37231-043-pak-iee.pdf

463
Initial Environmental Examination August 2012 PAK: Punjab Irrigated Agriculture Investment Program, Tranche 3 — Pakpattan Canal and Suleimanki Barrage Improvement Project Prepared by Punjab Irrigation Department, Government of Pakistan for the Asian Development Bank.

Transcript of 37231-043-pak-iee.pdf

  • Initial Environmental Examination August 2012

    PAK: Punjab Irrigated Agriculture Investment Program, Tranche 3 Pakpattan Canal and Suleimanki Barrage Improvement Project Prepared by Punjab Irrigation Department, Government of Pakistan for the Asian Development Bank.

  • Initial Environmental Examination

    PAKPATTAN CANAL

    INITIAL ENVIRONMENTAL EXAMINATION (IEE) REPORT

    July 2012

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    PUNJAB IRRIGATED AGRICULTURE INVESTMENT PROGRAM INITIAL ENVIRONMENTAL EXAMINATION

    Pakpattan Canal

    TABLE OF CONTENTS EXECUTIVE SUMMARY

    1. INTRODUCTION ........................................................................................................ 1-1 1.1 GENERAL ............................................................................................................ 1-1 1.2 PROJECT DETAILS ............................................................................................. 1-1 1.3 BACKGROUND ................................................................................................... 1-1 1.4 PROJECT OBJECTIVES ..................................................................................... 1-2 1.5 PROJECT LOCATION ......................................................................................... 1-2 1.6 PROJECT CATEGORIZATION ............................................................................ 1-3 1.7 OBJECTIVES OF THE REPORT ......................................................................... 1-5 1.8 STRUCTURE OF THE REPORT ......................................................................... 1-5 1.9 METHDOLOGY OF PERFORMING THE STUDY ................................................ 1-5 1.10 AREA OF RESPONSIBILITIES ........................................................................ 1-6

    2. LEGAL AND ADMINISTRATIVE FRAMEWORK POLICY ......................................... 2-1 2.1 REGULATORY REQUIREMENTS IN PAKISTAN ................................................ 2-1 2.2 NATIONAL CONSERVATION STRATEGY .......................................................... 2-1 2.3 NATIONAL ENVIRONMENT POLICY .................................................................. 2-1 2.4 GUIDELINES FOR ENVIRONMENTAL ASSESSMENT ...................................... 2-2

    2.4.1 Guidelines for the Preparation and Review of Environmental Reports, Pakistan Environmental Protection Agency, 1997 ..................................................................... 2-2 2.4.2 Guidelines of Public Consultation, Pakistan Environmental Protection Agency, May, 1997 ................................................................................................................... 2-2

    2.5 ENVIRONMENTAL INSTITUTIONS AND THEIR RESPONSIBILITIES ................ 2-2 2.5.1 Provincial EPA ............................................................................................... 2-2 2.5.2 Provincial Departments of Forestry and Wildlife ............................................. 2-2 2.5.3 Local Government and Municipalities ............................................................. 2-2 2.5.4 Social & Environmental Management Unit (SEMU) ........................................ 2-3 2.5.5 Environment-Related Statutes ........................................................................ 2-3

    2.6 ASIAN DEVELOPMENT BANK GUIDELINES ...................................................... 2-4 2.7 NATIONAL ENVIRONMENTAL QUALITY STANDARDS (NEQS) 2000 ............... 2-5 2.8 INTERNATIONAL CONVENTIONS ...................................................................... 2-7

    3. THE PROJECT .......................................................................................................... 3-1 3.1 GENERAL ............................................................................................................ 3-1 3.2 CULTIVATED COMMAND AREA (CCA) .............................................................. 3-1 3.3 PAKPATTAN MAIN CANAL ................................................................................. 3-1 3.4 NEED OF THE PROJECT .................................................................................... 3-2 3.5 DESCRIPTION OF PROJECT ............................................................................. 3-2

    3.5.1 Proposal for Rehabilitation & Up-grading Works ............................................. 3-2 3.6 WORK BASE AREA ............................................................................................. 3-6 3.7 BORROW AREA .................................................................................................. 3-6 3.8 MATERIAL REQUIREMENT / SOURCE .............................................................. 3-6

    4. ENVIORNMENTAL BASE LINE CONDITION ............................................................ 4-1 4.1 GENERAL ............................................................................................................ 4-1 4.2 PROJECT AREA OF INFLUENCE (AOI) ............................................................. 4-1 4.3 PHYSICAL ENVIRONMENT ................................................................................ 4-3

    4.3.1 Physiography and Soil .................................................................................... 4-3 4.3.2 Soil Types ...................................................................................................... 4-4

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    4.3.3 Surface Salinity .............................................................................................. 4-4 4.3.4 Seismicity Data .............................................................................................. 4-5

    4.4 HYDROLOGY ...................................................................................................... 4-6 4.4.1 Surface Water ................................................................................................ 4-6 4.4.2 Flood Record ................................................................................................. 4-8 4.4.3 Groundwater ................................................................................................ 4-10

    4.5 BIOLOGICAL ENVIRONMENT .......................................................................... 4-14 4.5.1 Flora ............................................................................................................. 4-14 4.5.2 Fauna ........................................................................................................... 4-15

    4.6 SOCIO ECONOMIC CONDITION ...................................................................... 4-19 4.7 SOCIAL CHARACTERISTICS ........................................................................... 4-21 4.8 GENDER ISSUES AND ANALYSIS ................................................................... 4-31

    5. STUDY OF PROJECT ALTERNATIVES .................................................................... 5-1 5.1 NO PROJECT OPTION (WORST CASE SCENARIO OPTION) ........................... 5-1 5.2 CONSTRUCTING NEW CANAL .......................................................................... 5-2 5.3 REHABILITATION OF EXISTING CANAL SYSTEM (SELECTED OPTION FOR DETAIL DESIGN) ........................................................................................................... 5-2 5.4 CONCLUSION ..................................................................................................... 5-2

    6. PUBLIC CONSULTATION ......................................................................................... 6-1 6.1 GENERAL ............................................................................................................ 6-1 6.2 CONSULTATION METHODOLOGY .................................................................... 6-1

    6.2.1 Stakeholder Identification ............................................................................... 6-1 6.2.2 Consultation Process and Technology ........................................................... 6-2

    6.3 OBJECTIVES ACHIEVED WITH THE PUBLIC CONSULTATION ....................... 6-4 6.4 CONSULTATION AND DISCUSSION DURING IMPLEMENTATION................... 6-2

    6.4.1 Public Hearing ................................................................................................ 6-2 6.5 INSTITUTIONAL ARRANGEMENT ...................................................................... 6-4

    6.5.1 Management Responsibilities ......................................................................... 6-4 6.6 SOCIAL COMPLAINTS REGISTER ..................................................................... 6-7

    7. IMPACT ASSESSMENT, MITIGATION AND ENHANCEMENT MEASURES ............ 7-8 7.1 POTENTIAL IMPACT SOURCES ........................................................................ 7-8 7.2 IMPACTS AND MITIGATION MEASURES DURING DESIGN PHASE .............. 7-11

    7.2.1 Weed in Canal Water ................................................................................... 7-11 7.2.2 Damage to Canal Banks .............................................................................. 7-11

    7.3 IMPACTS AND MITIGATION MEASURES DURING CONSTRUCTION PHASE ... 7-12

    7.3.1 Physical Environment ................................................................................... 7-12 7.4 BIOLOGICAL ENVIRONMENT .......................................................................... 7-21

    7.4.1 Damage to Biological Resources and Disturbance of Wildlife ....................... 7-21 7.5 SOCIO-ECONOMIC IMPACTS .......................................................................... 7-22

    7.5.1 Impacts of Land Acquisition.......................................................................... 7-22 7.5.2 Impacts on Local Population due to Migrating Labour from other Parts of the Country 7-23 7.5.3 HIV/AIDS and other Communicable Diseases .............................................. 7-23 7.5.4 Existing Services & Employment (Positive Social Impacts) .......................... 7-24

    7.6 OPERATIONAL AND MANAGEMENT (O&M) PHASE ....................................... 7-24 8. ENVIRONMENTAL MANAGEMENT PLAN ............................................................... 8-1

    8.1 MITIGATION PLAN .............................................................................................. 8-1 8.2 MITIGATION OF ADVERSE IMPACTS AT DESIGN PHASE ............................... 8-1 8.3 MITIGATION OF ADVERSE IMPACT AT CONSTRUCTION PHASE .................. 8-2 8.4 MONITORING PLAN ............................................................................................ 8-2 8.5 INSTITUTIONAL ARRANGEMENT ...................................................................... 8-3

    8.5.1 Management Responsibilities ......................................................................... 8-3 8.6 COMMUNICATION AND DOCUMENTATION ...................................................... 8-7

