Safety Talk : ACCESS SHAFT Climbing shutter By: Emad Salem

Transcript of 36th Safety Committee Meeting - draft 28-3-13 new

Page 1: 36th  Safety Committee Meeting - draft 28-3-13 new

Safety Talk : ACCESS SHAFT Climbing shutter

By: Emad Salem

Page 2: 36th  Safety Committee Meeting - draft 28-3-13 new

Items to be discussed1.Introduction

2.Sequence of the works

3.Safety precautions/Risk Assessments

4.Method Statement

5.Lesson learned from T02

Page 3: 36th  Safety Committee Meeting - draft 28-3-13 new

Introduction :- This presentation is to present the sequence of

Constructing SIX meter diameter climbing support

structure (used on all the blocks but Block 1): this will

consist of a frame with a system of 8Nos. “klik-klak”

brackets to anchor the formwork to the wall and support

it. The structure will be completed with two platforms

(top and bottom platform) at two different levels. The use

and lifting of the formwork will be one of the key aspects

to be managed and strictly controlled during construction

as it could potentially create severe Health and Safety

Hazards.

In particular, the structural failure of a single component

of the formwork might trigger the collapse of the entire

system with significant falls from height and serious

consequences.

Page 4: 36th  Safety Committee Meeting - draft 28-3-13 new

Sequence of the works:-

1.Surface preparation for construction joints between base slab and block n0.1.

2.Shaft survey as built and chipping SCL if necessary.

3.Geo textiles installations as separation later between CPL and Diagram wall

4.Block No.1 Rebar works.

5.RMD shutter panels preparation with the platform and inspections,

Lowering/Aligned in the passions by inclined jacks and anchor with the base slab.

6.Lowering Membrane and tightening

7.Installing the water stop between Block 1 and Block 2

8.Survey and QC inspection, then casting

9.Installed the injection hose between Block number No.1 AND No. 2

Page 5: 36th  Safety Committee Meeting - draft 28-3-13 new

Sequence of the works:-

10.Installed the rebar for block number 2

11.Dismantling Block No 1 shutter and lifting up to surface

12.Lowering frame structure with “klik-klak” resting on block 1 , 8 no shear pockets.

13. Lowering shutter panels fixed with the frame structure .

14. Setting out the shutter to the pouring position using turn buckle jacks and pouring.

15.Repeat point Item no. 6 to 9 with filler board between movement joints.

16.After concrete strength reach 20 mpa, close the shutter to the lifting position .

17.Lift up the shutter to the next block and repeat the same sequence each block.

18.After lifting each block ,grouting injection hoses ,casting previous shear pockets

and membrane joints welding.

Page 6: 36th  Safety Committee Meeting - draft 28-3-13 new

Surface preparation for construction joints between base slab and block n0.1.

Page 7: 36th  Safety Committee Meeting - draft 28-3-13 new

Shaft survey as built

Page 8: 36th  Safety Committee Meeting - draft 28-3-13 new

Geo textiles installations as separation later between CPL and Diagram wall

Page 9: 36th  Safety Committee Meeting - draft 28-3-13 new

Block No.1 Rebar works

Page 10: 36th  Safety Committee Meeting - draft 28-3-13 new

RMD shutter panels preparation with the platform and inspections, Lowering/Aligned in the passions by inclined jacks and anchor with

the base slab .

Page 11: 36th  Safety Committee Meeting - draft 28-3-13 new

Lowering Membrane and tightening

Page 12: 36th  Safety Committee Meeting - draft 28-3-13 new

Survey and QC inspection, then casting

Page 13: 36th  Safety Committee Meeting - draft 28-3-13 new

Installed the injection hose between Blocks

Page 14: 36th  Safety Committee Meeting - draft 28-3-13 new

Install the rebar for block number 2

Page 15: 36th  Safety Committee Meeting - draft 28-3-13 new

Lowering frame structure with “klik-klak” resting on block 1 , 8 no shear pockets.

Page 16: 36th  Safety Committee Meeting - draft 28-3-13 new

Setting out the shutter to the pouring position using turn buckle jacks and pouring .

Page 17: 36th  Safety Committee Meeting - draft 28-3-13 new

Lift up the shutter to the next block and repeat the same sequence each block.

Page 18: 36th  Safety Committee Meeting - draft 28-3-13 new

After lifting each block ,grouting injection hoses ,casting previous shear pockets and membrane joints welding.

Page 19: 36th  Safety Committee Meeting - draft 28-3-13 new

Safety precautions/Risk Assessments

Page 20: 36th  Safety Committee Meeting - draft 28-3-13 new

Safety precautions/Risk Assessments

Page 21: 36th  Safety Committee Meeting - draft 28-3-13 new

Safety precautions/Risk Assessments

Page 22: 36th  Safety Committee Meeting - draft 28-3-13 new

Safety precautions/Risk Assessments

Page 23: 36th  Safety Committee Meeting - draft 28-3-13 new

Safety precautions/Risk Assessments

Page 24: 36th  Safety Committee Meeting - draft 28-3-13 new

Safety precautions/Risk Assessments

Page 25: 36th  Safety Committee Meeting - draft 28-3-13 new

Safety precautions/Risk Assessments

Page 26: 36th  Safety Committee Meeting - draft 28-3-13 new

Safety precautions/Risk Assessments

Page 27: 36th  Safety Committee Meeting - draft 28-3-13 new

Safety precautions/Risk Assessments

Page 28: 36th  Safety Committee Meeting - draft 28-3-13 new

Safety precautions/Risk Assessments

Page 29: 36th  Safety Committee Meeting - draft 28-3-13 new

Lesson learned from T02

1.Full body harness must be used all the times while working on the shutter.

Setting out the climbing

2.Shutter must be surveyed before and after casting from minimum 8 points

from the centres.

3.All jacks must be proper tightening and secured .

4.Membrane sheets must be tensioned equally and checked from all the sides

and ensure for not air pockets.

Page 30: 36th  Safety Committee Meeting - draft 28-3-13 new

AnyQuestions..?