35 Oi › work › 03 › 350600.pdf35 Oi DuPont Engineering Barley Mill Plaza-Bldg. 27 Lancaster...
Transcript of 35 Oi › work › 03 › 350600.pdf35 Oi DuPont Engineering Barley Mill Plaza-Bldg. 27 Lancaster...
35 OiDuPont EngineeringBarley Mill Plaza-Bldg. 27Lancaster Pike & Rte. 141Wilmington, DE 19805
DuPont Engineering
November 29. 2000
Mr. Randy Sturgeon, 3HS23Remedial Project ManagerU.S. EPA, Region III1650 Arch StreetPhiladelphia, PA 19103-2029
SOUTH LANDFILL - SOUTH JAMES STREET CAP ASSESSMENTNewport Superfund Site, Newport, Delaware
Dear Randy,
Our assessment of the South Landfill - South James Street Cap alternatives is attached.We believe that incorporation of the existing asphalt roadway as part of the cap with a newshoulder overlapping the geosynthetic cap is the most desirable and cost-effective solution. Asdescribed in the attached report, road removal for a continuous cap installation would requiresignificant traffic interruption and extended DelDOT review.
Please contact me at (302) 992-5829 if you or your staff have any questions regarding thisassessment.
JLAipbbcc: K. Olinger, DNREC
C. Clayton, USCOEP. Welsh, DelDOTP. Meitner, Legal
Sincerely,
P.Y J'm L. Aker' Project Director
RR32l*650E I du Pont de Nemours and Company EN-3980 Rev 3/2000
DuPont Newport Superfund Site
SOUTH LANDFILL PROJECT1 SOUTH JAMES STREET ALTERNATIVES
ENGINEERING REPORT
prepared for:
DUPONT CORPORATE REMEDIATION GROUPW1LMINGTON, DELAWARE
submitted by:
URS CORPORATION
November 2000
AR32U65I
ENGINEERING REPORTSOUTH JAMES STREET ALTERNATIVES
SOUTH LANDFILL PROJECT
NEWPORT SUPERFUND SITE
NEWPORT, DELAWARE
Prepared for:DUPONT CORPORATE REMEDIATION GROUP
BARLEY MILL PLAZA 27
P.O. BOX 80027
WILMINGTON, DELAWARE 19880
Prepared by:
URS CORPORATION282 DELAWARE AVENUE
BUFFALO, NEW YORK 14202
(716)856-5636
SUBMITTED ELECTRONICALLY NOVEMBER 29,2000
C:\WENNTM>rofilcii\ujCTM>cilctop\Jamcii Sheet Report I !2900M>npoM Newport EvahiBlioti 112900 docI }fl9ff>0 3:04 PM
AR32U652
TABLE OF CONTENTSPage No.
1.0 INTRODUCTION.................................................................................................... 1-1
2.0 EXISTING CONDITIONS...................................................................................... 2-12.1 Site Inspection............................................................................................. 2-1
2.2 Design Drawings......................................................................................... 2-12.3 Delaware DOT Interview............................................................................ 2-2
3.0 ALTERNATIVE EVALUATION........................................................................... 3-1
3.1 Alternative 1 - Remove and Replace Existing Road................................... 3-1
3.2 Alternative 2 - Cap Over Existing Road/New Road Installation................ 3-23.3 Alternative 3 - Incorporating Existing Road as a Cap Component............ 3-2
3.4 Other Alternatives....................................................................................... 3-33.4.1 Low Permeability Soil Seal Between Asphalt and Geomembrane 3-33.4.2 Relocation of South James Street.................................................. 3-4
3.5 Conclusions and Recommendations........................................................... 3-4
FIGURES(following text)
Figure 1 Site Vicinity Plan
Figure 2 Existing Site Conditions
Figure 3 Remove and Replace South James Street - Typical Section
Figure 4 Cap Over South James Street, Construct New Roadway - Typical SectionFigure 5 Incorporating South James Street as a Cap Component- Typical Section
Figure 6 Geomembrane Overlap Detail
TABLES(following figures)
Table 1 South James Street Alternative Summary
C:\WTNNTMfcfilartiiSCT\DcslflopUamc* Sired Report 112900\Duponl Newport EvahMlion U2900.doc
]\fl9ma 3:04 PM !