    8.6.1 Data Recording and Maintenance .................................................................. 8-7

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    8.6.2 Storage of Information .................................................................................... 8-8 8.6.3 Meetings ........................................................................................................ 8-8 8.6.4 Reports .......................................................................................................... 8-8 8.6.5 Photographic Record of the Project Area ..................................................... 8-10 8.6.6 Record Register ........................................................................................... 8-10

    8.7 WASTE DISPOSAL PLAN ................................................................................. 8-11 8.7.1 Domestic Waste ........................................................................................... 8-11

    8.8 Construction Waste ............................................................................................ 8-11 8.9 TRAFFIC MANAGEMENT PLAN ....................................................................... 8-13 8.10 Closure of Roads ............................................................................................ 8-13 8.11 Strengthening Embankments Works ............................................................... 8-14 8.12 Diversion Channels ......................................................................................... 8-14 8.13 OUTLINE OF EMERGENCY RESPONSE AND CONTINGENCY PLAN ........ 8-14 8.14 HEALTH, SAFETY & ENVIRONMENT (HSE) PLAN ...................................... 8-15 8.15 TREE PLANTATION PLAN............................................................................. 8-16 8.16 BORROW AREAS RESTORATION PLAN ..................................................... 8-18 8.17 LAND ACQUISITION PROCEDURE .............................................................. 8-18 8.18 RISK MANAGEMENT PLAN ........................................................................... 8-18 8.19 ENVIRONMENTAL MANAGEMENT COST .................................................... 8-20

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    LIST OF TABLES

    Table 2.1: Effluent Discharge Standards Applicable to the Works

    Table 2.2: Gaseous Emission Levels

    Table 2.3: Noise Emission Levels

    Table 3.1: Source of Raw Material

    Table 4.1: Percentage Surface Salinity Statistics

    Table 4.2: Water Quality Parameters (WAPDA STANDARD)

    Table 4.3: Peak Discharge of Prominent Years in River Sutlej at Suleimanki Barrage

    Table 4.4: Shallow Groundwater Quality

    Table 4.5: Respondents Family Members

    Table 4.6: Respondents Age Group

    Table 4.7: Housing Characteristic of the Respondent

    Table 4.8: Access to Education Facilities

    Table 4.9: Social Amenities

    Table 4.10: Profession/Business

    Table 4.11: Household Income

    Table 4.12 Household Expenditures

    Table 4.13 Average Land Holding Size of the Family

    Table 4.14 Cultivator Status

    Table 4.15 Respondents age group

    Table 4.16 Respondents language

    Table 4.17 Marital Status

    Table 4.18 Respondents Educational Level

    Table 4.19 Source of Water for Domestic Use

    Table 6.1 List of Officials Contacted

    Table 6.2 Grievance Resolution Process

    Table 7.1 Evaluation of Environmental & Social Impacts

    Table 8.1 Environment & Management Cost

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    LIST OF FIGURES Figure 1.1: Pakpattan Canal Command Area Location Map

    Figure 4.1: Overall Environmental Study Area Map

    Figure 4.2: Physiography of Canal Command Area

    Figure 4.3: Seismic Zones of Pakistan

    Figure 4.4: Flood Inundated Area near the Canal Head Regulator

    Figure 6.1: Cities and Towns along the Pakpattan Canal LIST OF PLATES Plate 4.1: Existing Livestock Pond along the Canal

    Plate 4.2: Livestock Damage the Canal Banks

    Plate 4.3: Occasional Finding of Fruit Trees (above is Mango Tree)

    Plate 4.4: Fishing Contractor Catching Fish in Upper Pakpattan Canal

    Plate 4.5: Meeting with the Officials of NGO in Vehari

    Plate 4.6: A View of meeting with the cotton pickers

    Plate 5.1: Public Consultation along Khadir Branch (near town Sahka)

    Plate 5.2: Stakeholder Consultation at Water Management Office, Vehari

    Plate 6.1: Public Consultation along Khadir Baranch (near town Sahka)

    Plate 6.2: Stakeholder Consultation at Water Management Office Vehari

    LIST OF APPENDICES Appendix 4.1: Environmental Test Results

    Appendix 7.1: ABDs Rapid Environmental Assessment (REA) Checklist

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    vii

    ABBREVIATION

    ADB Asian Development Bank

    AOI Area of Influence

    BOD Biological Oxygen Demand

    CCA Cultivable Command Area

    CMS Conservation of Migratory Species

    COD Chemical Oxygen Demand

    COSHH Control of Substances Hazardous to Health

    EC Electrical Conductivity

    EMMP Environmental Management & Monitoring Plan

    EMP Environmental Management Plan

    EPA Environmental Protection Agency

    EPAs Environmental Protection Agencies

    EIA Environmental Impact Assessment

    FAO Food and Agriculture Organization

    GCA Gross Cultivated Area

    GRC Grievance Redress Committee

    IEE Initial Environmental Examination

    IWT Indus Water Treaty

    M&E Monitoring and Evaluation

    NCS National Conservation Strategy

    NEQS National Environmental Quality Standards

    NOC No-Objection Certificate

    O&M Operation and Maintenance

    PCIP Pakpattan Canal Improvement Project

    PEPA Pakistan Environmental Protection Act

    PEPC

    PHS

    Pakistan Environmental Protections Council

    Public Health and Safety

    PID Punjab Irrigation Department

    PMO Project Management Office

    PMU Project Management Unit

    PPE Personal Protective Equipment

    RSC Residual Sodium Carbonate

    SAR Sodium Adsorption Ratio

    SCARP Salinity Control and Reclamation Project

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    viii

    SEMU Social & Environmental Management Unit

    SFA Social Frame Work Agreement

    SMO SCARPS Monitoring Organization

    SOP Survey of Pakistan

    SSOP Soil Survey of Pakistan

    TDS Total Dissolved Solids

    US-EPA United States Environmental Protection Agency

    WAPDA Water and Power Development Authority

    WHO World Health Organization

    WWF Worldwide Fund for Nature

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    S- i

    EXECUTIVE SUMMARY Introduction For Pakpattan Canal Improvement Project (PCIP) an Environmental Assessment (EA)

    Report has been prepared to ensure the following objectives:

    ADBs Environment Safeguards Policy Statement

    The applicable environmental administrative and legal frame work on the project

    Environmental & social base line data of the project area of influence (AOI)

    Assessment of potential environmental impacts and determining mitigation measures

    of expected adverse impacts

    A basic Environmental Management Plan (EMP) Framework (inclusive of all major

    environmental aspects and risk based assessment plan) has been developed and the

    envisaged EMP implementation cost estimated. The EMP will be revised, upgraded and

    further details will be provided for each construction contract of the canal rehabilitation and

    upgrading work.

    The base line data was developed and analyzed to identify potential environmental impacts

    of the project. An Environmental Assessment Checklist methodology was adopted to identify

    the high risk activities and suggest their mitigation measures. Where possible, eliminating

    the risk by altering the scope or method of execution of work was preferred rather than

    minimizing the risk with control measures.

    Legal and Administration Framework Policy

    Pakistan Environmental Protection Act 1997 is the primary legislation which applies to

    environmental assessment studies in Pakistan. Under section 12 of the Act, a project

    falling under any category specified in Schedule II (SRO 339(1)/2000) requires the

    proponent to file an Environmental Impact Assessment (EIA) with the concerned

    Environmental Protection Agency (EPA), which in case of Pakpattan Canal is EPA

    Punjab.

    Pakpattan canal passes through mainly agricultural lands and does not pass through any

    environmentally sensitive area along the canal in respect of the sensitive habitat, wildlife or

    cultural heritage. The nature and scope of the construction works and the environmental

    setting of the Project are such that no permanent adverse environmental impacts are

    anticipated. According to ADB Environment Policy the project is categorized as category B

    project. However, because the canal system serves more than 15,000 ha, the EIA (As per

    section 12 of PEPA 1997) is mandatory for this project. All project activities should be compliant

    with NEQS and should establish monitoring and evaluation systems.

    Description of Project The project envisages mainly the raising and strengthening of banks, rehabilitation of

    bridges and other hydraulic structures along the canal. This project is not a construction of

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    S- ii

    new canal but a rehabilitation work leading to rehabilitation of Pakpattan Canal ultimately

    leading to optional and judicious water supply to agricultural fields.

    Description of the Environment

    Baseline Conditions of the area of influence (AOI) have been established considering the

    current and proposed development activities as well as the direct and indirect activities

    connected with the AOI. The information utilized for the IEE was collected by using GIS

    technology, collection of primary data (air, water and soil), stakeholder consultation including

    Wildlife, Fishery, Forestry Departments, field visits carried out by the environment team and

    review of environmental data of previous projects carried out in the area.

    A strip of Punjab Irrigation Department (PID) land is available along both banks of the canal

    which would be utilized for Contractors facilities (contractor camp, plant & equipment yard,

    work base area etc). The ambient air quality was analyzed and is found to be reasonably

    clean and no obvious source of the air pollution is identified during site visits. The climate of

    the area is arid characterized by long hot summers and short mild winters.

