26) 183 to 191

download 26) 183 to 191

of 9

Transcript of 26) 183 to 191

  • 8/2/2019 26) 183 to 191

    1/9

    183

    Environmental impact assessment:

    for whose needs?

    J H Y Katima

    ABSTRACT

    Tanzania, like many other developing countries, is keen to attract foreign

    investments to foster the countrys socioeconomic development. However,

    the competition among developing countries to attract foreign investmentpreference has in many cases sacrificed policies geared towards sustainable

    development for short-term economic gains. With the intention of

    conserving the global environment, the multinational financing institutions

    have made it mandatory that all development projects should be subjected

    to EIA before they can be funded. Is this sustainable? This case study

    suggests that an effective (and sustainable) EIA regime is dependent on,

    among other things:

    the governments political will;

    effective environmental legislation;

    institutional support; proper development objectives; and

    trained personnel.

    Unfortunately, many of these factors are not in place in Tanzania (and

    probably not in place in most developing countries). This has led in many

    cases to frustration on the part of environmental impact assessors,

    governmental advisors and the public at large. Because of economic

    considerations some projects have been given a go ahead despite negative

    assessment and public outcry. In some cases, projects have been assessed

    positively even though the negative impacts are obviously overwhelming,

    which may be due to the fact that the investor is paying for the assessmentand thus may influence the outcome of the assessment process. This case

    study examines the prawn project, which was subjected to EIA, rejected by

    the review team and approved for implementation by the government. The

    paper poses a question: For whose needs is the EIA conducted? The

    investor? The government? The assessor? The environment? The public?

    CaseStudy

    19

    See Topic 9

    UNEP EIA Training

    Resource Manual

    Reviewing

    UNEP EIA Training Resourc e Ma nua l Ca se stud ies from d evelop ing countries

  • 8/2/2019 26) 183 to 191

    2/9

    184

    INTRODUCTION

    The Rufiji River delta is the largest block of mangrove forest (mangroves) on

    the eastern African coast. The delta is linked to the interior river system by

    an extensive flood plain about 130km long and more than 20km wide. It is

    also linked to a system of ocean currents and coral reefs.

    The mangroves provide a unique ecosystem that displays dynamics of a

    flood plain and delta system as expressed by changes in mud and silt

    deposition, major fresh water outlets, and the creation of oxbow lakes, local

    flooding patterns, salt water intrusion etc. The mangroves provide an inter

    tidal fishery, serve as nursery grounds and breeding areas for the prawn

    industry for the locals and produce large quantities of mangrove poles for

    export.

    Mangroves protect the coastline from waves and currents and thus prevent

    coastal erosion. Through their retention of sediments brought downstream

    by rivers, they extend the coastland into the ocean. As they are highly

    productive elements of the marine ecosystem, mangroves generate large

    quantities of detritus, which form the basis of a complex marine food web

    thus making them a unique ecosystem that is rich in floral and fauna

    biodiversity in both freshwater and saline environments. The delta has been

    utilized over the years by the Rufiji people basically relying on fishing,

    mangrove poles and rice farming for their sustenance. The present

    population living in the delta is 35 000 people.

    The African Fishing Company Ltd (AFC), a subsidiary of Tannol Holding

    Ltd. of Korea, intends to develop a prawn farm covering about 6,000ha of

    surface water, with grow out ponds on 10 000ha of land. The proposed

    location of the prawn farm is within the Rufiji delta and the downstream

    end of the flood plain. The proposed farm will consist of production ponds

    plus water pumping stations, and supply and drainage canals. Staff

    quarters, and storage facilities for the materials and supplies will be built

    close to the farm. The target species for shrimp aquaculture is Penaeus

    monodon. AFC plans to employ semi-intensive production methods at farm

    level management.