flR32U653
APPENDICES(following tables)
Appendix A Telecon Memorandum
Appendix B Cost Estimates
C:\WINNnPTofik«\U!CT\Dciiltlop\Jamis Stica Report H2900M)upont Newport Evaluation M2900.doc11/29/00 3:04 PM li
AR32U651*
1.0 INTRODUCTION
The Newport Superfund Site in Newport, Delaware encompasses approximately 120acres along the north and south sides of the Christina River. The site includes the North Landfill,
the South Landfill, adjacent wetland areas, a former ballpark, and an operations area consistingof portions of the DuPont Holly Run Plant and the Ciba Newport Plant.
The United States Environmental Protection Agency (USEPA) Region III issued a
Record of Decision (ROD) for this site, dated August 26, 1993. The ROD describes the selectedremedy for the Newport Superfund Site, of which the South Landfill project is one component.
On August 8, 1995, the USEPA issued an Explanation of Significant Differences (ESD) for the
South Landfill portion of the remedy originally called for in the ROD. Dupont presently ispreparing a submittal package to further modify the original ROD and ESD. The modificationproposal intends to provide a more innovative use of available technology, better overallprotection to human health and the environment, and a reduction in project costs.
In summary, this modification proposal will include the installation of a soil-bentonite
barrier wall along the Christina River to act as a hydraulic barrier between the landfill and the
water body and a permeable reactive barrier wall around the remaining portions of the site to
provide treatment of groundwater migrating out of the landfill. In addition, a multilayer cap
consisting of a geosynthetic layer, a protective soil layer, and a topsoil layer will be installed
over the South Landfill and appropriately designed to promote drainage. The intent of the cap isto protect human health and the environment and to minimize infiltration into the landfill,
thereby extending the useful life of the permeable reactive barrier wall.
This report focuses on one portion of the South Landfill remedy. An existing state road
traverses the South Landfill site in a north-south direction in the eastern portion of the landfill.
This road originally was constructed in the early 1970s and is referred to as South James Street(see Figure 1). Waste presently exists under and on both sides of the roadway. The ROD and
ESD indicated that a section of South James Street would be removed, and, following the
capping of the South Landfill, would be reconstructed on top of the cap. This report has been
C:\WINMnProHca\niiCTMtotlncip\JamaiSlicctRcport It 2900\Dnpont Newport EvahMlion 112900 doc
11/29/00 3:04PM 1~1
AR32t*655
prepared to compare this approach to various other alternatives to determine if there is a more
cost effective, potentially less disruptive, and equally effective alternative.
The alternatives proposed focus on incorporating South James Street into the cap design
or constructing a new road on top of the cap in various configurations. The results andinterpretations of the alternative analysis will be incorporated into the development of DuPont's
submittal package noted above.
C:\WINOT\ProfBc*\uscT\Dc!!k)opUaiTKii Slrcc* Report 112900\Dupm< Newport Evaluation M2900.doc
11/29(00 3:04 PM 1-2
HR32U656
2.0 EXISTING CONDITIONS
The existing conditions and construction layout of South James Street were evaluated byvisually inspecting current roadway conditions, reviewing historic design drawings, and
interviewing Delaware Department of Transportation (DOT) personnel.
South James Street extends from the James Street Bridge to Old Airport Road,
paralleling southbound State Route 141 (see Figure 2). Ingress to and egress from southbound
State Route 141 can be made from South James Street. Since many businesses and commutersrely on this roadway, this roadway cannot be eliminated. Approximately 1,000 linear feet of
South James Street traverses the eastern portion of the South Landfill.
