMENT Physical environment consists of the environmental parameters covering physiography and
soil condition, water quality (surface and groundwater), ambient air quality and climate.
4.3.1 Physiography and Soil
The physiography of the canal command area is indicated on Figure 4.2.
Figure 4.2: Physiography of Canal Command Area
H I N D
U
K U
S H
RA N
G E
K A R AK O R A M
R A
D E O SA I
M T S L A
D A
K H
R A
N G
E
Z A
S K
A R
M T
N S
.
H A
ZA
R A
G R E A T
H I M
A L
A Y
AR
A N
G E
K A
I L A
S
R A N G E
P I R P A
N J
A L
R A
S I W
A L I K
R A
N G
E
H I
N D
UR
A S
S A F E D K O H
S A L T R A
.
T O
B A
K A KA R
C E
N T
R A
LB R
A H U
I
R A
.
R A S
K O
HR A
S I N J A R A I
C H A G AI H.
S U L A
I M
A N
R A
.
S A H A
NR
A.
C E N T R A L M A K R
A N
R A
.
M A K R A N K O S T R A. H A
L A
B A
B
H
K I
R T
H A
RR
A.
MILES 50 0 50 100 150 MILES
S C A L E
MOUNTAIN RANGE
DESERT
L E G E N D
INDUS PLAINS
A f
g h
a n
i s
t a
n
China
I r a n
Arabian Sea
I n
d i
a
FA
TA
Indu
s Rive
r
In
du
s R
ive
r
J helum
River
Chen
ab R
iver
Ravi
Rive
r
Sutle
j Rive
r
Hu
b River
Ha
ng
ol
Riv
er
Zh
ob
Riv
er
Da
sh
at
Riv
er
Disputed TerritoryJammu & KashmirIslamabad
Lahore
Quetta
Karachi
In
du
s R
ive
r
Peshawar
Gawader
GilgitAgency
Project Area
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
4-4
The main land form units which exist in the Pakpattan canal command area are:
- Recent Flood Plain
- Sub-Recent Flood Plain
- Miscellaneous Land Types
Recent Flood Plain covers about 12% of canal command area. It is further spilt into category
level plains (about 9%), bars and levees (about 3%). It lies along the right bank of river Sutlej
as a continuous strip and along the left bank of Sukh Beas in discontinuous patches. It is
partly subjected to inundation during high floods. Sub-Recent plain lies between recent flood
plain and Pleistocene river terrace. It occupies approximately 80% of the canal command
area and consists of level plain bar and levees. The remaining miscellaneous land consists
of roads, cities, industry, built-up area, canals etc.
4.3.2 Soil Types
The proposed Project area forms a part of the vast Indus plain, which is a part of the Indo-
Gangetic depression. This depression is of a synclinal nature. Synclinorium depression is a
fore deep downward of the Himalayan foreland of variable depth, converted into flat plains
by the simple process of alluviation. The alluvial deposits are underlain by rocks of
Precambrian age. The soil of the level area is generally medium to coarse texture. Bar and
levees have medium to coarse material. In sub-recent flood plain the soils of the bar and
levees are relatively coarser while those of channels / basin are predominantly clayey1.
4.3.3 Surface Salinity
SCARPS Monitoring Organization (SMO) undertakes the study to identify the saline area in
Pakpattan canal command area. Portable digital conductivity meter was used to measure
the EC of 0-15cm soil. A total of 746 surface samples were tested for salinity categorization.
Four categories namely, non-saline (S1 (EC up to 4dS/m)), slightly saline (S2(EC between 4
to 8dS/m)), moderately saline (S3(EC between 8-15dS/m)) and strongly saline (S4(EC above
15dS/m)) were recognized and mapped. The percentage of saline area found within the
canal command area is summarized in Table 4.1.