    Most of the canal banks length is planted with trees. Kiker (Acacia Nilotica) and Shesham

    (Dalbergia Sissoo) are the main species of trees found along the canal. The canal command

    area is famous for producing valuable crops (wheat, cotton etc) and fruits (mango, guava,

    water melon etc).

    The species of birds found in the area include pigeon, dove, egret, quail etc. Common wild

    mammals of the area include jungle cat, mongoose, jackal, porcupine etc. some species of

    reptiles and amphibians are found in the area e.g. snakes, variety of lizards, frogs, and

    toads,

    The Socio Economic Survey was conducted with the objectives to assess prevailing socio-

    economic conditions of the related communities and to predict the effects of the proposed

    different alternatives of rehabilitation works. The canal command area falls into four districts;

    Okara, Pakpattan, Vehari and Lodhran. Approximately 80 % of Canal command area falls

    into two districts; Pakpattan and Vehari. Total of 400 respondents i.e., 200 males for socio-

    economic survey and 200 females for gender development study, were selected from

    different project villages. The secondary data was collected from available documents i.e.

    District Population Census Report 1998 of four districts of the project and maps related to

    project area prepared by various Organizations / Departments. The occupational /

    professional status of the respondents of the project area has been classified mainly into two

    groups such as agricultural household and non-agricultural household. The members of non

    farm community were generally doing labour work, shop keeping, government / private

    employee, livestock, rearing business enterprises and receiving some remittances from

    abroad.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    S- iii

    The population of project area is totally based on rural setup. Average farm size in the canal

    command is 2.7 ha (6.8 acres). The villages are formed of permanent settlements.

    Habitation was classified according to the type of structure into three categories, i.e. Pacca

    (concrete or brick structure), Kacha (Mud houses) Semi Pacca (mixed structure). A

    significant majority of project households have electricity at their homes and only 2 percent

    community has landline telephone facility. Use of mobile phones has greatly increased as a

    way of communication. None of respondents was enjoying the facilities of Sui Gas and

    drainage system in project area. Hand pumps are the major source of water in villages and

    farmhouses, while the water supply systems are provided in cities.

    The average literacy ratio in the project area analyzed from survey findings was 54% and the

    literacy rate among the male members was higher (59 percent) than the females (41

    percent) of the study area.

    The PCIP will (i) ensure that the water supply to the distribution system in the entire canal

    command area is secure; and the project will result in an 8.6% increase in farm income as a

    result of the proposed intervention. A total of about 189,503 farm families or almost 2 million

    people will benefit from the PCIP.

    Environmental Impacts and Mitigation Measures

    Most of the adverse environmental and social impacts of the Project will be associated with

    the construction phase. Except for temporary resettlement during construction no permanent

    resettlement is needed. Other impacts associated with the construction phase will be

    temporary, reversible, phased over a period of time, localized and manageable.

    Most of the length of canal bank (path along the canal) and access roads in the project area

    are unpaved and may cause dust pollution during traffic movement. Air quality shall be

    controlled by regular spraying of water on unpaved paths. All vehicles, machinery,

    equipment and generators used during construction activities will be kept in good working

    condition to minimize the exhaust emissions. Cutting & burning trees and shrubs as a fuel

    shall be prohibited and clean source of energy would be provided at the contractors camp

    e.g. gas cylinders etc. Noise, air quality and water sources shall be monitored periodically,

    as specified in IEE report. All the work activities should be restricted within the allowed

    working hours.

    No designated environmentally protected or archaeological site falls within the direct project

    area of influence or along the canal banks. The Project will not have any significant impact

    on fish, fishermen communities, wildlife and wildlife habitat. However, monitoring measures

    have been recommended to ensure that any unforeseen impacts can be identified,

    compared with baseline and mitigated during the implementation stage. All forest, wildlife

    and fisheries laws should be fully respected and abided by the contractor and his work force.

    No fire arms should be carried out by the contractors work force.Tree cutting may require

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    S- iv

    the construction of diversion channels or escape channels. Every tree cut on site for the

    execution of work shall be replaced with plantation of minimum five new trees. The new

    plantation would be protected during the contract implementation from animals and daily

    routine activities. Public parks will be developed along the canal at suitable locations (away

    from existing settlements, if any). This will raise the aesthetic value of the area and provide a

    picnic spot to the local community.

    During construction, the Contactors work force is expected to be largely available from the

    local population, which will enhance the economic opportunities for the locals of working age

    group. Socio-economic conditions of the project area will generally have positive impact due

    to the project implementation entailing availability of jobs during construction phase.

    The Project will also improve some of the social infrastructure as part of the repair and

    rehabilitation of the irrigation structures and will reduce the exposure of local communities to

    flooding events and the associated social and economic damages. The livelihoods of

    farming communities will also improve through increased and equitable canal water

    availability and improved agricultural productivity through improved agricultural practices and

    road crossings. The representation of women and other vulnerable groups will be ensured in

    the Project benefits.

    The noticeable adverse impact of the Project will be temporary resettlement of affected

    communities and relocation of some of the cultural sties that lie within the canal right of way

    (ROW). Detailed resettlement action plans to mitigate these impacts will be prepared and

    implemented before commencing the work on site. Resettlement Framework and

    representative Resettlement Action Plans have been prepared as part of the feasibility study.

    It is very important to protect the water sources during the construction phase from

    accidental spills of diesel or any chemical, as any spill could percolate to the groundwater

    through the sandy stratum at site. All the solid waste and wastewater generated from the

    project activities and contractor camp are to be disposed of according to the waste disposal

    plan, which would be a component of the EMP. If the groundwater is to be used for the water

    supply in the contractors camp then it would be required to abstract water from sufficient

    depth and confirm that it meets the WHO standards.

    The EMP will also ensure reporting of all non-conformances and their rectification within a

    specified period of time

    The proposed project will bring about net-positive benefits in terms of improved water

    resource management through assured water availability from the Pakpattan Main Canal

    and will increase agricultural production from the project area.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    S- v

    Continuous environmental monitoring will be carried out for the entire construction phase, to

    ensure due diligence of environmental performance.

    Conclusion It is anticipated that all environmental and social issues involved during the construction and

    operational phase of the project are manageable, therefore it is concluded that the project is

    environmentally friendly, financially viable, economically sustainable, generally neutral and

    pro-poverty alleviation.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    1-1

    1. INTRODUCTION

    1.1 GENERAL The province of Punjab is only one fourth of the total area of Pakistan, yet its fertile land

    yields are more than 50% of the total national agricultural produce. One of the reasons for

    such high agricultural production is the efficient use of water resources through Punjabs

    irrigation network. The Punjab irrigation network comprises 24 canals fed by 14

    barrages/headworks and 9 major inter-river link canals, irrigating more than 21 million acres

    of land. Pakpattan Canal off takes from Sutlej River at Suleimanki Barrage. There are two

    barrages on Sutlej River; Suleimanki and Islam Barrage. Suleimanki is the first barrage on

    Sutlej after it enters into Pakistan.

    Asian Development Bank (ADB) is providing assistance to improve the management of

    Punjab Water Resources and increase the agricultural productivity of the province under the

    Punjab Irrigation Agriculture Investment Program (PIAIP).

    1.2 PROJECT DETAILS Punjab Irrigation Department (PID) is the executing agency of the Punjab Irrigated

    Agriculture Investment Program (PIAIP). Pakpattan Canal Rehabilitation & Up-grading

    (R&U) will be carried out under PIAIP. The consultancy of the project including feasibility and

    detailed design work was awarded to a joint venture of NESPAK, AAB and DMC in April

    2009.

    This report comprises the Initial Environmental Examination (IEE) study of the R&U of

    Pakpattan Canal System. The IEE study takes into account the natural environment (air,

    water, land, flora & fauna), human health and safety. This study evaluates the projects

    potential environmental risks and impacts in its areas of influence and outlines planning,

    designing and implementation by preventing, minimizing, mitigating or compensating for

    adverse environmental impacts and enhancing positive impacts throughout project

    implementation.

    The Social Assessment (SA) has been conducted to evaluate the projects potential positive

    and adverse effects on the affected people and to examine project alternatives where

    adverse effects may be significant. The breadth, depth and type of analysis in the social

    assessment are proportional to the nature of the project and scale of its potential effects,

    positive or adverse, on the affected people.

    1.3 BACKGROUND Pakpattan Canal and distribution network was completed in June 1926. The canals design

    discharge is 6,594 cusecs at head regulator built on the right flank of Sulemanki Barrage.

    Pakpattan Canal irrigates land in the districts of Okara, Pakpattan, Vehari, and Lohdran on

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    1-2

    the right side of the river Sutlej. The main Pakpattan Canal is perennial and ceases to

    operate for annual maintaining requirement during December/January. The total gross

    command area is about 1.4 million acres.