2.1 Site Inspection
On November 8, 2000, a site inspection was performed on the South Landfill site and
South James Street. Based on a visual inspection, the existing roadway lanes and shoulders are
asphalt. The asphalt surface in the travel lanes is in fair condition with little deterioration.
Asphalt sealant has been applied to various cracks in the asphalt surface (travel lane andshoulder). Portions of the asphalt surface within the pavement shoulders are deteriorating and
some portions have disintegrated resulting in cracked pavement and potholes.
2.2 Design Drawings
The original design drawings for South James Street (south of the James Street Bridge)
dated 1971/72 were reviewed and evaluated against the visual inspection activities. South JamesStreet originally was referred to as an access road from Basin Road to Old Airport Road, and was
proposed to be constructed of borrow fill. This proposed construction subsequently was
modified to asphalt pavement, although no record drawings were available from the Delaware
DOT, Therefore, the actual pavement cross sections (both course thicknesses and mix types)currently are unknown. The alignment shown on the original design drawings was similar to thatidentified during the site inspection.
CAWINNTiProfaartu«CTM5crfrtopUamoi Slrc« Report I l2900\DuponT Newport Evahulkm Il2900.doc
ll/29fl» 3:04 PM 2-1
AR324657
2.3 Delaware DOT Interview
Delaware DOT personnel were interviewed to discuss the history of South James Street
and the proposed alternatives being evaluated. DOT personnel verified that the street originally
was planned to be a fill access road and subsequently was changed to an asphalt pavement road.
The course thicknesses and mix types of the South James Street roadway were unknown to DOT
personnel.
Based on the discussion of the alternatives being evaluated, DOT personnel noted these
concerns:
• Many businesses and commuters currently rely on this road and, therefore, the
roadway should remain active.
• Traffic disturbances should be kept to a minimum during the performance of the
South Landfill project
• The existing roadway should not be permanently removed.
• A removal and replacement alternative may involve/require public participation
Based on these considerations, DOT personnel favored incorporating the existingroadway into the proposed landfill cap. A memorandum of the telephone interview between
URS and Delaware DOT personnel is provided in Appendix A.
t Strccl Report 112900\Dnpml Newport Evaluslion I12900.doc
2-2
AR32U658
3.0 ALTERNATIVE EVALUATION
Various road alternatives were compared to the ROD/ESD South James Street remedy todetermine if there are more cost effective, potentially less disruptive, and equally effective
approaches. Including the original proposal, three alternatives were evaluated in detail:
• Alternative 1 - Remove and Replace Existing Road (original proposal)
• Alternative 2 - Cap Over Existing Road/New Road Installation
• Alternative 3 - Incorporating Existing Road as a Cap Component
Other alternatives also were considered, but not in detail due to the reasons presented below.
3.1 Alternative 1 - Remove and Replace Existing Road
This alternative was the proposed remedy for South James Street in the 1993 ROD andwas maintained under the 1995 ESD. Under this alternative, a section of South James Street
would be removed and replaced on top of the proposed South Landfill cap. The cross-section of
the new roadway would be comparable in material types, course thicknesses, and vertical profile
to the existing road. A typical section of roadway for this alternative is shown in Figure 3.
For this alternative, a 1,200-linear-foot temporary bypass road would need to beconstructed east of the existing South James Street. Temporary traffic controls would need to be
implemented along this temporary roadway to maintain existing traffic flow in a reliable and safe
manner. After the temporary bypass roadway is constructed and operational, approximately
1,000 linear feet of South James Street would be removed. The subsurface barrier wall proposedto be constructed under the roadway would then be installed. The subgrade under the removed
portion of South James Street would then be over-excavated for cap placement (this would allow
the vertical profile of the new roadway to match that of the original). The landfill cap systemwould then be extended over the original location of South James Street. Following this cap
installation, a new portion of South James Street would be reconstructed on top of the cap system
along the road's previous alignment. This alternative likely would result in a cap low point,
C:\WINNTNProfika\iis Dciiklop\Iamc« StrcM Report 112900\Duponl Newport Evaluation M2900.doc
11/29AX) 3:04PM 3-1
AR32i*659
thereby complicating cap drainage features due to the over-excavation required for the capinstallation.
