3.3 project fiche
-
Upload
dagny-gisladottir -
Category
Business
-
view
1.473 -
download
0
Transcript of 3.3 project fiche
![Page 1: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/1.jpg)
Sustainable Economic Development of the Sudurnes region, Iceland
Preparation of Project Proposals‘The project fiche’
JOSE MATEOS MORENO
Ásbrú, January 2012
![Page 2: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/2.jpg)
2
1. Preparation of the project application form
2. Activity and resource planning
Contents
![Page 4: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/4.jpg)
4
Project Design: definition of a Project
• Economically indivisible series of activities for a precise technical function
• Identified outputs and objectives• Clearly defined beginning and end• A programme is a heterogeneous group of
measures and projects
![Page 5: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/5.jpg)
5
Elements of project design
• Why: the problem or need and wider objectives• What: activities, results and project purpose• How: internal and diagonal logic:
- Indicators for monitoring and evaluation- Risk analysis and assumptions- Preconditions- Finance: costs and co-financing- Implementation schedule
![Page 6: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/6.jpg)
6
Project Design: TasksResponsibilities of Final Beneficiary:• Designing of project proposals and submitting them
to IBs
Responsibilities of Lead Ministry (Sectoral Offices):
• Compliance with the sectoral strategic documents • Verifies technical quality of the project proposal • Verifies if the project proposal meets the eligibility
criteria for IPA measures • Ensures the national financial contribution for the
project
![Page 7: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/7.jpg)
7
The project application procedure should:
• Promote high quality project preparation• Asess if EU principles are met (horizontal
issues)• Check for availibility of all necessary
documents (feasibility studies, EIA, permits etc)
• Show main results of EIA and feasibility/CBA studies
• The format (project fiche or application form) is a tool for uniform communication of relevant key project information
![Page 8: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/8.jpg)
8
Elements of a project proposal ‘Project fiche’
1) Basic information 2) Objectives 3) Description4) Institutional Framework5) Detailed Budget6) Implementation Arrangements7) Implementation Schedule8) Cross cutting issues
1) Equal Opportunity 2) Environment
9) Rates of Return10) Investment Criteria11) Conditionality and Sequencing
Annexes: Logframe, implementation chart, contracting and disbursement schedule, list of preparation studies, laws, plans.
![Page 9: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/9.jpg)
9
Activities in Project Design
A. Information gathering for the problem analysis and the elements of project design
B. Deciding the scale and scope of the project
C. Assembling the project design elements
D. Filling in the project proposal (fiche)
![Page 10: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/10.jpg)
10
A) Information gathering
– Outcome of previous projects / gaps– Linked or other relevant activities– Views of potential beneficiaries / recipients– Monitoring/evaluation recommendations– OPs and any other government strategies or plans– Financial information – national funds available– Statistics available for Indicators of Achievement– Gender information– Institutional ‘audit’ of staffing / capacity / resources– Environmental Impact Assessment (EIA) / feasibility
studies (CBA) – Material for Fiche annexes
![Page 11: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/11.jpg)
11
B) Deciding the scope and scale
Scope: type of activities to include should depend on:
- type of needs/problems- cost/feasibility issues- dependency of success on specific activities
Size (capacity) of the project should depend on:
- market demand/need for the services of the project (feasibility study)
![Page 12: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/12.jpg)
12
C) The project design elements and logframe
D) Filling in the project fiche
![Page 13: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/13.jpg)
13
The logic of project design
Needs/Problems (t)
Overall objective
Project purpose Expected results
Input
Activity
![Page 15: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/15.jpg)
15
• Briefly explain the origins of the project and outline why it is being undertaken
• Problem or need analysis: causes of the problems and size of the problem
Example: High level of unemployment because of low economic activity
1. Why: Start with problem or need identification
![Page 16: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/16.jpg)
16
2. Objectives: Overall objective
• The Overall Objective should explain why the project is important to society, in terms of the longer-term benefits to beneficiaries and the wider benefits to other groups.
• The Overall Objective will not be achieved by the project alone, but will require the impacts of other programmes and projects (and probably other actions) as well.