    In 1960, under the Indus Water Treaty, India was given the rights of the eastern rivers water,

    including Ravi, Sutlej and Beas. Consequently upon the construction of Bhakra/Nangal Dam

    on river Sutlej and Pandoh & Pong Dam on Beas, discharge in Sutlej was reduced

    significantly. This entailed a significant work for conveying water from western rivers through

    link canals to overcome the shortfall in the eastern rivers. Balloki-Suleimanki Link canal (B.S

    Link) brings about 25,000 cusecs from Balloki barrage to feed the canals off taking from the

    Suleimanki Barrage.

    With the construction of Sidhni Mailsi Bahawal Link (SMB Link) canal Pakpattan main canal

    was split into two parts i.e. Pakpattan Canal Upper (PC (U)) from RD 0-567 and Pakpattan

    Canal Lower (PC (L)) from RD 568 to 667. Due to bifurcation, PC (L) now draws its supplies

    from SMB Link with a new head regulator at RD 195+171/R of SMB Link.

    1.4 PROJECT OBJECTIVES The system at present is facing many maintenance problems like deteriorated condition of

    80 years old structures with upstream and downstream erosion, bermless reaches with

    eroded banks and reduced free board. The system cannot take its authorized discharge

    safely and is being run by adopting a rotational program.

    The project aims to upgrade water resources and irrigation infrastructure of Pakpattan Canal

    System and address the following main problems in this project:

    The decks of most of the road bridges on the canal have deteriorated and are risky for

    present traffic requirements.

    Repair of regulation machinery and other hydraulic structure for smooth operation of

    the canals.

    Raising & strengthening of banks.

    Improve the efficiency of canal system ensuring fulfillment of water requirement at the

    tail end area.

    1.5 PROJECT LOCATION Pakpattan canal off takes from river Sutlej at right side of Suleimanki Headworks. Its

    command area lies between 29o51 to 30o27 latitudes north and 72o12 to 73o38 longitudes

    east. The canal command area is bounded by river Sutlej in the south-east, boundary of

    Lower Bari Doab Canal in the north and river Chenab in the west. Approximately one million

    acres of the canal command area falls in south-eastern part of Punjab Province as shown in

    Figure 1.1.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    1-3

    1.6 PROJECT CATEGORIZATION According to ADB Safeguard Policy Statement 2009 and Environment Policy 2002

    guidelines, projects are to be categorized into three environmental categories; A, B, or C. All

    the anticipated adverse environmental impacts of the project are mitigable, temporary,

    nature and localized. Also there is no environmentally sensitive or archeological site falling

    within project area of influence; therefore the project is classified as Category B. This report

    comprises the Initial Environmental Examination (IEE) of the proposed project to fulfill the

    requirements according to ADBs, Safeguard Policy Statement 2009.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    1-4

    Figure 1.1: Pakpattan Canal Command Area Location Map

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    1-5

    1.7 OBJECTIVES OF THE REPORT The main objectives of the report are as follows:

    The application of environmental administrative and legal frame work on the project

    Develop Environmental Baseline Data for the project Area of Influence (AOI), derive

    land use and environmental maps.

    Assessment of potential environmental Impacts and development of mitigation

    measures to cater for adverse impacts.

    Preparation of framework of Environmental Management Plan (EMP) and envisaged

    EMP implementation cost for this project.

    1.8 STRUCTURE OF THE REPORT This report is divided into following chapters:

    Chapter 1 Introduction

    Chapter 2 Legal and Administrative Framework Policy

    Chapter 3 The Project

    Chapter 4 Environmental Baseline Conditions

    Chapter 5 Study of Project Alternatives

    Chapter 6 Public Consultation

    Chapter 7 Impact Assessment, Mitigation and Enhancement Measures

    Chapter 8 Environmental Management Plan

    Appendices

    1.9 METHDOLOGY OF PERFORMING THE STUDY The environmental and social data were collected and analyzed for the overall

    environmental study area. Data was collected during site visits and stakeholder consultation

    works. The concerned departments and institutions consulted are Wildlife, Forestry &

    Fishery Department, Water Management Office, Irrigation, SMO, SEMU and Land

    Reclamation Directorate of PID etc.

    The base line data was developed and analyzed to identify potential environmental impacts

    of the Project. A risk based methodology was adopted to identify the high risk activities and

    suggest their mitigation measures. Where possible, eliminating the risk by altering the scope

    or method of execution of work was preferred rather than minimizing the risk with control

    measures. Public consultations were also undertaken including a gender study to take into

    account the public point of view about the project.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    1-6

    1.10 AREA OF RESPONSIBILITIES The following experts were involved for the preparation of this Initial Environmental

    Examination Report:

    Project Manager Tariq Altaf

    Deputy Team Leader (Canals) Ehsan Ullah Sardar

    Sub-Team Leader Mukhtar Ahmad

    Environmental Specialist Ahsan Bela

    Rural Sociologist Abdul Hameed

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    2-1

    2. LEGAL AND ADMINISTRATIVE FRAMEWORK POLICY This chapter provides an overview of the policy framework and national legislation that

    applies to the proposed Project. The Project is expected to comply with all national

    legislations and Asian Bank Guidelines relating to environmental and social issues, and all

    the required regulatory clearances will be obtained.

    The environmental study includes primarily Pakistan Environmental Protection Act 1997

    (PEPA 1997), Pakistan IEE and EIA review regulations (2000) and Asian Development Bank

    SPS. All other laws and guidelines relevant to the project have also been reviewed.

    Synopses of relevant laws and guidelines are provided in this chapter.

    2.1 REGULATORY REQUIREMENTS IN PAKISTAN Under section 12 (with subsequent amendment) of the 1997 Act, a project falling under any

    category specified in Schedule I (SRO 339(1)/2000), requires the proponent to file an IEE with

    concerned federal agency (Pak-EPA). Projects falling under any category specified in schedule

    II require the proponent to file an EIA with the federal agency. Within ten working days of the

    lodging of IEE or EIA, the federal agency will confirm that the document submitted is complete

    for the purpose of review.

    2.2 NATIONAL CONSERVATION STRATEGY The Pakistan National Conservation Strategy (NCS) was approved by federal cabinet in March

    1992 and is the principal policy document on environmental issues in the country. The NCS

    outlines the countrys primary approaches towards encouraging sustainable development,

    conserving natural resources and managing resources. The NCS has 68 specific programs in

    14 core areas in which policy intervention is considered crucial for the preservation of

    Pakistans natural and physical environment. The core areas that are relevant in the context of

    the proposed Project are pollution prevention and abatement, conserving biodiversity and

    preservation of cultural heritage.

    2.3 NATIONAL ENVIRONMENT POLICY The National Environmental Policy provides an overarching framework for addressing the

    environmental issues facing Pakistan, particularly pollution of fresh water bodies and coastal

    waters, air pollution, lack of proper waste management, deforestation, loss of biodiversity,

    desertification, natural disasters and climate change. It also gives directions for addressing the

    cross sectoral issues elaborating the underlying causes of environmental degradation and

    international obligations. The policy provides broad guidelines to the Federal Government,

    Provincial Government, Federally Administrated Territories and Local Government for

    addressing environmental concerns and ensuring effective management of their environmental

    resources.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    2-2

    2.4 GUIDELINES FOR ENVIRONMENTAL ASSESSMENT The Pak-EPA has published set of environmental guideline for conducting environmental

    assessment and the environmental management of different types of development projects.

    The guidelines relevant to the proposed Project are listed below.

    2.4.1 Guidelines for the Preparation and Review of Environmental Reports, Pakistan Environmental Protection Agency, 1997

    The guidelines, targeted at project proponents, specify:

    The nature of the information to be included in environmental reports

    The minimum qualification of the IEE/EIA conductors appointed

    The need to incorporate suitable mitigation measures during project implementation

    The need to specify monitoring procedures

    The report must contain baseline data relating to the project area, an interpretation of the data

    and mitigation measures.

    2.4.2 Guidelines of Public Consultation, Pakistan Environmental Protection Agency, May, 1997

    These guidelines deal with possible approaches to public consultation and techniques for

    designing an effective program of consultation that reaches out to all major stakeholders and

    ensure that their concerns are incorporated in any impact assessment study.

    2.5 ENVIRONMENTAL INSTITUTIONS AND THEIR RESPONSIBILITIES

    2.5.1 Provincial EPA The Punjab Irrigation Department (PID) will be responsible for providing the complete

    environmental documentation required by the provincial EPA and remain committed to the

    approved project design. No deviation is permitted during project implementation without the

    prior and explicit permission of the EPA.

    2.5.2 Provincial Departments of Forestry and Wildlife The rehabilitation works are expected to involve some clearing of vegetation that exists on

    government land where labour camp and batching plants are to be installed. Widening and

    strengthening of the embankments may also involve some uprooting of trees. All the trees

    along the canal belong to Forest department. Plantation at the irrigation rest houses and at the

    barrages belongs to irrigation department. Wildlife department nominates any sensitive wildlife

    area as game reserve or highly sensitive area as wildlife sanctuary. A competent person should

    manage the work activities in wildlife sensitive areas to minimize any adverse impacts on

    wildlife habitat. However no environmentally sensitive area has been identified within the direct

    influence of the project activities.