Advantages, disadvantages, and costs associated with the removal and replacement of the
South James Street roadway alternative are provided in Table 1.
3.2 Alternative 2 - Cap Over Existing Road/New Road Installation
This alternative would consist of installing a landfill cap over the existing South James
Street roadway and installing a new roadway on top of the cap. This alternative is similar toAlternative 1 except that it would not include the removal of the existing section of South James
Street. A typical section of roadway for this alternative is shown in Figure 4.
Advantages, disadvantages, and costs associated with installing a landfill cap over theexisting South James Street roadway and installing a new roadway on top of the cap are provided
in Table 1.
3.3 Alternative 3 - Incorporating Existing Road as a Cap Component
Under this alternative, the existing South James Street roadway would remain in placeand act as a portion of the landfill cap. The proposed geomembrane landfill cap would extend
only under the roadway shoulders and be discontinuous to avoid complete roadway removal and
reconstruction. In this "shingled" approach, the roadway would prevent infiltration where the
geomembrane is made discontinuous. Precipitation would drain towards the adjoining roadsidedrainage channels, away from the shoulder/geomembrane overlap. A typical section of roadway
for this alternative is shown in Figure 5.
Based on the deteriorated conditions of the roadway shoulders, a portion would be
sawcut and removed. The geomembrane component of the proposed landfill cap would then beinstalled and anchored under the location of the removed shoulders. Following the
geomembrane installation, the roadway shoulders would be replaced in-kind. A typical
C:\WTNNT\Profilc3\UiCT\DcsklopUiima! Street Report 112900\Duporl Newport Evahmiion 112900. Joe
II/29AH) 3:04 PM 3-2
AR32i*660
geomembrane overlap detail is provided in Figure 6. Considerations would be implemented to
maintain adequate stormwater control.
It is understood that this alternative would have a greater potential for landfill capinfiltration (e.g., future pavement cracking and incidental infiltration between geomembrane and
asphalt shoulder). However, the proposed South Landfill project remedy involves the treatment
of groundwater, not containment, and the impact to the remedy from minor infiltration through
the cap would be insignificant.
Advantages, disadvantages, and costs associated with the South James Street tie-in
alternative are provided in Table 1.
3.4 Other Alternatives
Other road alternatives that were evaluated included:
• Placing a low permeability soil seal between the asphalt and geomembrane
• Relocating South James Street elsewhere on the site
3.4.1 Low Permeability Soil Seal Between Asphalt and Geomembrane
This alternative would include the installation of a low permeability soil layer under theexisting roadway shoulder and terminating the geomembrane cap in the low permeability soil
material. The existing roadway would be upgraded as noted for Alternative 3 with the shoulderpavement being placed on the low permeability soil to provide a seal. The alternative was not
considered further because:
• Low permeability material does not provide a good road subbase, as it lends
itself to frost heave.
• The thermal expansion and contraction of the stiff geomembrane would not
guarantee a reliable seal within the low permeability soil. Thermal expansion
C:\WINNT\Profflai\nsCT\Dciilnop\IainDi Sired Report 112900\Duponl Newport Evalnalion 112900.doc
1I/29AX) 3:04 PM 3-3
AR32i»66l
and contraction could result in geomembrane liner ripples that could cause
openings in the liner at critical water flow locations (roadway subbase).
3.4.2 Relocation of South James Street
This alternative would include constructing a new section of roadway in a new alignment
over the completed landfill cap. The new section of roadway would then be tied into the
remaining South James Street pavement beyond the limits of the South Landfill cap. This
alternative has similar advantages and disadvantages to the removal and replacement alternative.
