    Rubber Tyred Gantry Crane - Site Assembly Procedure

  • 5/28/2018 30973377 RTG Site Assembly R1

    2/20

    Rubber Tyred Gantry Crane Site Assembly - Man Power Description

    Structural Works

    1. Fabricators Fabricators for Structural Plate Cutting and Plate Edge Weld

    Preparation.

    - Fabricators for General Works.

    2. Welders Welders Pre-Qualified (6G Position) M.A.W. Welding Process Full

    Penetration One (1) Side.

    - Welders for General Works.

    Mechanical

    1. Mechanical Mechanics for Detailed Assembly, Gantry Drives, Mechanical

    Systems.

    2. Mechanical Mechanics for Basic works including Assembly of Ladders, Access

    Ways, Wheel Guards,etc.

    Electrical

    1. Electrical Electricians Pre-Qualified for Final Termination Works.2. Electrical Electricians for Cable Tray Installation and Cable Pulling / Cable Tying.

    Riggers Experienced Riggers for the Slinging & Lifting Arrangements of the Portal

    Structure and Assist with the installation of the balance of the modules for the RTG

    Crane

  • 5/28/2018 30973377 RTG Site Assembly R1

    3/20

    Gantry Assembly

    Trolley & Hoist

    Assembly

    Head Block

    Assembly

    Cabin

    Spreader

    Resistor Platform

    & Resistors

    Cable Chain

    Festoon System

  • 5/28/2018 30973377 RTG Site Assembly R1

    4/20

    LEG

    Bridge Girder

    Walkway

    Access Way

    Diesel

    Generator

    E-Room

    Tie Rod

    Diesel Generator

    Sliding and

    Folding Access

    Platform

    Exhaust

    System

    Sill Beam

  • 5/28/2018 30973377 RTG Site Assembly R1

    5/20

    Picture 1 Lay out Bridge Girder andLeg Structures and Level Align.

    A qualified Structural Surveyor with aLevel Instrument and Theodolyte isrequired.

    Measure the Structures and confirmAlignments and Measure the LegStructure to be Cut / Trimmed for theconnection to the Bridge Girder.

    Picture 2 - Cut / Trim / EdgePreparation of the Leg Structure Jointto the Bridge Girder. Note that theWeld Joint Design is Full Penetrationfrom one (1) Side with Backing Strip.

    After Preparation Tack up Structural Surveyor with a Level

    Instrument and Theodolyte to ConfirmAlignments and Measurements.

    Full Penetration Weld Process

    Q.C. NDT U.T. 100%

    Picture 1

    Picture 2

    Weld Joint

    Structure Support

    Stands

  • 5/28/2018 30973377 RTG Site Assembly R1

    6/20

    6

    After the welding process is completed,

    the Weld Joint and surrounding area

    must be Painted with the CoatingSpecification As per ISO 8501-1 and

    by mechanical power tool cleaning.

    Picture 3 The Leg Connection to the

    Sill Beams must be prepared.

    Measurement Joint Preparation and

    Structural Surveyor with a Level

    Instrument and Theodolyte to Confirm

    Alignments and Measurements.

    Note that the Weld Joint Design is Full

    Penetration from one (1) Side with

    Backing Strip

    Picture 3

  • 5/28/2018 30973377 RTG Site Assembly R1

    7/20

    After the Structural (Fabrication / Welding / Coating of the Welded Joints) the following items can

    be completed.

    Picture 4 (next Slide)

    1. Cable Tray Installation

    2. Cable Installation

    3. Cable Tray Covers Installation

    4. Generator Exhaust Pipe Installation

    5. Walkway Grating Installed

    6. Crane Signs Painted (These signs are painted where the Lifting Arrangement will not damage theSigns. In these areas the signs will be completed using a Man Lift)

    7. Portal (Bridge Girder) Flood Light Installation including cabling (Photo Below)

    8. Final Paint Touch Up where damage has occurred during installation works

    Flood Light

    Installation

  • 5/28/2018 30973377 RTG Site Assembly R1

    8/20

    Picture 4

    Exhaust Pipe

    Walkway Gratings

    Cable Trays & Cables Installed

    Coating System applied

    after welding

    Crane SignsApplied

  • 5/28/2018 30973377 RTG Site Assembly R1

    9/20

    At the same time the Structural Assembly is being prepared the Lower Sill Beam

    and Gantry is assembled and aligned.

    First item of this works is to Assemble the Equalizer Beam / Wheel Fork Assembly

    to the Sill Beam with the Pin Connection (NCSC will Supply the Equalizer Beam /

    Wheel Fork Assembly ). Picture 5 (Next Slide) shows the completed assembly.

    Picture 5 The following is the preparation procedure for the Sill Beam Assembly

    to accept the Upper Portal Assembly Connection:

    1. Install Sill Beam / Gantry Assembly to Leveled Support Stands. Again the process

    must be done with qualified Structural Surveyor with a Level Instrument and

    Theodolyte to Confirm Alignments and Measurements.