    2.5.3 Local Government and Municipalities The PID and its contractors must ensure that the project meets the criteria of district

    governments as related to the establishment of construction camps and plants, and the safe

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    2-3

    disposal of wastewater, solid waste and toxic materials. The PID will coordinate and monitor

    environment-related issues.

    2.5.4 Social & Environmental Management Unit (SEMU) Punjab Irrigation Department (PID), under Punjab Irrigation and Drainage Authority (PIDA),

    established the Social and Environmental Management Unit (SEMU) in December 2006 to

    enable it to address the environmental and social issues in a timely and effective manner during

    operation, maintenance, rehabilitation, construction of new canals and drains etc. SEMU has

    developed checklists for canal rehabilitation works covering construction or remodeling of J-

    Head Spur / Dike / Flood Bund / Training Works, new canals, new distributaries or lining of any

    channel. SEMU may also be involved as an independent environmental monitoring

    organization during construction phase of this Project.

    2.5.5 Environment-Related Statutes This section outlines statutes apart from the Pakistan Environmental Protection Act, 1997,

    which are relevant to the project.

    The Forest Act, 1927 (and Provincial Acts and Rules)

    The Act, inter alia, deals with the matters related with protection and conservation of natural

    vegetation/habitats. It empowers the concerned agency to declare protected and reserved

    forest areas and their maintaining. In spite of the fact that it recognizes the right of people for

    access to the natural resources for their household use, it prohibits unlawful cutting of trees and

    other vegetation from forest reserve area. The permission is required prior to undertake any

    tree cutting from the Forest Department of Punjab province. The contractor will inform formally

    to the Punjab Forest Department and PID at-least 1 month before cutting any tree on site.

    Provincial Wildlife (Protection, Preservation, Conservation and Management) Act,

    Ordinances and Rules

    In addition to empowering provincial wildlife department to establish game reserves, parks, and

    wildlife sanctuaries, these acts regulate the hunting and disturbance of wildlife. This law will

    help in eliminating any trespassing into protected areas.

    Antiquities Act, 1975

    The Antiquities Act relates to the protection, preservation and conservation of

    archaeological/historical sites and monuments. There are no archeological site(s) or cultural

    heritage site inside or in the AOI of the project. Nevertheless if there is chance find during the

    construction phase this law would provide due guidance.

    Provincial Local Government Ordinances, 2001

    These ordinances, issued following the devolution process, establish regulations for land use,

    conservation of natural vegetation, air, water, and land pollution, the disposal of solid waste and

    wastewater effluents, as well as matters related to public health and safety. This law will help as

    and when participatory management of irrigation system becomes the order of the day.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    2-4

    Factories Act, 1934

    The clauses relevant to the project are those that are related with the health, safety and welfare

    of workers, disposal of solid waste and effluent, and damage to private and public property.

    The Factories Act also provides regulations for handling and disposing of toxic and hazardous

    materials. There are no factories / industries inside the project area.

    Land Acquisition Act 1894

    Land Acquisition Act (LAA), 1894 is the primary law governing land acquisition in Pakistan. For

    the acquisition of land, the above-mentioned Act, rules and regulations are followed whether

    the acquisition is for Government of Punjab or any other agency. Up to this stage no permanent

    land acquisition has been anticipated in the design of the project. Should there be a need for

    temporary acquisition, this law would be helpful.

    2.6 ASIAN DEVELOPMENT BANK GUIDELINES The Asian Development Banks Safeguard Policy Statement (SPS) 2009 and Environmental

    Policy 2002 require that environmental considerations be incorporated in to ADBs funded

    project to ensure that the project will have minimal environmental impact and be

    environmentally sound. Occupational health & safety of the local population should also be

    addressed as well as the project workers as stated in SPS. A Grievance Redress

    Mechanism to receive application and facilitate resolution of affected peoples concerns,

    complaints, and grievances about the projects environmental performance is also

    established and provided in chapter-6.

    Environmental Category

    According to ADB guidelines, projects are to be categorized in to the following environmental

    categories; A, B, or C as given in the table below. Once the project has been categorized,

    the chief compliance officer must confirm it at the management review meeting. At any stage

    the category can be changed with the approval of the chief compliance officer if further

    studies and investigations reveal that the projects potential impacts are worse, minimal or

    negligible.

    ADB Environmental Categories

    Category A:

    Criterion

    Projects with potential for significant adverse environmental impacts.

    This is applicable in case of mega projects causing global or at least regional impacts.

    This types of project require a first class EIA to be produced and implemented.

    It is not applicable on this project.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    2-5

    Category B:

    Criterion

    Projects judged to have some adverse environmental impacts, but of lesser degree

    and/or significance than those for category A projects.

    This is applicable in case of projects with localized and mitigable impacts. Rehabilitation

    & Upgrading of Pakpattan Canal is a Category B project. The project involves

    rehabilitation and repair of an already existing structure without causing any permanent

    change in the surrounding environment. All impacts shall be localised, limited and

    mitigable. Such projects according to ADB require an IEE and EMP only.

    Category C:

    Criterion

    Projects unlikely to have adverse environmental impacts. It is not applicable on this

    project

    2.7 NATIONAL ENVIRONMENTAL QUALITY STANDARDS (NEQS) 2000 The NEQS 2000 specify the following standards:

    1. Maximum allowable concentration of the Pollutants, (32 parameters) in emission and

    liquid industrial effluents discharged to inland water.

    2. Maximum allowable concentration of pollutants (two parameters) in gaseous

    emission from vehicle exhaust and noise emission from vehicles.

    3. Maximum allowable noise level from vehicles

    4. Maximum allowable limits for Drinking Water

    5. Maximum allowable limit for Ambient Air Quality

    These standards apply to the gaseous emission and liquid effluents discharged by campsite

    and construction machinery. The standards for vehicles will apply during the construction as

    well as operation phase of the project. Precise standards for air quality are not available

    under NEQS, 2000. The National Environmental Quality Standards (NEQS) 2000 specify the

    following standards:

    1. Discharge to inland waters:

    The standard prescribes the maximum allowable concentration for 32 contaminants in the

    municipal and liquid industrial effluents being discharged to the environment.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    2-6

    Determinants which will be relevant to the contractors activity and discharges into inland

    waters and their limits are listed in the following Table 2.1.

    Table 2.1: Effluent Discharge Standards Applicable to the Works

    Determinant Limit

    Temperature 40oC =

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    2-7

    There are no prescribed limits for the concentrations of microbiological determinants which

    will be required to be met by any wastewater discharged from the contractors work camps.

    Appropriate international standards will be considered in the Environmental Management

    Plan.

    2. Gaseous emission from industrial sources:

    Maximum allowable concentrations of air based pollutants at construction site are given in

    Table 2.2:

    Table 2.2: Gaseous Emission Levels

    Determinant Limit

    Carbon Monoxide (CO) 9 ppm (8 hours)

    35 ppm (1 hour)

    Sulphur Dioxide (SO2) 140 ug/m3

    Nitrogen Dioxide (NO2) 100 ug/m3

    3. Environmental Noise Levels

    While no environmental noise levels are currently in place, values have been submitted to

    the Expert Advisory Committee on NEQS for consideration. The levels which are being

    proposed are summarized in Table 2.3.

    Table 2.3: Noise Emission Levels

    Category Daytime dB(A) (06:00 21:00) Night-time dB(A) (21:00 06:00)

    Residential Area 55 45

    Commercial Area 65 55

    Industrial Area 75 70

    Silence Zone 50 40

    The Standard prescribed for maximum allowable noise levels for road vehicles and

    construction machinery is 85 dB (measured 7.5m from vehicle/machinery).

    2.8 INTERNATIONAL CONVENTIONS Pakistan is signatory to a number of International Conventions, Protocols and

    Understandings relating to the environment. Those relevant to the project are described in

    the following paragraphs.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    2-8

    Convention on Biological Diversity

    The Convention of Biological Diversity was the outcome of the Earth Summit held in Rio-

    de-Janeiro in 1992. The Convention binds the signatories to respect, protect and conserve

    the earth environment and bio-diversity through sustainable use of natural resources. In all

    development projects in Pakistan the protocols of this convention are respected in letter and

    spirit.

