28_pdfsam_2.3- Mechanical, HVAC & Plumbing Specification Novotel

1
7/28/2019 28_pdfsam_2.3- Mechanical, HVAC & Plumbing Specification Novotel http://slidepdf.com/reader/full/28pdfsam23-mechanical-hvac-plumbing-specification-novotel 1/1 Gulf House Engineering January 2010 07-C106 NOVOTEL AL DANA RESORT TOWERS PAGE 25  SECTION 15010 MECHANICAL GENERAL PROVISIONS Upon approval, any necessary changes to the engineering and installation as a result of these deviations shall be the responsibility of the Sub-contractor. Proposed equipment shall be submitted for approval by the Supervision Employer’s Representative before ordering is placed. All necessary information requested by the Supervision Employer’s Representative for the review of the proposal shall be submitted. PART 3 – EXECUTION 3.1 COORDINATION OF WORK A master programme shall be discussed and issued to the Contractor after the kick-off meeting. The Contractor to submit a detailed construction schedule level 1 within 21 days of the kick-off meeting for approval along with a list of the long lead items. Upon approval, the Contractor shall submit detailed construction schedule level 2 for approval. Sub-contract documents establish scope, materials and quality but are not detailed installation instruction. Coordinate work with related trades and furnish, in writing, any information necessary to permit the work of related trades to be installed satisfactorily and with the least possible conflict or delay. The time frame to answer for request of information (RFI) shall be 14 days and should be signed by the Employer’s Representative.  The drawings show the general arrangement of equipment and appurtenances. Follow these drawings as closely as the actual construction and the work of other divisions will permit. Provide off-sets, fittings, and accessories which may be required but not shown on the drawings. Investigate the site, and review drawings of other divisions to determine conditions affecting the work, and provide such work and accessories as may be required to accommodate such conditions.  The locations of thermostats, switches, panels, grilles, faucets, taps, and other equipment indicated on the drawings are approximately correct. Exercise particular caution with reference to the location of panels, thermostats, switches, etc., and have the precise and definite locations accepted by the Supervision Employer’s Representative before proceeding with the installation.  The drawings show only the general run of services and approximate location of equipment, outlets, panels, etc. Any significant changes in location of equipment, outlets, panels, etc., necessary in order to meet field conditions shall be brought to the determine attention of the Supervision Employer’s Representative for review before such alterations are made. Modifications shall be made at no additional cost to the Sub-contract. Carefully check space requirements with other division works to ensure that equipment can be installed in the space allotted.

Transcript of 28_pdfsam_2.3- Mechanical, HVAC & Plumbing Specification Novotel

Page 1: 28_pdfsam_2.3- Mechanical, HVAC & Plumbing Specification Novotel

7/28/2019 28_pdfsam_2.3- Mechanical, HVAC & Plumbing Specification Novotel

http://slidepdf.com/reader/full/28pdfsam23-mechanical-hvac-plumbing-specification-novotel 1/1

Gulf House EngineeringJanuary 2010

07-C106 NOVOTEL AL DANA RESORT TOWERS PAGE 25 

SECTION 15010 MECHANICAL GENERAL PROVISIONS

Upon approval, any necessary changes to the engineering and installation as aresult of these deviations shall be the responsibility of the Sub-contractor.

Proposed equipment shall be submitted for approval by the SupervisionEmployer’s Representative before ordering is placed. All necessary information

requested by the Supervision Employer’s Representative for the review of theproposal shall be submitted.

PART 3 – EXECUTION

3.1 COORDINATION OF WORK

A master programme shall be discussed and issued to the Contractor after thekick-off meeting. The Contractor to submit a detailed construction schedule level1 within 21 days of the kick-off meeting for approval along with a list of the long

lead items. Upon approval, the Contractor shall submit detailed constructionschedule level 2 for approval.

Sub-contract documents establish scope, materials and quality but are notdetailed installation instruction.

Coordinate work with related trades and furnish, in writing, any informationnecessary to permit the work of related trades to be installed satisfactorily andwith the least possible conflict or delay. The time frame to answer for request of information (RFI) shall be 14 days and should be signed by the Employer’sRepresentative.

 The drawings show the general arrangement of equipment and appurtenances.Follow these drawings as closely as the actual construction and the work of otherdivisions will permit. Provide off-sets, fittings, and accessories which may berequired but not shown on the drawings. Investigate the site, and reviewdrawings of other divisions to determine conditions affecting the work, andprovide such work and accessories as may be required to accommodate suchconditions.

 The locations of thermostats, switches, panels, grilles, faucets, taps, and otherequipment indicated on the drawings are approximately correct. Exerciseparticular caution with reference to the location of panels, thermostats, switches,etc., and have the precise and definite locations accepted by the Supervision

Employer’s Representative before proceeding with the installation.

 The drawings show only the general run of services and approximate location of equipment, outlets, panels, etc. Any significant changes in location of equipment,outlets, panels, etc., necessary in order to meet field conditions shall be broughtto the determine attention of the Supervision Employer’s Representative forreview before such alterations are made. Modifications shall be made at noadditional cost to the Sub-contract.

Carefully check space requirements with other division works to ensure thatequipment can be installed in the space allotted.