Additional disadvantages would include:
• Potential sight distance concerns
• Construction of a roadway outside the current DOT right-of-way, which would
introduce complex property acquisition/easement issues
• Technically difficult transition from the fixed South James Street Bridge to the
relocated roadway, since the transition area would be close to limits of landfill
• Increased costs based on longer roadway replacement distance
Based on these considerations, this alternative was not considered further.
3.5 Conclusions and Recommendations
Alternative 3, incorporating existing road (South James Street) as a cap component, is
the selected alternative for several reasons. First, this alternative would best address DOT's
requirement to minimize traffic disruptions during construction activities. Second, it would be as
effective as the other alternatives considering the overall remedy being implemented. Third, this
alternative would be the most readily constructed. Fourth, this is also the least expensive
alternative.
C:\WTNNT\Piofacit\UiCi\DtHiklop\Jmiai Sired Report 1129OO\Dupont Newport Evaluation 112900.doc3:04PM 3-4
FIGURES
C:\WlNKnProfil<a\n»crM)ciitaop1JBmc«Strcd Report 11290fl\Dnptin* Newport Evaluation 1129fl0.doc11/29.W) 3:04 PM
AR32i»663
tlJa:r>o
O
I/)
oQ_=)O
AR32U661*
AR32U66S
to
o
o:ui
S
ftfe
: o
w) ^LJ <
< 51
) LJO LJ-!w r_oo
oUJ t—
X<oQ LJ
fe 5O LJCL IIrt
• I I .——i»- o
a:
1LUQ
O
AR32U666
§! ^\ i *LJC£Z>O
,1 III , 5 s °P^£i ~i—————n m s . => K ss IK >=l""'• a ' • I IS! ^*. « -^ ^ itu. H(r
<olLJ5<—)XI—
oI CM
_) LJ0O
LJ
rro
" I?* te ^i O
oLJ
AR32i»667
LJLJrrk o_oo o
<(/)
sI- p Oa: < oo a:a. o
oo
oo_oo
AR32I+668
ooO)
EXISTING ASPHALTSHOULDER
REPLACEDASPHALTSHOULDER
STONEAGGREGATE 4DEPTH
GEOMEMBRANE
NOT TO SCALE
?| MAC* I DUPONT NEWPORT SOUTH LANDFILL , rir,IDr RGEOMEMBRANE OVERLAP DETAIL I MbUKL b
TABLES
Ci\WINVnProSc«\u!icrt)ciiktop\Jainai Street Report 112900\Duponl Newport Evaluation 112900.docII/29AX) 3:04 PM
AR32U670
S
<*>u H wrj u Hg w 55H »^25>-- r* r.
TABLE 1
£ET ALTERS
.ANDFILL PI
T SUPERFUI
JczJ*NNK°£H£V3 & l>W O gS co z;-S
MH&O<x>
QU
5?^ioH<JV)U
DISADVANTAGES
wUOis>
zo£sL></3Uou£M5aJH
•<
O
o'o«n&
Since the cap would be
installed under the roadway,
future ca
p accessibility w
ill be more dif
ficult
. In
addition, the cap installation wi
ll be
at a low p
oint
under the road, creating stonn drainage design
concerns.
. Construction of a temporary bypass road would be
required As a result, more
traff
ic co
ntrol measures
would need
to be implemented and thi
s would
resul
tin si
gnificant disruptions to tr
affic flow.
The DOT indicated p
ublic participation may be
required fo
r this alternative.