    The proposed development is planned to be accomplished in eight years

    with the first year of operation targeted to build 500ha of ponds. The pondswill be of 6ha x 1m average depth in size. There will also be some smaller

    ponds of the size of 0.1m x 1.0ha built for research and development

    purposes. A hatchery is proposed at Bwenjuu Island in the Mafia Island

    Marine Park where brood stock will be stocked at a density of 10 to 12

    prawns per m2 and will be fed with feed meals. There will be 2.3 crops of

    prawn per year with an annual production of about 2680 to 4600kg/ha. The

    annual feed is estimated to be between 6624 and 8280kg/ha. The estimated

    labour requirements are as follows: construction 250-500 people; farm

    operation about 6000 people; the hatchery 500 people; at the processing

    plant 1200 people. Other project components include:

    UNEP EIA Training Resourc e Ma nua l Ca se stud ies from de velop ing countries

  • 8/2/2019 26) 183 to 191

    3/9

    185

    deep sea fishing in the Exclusive Economic Zone (EEZ) of the Tanzaniacoastal waters with a total fleet of six vessels;

    the provision of fish meal plant at Mwanza to recycle waste from theprocessing units and a feed mill at Mbegani for production of feed stuff

    from cereals and other unwanted fish and additives; and

    the provision of training and education for personnel.NATURE AND SCOPE OF ISSUES

    Policy and legal issues

    In licensing the project the following pieces of legislation were contravened:

    The National Land Policy of 1995 and Land Ordinance of 1923 were

    contravened by transferring right of occupancy to the developer withoutrecognizing the customary rights of smallholders. The Forest Ordinance of

    1997 and the Forest Ordinance Cap 389 of 1957 were contravened by

    allowing the developer to establish the prawn farm in the forest reserve. All

    mangrove forests are forest reserves. Allowing the developer to establish a

    hatchery at Bwenjuu Island has violated the Marine-Park and Reserve Act

    No. 29 of 1994. The project also falls within the licensed area to CANOP for

    the purpose of oil exploration. Other legislation contravened includes: the

    Water Utilization (Control and regulation) No. 110 of 1981 and international

    conventions such as CITES Convention (because of the existence of two

    endangered species in the area i.e. the Dugong and the Nile Crocodile) and

    the Ramsar Convention (because the Delta is a contiguous wetland which is

    part of the international landing sites for migratory birds). There also other

    development projects within the area e.g. The Mangrove Management

    Project, The Rufiji Delta and Floodplain Environmental Management and

    Biodiversity Conservation of Forest, Woodland and Wetland, The Rufiji

    Basin Management and Irrigation Project and The WWF Coastal Forest

    Project.

    Environmental issues

    Loss of mangrove forest is estimated to be 1200ha. There is loss of

    biodiversity in mangrove areas as a result of destruction of breeding sites

    and nursery grounds for fish and other intertidal fauna, destruction of rare

    species of mangroves such as Rhizophora, together with the threat to

    endangered Dudong and Nile crocodile and over-exploitation of wild fish

    stock by increased human population. Self generated pollution and

    eutrophication in ponds, rivers and the ocean will come from effluents

    containing antibiotics and toxic chemicals. Other impacts will be the

    acidification and salinization of agricultural lands, disposal of wastes in

    Kioboni and Bumba rivers and associated water borne diseases and

    formation of complex land uses e.g. a town within the mangroves forest

    UNEP EIA Training Resourc e Ma nua l Ca se stud ies from d evelop ing countries

  • 8/2/2019 26) 183 to 191

    4/9

    186

    reserve and flood plain. There are no suitable soils within the reserve for

    housing, sanitary landfill, oxidation ponds/lagoons, septic tanks etc.

    Socio-cultural issues

    The project will result in loss of agricultural land, displacement and

    resettlement of local people, increased social conflicts between those who are

    for the project and those against it, increased government costs for provision

    of infrastructure and social services and changes in cultural values.

    Economic issues

    Calculations indicate that the project will make a net loss of US$ 24.9 million

    in year one and a net forex gain of US$ 120 million in the fifth year.

