3G Single Site Verification Report Site ID: DHK_V1415 24-08-2015 Commercial-in-Confidence

Transcript of 3 g ibs walk test report dhk_v1415_tems

Page 1: 3 g ibs walk test report dhk_v1415_tems

3G Single Site Verification ReportSite ID: DHK_V1415

24-08-2015

Commercial-in-Confidence

Page 2: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Contents

1 Introduction.....................................................................................................................................31.1 Site Information.................................................................................................................................................3

2 Test Details.......................................................................................................................................42.1 Tool & SIM Information....................................................................................................................................42.2 DT Check List....................................................................................................................................................42.3 Drive Test Plots……............................................................................................................................................

2G Drive Test Plots RxLevel Plot (Idle Mode)..................................................................................................................................5RxQual Plot.......................................................................................................................................................63G Drive Test Plots RSCP Plot (Idle Mode)......................................................................................................................................5Ec/Io Plot...........................................................................................................................................................6UE Tx power plot..............................................................................................................................................8

3 Summary..........................................................................................................................................93.1 DT KPI...............................................................................................................................................................93.2 Analysis............................................................................................................................................................103.3 Comments........................................................................................................................................................11

2023-05-02 Huawei Confidential Page 2 of 66

Page 3: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Introduction

1.1 Site InformationItems Details

Cluster Name/ID 3G_DHK_CL11 & 12

Sub cluster Name/ID 3G_DHK_CL11 & 12

Cluster Type Urban

Site Name/ID DHK_V1415

Number of cell 01

District Name Dhaka

Serving Area Suvastu Najar Valley, North Badda, Progoti Soroni, Dhaka.

RNC Name RNDH01

Report Prepared: Ishaque Uddin

Drive Test Engineer: Habib

3G Site engineering parameter:

3G Cell Name 3G Cell ID LAC (DEC) RNCID (DEC) PSC UARFCH_DL

DHK_V1415_4 4147 750 231 511 10738

3G physical parameter:

Node B ID Cell name Azimuth Tilt (M) Tilt (E) Height(m) LONG LAT Comment

DHK_ V1415 DHK_V1415_4 90.42506 23.78991 ok

2023-05-02 Huawei Confidential Page 3 of 66

Page 4: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Floor wise sectors:

Floor Serving cell ID (2G) Serving PSC (3G) CommentBasement 1 4144 (IBS),3675 511 (IBS), 120 BL Feedback:

3G : NOK. In some area coverage is poor. Huawei need to proposed solution plan. 3G legend should be as per proposal indoor format.

2G: NOK. IBS is not serving in most of the floors. Poor Rx level.

Huawei Feedback: 2G: Rx level is fair ( Basement 1, Basement 2,

Basement 1, GF,3rd FL). Others floor coverage is under satisfactory level.Need to check the conectivity of all DAS & combiner in the all week Rx level floors.Overall Rx Qual is under satisfactory level in all floors.

For permanent solution,Additional antenna required for poor Rx level floors.

3G: Overall serving pattern is satisfactory level except few samples in few floors.RSCP is poor ( Basement 1, Basement 2, Basement 1, GF, 1st FL, 3rd

FL). Overall Ec/No is under satisfactory level. Need to check the conectivity of all DAS & combiner in the all week RSCP floors.Also need to increse the CPICH power for more RSCP. For permanent solution,Additional antenna required for poor RSCP floors.

Basement 2 4144 (IBS) 511 (IBS)

Basement 34144 (IBS) 511 (IBS)

GF 4144 (IBS),8273,3674,3675

511 (IBS),104,112,120,272

1st FL 4144 (IBS) 511 (IBS)2nd FL 4144 (IBS),3674 511 (IBS)3rd FL 4144

(IBS),10752,3674,3675 511 (IBS),104,1124th FL

4144 (IBS) 511 (IBS),112

2023-05-02 Huawei Confidential Page 4 of 66

Page 5: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

2 Test DetailsTool &SIM Information

Start date 8/09/2014 Finish date 8/09/2014

Report Date 5/09/2014

Test software Genex probe Test mobile Huawei 2800

Extra antenna Not Used Data Card HUAWEI-E372UMax car speed Walk Test Avg. Car speed Walk Test

