3_003 High Pressure Stripper Replacement AFA 19
Transcript of 3_003 High Pressure Stripper Replacement AFA 19
-
8/8/2019 3_003 High Pressure Stripper Replacement AFA 19
1/9
19th
AFA Intl Fertilizer Technical
Conference & Exhibition18- 20 April 2006Four Seasons Hotel
Doha- Qatar
High Pressure stripper replacement in urea plant
Mr. Basheer Al-AWAMI Process Review Team Leader
Mr. Praveen GARG Cost Contral TeamAlbayroni
S. Arabia
-
8/8/2019 3_003 High Pressure Stripper Replacement AFA 19
2/9
1
1
2
INTRODUCTION
BACKGROUND
HISTORY OF HP STRIPPER
DESIGN & SIZING HIGHLIGHTS
PROJECT MILESTONES
PROJECT ACHIEVEMENTS & CHALLENGES
OPERATION BENEFITS
PROJECT COST
CONCLUSION
-
8/8/2019 3_003 High Pressure Stripper Replacement AFA 19
3/9
2
3
Al-Jubail Fertilizer Co. ALBAYRONI was established in 1979 in Al-Jubail Industrial City; K.S.A.
A joint venture between SABIC and TFC.
It produces four major products namely Ammonia, Urea, 2-EthylHexanol 2-EH & Di-Octyl Phthalate DOP.
Commercial production of Ammonia and Urea Plants was started in1983 and for 2-EH & DOP was in 1995 & 1996 respectively.
Urea Plant is a Stamicarbon based technology with a design capacityof 1600 MTPD. Actual production is +1900 MTPD.
4
HP Stripper material of construction in Urea plant was BC.05 with acorrosion rate of 0.06 mm/y
In operation from 1983 to 2005
Due to tube thinning, about 3.1% of total area was plugged
In 2003, it was decided to replace it with a new modified one.
In July 2005, HP Stripper failed due to tube rupture.
The new one was installed during T/A 2005.
-
8/8/2019 3_003 High Pressure Stripper Replacement AFA 19
4/9
3
5
HP Stripper failed during operation. This happened 8 days before the scheduled T/A in July
2005. Plant was S/D and new one was installed.2005
The wall thickness remains 2.35-mm max. and 1.30-mm min. 58 tubes were plugged due to
low thickness.2003
The wall thickness remained at 2.35-mm max. & 1.35-mm min. 23 tubes were plugged due
low thickness.2002
Inlet box found severely corroded. Liquid dividers were changed due to mal-distribution of
liquid. The corrosion rate was 0.06 mm/year.1997
Wall thickness remained 2.44-mm max. and 1.95-mm min.1995
First inspection by Stamicarbon B.V. Eddy current inspection carried out for all the tubes &
used as the base line data. Wall thickness was 2.52-mm max. & 1.2-mm min.1993
Manhole liner showed 1-2 mm pitting due to lack of passivation.1991
EventYear
6
Three options were considered, namely:
Replacement in kind.Similar capacity replacement with upgraded metallurgyHigher capacity replacement with upgraded metallurgy.
SAFUREX Material Selected:
First use in Urea plants was in 1997.Lowest corrosion rate when compared to BC.05.Lower tube thickness due to high mechanical strength.Passivation air can be reduced and hence more CO2 feed ispossible.Low susceptibility to stress corrosion cracking
-
8/8/2019 3_003 High Pressure Stripper Replacement AFA 19
5/9
4
7
14 August 05Commissioning
18 MonthsTotal Project Period
July - August 05Installation13 May 05Delivery to site
15 Feb 05Final inspection and release for dispatch
25-27 Jan 05Hydro test - Shell side (51 barg) & Tube side (265 barg)
July 04 to Jan 05Fabrication
Jun - Sep 04Sourcing of major components
15 June 04Approval of design and fabrication drawings
22-24 Mar 04KOM at SBN shop. ALBAYRONI, Stamicarbon and TUV participated
15 Feb 04Issue of Letter of intent by SABIC
DURATIONDESCRIPTION
8
2.54.5CO2
3.56.5Ammonia
Desorber & Hydrolyser Inlet, wt%
1.41.9Re-circulation Pressure, Bar
26.526.25H2O
57.255.55Urea
9.369.90CO2
6.608.00Ammonia
Outlet Composition, wt %
0.8530.871Steam Consumption, MT/MT Urea
161165Bottom Temperature, C
82 ~ 8378 ~ 80Stripping Efficiency, %
27802650Number of Tubes
1880 19401850 - 1900Actual Production, MT/D
21501600Design Capacity, MT/D
New StripperOld StripperEquipment Performance
-
8/8/2019 3_003 High Pressure Stripper Replacement AFA 19
6/9
5
9
Achievements:Engineering, Procurement, and Construction was completed within the timeframe of the project.Performance Test Run was successful and met all the guarantee figures.Equipment was installed without any change in the existing piping orstructure.Plant production could be increased by 30 MT/D.Specific consumption of NH3/ Urea dropped from 0.591 to 0.580.
Challenges:Higher weight of the new stripper.Changing the material of construction to SAFUREX.Installation of equipment in limited time and space.
10
1002,800,000Total Project Cost
11300,000Installation at site
9270,000Transportation ex-works to job site
722,000,000Material & Fabrication
8230,000Design & Engineering
% of TOTALCOST
COSTUS $
DESCRIPTION
-
8/8/2019 3_003 High Pressure Stripper Replacement AFA 19
7/9
6
11
Regular inspection may minimize the chances of sudden equipment failures.
SAFUREX is a proven material for Urea HP equipment.
Prior to any equipment replacement, future plant upgrades and expansionrequirements should be considered, if possible.
Installation of the new HP Stripper in Al-Bayroni was successful as severaloperational benefits were realized:
Higher Production.
Lower Ammonia & steam consumption.
Recycle of NH3 & CO2 reduced.
Venting of NH3 & CO2 reduced.
12
-
8/8/2019 3_003 High Pressure Stripper Replacement AFA 19
8/9
7
13
14
-
8/8/2019 3_003 High Pressure Stripper Replacement AFA 19
9/9
8
15
16