• Example: to improve business environment in a region
![Page 17: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/17.jpg)
17
2. Objectives: Project Purpose
The single central objective of the project in terms of sustainable benefits to be delivered to the project beneficiaries.
• Example: to improve business infrastructure for new start-ups.
• To improve tourist infrastructure in a region.
![Page 18: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/18.jpg)
18
3a. Results
Results impact and sustainability
What is achieved what changes
what lasts
The results are what the project management is responsible for achieving by its completion date.
![Page 19: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/19.jpg)
19
3b. Activities
• The specific tasks to be undertaken during a project’s life to obtain results.
Activities should indicate:• what the person or organisation
responsible for the project should do.• how the project’s goods and services will
be delivered
![Page 20: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/20.jpg)
20
3c. Indicators
Measurable indicators that will show whether or not objectives have been achieved at each level of the logframe hierarchy and at defined times
Indicators provide the basis for designing an appropriate monitoring (and evaluation) system
Sources of Verification: the means by which the indicators or milestones will be recorded and made available to project management or those evaluating project performance.
![Page 21: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/21.jpg)
21
Risks & assumptions and Pre-conditionsRisks: factors which could affect the progress or
success of the project
In LFA: risks should always be expressed as assumptions
Risk analysis and risk management strategy for larger projects
Pre-conditions: constraints that have to be met before the project starts
![Page 22: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/22.jpg)
22
4. Institutional Arrangements
• Institutional framework within which the project will operate.
• Identify any constraints or changes that can have impact on results
• Chain of command• (a) who will be appointed as the "Engineer“• (b) who will be the "Employer" — the institution
responsible for providing the site and for paying the contractor
• (c) who will be or become "Owner" of the asset after project completion
![Page 23: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/23.jpg)
23
5. Detailed Budget
• Budget: estimation of investment costs• Clarify the cost estimation• Maintenance costs are not covered by EU
funds: make reservation in national budget• Specify co-financing of national budget,
municipalities, loans etc. (column funding source in resource schedule)
![Page 24: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/24.jpg)
24
6. Implementation arrangements
• Implementing agency of the project (details)
• Contracting parties
![Page 25: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/25.jpg)
25
7. Implementation schedule
A) Start of tendering/call for proposalsGive date, including when TORs and/or project specifications will be ready
B) Start of project activity
Expected date of commencement of first contract/grant scheme
C) Project completion
Expected date of last payment under last contract/grant
![Page 26: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/26.jpg)
26
Project Fiche – Step by Step
• Following the standard Project Fiche format – contained in an Annex to the Phare / Pre-Accession Instrument 2005 Programming Guide– Note: the format is very similar to Phare
2004– Fiche format can be found just after blue tab
(Day 1) in the training manual
![Page 27: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/27.jpg)
27
Project Fiche
• Introduction - Phare 2005 Project Fiche Format • Period 2005-07: multi-annual PF for Economic
and Social Cohesion (ESC) investments and for Institution Building (IB) and associated investment (if feasible)
• PF can be for:– Stand-alone projects– Sectoral / sub-sectoral projects– Single-year / multi-annual projects
• PF has several annexes including: list of laws, list of relevant strategic plans and studies
![Page 28: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/28.jpg)
28
Project Fiche
• 1 Basic Information (using PF numbering system)
• 1.1 CRIS Number – allocated after FP registered
• 1.2 Title – accurate, few words & full meaning!• 1.3 Sector – to be defined by DG ENLARG• 1.4 Location
– country/region/city for investment project – Institutional location for IB project
• 1.5 Duration
![Page 29: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/29.jpg)
29
Project Fiche
2 Objectives
2.1 Overall Objective(s)• Normally only one overall objective • Take from Logframe• Overall objective should explain why project
is important to society and refer to longer term benefits. Remember: the project will only partially achieve the overall objective.
![Page 30: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/30.jpg)
30
Project Fiche
2.2 Project Purpose• From logframe• Normally one purpose per project• Project purpose is the single central objective
of the project.