USIM IMSI Mobile Number1

2

3

4

2.2 DT Check List

Category ChecksCheck

Comment(OK/ NOK/NA)

General Confirm Site is on -air and no alarm on site. OK

Check with Neighbor Relation table OK

Check R99 (Voice, VP 5 call sampling in each sector) OK

Check HSPA (5 calls in each sector) OK

Check cell reselection (2G to 3G and vice versa) OK

Dedicated Mode

Call from BL to BL (both incoming and outgoing) OK

Call from BL to Others operators (both incoming and outgoing) OK

Inter system HO (3G to 2G) OK

Voice QualityTest Handover to first neighbor (both incoming and outgoing) OK

Silent call OK Not found

2023-05-02 Huawei Confidential Page 5 of 66

Page 6: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

2.3 2G Walk test plots for all Floors (As per D4U):Basement 1 (Progoti Soroni End) Serving Cell ID Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 6 of 66

Comments: Overall serving pattern is under satisfactory level.One spot found serving macro cell due to DAS does not work properly.

Page 7: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 1 (Progoti Soroni End) Post_RxLevel Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 7 of 66

Comments: Oeverall Rx level is fair.

Recommendations: Rx level is fair due to DAS does not work properly.Need check the connectivity of All DAS in this floor.

Page 8: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 1 (Progoti Soroni End) Post_RxQual Plot-(Dedicate Mode-MS2)

2023-05-02 Huawei Confidential Page 8 of 66

Comments: Overall Rx Qual is under satisfactory level.

Page 9: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 2 (Progoti Soroni End)Serving Cell ID Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 9 of 66

Comments: Overall serving pattern is under satisfactory level.

Page 10: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 2 (Progoti Soroni End)Post_RxLevel Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 10 of 66

Comments: Oeverall Rx level is fair.

Recommendations: Rx level is fair due to DAS does not work properly.Need to check the connectivity of All DAS in this floor. Also additional antenna required.

Page 11: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 2 (Progoti Soroni End)Post_RxQual Plot-(Dedicate Mode-MS2)

2023-05-02 Huawei Confidential Page 11 of 66

Comments: Overall Rx Qual is under satisfactory level.

Page 12: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 3 (Progoti Soroni End)Serving Cell ID Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 12 of 66

Comments: Overall serving pattern is under satisfactory level.

Page 13: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 3 (Progoti Soroni End)Post_RxLevel Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 13 of 66

Comments: Oeverall Rx level is fair.

Recommendations: Rx level is fair due to DAS does not work properly.Need check the connectivity of All DAS in this floor.Also additional antenna required.

Page 14: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 3 (Progoti Soroni End)Post_RxQual Plot-(Dedicate Mode-MS2)

2023-05-02 Huawei Confidential Page 14 of 66

Comments: Overall Rx Qual is under satisfactory level.

Page 15: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Ground Floor Serving Cell ID Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 15 of 66

Comments: Overall serving pattern is not satisfactory level.three macro cells are serving in this floor due to DAS does not work properly.

Page 16: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Ground Floor Post_RxLevel Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 16 of 66

Comments: Oeverall Rx level is fair.

Recommendations: Rx level is fair due to DAS does not work properly.Need check the connectivity of All DAS in this floor.

Page 17: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Ground Floor Post_RxQual Plot-(Dedicate Mode-MS2)

2023-05-02 Huawei Confidential Page 17 of 66

Comments: Overall Rx Qual is under satisfactory level.

Page 18: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

1st Floor Serving Cell ID Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 18 of 66

Comments: Overall serving pattern is under satisfactory level.

Page 19: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

1st Floor Post_RxLevel Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 19 of 66

Comments: Oeverall Rx level is under satisfactory level.

Page 20: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

1st Floor Post_RxQual Plot-(Dedicate Mode-MS2)

2023-05-02 Huawei Confidential Page 20 of 66

Comments: Overall Rx Qual is under satisfactory level.