This was die most ex
pensive alternative
evaluated
— i (N r •*
S>
fK _1 §13 yo -a-SI2 1•5 S-2 •£•S «5. <n k.g S3 W$ £ *
liiu », a4J J 1*•° •€ rSIs*Ml&• « o & 2g "C 9 y is?Sl^a ^8b'*oo 5 3JS 1-*-< O siH •« t
-
eo _.'ft 8 "3 ;U IS fl 1 1-a u 6 -B."oS OT 4 •§* 8<a « -• o E"«^S«g J S S Q
1 &^ Soat oS o on &J
-
oSo*v£>1-1V»
1-1 ^l1 Jill -1 - ? a "3 8 3 ^ * 2 g •? s|J-s gag "jail S1 JJssi illil^il s -sIB*! S 8|« S-g jg| a s3§=3-i Syl.y^-l-So-S.e- «TjE-S-^ l-e^tfi^S-rtrS^.y g-•^ w g _£• g T3.§T3!>**1!wa **
Ills llHl^Ji^ll|lf iStJ HHlta 111 §8 liirilnh1 •»l« U ! f ill 1^i§-fiiiii|iiii^|lillllIltlllllllaNI--i cs <*i Tt vi
<ut?s «-« 5^ Q-5 ^n -•« °? 1 «.5 S ?-a -^ fE? « E^ e S.^ £ 5at ^o c qd SJ «.S e BI M .s0 fe B t3X .S S .8•" "£ 53 G
|1 JiS "i 2 u-. B ii& a 55 cjf <j 13 o
CJ —— '"- r-., 'S 0 Ew C B| fe -5 .3
1 1 3 S>S S* 2s '3 * sI c 8 ?8 s -^ ioo 5 3 ™5 g « 13[2| £ fS— c-i
T; B i-u. 3 a s c^^ S f oO g -3 <« uM ° -5 a ° 5 n »5 E eg1. -| | | -| |PJ a> 9 O BJ O fl) rO w 4 U vi Qi U
<
ooor-"mG >
The lan
dfill ca
p would not be continuous an
d the
potential exists fo
r incident
infiltration to
enter th
elandfill between
the geomembrane
cap and the
roadway.
This disadvantage however, is no
t critical
since the treatment remedy employed can readily
address incidental infiltration.
~
"S5t$•d ^•§ o&• eK v« -3•° • u° "? fc .9 5TS a liiO .5 i5^ E £•« ., -E w!•* 5 £C T3 S "^"> "3 u ~II « Sf s J5F *§ ^
o o M&s S 31.1 15_ — -Q ?3« a. c rt~" p %p~* l*J0 5 g o.1 3 "i^ QJ H -3
S "2 ts §ia p u ain & . ^ Sc je ta g05 o gu u °— H
'CuH*-J
«iWC^ «S S crt G u1- s-se-3 u &g 3 « gj£ So
m
03X•acuD.
3S~au•agoHcu5
1i§O*
AR32l*67l
APPENDIX A
TELECON MEMORANDUM
C:\WINNT\Profflca\mciMfcsklop\JaiTKai Sired Report 112900\Dupont Newport Evaluation I I2900.do11/29«0 3:04 PM
URS Telecon Memorandum
Date: November 13, 2000
To: Files: 05-00035849.00
From: Michael Azzarella
Subject: Newport South Landfill - Telephone Conversation with Delaware DOT
Today, Rick Hody, a URS roadway designeer, and I spoke with Paul Welsh of the DelawareDepartment of Transportation (DOT) to discuss the proposed South James Street work required forthe South Landfill remedy.
Paul gave us a little background about South James Street over the South Landfill. The street wasoriginally proposed to be an access road that would be constructed with borrow materials.Presently, this road has an asphalt pavement surface and no as-builts are available for the presentroad cross section (course thicknesses and material mixes). Paul indicated that his departmentwould be willing to go out and perform core sampling (if required and with advance notice) toverify materials types and thicknesses.
Paul indicated that this road is probably a secondary or tertiary road, but many businesses andcommuters rely upon this road, especially since it has an ingress to and egress from southboundState Route 141. Paul also indicated that this road should not be permanently eliminated during theSouth Landfill capping activities.