![Page 31: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/31.jpg)
31
Project Fiche
2.3 Accession Partnership (AP) & NPAA Priority• Need to identify and outline AP/NPAA policy
priority addressed by project• Include implementing measures from Action
Plan for AP priorities related to strengthening administrative and judicial capacity
![Page 32: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/32.jpg)
32
Project Fiche
2.4 Contribution to NDP (and/or Structural Funds Dev Plan)
• Normally applies to ESC projects only• Show relevant parts of NDP/SFDP and
project contribution
2.5 Cross Border Impact • CBC projects only• “Impact” = what changes as result of project• Write “not applicable” if not a CBC project
![Page 33: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/33.jpg)
33
Project Fiche
3 Description• Provide clear picture of the use of funding
sought
3.1 Background and Justification• Clarify Civil Society involvement and
consultation• Stand-Alone Project – project origins and
reasons• Sector Programmes – show link with
government sector strategy & concentrate on legislative / administrative deficiencies
![Page 34: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/34.jpg)
34
Project Fiche
3.2 Sectoral Rationale (sector programmes only)• Summarise how Govt strategy helps achieve overall
objective• Describe how EU project will be programmed
3.2.1 Identification of Projects• Section based on “Gap Analysis”
3.2.2 Sequencing• Projects sequenced into the three funding years
(2005/6/7) • Key decisions: which project is dependent on earlier
one; and, should any project be split into stages?
![Page 35: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/35.jpg)
35
Project Fiche
3.3 Results• Need following information for each
project– Starting position (benchmark)– Project purpose– Description of activities proposed– Rational for breakdown of projects into contracts– Sequencing and timing imposed
• “Results” must correspond with logframe
![Page 36: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/36.jpg)
36
Project Fiche
3.4 Activities (including Means)• Describe activities during life of project (from
logframe) and means (specific contracts / grants / subsidies – matched with budget breakdown)
• Means should show starting position (contract aim) and final position (assets in place & competencies acquired)
![Page 37: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/37.jpg)
37
Project Fiche
3.5 Linked Activities • Describe earlier EU activities and projects in
this area• Show connections with each other and to the
project• Describe relevant current activities by other
parties (government, private sector, donors, IFIs)
![Page 38: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/38.jpg)
38
Project Fiche
3.6 Lessons Learned • Show that project design incorporates
lessons learned from all relevant sources of experience
• “Cast the net widely” e.g. look at other Candidate Countries under Phare pre-Accession schemes
• The description must be detailed and convincing!
![Page 39: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/39.jpg)
39
Project Fiche
4. Institutional Framework • Identify project’s institutional framework & any
constraints• Will project results lead to change in
institutional framework?• Describe chain of command to ensure project
implementation (who is responsible for what?)
![Page 40: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/40.jpg)
40
Project Fiche
• IB Twinning Projects: • Show how project fits IB plan• Identify beneficiary institution and outline project
scope
• Investment Projects: • Need to identify the “engineer”, “employer” and
“owner”
• Sector Programmes: • Describe donor coordination and monitoring system
![Page 41: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/41.jpg)
41
Project Fiche
5 Detailed Budget• See budget model in Fiche format• Make sure figures add up, are consistent with
Section 11 (Investment Criteria) and Annex 3 (Contracting and Disbursement Schedule)
• Quantify co-financing from national sources and state degree of certainty (also IFI co-financing)
• Investment Projects (ESC): require national public co-financing. Not IB.
• Twinning: expected budget of twinning covenant
![Page 42: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/42.jpg)
42
Project Fiche
6 Implementation Arrangements
6.1 Implementing Agency: Contact details of CFCU
6.2 Twinning: imp. Arrangements, beneficiary etc.
6.3 Non-Standard Aspects: describe N-SA (e.g. grant or fund) or confirm PRAG will be followed
6.4 Contracts: expected # and value of contracts by project / year / phase
![Page 43: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/43.jpg)
43
Project Fiche
7 Implementation Schedule
7.1 Start Tendering / Call for Proposals: • Date (also, when will TOR / Tech Specs be
ready?)7.2 Start of Project Activity: • date first contract / grant scheme starts7.3 Project Completion: • date of last payment under last contract / grant
![Page 44: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/44.jpg)
44
Project Fiche
8 Equal Opportunity• How will equal opportunity by women and
men be assured and how will women’s participation be measured?