    Ramsar Convention

    The Convention on Wetland of International Importance, especially on Waterfowl Habitats

    held in Iran in 1972 at village Ramsar in Iran, places an obligation on the signatories to

    protect habitats of migratory waterfowl. There is no Ramsar site within the canal command

    area and AOI of the project.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    3-1

    3. THE PROJECT

    3.1 GENERAL Pakpattan canal off takes from right side of Suleimanki Barrage with design discharge of

    6594 cusec. With the construction of Sidhnai-Mailsi Bahawal Link (SMB Link), the main

    canal was split into two parts viz Pakpattan Canal Upper from RD 0+000 to 567+372 and

    Pakpattan Canal Lower from RD 568+000 to RD 667+000. Pakpattan canal lower draws its

    supplies from Sidhnai Mailsi Bahawal (SMB) link with a new head regulator at RD 195+171 /

    R of SMB Link. Gross Command Area (GCA) of Pakpattan canal is 1.4 lac acres whereas

    Cultivated Command Area (CCA) is 1.29 lac acres which fall, mainly in Pakpattan and

    Vehari districts.

    3.2 CULTIVATED COMMAND AREA (CCA) The Pakpattan Canal command is located between River Sutlej on its south and Old Sukh

    Beas Nallah running along boundary of Lower Bari Doab Canal in its north. In the eastern

    side it starts from the edge of the eastern border of Pakistan with India at Suleimanki

    Barrage. The total length is approximately 134 miles extending up to Lodhran district from

    the Suleimanki Barrage. The command area width varies and at places reaches up to 26

    miles. The 90% command area falls in districts Pakpattan and Vehari. The remaining 10 %

    area is in Okara and Lodhra districts.

    3.3 PAKPATTAN MAIN CANAL The whole main canal is divided into two parts viz Pakpattan Canal Upper from RD 0 to 568

    and Pakpattan Canal Lower from RD 568 to 667. The upper canal and its associated

    distribution system feed from Suleimanki Barrage and Lower section draws its supplies from

    SMB Link with a new head regulator at RD 195 of SMB Link. The design discharge of

    Pakpattan canal lower is 940 cusecs. Due to addition of additional area the canal was

    allowed to run with a discharge of 1160 cusecs.

    Khadir branch is the main branch off taking from Pakpattan upper at RD 112 with design

    discharge of 2230 cusecs and irrigates area falling namely in Pakpattan and Vehari districts.

    Two Link Canals are connected with Pakpattan Upper Canal. MP (Motgomery Pakpattan)

    Link was constructed to deliver 1000 cusecs of supplies from LBDC (Lower Bari Doab

    Canal) to Pakpattan Canal at RD 266. Water is run up to RD 406 Pakpattan Canal Upper,

    from where it passes into Pakpattan-Islam Link for use at Islam Barrage i.e. non-perennial

    feeding to Upper Bahawal Canal and Qaim Canal.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    3-2

    3.4 NEED OF THE PROJECT The system at present is facing many maintenance problems like deteriorated condition of

    80 years old structures with upstream and downstream erosion, bermless reaches, eroded

    banks, insufficient free board, vulnerability to breaches, accumulation of silt and debris and

    water storage at tails etc. The damages mainly occurred due to the event of 1988 flood. The

    flood caused breaching in RMB at Suleimanki Barrage and flows routed back to the river

    through breaches in Pakpattan Canal, which resulted in uncontrolled supplies in the canal.

    Due to this excessive discharge, serious damages mainly downstream of all the

    falls/regulators and other structures have taken place. No major rehabilitation works were

    carried out during the life time, consequently the main canal has become less efficient.

    Pakpattan Main Canal is unable to run with its authorized discharge safely and is being run

    by adopting a rotational program.

    It is proposed under PIAIP Project to rehabilitate and upgrade the Pakpattan Canal System.

    3.5 DESCRIPTION OF PROJECT The project envisages mainly the raising and strengthening of banks, rehabilitation of

    bridges and other hydraulic structures along the canal. This project is not a construction of

    new canal but a rehabilitation work leading to rehabilitation of Pakpattan Canal ultimately

    leading to optional and judicious water supply to agricultural fields.

    3.5.1 Proposal for Rehabilitation & Up-grading Works

    - Structures in dilapidated condition to be reconstructed, while others to be

    rehabilitated.

    - Stilling basin for fall structures to be reconstructed to dissipate energy properly.

    - To restore PC (U) section, studs/spurs are to be constructed where channel

    banks are eroded and section widened.

    - New VR Bridges to facilitate local peoples of the area when required.

    - Foot Bridges will be constructed when required.

    - Outlets in bad condition to be reconstructed/ rehabilitated.

    - Banks of channels to be raised to cater for required free board.

    - Cattle Ghats to be rehabilitated in order to protect channel section in the area

    having substantive number of cattle.

    - To minimize embayment near structures brick masonry protection to be provided

    u/s & d/s of structures.

    - Defective and worn out gates and hoisting arrangement to be replaced.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    3-3

    - Gates will be provided at Head of distributaries and minors where they do not

    exist.

    - New distribution complex to be constructed at the tail of PC upper for efficient

    feeding of the tail distributaries.

    - The analysis accommodation facilities along the canal for the irrigation staff and

    Rest Houses need renovation.

    - Operator / Gauge Reader Huts need renovation or rehabilitation.

    The works include civil, mechanical and electrical works. The possible components of the

    works are as follow: -

    Hydraulic Design of Main Canal

    Pakpattan Canal Upper was originally designed for a discharge of 6594 cusecs by Kennedy

    Theory with bed width 180 ft, FSD 12 ft which was revised in 1972, and designed by lacey

    theory having bed width 195 ft, FSD 10 ft using Lacey silt factor of 0.86. It is proposed to

    tighten the section of the canal from last design 195 ft bed width to its original bed width 180

    ft, and an increase in water depth by 2 ft. It will help to remove the silt bed to its original

    level.

    Falls and Cross Regulators on Pakpattan Canal

    In order to reduce the D/S embayment and erosions consultants will check the structure

    hydraulically and modify according to the design requirements during detail design stage. All

    fall / x-regulator will be redesigned to control the flow conditions. Step drop structures are

    proposed to be replaced with glacis type fall structure and stilling basin.

    Embayment Down Stream of Structure

    Bank erosion and embayment downstream of structures is a common problem of Pakpattan

    Canal System. Previously stone pitching was provided on the eroded bank to restrict further

    embayment. However bank erosion shifted to the end of stone pitching and canal

    embayment moved further. In order to restrict turbulent wave formation, proper transition is

    being proposed to protect canal banks from erosion.

    Cattle Ghats on Pakpattan Main Canal

    Mostly banks are eroded due to trespassing where there is populated area near the canal.

    Previously to protect banks from erosion, cattle ghats were constructed which are in bad

    shape. Therefore, to protect banks from erosion it is proposed to rehabilitate the existing

    cattle ghats.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    3-4

    Head Regulators of Distributaries

    Gates and hoisting arrangement need to be repaired for the proper functioning of the canal

    system. Therefore it is proposed to construct/rehabilitate the head regulators and where ever

    required gates and hoisting arrangement will be replaced.

    Bank Strengthening

    Bank strengthening is required in various reaches of Pakpattan Canal. Most of the channels

    in the distribution system have insufficient free board. Therefore, it is proposed to attain

    proper shape of the channel prism and strengthening of channel banks.

    Protection Down Stream and Upstream of Structures

    During condition survey it was found that embayment exists upstream and downstream of

    structures in main canal as well as in distributaries and minors. It is proposed to provide

    brick side protection works in the canal prism near structures as per requirements.

    Platforms for Regulation at Head Regulators

    Most of the channels head regulators need deck platforms with railing and stairs; platforms

    will be constructed of appropriate width and height where required. Slab widths at some

    head regulators of the distributaries with already are to be increased for proper regulation.

    Killa Bushing

    Killa bushing will be provided to convert the channel section to its design parameters. Berms

    developed by the Killa bushing will also increase the safety of canal.

    Removal of Sarkanda

    Sarkanda growth is common along the main canal and causes obstruction to flow. For

    altering smooth flow in channel, sarkanda is proposed to be removed.

    Tail Reach of Pakpattan Canal (Upper)

    Due to split-up of PC discharge is reduced in tail reach of PC(U) and the channel is

    meandering in wider section. To attain proper shape of the channel section it is proposed to

    be redesigned and straightened for the actual flow.

    Tail Distribution Complex

    Four distributaries 9L, 7R, 6R and 10L off-take from PC(U) at RD 546+830, 547+475,

    547+581 and 567+382 respectively. As per discussion with field supervisory staff and

    concerned officials, regulation problems exist there. It is proposed to construct a combined

    distribution complex at RD 546+830 on PC (U) to regulate flows into distributaries.

    Discharge D/S of RD 546+830 is reduced to 12.04 cusecs, it is proposed that the tail of the

    PC (U) be curtailed at this point and a distributor complex be constructed and it may be

    renamed as 10L Disty instead of PC (U)

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    3-5

    Proposed Plan for Tail Distributor Complex to Cater Regulation Problem at Tail of PC (U)

    Village Road Bridges

    Village Road Bridges, which are damaged or in dilapidated condition on Pakpattan Main

    Canal and will be reconstructed/rehabilitated. New Village Road Bridges are also proposed

    to be constructed to facilitate local people and avoid damage to the canal system.