    However, the government has given a tax exemption and forex retention

    holiday of 5 years, and the experience world-wide has shown that such

    projects fail in their fifth year which means the government will not realize

    anything. Using the overall risk of 30% the estimated foregone benefits in

    Rufiji delta area ranges between US$ 72-107 million which exceeds the

    adjusted income benefits of the project which is US$ 21 million.

    Process and procedural context

    Unfortunately, there is no legal requirement for EIA in Tanzania. There is

    neither environmental policy nor environmental law. However, there is a

    National Environmental Management Council which advises the

    Government on environmental issues and the Division of Environment

    under the Vice Presidents Office, which looks after policy issues. The

    National Environmental Management Council has developed EIA

    guidelines.

    The Investment Promotion Centre has the sole responsibility of approving

    all foreign projects. Its mandate is to assess economic viability. In this

    particular case, maybe because of public pressure, the government required

    an EIA before it approved the project. The developer had to produce an EIS

    for evaluation. Furthermore, the developer intends to borrow money from

    international financing bodies, in which case he has to show the

    environmental impact of the proposed project.

    The EIS was sent to the Environment Management Council for Evaluation.

    The Council constituted a team of 11 experts, with three foreign experts

    from the USA, Zimbabwe and Germany. The reviewers prepared a report,

    and the NEMC also organized a public hearing, which drew participants

    from the Rufiji people, experts in different fields, and politicians. Written

    comments were received from within and outside the country. The

    Councillors mostly represented the Rufiji people. Thirty-two participants

    gave verbal comments on the project during the public hearing and 18

    written comments were also read during the public hearing. The EIA review

    UNEP EIA Training Resourc e Ma nua l Ca se stud ies from de velop ing countries

  • 8/2/2019 26) 183 to 191

    5/9

    187

    team raised numerous questions about the EIA and the recommended

    mitigation measure. These views were supported in public hearings.

    MITIGATION MEASURES

    Mangrove forest

    The EIA proposed a no-net loss of mangroves by suggesting that the project

    replant mangroves in other areas. This was found to be unrealistic by the

    review team as the mangrove species respond differently to ecological

    requirements and other environmental factors and they are site-specific.

    Also there are not enough bare saline areas or clear cut mangrove areas in

    the Delta for replanting to compensate for the mangroves cut in the prawn

    farm project. The project does not give alternatives to meet the objectives of

    the mangrove management project. However, the EIA report admits theserious negative impacts of construction of canals, roads and other prawn

    farm project activities.

    Fisheries and marine environment

    The EIA does not cite the fact that there are no alternative sites for hatchery

    and grow out ponds. The EIA proposes that the use of DDT and antibiotics

    should be minimized without suggesting alternatives and thus there was no

    guarantee in the management submission in response to the EIA. The EIA

    also reports that AFC is committed to implement the mitigation plan.

    However, there are no funds budgeted to implement the plan. It was alsoobserved that unless there are screens at pump intakes there would be a

    massive killing of fish and other aquatic zooplankton. Besides, there are no

    funds set aside for this measure.

    Land use

    There are no mitigation plans to avoid a town growing in the mangrove

    forest reserve. The septic tanks and/or oxidation pond necessary for the

    treatment of domestic waste requires suitable soil, which is not available in

    the delta. The ponds and other related structures will most likely be

    inundated during spring tides at equinoxes. There is no mitigation plan forthis. There is a provision of 1m high levees above the surface which is not

    enough to mitigate the inundation impact since the spring tides could be as

    high as 1.5m.

    Social benefits that are proposed for the locals who will be affected do not

    have financial commitment. Nor are there funds set aside for resettlement of

    the displaced families. No funds have been set aside set for land acquisition.

    And finally there are no alternative sites for the project.