• Description should be precise and concrete
![Page 45: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/45.jpg)
45
Project Fiche
9 Environment• Has initial environmental screening or EIA been
carried out? When? Copy available?• EIA may be required by int. / national law, or be
pre-condition for funding, for project proposals of a particular type or size
• Directive 85/337/EC requires MS to adopt legislation to ensure projects likely to have significant env. impact subject to EIA
• Describe major anticipated environmental effects of project
![Page 46: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/46.jpg)
46
Project Fiche
10 Rates of Return (applies to all ESC projects)• Need to follow Commission Guide to Cost-
Benefit Analysis of Major Projects– Economic Rate of Return?– Financial Rate of Return (where applicable)?– Pre-Feasibility / Feasibility studies
completed? When? By whom? Copy available?
![Page 47: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/47.jpg)
47
Project Fiche
11 Investment Criteria (applies to all investments)
11.1 Catalytic Effect• Project must catalyse a priority accession activity
which would not have occurred / been delayed 11.2 Co-financing• All investment projects (and inv. associated with
IB projects) need co-financing from national public funds
• EC will fund up to 75% of eligible public expenditure
![Page 48: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/48.jpg)
48
Project Fiche
11.3 Additionality• EC funds must not displace other funding
(esp from private sector)• Demonstrate by referring to low rates of
return (as shown in Section 10)11.4 Project Readiness and Size• Project ready for contracting - all studies
complete (for year 1 at least)• EUR 2m EC contribution – minimum inv.
project size
![Page 49: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/49.jpg)
49
Project Fiche
11.5 Sustainability• Investment must be sustainable in long run• Complies with EU norms and standards and
is in line with the Acquis for relevant sector• No adverse environmental impact• Financially sustainable
11.6 Compliance With State Aids Provisions• Respects state aid provision of Europe
Agreement
![Page 50: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/50.jpg)
50
Project Fiche
12 Conditionality and Sequencing• Must be completed for all projects• Describe specific and achievable
conditionalities showing what should be done by when and by whom
• Exclude general conditionalities outside project control
• Most effective conditionality = action that must be carried out / approved before project starts (e.g. institutional restructuring plan)
• Include most important project milestones
![Page 51: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/51.jpg)
51
Annexes to Project Fiche• Logframe• Detailed implementation chart (year one at least)• Contracting and disbursement schedule, by quarter,
for project duration • Studies– All Projects: list of (pre-) feasibility studies, ex-ante
evaluations, other preparatory work– Investment Projects: exec. summaries of economic &
financial studies, EIAs etc.• Reference list of relevant laws and regulations• Reference list of relevant strategic plans and studies
![Page 53: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/53.jpg)
53
Activity and resource schedules(see examples)
• Logframe: broad description of activities• Operational detail necessary
![Page 54: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/54.jpg)
54
Resource schedule
Activities, inputs- Equipment- Salaries etc. Units, cost per unit,
funding source
Cost per
planning period
![Page 55: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/55.jpg)
55
Contracting and disbursement schedule
• Show for project period contracting points
• Show for project period expected payments in time
![Page 56: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/56.jpg)
56
Conclusions
• Good project design starts with a sound problem analysis (problem tree) and make use of logframe
• Project design should be logical and have measurable objectives (logframe)
• The project fiche and logframe can help you to draft a good proposal
![Page 57: 3.3 project fiche](https://reader035.fdocuments.net/reader035/viewer/2022062512/554a1ca6b4c9055c598b5586/html5/thumbnails/57.jpg)
57
Exercise: project fiche and activity plan
Trainer will present background information on a real case Project Fiche
Trainer will lead a group discussion covering:- problem/need- overall objective- project purpose- results and activities for the project
Trainer will go through PF documentation and comment it together with WG Members