    Rehabilitation of Gauge Reader Huts

    In order to increase the work efficiency and facilitate the irrigation staff, Gauge Reader Huts

    are proposed to be reconstructed / rehabilitated. Presently most of the huts are not in livable

    condition.

    Renovation of Rest Houses and Residences of Field Staff

    Most of the Rest Houses and residences for the field staff were constructed during 1st and

    2nd quarter of 20th century. No major rehabilitation work has been undertaken since then.

    Most of these rest houses are not in satisfaction condition. To facilitate the supervisory staff

    these rest houses/residences are proposed to be rehabilitated under PIAIP Project. These

    rest houses can be used as FOs headquarter or meeting point in future. Boundary walls are

    proposed to be constructed to ensure security as most of the rest houses do not have

    boundary walls.

    Diversion Channels

    Diversion channels will be constructed (where required) to maintain the routine canal flows.

    PID land is available along the canal and no private land will be acquired for this activity. The

    excavated material will be back filled at the completion of project and land will be restored to

    its original condition.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    3-6

    3.6 WORK BASE AREA The work base area and all the access roads will be located within the PIDs land. Therefore

    no private land acquisition is required to establish the work base area and access roads.

    Modification and maintenance of the surface of the bunds and access roads will be

    undertaken to ensure dust free environment of the area.

    3.7 BORROW AREA PID owned and private land may be required for the contractors facilities (offices, residential

    areas, material/plant/equipment yard, batching plant (if required) etc). The locations of these

    facilities will be suggested during detail design stage according to environmental point of

    view. A strip of land, approximately 50 ft. wide, along the canal belongs to PID. This land

    should be preferred for developing contractors facilities. Irrigation rest houses are located

    along the canal, which could be developed and utilized by the contractor.

    It is envisaged that private land may also be required to obtain some fill material. Most of the

    land found along the canal is agricultural land and may be used borrow area, if required,

    after obtain Engineers approval. However the land would be restored for agricultural or other

    desirable purpose at the completion of the project.

    3.8 MATERIAL REQUIREMENT / SOURCE The civil works will require the following materials

    Cement, Crush, Sand, Plastisizer, Air Entraining Agents, Steel Reinforcement, Epoxy and

    Grouting material, and earth work.

    The material associated with Mechanical Works of the Project is Gates, Hoisting System, Cables, Motors, Gear Box and Welding Materials

    Table 3.1: Source of Raw Material

    Sr. No. Raw Material Availability Source

    1 Earth Material (soil) Available locally, borrowed from the lands temporarily acquired for the purpose.

    2 Aggregate (crush) Available at many sources, such as: Quarries at Sakhi Sarwar (160 miles), Margalla Hills (320* miles) and Sikhanwali (220* miles), Sargodha (230* miles). The choice will however will depend upon the quality and suitability of the rock material of the construction of the hydraulic structures.

    3 Rip-rap material Available from the three locations indicated above.

    4 Sand Though available locally, the construction grade would need to be acquired from Chenab River bed (100* miles) or other approved site.

    5 Water for preparation of Ample useable (at most of the locations)

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    3-7

    Sr. No. Raw Material Availability Source

    concrete groundwater aquifer is available along the canal. The contractor will install tube well within PID land at the agreed location with consultants environmentalist and Project Management Staff.

    6 Water for compaction of embankments

    Canal water can be used for this purpose with the permission of regulating authorities and supervision consultants

    7 Cement Portland cement is locally available from the two factories situated at Daud Khel (250* miles). However, the cement of other grades is available within the country for the factories at D.G.Khan (260* miles), Karachi (800* miles), Chakwal (300* miles), Islamabad (281* miles), Wah (365* mile) etc.

    8 Reinforcement steel Available from re-rolling mills at Lahore (94* miles).

    9 Mechanical parts of the Gates

    Could be manufactured at Heavy Mechanical Complex at Taxilla (365* miles), Factories at Lahore (94* miles) and Gujranwala (160* miles) and /or imported from abroad.

    * All distances are given from Pakpattan Canal Head Regulator.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    4-1

    4. ENVIORNMENTAL BASE LINE CONDITION

    4.1 GENERAL The data were collected regarding the physical environment, biological environment and

    social aspects of the study area during stakeholder consultation and technical visits

    conducted by the environment team.

    4.2 PROJECT AREA OF INFLUENCE (AOI) The area of project influence referred as Area of Influence (AOI) is the area likely to be

    affected by the project, including all its ancillary aspects such as canals, sites for proposed

    diversion channel(s), escape channel(s), relocation and access roads, borrow and waste

    disposal areas and labour camps as well as unplanned developments induced by the

    project.

    Although the major construction activities remain restricted to the construction site which is

    along the canal and its distributaries, yet the situation in which construction related activities

    could extend beyond the construction site include:

    a) The Labour camp site, batching plant, material storage depots, equipment

    and machinery yards

    b) Borrow areas for soil materials

    c) Construction of haul tracks in order to transport construction material

    d) Impact of accidental canal closure on canal command area

    The canal command area falls in four districts; Okara, Pakpattan, Vehari and Lodhran out of

    which the major part is covered in districts Pakpattan and Vehari. Other main cities/towns

    located along the canal are Arifwala, Burewala, Mailsi, Luddan, Tibba Sultanpur, Gaggo,

    Sahuka, Machiwal, Karampur, Shaikh Fazal and Thingi.

    Overall environmental study area map is given in Figure 4.1.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    4-2

    Figure 4.1: Overall Environmental Study Area Map

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    4-3

    4.3 PHYSICAL ENVIRONMENT Physical environment consists of the environmental parameters covering physiography and

    soil condition, water quality (surface and groundwater), ambient air quality and climate.

    4.3.1 Physiography and Soil

    The physiography of the canal command area is indicated on Figure 4.2.

    Figure 4.2: Physiography of Canal Command Area

    H I N D

    U

    K U

    S H

    RA N

    G E

    K A R AK O R A M

    R A

    D E O SA I

    M T S L A

    D A

    K H

    R A

    N G

    E

    Z A

    S K

    A R

    M T

    N S

    .

    H A

    ZA

    R A

    G R E A T

    H I M

    A L

    A Y

    AR

    A N

    G E

    K A

    I L A

    S

    R A N G E

    P I R P A

    N J

    A L

    R A

    S I W

    A L I K

    R A

    N G

    E

    H I

    N D

    UR

    A S

    S A F E D K O H

    S A L T R A

    .

    T O

    B A

    K A KA R

    C E

    N T

    R A

    LB R

    A H U

    I

    R A

    .

    R A S

    K O

    HR A

    S I N J A R A I

    C H A G AI H.

    S U L A

    I M

    A N

    R A

    .

    S A H A

    NR

    A.

    C E N T R A L M A K R

    A N

    R A

    .

    M A K R A N K O S T R A. H A

    L A

    B A

    B

    H

    K I

    R T

    H A

    RR

    A.

    MILES 50 0 50 100 150 MILES

    S C A L E

    MOUNTAIN RANGE

    DESERT

    L E G E N D

    INDUS PLAINS

    A f

    g h

    a n

    i s

    t a

    n

    China

    I r a n

    Arabian Sea

    I n

    d i

    a

    FA

    TA

    Indu

    s Rive

    r

    In

    du

    s R

    ive

    r

    J helum

    River

    Chen

    ab R

    iver

    Ravi

    Rive

    r

    Sutle

    j Rive

    r

    Hu

    b River

    Ha

    ng

    ol

    Riv

    er

    Zh

    ob

    Riv

    er

    Da

    sh

    at

    Riv

    er

    Disputed TerritoryJammu & KashmirIslamabad

    Lahore

    Quetta

    Karachi

    In

    du

    s R

    ive

    r

    Peshawar

    Gawader

    GilgitAgency

    Project Area

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    4-4

    The main land form units which exist in the Pakpattan canal command area are:

    - Recent Flood Plain

    - Sub-Recent Flood Plain

    - Miscellaneous Land Types

    Recent Flood Plain covers about 12% of canal command area. It is further spilt into category

    level plains (about 9%), bars and levees (about 3%). It lies along the right bank of river Sutlej

    as a continuous strip and along the left bank of Sukh Beas in discontinuous patches. It is

    partly subjected to inundation during high floods. Sub-Recent plain lies between recent flood

    plain and Pleistocene river terrace. It occupies approximately 80% of the canal command

    area and consists of level plain bar and levees. The remaining miscellaneous land consists

    of roads, cities, industry, built-up area, canals etc.

    4.3.2 Soil Types

    The proposed Project area forms a part of the vast Indus plain, which is a part of the Indo-

    Gangetic depression. This depression is of a synclinal nature. Synclinorium depression is a

    fore deep downward of the Himalayan foreland of variable depth, converted into flat plains

    by the simple process of alluviation. The alluvial deposits are underlain by rocks of

    Precambrian age. The soil of the level area is generally medium to coarse texture. Bar and

    levees have medium to coarse material. In sub-recent flood plain the soils of the bar and

    levees are relatively coarser while those of channels / basin are predominantly clayey1.