    UNEP EIA Training Resourc e Ma nua l Ca se stud ies from d evelop ing countries

  • 8/2/2019 26) 183 to 191

    6/9

    188

    Water resources

    The drainage canals at the hatchery will be directed into small sedimentation

    basins before discharging by an overflow into coastal waters; no treatment is

    proposed. The EIA proposes, as a mitigation measure, that the pond

    sediments be stored in specified areas and allows rainfall to leak in and

    percolate to the ground. Also the EIA proposes that the pond sediments

    could be used for road construction or other repair work. The review team

    and the public hearing questioned the proposal because impact on ground

    and surface water was not analyzed. There is no proposed mitigation

    measure for an increase in waste matter, which will be disposed of in the

    Kiomboni and Bumba rivers. The contamination of the two rivers by the

    excessive use of lime will raise the pH of the rivers which serve as potable

    water for the local residents.

    Agriculture

    No specific mitigation measure is proposed by the EIA despite the fact that

    there is a possibility that polluted water from the prawn farm will leak into

    agricultural fields.

    Wildlife

    The EIA does not look at alternative usage of the Delta e.g. wild life

    protection for ecohunting and ecotourism. There are no mitigation measure

    against possible poaching of Dugong and Nile Crocodiles, which are already

    in alarmingly low numbers.

    Socio-cultural

    The EIA report uses cautionary words (non-committal) to address the

    socioeconomic benefit of the project to the local people e.g. such words as

    the proponent will support to a certain extent a dispensary, health centres,

    schools and water. However, no financial commitment is made. The EIA

    does not provide mitigation measures to cover the cost of displacing and

    resettling people, costs of infrastructure and services for resettled people,

    loss of boat tract in one of the sites, and the decline of food security through

    the decline of agricultural land. However, the EIA proposes to discourageclearance of vegetation for agricultural purposes (i.e. after the project has

    cleared thousands of hectares for ponds).

    There will be increased hygiene risks through water borne diseases and

    increased demand (with its environmental and social consequences) for fuel-

    wood, drinking water, farmland and settlement areas. The EIA gives vague

    statements such as insurance that local cultural pattern will be maintained.

    UNEP EIA Training Resourc e Ma nua l Ca se stud ies from de velop ing countries

  • 8/2/2019 26) 183 to 191

    7/9

    189

    MONITORING PLAN

    There were no comprehensive baseline studies done which could have been

    used in the monitoring activity. The roles of the developer, the government,

    local residents and other stakeholders are not clearly defined in the

    monitoring plan. Besides this, monitoring activity is neither costed nor

    budgeted for.

    RESULTS AND IMPLICATIONS

    The EIA review-team and the public hearing concluded that the EIA report

    was highly biased in favour of the project. It was proposed that the project

    be rejected on the following grounds:

    The project is planned to be located in a Mangrove Forest Reserve and

    Mafia Island Marine Park. Millions of dollars have already been spent

    on both projects.

    The plan is to discharge untreated effluents into the rivers that drain

    into the Mafia channel and Bwenjuu Island reefs.

    This will release untreated effluents containing silt, suspended solids

    from the remains of feed and pond sediments, dissolved chemicals

    from fertilizers, prawn feed, medicines (including antibiotics) and

    other nutrients.

    There are conflicts with existing and planned land use plans for theRufiji basin and Mafia Islands.

    The proposal has many negative socioeconomic impacts on both the

    vicinity of the proposed site and beyond.

    The EIA is unsatisfactory, given so many uncertainties in the form of

    the size of the project, the newness of technology that is expected to

    be used and the relatively unknown baseline conditions.

    The EIA, which looks very much like a polished project proposal, is

    biased.

    The Environment Management Council advised the government that:

    The project should be rejected, and proper land-use plan and baseline

    studies should be carried out in the Rufiji basin in order to harmonies

    the various competing interests in the area.

    A moratorium should be declared on all commercial mariculture in

    Tanzania until the government establishes proper guidelines for the

    development of commercial aquaculture in the country.