Page 21: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

2nd Floor Serving Cell ID Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 21 of 66

Comments: Overall serving pattern is under satisfactory level.

Page 22: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

2nd Floor Post_RxLevel Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 22 of 66

Comments: Oeverall Rx level is under satisfactory level.

Page 23: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

2nd Floor Post_RxQual Plot-(Dedicate Mode-MS2)

2023-05-02 Huawei Confidential Page 23 of 66

Comments: Overall Rx Qual is under satisfactory level.

Page 24: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

3rd Floor Serving Cell ID Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 24 of 66

Comments: Overall serving pattern is almost ok.Maximum samples are found serving ok.Some samples are found macro cell due to DAS issue.

Page 25: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

3rd Floor Post_RxLevel Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 25 of 66

Comments: Overall Rx level is poor.

Recommendation: Need to check the connectivity of all DAS in this floor.

Page 26: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

3rd Floor Post_RxQual Plot-(Dedicate Mode-MS2)

2023-05-02 Huawei Confidential Page 26 of 66

Comments: Overall Rx Qual is under satisfactory level.

Page 27: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

4th Floor Serving Cell ID Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 27 of 66

Comments: Overall serving pattern is under satisfactory level.

Page 28: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

4th Floor Post_RxLevel Plot-(Idle Mode-MS1)

2023-05-02 Huawei Confidential Page 28 of 66

Comments: Oeverall Rx level is almost ok.One spot is found week coverage.

Recommendations: Need to check the connectivity of L4O15 for improving 2G coverage value.

Page 29: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

4th Floor Post_RxQual Plot-(Dedicate Mode-MS2)

2023-05-02 Huawei Confidential Page 29 of 66

Comments: Overall Rx Qual is under satisfactory level.

Page 30: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

3G Walk test plots for all Floors (As per D4U):Basement 1 (Progoti Soroni End) PSC Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 30 of 66

Comments: Overall serving pattern is under satisfactory level.

Page 31: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 1 (Progoti Soroni End) RSCP Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 31 of 66

Comments: Overall RSCP is Poor.

Recommendation: Need to check the connectivity of all DAS in this floor.For more RSCP, need to increase CPICH power.

Page 32: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 1 (Progoti Soroni End) Ec/Io Plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 32 of 66

Comments: Overall Ec/No is under satisfactory level.

Page 33: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 1 (Progoti Soroni End) UE Tx power plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 33 of 66

Comments: Overall Tx power fair. Tx power will be improve after improving 3G coverage.

Page 34: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 2 (Progoti Soroni End)PSC Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 34 of 66

Comments: Overall serving pattern is under satisfactory level.

Page 35: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 2 (Progoti Soroni End)RSCP Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 35 of 66

Comments: Overall RSCP is Poor.

Recommendation: Need to check the connectivity of all DAS in this floor.For more RSCP, need to increase CPICH power.

Page 36: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 2 (Progoti Soroni End)Ec/Io Plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 36 of 66

Comments: Overall Ec/No is under satisfactory level.

Page 37: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 2 (Progoti Soroni End)UE Tx power plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 37 of 66

Comments: Overall Tx power fair. Tx power will be improve after improving 3G coverage.

Page 38: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 3 (Progoti Soroni End)PSC Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 38 of 66

Comments: Overall serving pattern is under satisfactory level.

Page 39: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 3 (Progoti Soroni End)RSCP Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 39 of 66

Comments: Overall RSCP is Poor.

Recommendation: Need to check the connectivity of all DAS in this floor.For more RSCP, need to increase CPICH power.

Page 40: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 3 (Progoti Soroni End)Ec/Io Plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 40 of 66

Comments: Overall Ec/No is under satisfactory level.

Page 41: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 3 (Progoti Soroni End) UE Tx power plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 41 of 66

Comments: Overall Tx power fair. Tx power will be improve after improving 3G coverage.

Page 42: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Ground Floor PSC Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 42 of 66

Comments: Overall serving pattern is almost ok.Few samples are serving macro cell.

Page 43: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Ground Floor RSCP Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 43 of 66

Comments: Overall RSCP is Poor.