Table 4.1: Percentage Surface Salinity Statistics
1 data obtained from Reconnaissance Soil Survey Report of Sahiwal and Multan areas prepared by Soil Survey of Pakistan
Class Percentage
Non Saline (S1) 90
Slightly Saline(S2) 1
Moderately Saline (S3) 1
Strongly Saline (S4) Negligible
Miscellaneous Land Type 8
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
4-5
4.3.4 Seismicity Data
Earthquake in non-cohesive soil may cause serious problems. In extreme cases liquefaction
can occur if
Relative density is low
Initial confining pressure (overburden) is low
Earthquake intensity is high
Duration of ground shaking is long
National Seismic Monitoring Centre of Pakistan issued the seismic zone map for Pakistan,
as shown in Figure 4.3. Pakpattan canal command area falls in low hazard area and low risk
associated with the infrastructure found in this area.
Figure 4.3: Seismic Zones of Pakistan
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
4-6
4.4 HYDROLOGY The main source of water within the AOI can be divided into surface water and groundwater. 4.4.1 Surface Water
Pakpattan canal system is the main source of the surface water within the canal command
area. There are some seasonal nallahs which run during the monsoon period but due to lack
of any collection and storage infrastructure, it is too scant and unreliable to be of any
agricultural or other use. Pakpattan canal is a perennial canal and closes only for cleaning
purpose. The main canal is divided into two parts; Upper Pakpattan and Lower Pakpattan
canal. The Upper canal off-takes from river Sutlej at Suleimanki Barrage and Lower canal
feed through SMB Link canal. M.P Link canal is another source of upper Pakpattan canal
and brings about 1000 cusecs of water from L.B.D.C. Pakpattan-Islam Link canal off-take
from upper Pakpattan at RD 406 and takes about 1000 cusecs of Upper Pakpattan canal
water to Islam Barrage to accommodate the discharge of Upper Bahawal and Qaim Canal.
The discharge capacity of the Upper Pakpattan canal at the head regulator (Suleimanki
Barrage) is 6,594 cusecs.
Irrigation Standards Guideline of FAO Paper 29, Hanson et al., 1999 and WAPDA, are used to interpret
infiltration issues resulting from the use of Pakpattan Canal waters for irrigation. FAO has
defined infiltration as a function of both Sodium Adsorption Ratio (SAR) and Electrical
Conductivity (EC) whereas WAPDA Standards (described in table 4.2) define infiltration as a
function of SAR and or Residual Sodium Carbonate (RSC) only.
Table 4.2: Water Quality Parameters (WAPDA STANDARD)
Human Consumption The canal water analysis indicates that water quality does not meet the WHO drinking water
standards and is not fit for human consumption for drinking without any treatment (results
attached in appendix 4.1)
Recreation Use The canal can be used for recreational activities i.e. bathing, water sports etc as the canal
water quality meets the available standard for recreational purposes (results included in
appendix 4.1) USA Environmental Protection Agency (USEPA), 2003 defines maximum limit
of E-coil equal to 126 per 100ml for freshwater for recreational use.
Symbols Usable Marginal Hazardous
EC x 106 S/cm 0 1500 1500 3000 > 3000
RSC (meq/l) 0 2.5 2.5 5.0 > 5.0
SAR (mg/l) 0 10 10 18 > 18
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
4-7
Water Pond for Livestock Lined ponds recently constructed along Pakpattan Upper are not working properly. The
ponds were designed to accommodate the livestock and minimize canals bank damage
from the livestock. The pond water is supposed to be replaced with the canal water through
the installed pipe work on regular basis. But it seems that the pipes are blocked or were
wrongly designed. The ponds remain filled with dirty water and add the nuisance to the local
environment e.g. odor, mosquitoes breeding place etc. Also, in some cases, the pond water
escaped to the adjacent agricultural land through the cracks in the structure and damaged
the crop. Most of the ponds are damaged and not safe to be used by livestock.