    UNEP EIA Training Resourc e Ma nua l Ca se stud ies from d evelop ing countries

  • 8/2/2019 26) 183 to 191

    8/9

    190

    Large scale aquaculture should not be conducted in ecologically

    sensitive areas like mangroves.

    The letter of offer allocating part of Bwejuu Island to the AFC shouldbe revoked, since this offer contravenes the National Policy (1995) and

    the Mafia Island Management Plan and legislated under the Marine

    Parks and Reserves Act No. 29 of 1994.

    Against all these recommendations the government approved the project

    without consulting the National Environment Management Council. In

    whose needs was EIA carried out? That is the question.

    LESSONS LEARNED

    EIA can not have any meaning, unless there is a strong governmentcommitment in a form of a policy and environmental law.

    Lack of awareness of the importance of avoiding unnecessary

    environmental degradation hampers the success of the EIA regime.

    As long as EIA remains the responsibility of the developer, objective

    EIA will take time to come by. This leaves a loophole for influencing

    the EIA in the proponents favour. Using experts from abroad is not a

    solution; this is because the local experts know the local environment

    better and they are the ones who have to perform the monitoring. In

    these circumstances the use of foreign experts is not sustainable.

    Lack of harmonized institutional arrangement with a clear and

    properly co-ordinated flow of events guarantees a continued

    contradiction in approval processes.

    Financial institutions should not only be concerned with seeing EIA

    reports but should also be interested to ensure that the

    recommendations are implementable and that the local capacity to

    monitor the implementation is in place.

    Some funds, such as those of GEF, could be used to commission EIA

    initially to ensure an unbiased report.

    UNEP EIA Training Resourc e Ma nua l Ca se stud ies from de velop ing countries

  • 8/2/2019 26) 183 to 191

    9/9

    191

    LIST OF RELEVANT PUBLISHED PAPERS AND OTHER SOURCE

    MATERIAL

    Boyd C.E. 1996, Environmental Impact Statement for Ecologically-Responsible

    Shrimp Farming Project in the Rufiji Delta, Tanzania, prepared for the African

    Fishing Company Ltd. Dar es Salaam. 112pp.

    Fottland, H. and Sorensen, C. 1996, Issues Related to the Establishment of Prawn

    Farm in Tanzania with example from the Rufiji Delta, Catchment Forestry Report

    96.4. Dar es salaam, October 1996, 35pp.

    Hughes, R. 1996, Environmental Impact Statement for an Ecologically Responsible

    Shrimp Farming Project in the Rufiji Delta, Tanzania: Some thoughts, review, Report

    for Institute of Resource Assessment, University of Dar es Salaam, 5 September 1996.

    Kerario, E.J.C., Mango, G.K., Nhwani, L.B., Dallu, A.M., Tibanyenda, R., Faraji, H.M.,

    Ndimbo, M.M., Mungongo, C.G., Milne, G.R., Mitzlaff, U., Vergne P.J. 1997, Review

    of EIA for an Environmentally-Responsible Prawn Farming in the Rufiji Delta,

    Tanzania, prepared for the National Environment Management Council.

    Ndimbo, E.K., Bwathondi, P.O.J., Mwasonja, G.J., Ntara, M.M., Wagner, G.M.,

    Kabigumila, J. Chachage, C.S.L., Mvungi, A.A.K., Wagner, S., Boyd C.E., Scura, E.W.

    and Massaut, L. 1997, An Environmentally Responsible Prawn Farming Project in the

    Rufiji Delta, Tanzania, Vols I and II, April 1997.

    United Republic of Tanzania 1994, Report on Existing Legislation Pertaining to

    Environment, May 1994.

    The author:

    J H Y Katima

    Department of Chemical & Process Engineering

    University of Dar es Salaam

    P.O. Box 35131

    Dar es Salaam

    TANZANIA

    Key words

    EIA process and

    procedures

    review

    mitigation

    decision

    making

    UNEP EIA Training Resourc e Ma nua l Ca se stud ies from d evelop ing countries