Recommendation: Need to check the connectivity of all DAS in this floor.For more RSCP, need to increase CPICH power.

Page 44: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Ground Floor Ec/Io Plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 44 of 66

Comments: Overall Ec/No is almost ok.

Page 45: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Ground Floor UE Tx power plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 45 of 66

Comments: Overall Tx power Poor. Poor Tx power will be improve after improving 3G coverage.

Page 46: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

1st Floor PSC Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 46 of 66

Comments: Overall serving pattern is under satisfactory level.

Page 47: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

1st Floor RSCP Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 47 of 66

Comments: Overall RSCP is Poor.

Recommendation: Need to check the connectivity of all DAS in this floor.For more RSCP, need to increase CPICH power.

Page 48: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

1st Floor Ec/Io Plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 48 of 66

Comments: Overall Ec/No is under satisfactory level.

Page 49: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

1st Floor UE Tx power plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 49 of 66

Comments: Overall Tx power fair. Tx power will be improve after improving 3G coverage.

Page 50: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

2nd Floor PSC Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 50 of 66

Comments: Overall serving pattern is under satisfactory level.

Page 51: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

2nd Floor RSCP Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 51 of 66

Comments: Overall RSCP is almot ok..

Recommendation: For more RSCP, need to increase CPICH power.

Page 52: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

2nd Floor Ec/Io Plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 52 of 66

Comments: Overall Ec/No is under satisfactory level.

Page 53: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

2nd Floor UE Tx power plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 53 of 66

Comments: Overall Tx power fair. Tx power will be improve after improving 3G coverage.

Page 54: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

3rd Floor PSC Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 54 of 66

Comments: Overall serving pattern is under satisfactory level.

Page 55: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

3rd Floor RSCP Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 55 of 66

Comments: Overall RSCP is Poor.

Recommendation: Need to check the connectivity of all DAS in this floor.For more RSCP, need to increase CPICH power.

Page 56: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

3rd Floor Ec/Io Plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 56 of 66

Comments: Overall Ec/No is under satisfactory level.

Page 57: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

3rd Floor UE Tx power plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 57 of 66

Comments: Overall Tx power fair. Tx power will be improve after improving 3G coverage.

Page 58: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

4th Floor PSC Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 58 of 66

Comments: Overall serving pattern is under satisfactory level.

Page 59: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

4th Floor RSCP Plot-(Idle Mode-MS3)

2023-05-02 Huawei Confidential Page 59 of 66

Comments: Overall RSCP is almost ok.Some samples are found fair RSCP.

Recommendation: Need to check the connectivity of all DAS in this floor.For more RSCP, need to increase CPICH power.

Page 60: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

4th Floor Ec/Io Plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 60 of 66

Comments: Overall Ec/No is under satisfactory level.

Page 61: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

4th Floor UE Tx power plot-(Dedicate Mode-MS4)

2023-05-02 Huawei Confidential Page 61 of 66

Comments: Overall Tx power fair. Tx power will be improve after improving 3G coverage.

Page 62: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 1 -Ping test :

Basement 2-Ping test :

2023-05-02 Huawei Confidential Page 62 of 66

Page 63: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

Basement 3-Ping test :

Ground Floor -Ping test :

2023-05-02 Huawei Confidential Page 63 of 66

Page 64: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

1st Floor -Ping test :

2nd Floor -Ping test :

2023-05-02 Huawei Confidential Page 64 of 66

Page 65: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

3rd Floor -Ping test :

4th Floor -Ping test :

3.1.1 DT KPI

CLASSES INDICATORS SERVICES Minimum accepted value Measured value (MAX)

Measured value (Average)

2023-05-02 Huawei Confidential Page 65 of 66

Page 66: 3 g ibs walk test report dhk_v1415_tems

OTBL 2G Modernization & 3G Project

4th FL= 100%

Comment on poor coverage (if any):1. InGround FL under the stair RSCP is bad because of Macro cell served that position.3.2

Analysis

1. No abnormalities found.

3.3 Comments1. All the KPIs reflect good performance and show no abnormalities.

2023-05-02 Huawei Confidential Page 66 of 66