We discussed possible alternatives for integrating the existing roadway into the cap and building anew road over the cap. Paul noted that integrating the roadway into the cap (i.e. roadway tie-in)would result in the least amount of traffic disturbance, which is a very important issue to the DOT.We indicated that this alternative would require roadway shoulder repair and cap tie-in acivities.We inquired about their requirements for this work and Paul indicated that we need to propose theconstruction activities to the DOT based on DuPont's needs to provide a suitable cap for theremedy work. Paul indicated that a tresspass agreement would need to be executed by DuPont andthe DOT to conduct work on the roadway as approved by the DOT.
When the discussion addressed the installation of a new roadway, Paul expressed his hesitation.Paul did not understand the use of the new roadway if the existing road could be incorporated intothe cap system. Paul questioned if there was area available to install a bypass road, and expressedhis concerns about the road installation in a potentially hazardous area. A bypass road would resultalso result in significant disturbances to traffic flow in this area. Paul indicated that a roadwayremove and replacement activity may also require public input.
Paul also expressed concerns about a proposal to put a new road over an old road with the capbetween. Raising the vertical profile may not be possible due to the fixed elevation and requiredapproach distances to the James Street Bridge.
AR32U673
URS Page 2 of2
Based on our conversations, we feel that if the Paul had to recommend an alternative, he wouldfavor the alternative which incorporates the existing roadway into the cap design (i.e. tie-in). TheDOT is willing to work with DuPont for a solution that would be acceptable to both parties.
APPENDIX B
COST ESTIMATES
C:\WHflJTAPralilcs\iwT\Dcsklop\Jancs Sired Report 112900M)npoiit Newport Evaluation 112900 docll/29«0 3:04 PM
RR32U675
APPENDIX B - COST ESTIMATES
SOUTH JAMES STREET ALTERNATIVES
NEWPORT SUPERFUND SITE SOUTH LANDFILL PROJECT
Cost estimates were developed for:
• Alternative 1 - Removal and replacement of a section of South James Street with
the proposed South Landfill cap system installed under the roadway
• Alternative 2 - Placing the South Landfill cap over a section of the existing
South James Street roadway followed by construction of a new section ofroadway
• Alternative 3 - Incorporating the existing South James Street roadway as a
landfill cap component.
Alternative 1 - Remove and Replace Existing Road
This cost estimate includes removing a section of South James Street, installing theproposed South Landfill cap under the location of the removed roadway, and reinstalling a
section of South James Street over the cap in the previous location. As noted in the Engineering
Report, the actual pavement cross-sections (both course thicknesses and mix types) presently are
unknown. The typical cross-section, as shown in Figure 3, was used as the basis for establishingthe cost of a new roadway to replace a portion of South James Street. The estimated cost for this
alternative is approximately $390,000.
Alternative 2 - Capping Over Existing Road/New Road Installation
This cost estimate includes constructing the proposed South Landfill cap over a sectionof the existing South James Street roadway and constructing a new section of roadway over the
cap. The estimated cost for this alternative is approximately $360,000
C:\WlNNT\Profilot\uncf\Dcstaop\JamaiSlrccl Rqmrt 112900\Dnpont Newport Evaluation H2900.doc
11/29/00 3:<MPM B-l
AR32i*676
Alternative 3 - Incorporating Existing Road as a Cap Component
This cost estimate includes incorporating South James Street as a landfill cap component
and repairing the existing roadway. The estimated cost for this alternative is approximately
$57,000.