    2. The two (2) Sill Beam Assemblies (Diesel Side & E-Room Side) must be aligned

    centrally and together with the Four (4) corners of the Structure Leveled and

    Aligned

    3. The Sill Beam Assemblies and also tied with Counter Weight Blocks for Safety

    during the Pre-Assembly and Assembly of the Upper Portal Structure (two (2)

    Counterweights per side each Counterweight 10Tons)

    4. Backing Strip installed at the Four (4) Upper Portal Connection Areas.

  • 5/28/2018 30973377 RTG Site Assembly R1

    10/20

    Backing Strip

    Level Support Stands

    Equalizer /

    Wheel Fork

    AssemblyCounter Weight Blocks

    Picture 5

  • 5/28/2018 30973377 RTG Site Assembly R1

    11/20

    Picture 6 (Next Slide) The Upper Portal Assembly - weight includind AccessWays, Cable Trays and Cables = 31Ton ( 1 Bridge Girder & 2 Legs ) is lifted intoposition using the Following Lifting Arrangement (Note also the pre-installation ofthe Tie Rods)

    1. 1 x Lifting Spreader Beam 5T.

    2. 2 x Lifting Beams - 0.75T ea x 2 = 1.5T.

    3. 2 x Lifting Wire Rope Sling Arrangements ( Each Sling Arrangement Capacity 35T).

    4. 1 x 150 T Crawler Crane.

    5. 2 x 50T Hydraulic Mobile Crane (to Tail out the Legs during the initial Lift).

    After placing the Upper Structure and Sliding the Legs over the Backing Strip on

    the Sill Beam the Structure Alignment must be confirmed by the qualifiedStructural Surveyor with a Theodolyte.

    The Upper Portal must be re-strained by wire ropes to counterweight blocks tensioning with Chain Blocks. Fixed Points are mounted under the Bridge Girder.

    The Full Penetration Weld Joint Preparation must be Q.C. Inspected and approved.

    After all the above has been completed the Welding Process can be completedwith the N.D.T. 100% U.T. Inspection.

    After the welding process is completed, the Weld Joint and surrounding area mustbe Painted with the Coating Specification As per ISO 8501-1 and by mechanicalpower tool cleaning.

    Picture 7 (2nd Next Slide) After the Two (2) Upper Portal Assembles areinstalled the Rail Distance (Shown by the Red Arrow) must be confirmed and thenthe Tie Rods between the two (2) Assemblies may be connected.

  • 5/28/2018 30973377 RTG Site Assembly R1

    12/20

    Lifting Frames

    150T

    Crawler

    Crane

    Lifting SpreaderBeam

    Tie

    Rods

    Picture 6

    Welding

    Process

    Cables From Upper Portal to

    Counterweight Blocks

  • 5/28/2018 30973377 RTG Site Assembly R1

    13/20

    Rail Distance

    Picture 7

    Tie Rod

    Connection

  • 5/28/2018 30973377 RTG Site Assembly R1

    14/20

    Picture 8

    1. Generator Installation weight 10T

    2. Generator Access Platforms Installation

    3. Sill Beam Cable Tray Installation4. Electrical Junction Box Installation

    5. Electrical Cable Installation and

    Termination

    Picture 9

    1. E-Room Installation weight 8T

    2. E-Room Access Platforms Installation

    3. Sill Beam Cable Tray Installation

    4. Electrical Junction Box Installation

    5. Electrical Cable Installation and

    Termination.

    Picture 8

    Picture 9

  • 5/28/2018 30973377 RTG Site Assembly R1

    15/20

    Picture 10

    1. Install Resistor Bank Platform and

    Resistors

    2. Install Access Ways and LightingSystems

    Picture 11

    1. Install Gantry Drive Assemblies

    (Electric or Chain Drive)

    2. Install Wheel Turning and Locking

    Assemblies

    3. Install Diesel Fule Tank Systems

    4. Picture 12 (next page) shows Wheel

    Assemblies which will be supplied by

    NCSC to be installed.

    Picture 10

    Picture 11

  • 5/28/2018 30973377 RTG Site Assembly R1

    16/20

    Picture 12 - Wheel Assemblies which

    will be supplied by NCSC

    Picture 12 (a) Install Wheel Guards

    and Gantry Drive Protections (noted

    with red arrows)

    Picture 12

    Picture 12 (a)

  • 5/28/2018 30973377 RTG Site Assembly R1

    17/20

    Picture 13 Cabin Assembly Supplied by NCSC.

    Picture 14 - Cabin to TrolleyInstallation. The Electrical TerminationWorks from the Cabin to the TrolleyJunction Box can be completed at thephase.

    The complete Trolley Assembly is the

    lifted onto the Crane Upper Structureand the Final Electrical / Mechanicalworks can be completed weight 27Tusing the 150T Crawler Crane.

    Picture 13

    Picture 14

  • 5/28/2018 30973377 RTG Site Assembly R1

    18/20

    Picture 15 & 16 Cable Track & Chain

    Festoon System installed and

    Electrical Termination workscompleted.

    Note After all the Electrical

    Termination Works are completed a

    Complete Line Check to be done and

    the Wiring Diagram is marked up as

    confirmation.

    Picture 15

    Picture 16

  • 5/28/2018 30973377 RTG Site Assembly R1

    19/20

    Picture 17 Install Head Block

    Assembly (supplied by NCSC) and

    Reeve Main Hoist and Anti-Sway Rope

    System.

    Pictures 18 & 19 Typical Cable Tray,

    Junction Box and Intercom Installation

    works.

    Picture 17

    Picture 18 Picture 19

  • 5/28/2018 30973377 RTG Site Assembly R1

    20/20

    Picture 20 After all Structural /

    Mechanical / Electrical works

    (confirmed by Q.C.) the RTG Crane is

    Hand Over to the Commissioning

    Team.

    Picture 21 RTG Cranes ready for

    Shipment and loading to Barge

    Picture 20

    Picture 21