    4.3.3 Surface Salinity

    SCARPS Monitoring Organization (SMO) undertakes the study to identify the saline area in

    Pakpattan canal command area. Portable digital conductivity meter was used to measure

    the EC of 0-15cm soil. A total of 746 surface samples were tested for salinity categorization.

    Four categories namely, non-saline (S1 (EC up to 4dS/m)), slightly saline (S2(EC between 4

    to 8dS/m)), moderately saline (S3(EC between 8-15dS/m)) and strongly saline (S4(EC above

    15dS/m)) were recognized and mapped. The percentage of saline area found within the

    canal command area is summarized in Table 4.1.

    Table 4.1: Percentage Surface Salinity Statistics

    1 data obtained from Reconnaissance Soil Survey Report of Sahiwal and Multan areas prepared by Soil Survey of Pakistan

    Class Percentage

    Non Saline (S1) 90

    Slightly Saline(S2) 1

    Moderately Saline (S3) 1

    Strongly Saline (S4) Negligible

    Miscellaneous Land Type 8

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    4-5

    4.3.4 Seismicity Data

    Earthquake in non-cohesive soil may cause serious problems. In extreme cases liquefaction

    can occur if

    Relative density is low

    Initial confining pressure (overburden) is low

    Earthquake intensity is high

    Duration of ground shaking is long

    National Seismic Monitoring Centre of Pakistan issued the seismic zone map for Pakistan,

    as shown in Figure 4.3. Pakpattan canal command area falls in low hazard area and low risk

    associated with the infrastructure found in this area.

    Figure 4.3: Seismic Zones of Pakistan

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    4-6

    4.4 HYDROLOGY The main source of water within the AOI can be divided into surface water and groundwater. 4.4.1 Surface Water

    Pakpattan canal system is the main source of the surface water within the canal command

    area. There are some seasonal nallahs which run during the monsoon period but due to lack

    of any collection and storage infrastructure, it is too scant and unreliable to be of any

    agricultural or other use. Pakpattan canal is a perennial canal and closes only for cleaning

    purpose. The main canal is divided into two parts; Upper Pakpattan and Lower Pakpattan

    canal. The Upper canal off-takes from river Sutlej at Suleimanki Barrage and Lower canal

    feed through SMB Link canal. M.P Link canal is another source of upper Pakpattan canal

    and brings about 1000 cusecs of water from L.B.D.C. Pakpattan-Islam Link canal off-take

    from upper Pakpattan at RD 406 and takes about 1000 cusecs of Upper Pakpattan canal

    water to Islam Barrage to accommodate the discharge of Upper Bahawal and Qaim Canal.

    The discharge capacity of the Upper Pakpattan canal at the head regulator (Suleimanki

    Barrage) is 6,594 cusecs.

    Irrigation Standards Guideline of FAO Paper 29, Hanson et al., 1999 and WAPDA, are used to interpret

    infiltration issues resulting from the use of Pakpattan Canal waters for irrigation. FAO has

    defined infiltration as a function of both Sodium Adsorption Ratio (SAR) and Electrical

    Conductivity (EC) whereas WAPDA Standards (described in table 4.2) define infiltration as a

    function of SAR and or Residual Sodium Carbonate (RSC) only.

    Table 4.2: Water Quality Parameters (WAPDA STANDARD)

    Human Consumption The canal water analysis indicates that water quality does not meet the WHO drinking water

    standards and is not fit for human consumption for drinking without any treatment (results

    attached in appendix 4.1)

    Recreation Use The canal can be used for recreational activities i.e. bathing, water sports etc as the canal

    water quality meets the available standard for recreational purposes (results included in

    appendix 4.1) USA Environmental Protection Agency (USEPA), 2003 defines maximum limit

    of E-coil equal to 126 per 100ml for freshwater for recreational use.

    Symbols Usable Marginal Hazardous

    EC x 106 S/cm 0 1500 1500 3000 > 3000

    RSC (meq/l) 0 2.5 2.5 5.0 > 5.0

    SAR (mg/l) 0 10 10 18 > 18

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    4-7

    Water Pond for Livestock Lined ponds recently constructed along Pakpattan Upper are not working properly. The

    ponds were designed to accommodate the livestock and minimize canals bank damage

    from the livestock. The pond water is supposed to be replaced with the canal water through

    the installed pipe work on regular basis. But it seems that the pipes are blocked or were

    wrongly designed. The ponds remain filled with dirty water and add the nuisance to the local

    environment e.g. odor, mosquitoes breeding place etc. Also, in some cases, the pond water

    escaped to the adjacent agricultural land through the cracks in the structure and damaged

    the crop. Most of the ponds are damaged and not safe to be used by livestock.

    Plate 4.1: Existing Livestock Pond along the Canal

    As the constructed ponds do not serve the purpose, animals use the canal water and

    damage the canal banks.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    4-8

    Plate 4.2: Livestock Damage the Canal Banks

    4.4.2 Flood Record

    Under Second Flood Protection Sector Project (FPSP-II), flood risk maps for 5 year and 50

    year return period were developed for Sutlej River; part of the map shown in Figure 4.4. The

    map indicates the potential area inundated during flood. This information will be used to

    prepare the flood protection plan and contractors facilities set up e.g. labour camp, batching

    plant, plant & equipment yard etc during detailed design and project implementation phase.

    Five (5) years and fifty (50) years flood calculated at Suleimanki barrage from the statistical

    analysis are approximately 125,000 cusecs and 350,000 cusecs respectively. The historical

    record of major flood pass through the Suleimanki barrage is summarized in Table 4.3.

    Table 4.3: Peak Discharge of Prominent Years in River Sutlej at Suleimanki Barrage

    Years Discharge through

    weir (Cusecs) Through Breaches in Flood Embankment

    Total (Cusecs)

    1942 325,000 Nil 325,000 1943 309,000 Nil 309,000 1947 360,000 Nil 360,000 1950 332,000 Nil 332,000 1955 422,000 175,000 597,000 1988 400,000 100,000 500,000 1995 302,000 Nil 302,000

    The most recent flood that caused breach in RMB at Suleimanki barrage and damaged

    Pakpattan upper and Khadir branch occurred in 1988. There was no flood in 2010 as the

    flood only occurred in western rivers (Rivers Sindh, Jehlum and Chenab).

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    4-9

    Figure 4.4: Flood Inundated Area near the Canal Head Regulator

    Legend

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    4-10

    4.4.3 Groundwater

    Unconfined aquifer can be found as shallow as five 5m depth from ground level at some

    places along the canal. The aquifer constitutes loose sand of high permeability. Hand pumps

    and tubewells are the two most common sources of groundwater within the canal command

    area. Groundwater is mainly used for drinking and agriculture purposes.

    Groundwater Quality in Canals Command Area The secondary data for groundwater quality has been collected from Directorate of Land

    Reclamation and SMO offices for canals command area. The groundwater was classified on

    the basis of laboratory analysis arranged by SMO for Electrical Conductivity (EC), Sodium

    Adsorption Ratio (SAR) and Residual Sodium Carbonate (RSC) during 2003-04. For ease in

    description, the groundwater has been expressed as usable, marginal and hazardous for

    irrigation as determined by the adverse value of any of the above mentioned three

    parameters. The classification criteria used is not intended to be strict in relation to the

    effects of irrigation water on soil and crop growth which can be truly adjusted according to

    environmental factors such as climate, type of soil, crops grown and management practices.

    SMO also carried out testing for pH and EC in the field by using digital portable pH and EC

    meters and sent all the water samples to the laboratory for detailed chemical analysis. The

    samples were analyzed for pH, soluble cations, soluble anions, dissolved salts, EC, SAR

    and RSC. These parameters are used for the classification of water as usable, marginal and

    hazardous. The parameters associated with these classifications are as follow:

    Usable EC < 1500 S/cm; SAR 18mg/l; RSC >5 meq/l

    Using the above parameters, 609 water samples were collected out of which 345 were from

    hand pumps and 264 from shallow tubewells (SMOs publication No. 29). The results are

    summarized in Table 4.4.

    Table 4.4: Shallow Groundwater Quality

    Source Shallow Water Quality

    Usable (%) Marginal (%) Hazardous (%)

    Hand pumps 61 30 9

    Tubewells 75 21 4

    Water quality of tubewells is relatively better than that of hand pumps mainly because the

    depth of extraction is deeper in case of tubewells.

  • Rehabilitation and Upgrading of Pakpattan Canal IEE Report

    4-11

    Depth of Water Table SCAPRs Monitoring Organization (SMO) is engaged in monitoring the water table depth in

    Indus Plain bi-annually i.e. during pre-monsoon and post- monsoon through a network of

    piezometers and tubewells. On the basis of data collected by SMO during 2002-03, it was

    found that water table was not encountered within 300cm of depth from grou