C:\WtNNTtf1roHi»WiCTtt>cstoopU«mc» Slrect Report 112900\Duponl Newport Evaluation 112900.doc
3:04PM B~2
AR324677
DUPONT NEWPORT SOUTH LANDFILLSOUTH JAMES STREET TIE-IN ALTERNATIVES
COST ESTIMATE
ALTERNATIVE 1REMOVE AND RECONSTRUCT NEW ROAD
LINER UNDER ROAD
DESCRITION UNIT QUANTITY UNIT TOTALCOST COST
Mobilization/Demobilization US 1 $14,744 $14,744
Temporary Road (Install & Remove) SY 3,200 $13.44 $43,008
Excavation & Disposal of Existing Road CY 6,000 $8.26 $49,560(Disposal of Materials Onsite)
Subbase Fill and Compaction CY 4,000 $15.13 $60,520
Asphallic Pavement___________- Base Course - Shoulders SY 1,950 $5.27 $10,277
- Base Course - Lane SY 3,100 $9.07 $28,117
- Binder Course - Shoulder SY 2,300 $3.57 $8,211
- Binder Course - Lane SY 2,750 $8.38 $23,045
Surveying DAY 10 $1,125 $11,250
Striping LF 3,000 $0.24 $720
Traffic Control LS 1 $37,955 $37,955
Additional Cap Installation* AC 1 $77,255 $77,255
Subtotal $364,662Contingencies - 5% $18,233Total $382,895Say $390,000
* From DuPont North Landfill Cap Cost Estimate
AR32i»678
DUPONT NEWPORT SOUTH LANDFILLSOUTH JAMES STREET TIE-IN ALTERNATIVES
COST ESTIMATE
ALTERNATIVE 2REMOVE AND RECONSTRUCT NEW ROAD
LINER OVER EXISTING ROAD
DESCRITION UNIT QUANTITY UNIT TOTALCOST COST
Mobilization/Demobilization LS 1 $13,092 $13,092
Temporary Road (Install & Remove) SY 3,200 $13.44 $43,008
Protective Fill Over Ext. Roadway CY 1,300 $15 $19,669
Geotextile Cushion Under Cap SY 4,950 $3 $12,375
Fill at Road Slope to Existing Grade CY 2,000 $15 $30,260
Asphaltic Pavement___________- Base Course - Shoulders SY 1,950 $5.27 $10,277
- Base Course - Lane SY 3,100 $9.07 $28,117
- Binder Course - Shoulder SY 2,300 $3.57 $8,211
- Binder Course - Lane SY 2,750 $8.38 $23,045
- Wearing Course SY 5,250 $4.23 $22,208
Surveying DAY 10 $1,125 $11,250
Striping LF 3,000 $0.24 $720
Traffic Control LS 1 $37,955 $37,955
Additional Cap Installation* AC 1 $77,255 $77,255
Subtotal $337,441Contingencies - 5% $16,872Total $354,313Say $360,000
* From DuPont North Landfill Cap Cost Estimate
AR32U679
DUPONT NEWPORT SOUTH LANDFILLSOUTH JAMES ETREET TIE-IN ALTERNATIVES
COST ESTIMATE
ALTERNATIVE 3INCORPORATE EXISTING ROAD AS A CAP COMPONENT
REPLACE SHOULDER
DESCRITION UNIT QUANTITY UNIT TOTALCOST COST
Mobilization/Demobilization LS 1 $3,500 $3.500
Shoulder Repair- shoulder sawcutting LF 2,000 $1.16 $2,320- remove shoulder, 8' width SY 900 $0.60 $540- install bedding stone, 8' width CY 30 $118 $3,540- install asphalt pavement, 2" shoulder SY 900 $3.57 $3,213
Saw Cut Pavement for Barrier Wall LF 268 $5.96 $1,597
Pavement and Base Course Removal CY 25 $65 $1,620
Stone Base Course Installation CY 15 $99 $1,481
Asphalt Pavement - 5" Total Depth SY 60 $20.94 $1,256
Liner Installation Under Shoulder SY 1,000 $6.30 $6,300
Surveying DAY 7 $1,125 $7,875
Traffic Control LS 1 $18,200 $18,200
Subtotal $51,443Contingencies -10% $5,144Total $56,587Say $57,000
Note: For shoulder replacement, sawcut, remove and replace approximately 8' (41 each side)
AR32i*680
coro
00
JJ«
Bartey Mill Plaza, Building 27 flfc 3 ? jj fester Pike & Route 141 . WHmJngton. DE 19805 I