Plate 4.1: Existing Livestock Pond along the Canal
As the constructed ponds do not serve the purpose, animals use the canal water and
damage the canal banks.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
4-8
Plate 4.2: Livestock Damage the Canal Banks
4.4.2 Flood Record
Under Second Flood Protection Sector Project (FPSP-II), flood risk maps for 5 year and 50
year return period were developed for Sutlej River; part of the map shown in Figure 4.4. The
map indicates the potential area inundated during flood. This information will be used to
prepare the flood protection plan and contractors facilities set up e.g. labour camp, batching
plant, plant & equipment yard etc during detailed design and project implementation phase.
Five (5) years and fifty (50) years flood calculated at Suleimanki barrage from the statistical
analysis are approximately 125,000 cusecs and 350,000 cusecs respectively. The historical
record of major flood pass through the Suleimanki barrage is summarized in Table 4.3.
Table 4.3: Peak Discharge of Prominent Years in River Sutlej at Suleimanki Barrage
Years Discharge through
weir (Cusecs) Through Breaches in Flood Embankment
Total (Cusecs)
1942 325,000 Nil 325,000 1943 309,000 Nil 309,000 1947 360,000 Nil 360,000 1950 332,000 Nil 332,000 1955 422,000 175,000 597,000 1988 400,000 100,000 500,000 1995 302,000 Nil 302,000
The most recent flood that caused breach in RMB at Suleimanki barrage and damaged
Pakpattan upper and Khadir branch occurred in 1988. There was no flood in 2010 as the
flood only occurred in western rivers (Rivers Sindh, Jehlum and Chenab).
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
4-9
Figure 4.4: Flood Inundated Area near the Canal Head Regulator
Legend
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
4-10
4.4.3 Groundwater
Unconfined aquifer can be found as shallow as five 5m depth from ground level at some
places along the canal. The aquifer constitutes loose sand of high permeability. Hand pumps
and tubewells are the two most common sources of groundwater within the canal command
area. Groundwater is mainly used for drinking and agriculture purposes.
Groundwater Quality in Canals Command Area The secondary data for groundwater quality has been collected from Directorate of Land
Reclamation and SMO offices for canals command area. The groundwater was classified on
the basis of laboratory analysis arranged by SMO for Electrical Conductivity (EC), Sodium
Adsorption Ratio (SAR) and Residual Sodium Carbonate (RSC) during 2003-04. For ease in
description, the groundwater has been expressed as usable, marginal and hazardous for
irrigation as determined by the adverse value of any of the above mentioned three
parameters. The classification criteria used is not intended to be strict in relation to the
effects of irrigation water on soil and crop growth which can be truly adjusted according to
environmental factors such as climate, type of soil, crops grown and management practices.
SMO also carried out testing for pH and EC in the field by using digital portable pH and EC
meters and sent all the water samples to the laboratory for detailed chemical analysis. The
samples were analyzed for pH, soluble cations, soluble anions, dissolved salts, EC, SAR
and RSC. These parameters are used for the classification of water as usable, marginal and
hazardous. The parameters associated with these classifications are as follow:
Usable EC < 1500 S/cm; SAR 18mg/l; RSC >5 meq/l
Using the above parameters, 609 water samples were collected out of which 345 were from
hand pumps and 264 from shallow tubewells (SMOs publication No. 29). The results are
summarized in Table 4.4.
Table 4.4: Shallow Groundwater Quality
Source Shallow Water Quality
Usable (%) Marginal (%) Hazardous (%)
Hand pumps 61 30 9
Tubewells 75 21 4
Water quality of tubewells is relatively better than that of hand pumps mainly because the
depth of extraction is deeper in case of tubewells.
-
Rehabilitation and Upgrading of Pakpattan Canal IEE Report
4-11
Depth of Water Table SCAPRs Monitoring Organization (SMO) is engaged in monitoring the water table depth in
Indus Plain bi-annually i.e. during pre-monsoon and post- monsoon through a network of
piezometers and tubewells. On the basis of data collected by SMO during 2002-03, it was
found that water table was not encountered within 300cm of depth from grou