21113 M-00-d07 Urs Hot Water Generator ( 10 m3)-r0
-
Upload
dhanulagwankar -
Category
Documents
-
view
3 -
download
1
description
Transcript of 21113 M-00-d07 Urs Hot Water Generator ( 10 m3)-r0
-
SPECTRUM
Client: M/s NAVIN FLUORINE INTERNATIONAL LTD
HOT WATER GENERATOR (10M3)
MANUFACTURING PLANT NO.2 AT DEWAS
TECHNICAL SPECIFICATION
-
TECHNICAL SPECIFICATION
HOT WATER GENEARTOR ( 10 M3/HR) PROJECT NO 21113 REVISION NO 00
DOCUMENT NO M-00-D07 PAGE NO . PAGE1 OF 12
File Location
Z:\PRJ1\API\NFIL 21113\PROCUREMENT\UTILITY\URS\Floated\Hot Utilities system\21113 M-00-D07 URS HOT WATER GENERATOR ( 10 m3)-R0.docx
Format No: SOP/ENG/005/02 Rev. 00 01/01/2013
REVISION HISTORY
REVISION EFFECTIVE DATE REASON FOR REVISION 00 02-01-2014 FIRST ISSUE
-
TECHNICAL SPECIFICATION
HOT WATER GENEARTOR ( 10 M3/HR) PROJECT NO 21113 REVISION NO 00
DOCUMENT NO M-00-D07 PAGE NO . PAGE2 OF 12
File Location
Z:\PRJ1\API\NFIL 21113\PROCUREMENT\UTILITY\URS\Floated\Hot Utilities system\21113 M-00-D07 URS HOT WATER GENERATOR ( 10 m3)-R0.docx
Format No: SOP/ENG/005/02 Rev. 00 01/01/2013
TABLE OF CONTENTS
1.0 APPROVAL SIGNATURES 3 2.0 OVERVIEW 4 3.0 INSPECTION, TESTING AND DISPATCH 4 4.0 DRAWINGS & DOCUMENTS 5 5.0 PACKING 5 6.0 SPARES 6 7.0 DATASHEET 6
-
TECHNICAL SPECIFICATION
HOT WATER GENEARTOR ( 10 M3/HR) PROJECT NO 21113 REVISION NO 00
DOCUMENT NO M-00-D07 PAGE NO . PAGE3 OF 12
File Location
Z:\PRJ1\API\NFIL 21113\PROCUREMENT\UTILITY\URS\Floated\Hot Utilities system\21113 M-00-D07 URS HOT WATER GENERATOR ( 10 m3)-R0.docx
Format No: SOP/ENG/005/02 Rev. 00 01/01/2013
1.0 APPROVAL SIGNATURES
This document is prepared by the SPCPL team for the project of NAVIN FLUORINE INTERNATIONAL LIMITED, DEWAS under the authority of their Project Manager. Hence this document before being effective shall be approved by the QA team of NAVIN FLUORINE INTERNATIONAL LIMITED, DEWAS, and authorized by the appropriate Project Authority.
SPCPL
Name Designation Signature Date
Prepared By Rajesh Yerawar Sr. Executive - Mechanical
Checked By Akhilesh Verma Manager - Mechanical
Approved By Sanjay Katkade GM-Engineering
CLIENT
Name Designation Signature Date
Approved By
Authorized By
-
TECHNICAL SPECIFICATION
HOT WATER GENEARTOR ( 10 M3/HR) PROJECT NO 21113 REVISION NO 00
DOCUMENT NO M-00-D07 PAGE NO . PAGE4 OF 12
File Location
Z:\PRJ1\API\NFIL 21113\PROCUREMENT\UTILITY\URS\Floated\Hot Utilities system\21113 M-00-D07 URS HOT WATER GENERATOR ( 10 m3)-R0.docx
Format No: SOP/ENG/005/02 Rev. 00 01/01/2013
2.0 OVERVIEW
2.1 PROJECT INTRODUCTION
Navin Flourine International Limited has envisioned setting up an Manufacturing plant No.2 facility at Dewas along with the necessary utilities Nearest railway station : DEWAS Nearest airport : INDORE Ambient conditions:
Summer ( DB / WB / % RH) 40 C / 24.4 C / 28 % Monsoon ( DB / WB / % RH) 28 C / 26 C / 82 % Winter ( DB / WB / % RH) 10 C / 5.6 C / 50 %
2.2 PROJECT STANDARD
The design, manufacturing, testing at factory of Hot Water Generator shall comply with the latest applicable standards.
3.0 INSPECTION, TESTING AND DISPATCH
The Hot water Generator will be subjected to inspection at manufacturers works in the presence of purchaser/consultant. During inspection following routine tests shall be carried out:
Visual inspection for workmanship and verification with respect to specifications. Mechanical operation of valves etc. Functional test for control circuits. Tightness of screwed/bolted connections
The vendor shall supply to purchaser 3 sets of the certificates of Internal routine tests.
-
TECHNICAL SPECIFICATION
HOT WATER GENEARTOR ( 10 M3/HR) PROJECT NO 21113 REVISION NO 00
DOCUMENT NO M-00-D07 PAGE NO . PAGE5 OF 12
File Location
Z:\PRJ1\API\NFIL 21113\PROCUREMENT\UTILITY\URS\Floated\Hot Utilities system\21113 M-00-D07 URS HOT WATER GENERATOR ( 10 m3)-R0.docx
Format No: SOP/ENG/005/02 Rev. 00 01/01/2013
4.0 DRAWINGS & DOCUMENTS Vendor to submit following Drawing & Documents at various stages.
4.1 Drawings (3 Sets) - GA Drawings, Engineering Drawings (For approval, Approved, As built, As installed) - Electrical Circuit Diagrams - System schematics
4.2 Manuals and Procedures (3 Sets) - Operation and Maintenance manuals - Specialized procedures, if applicable (such as Calibration, Cleaning, etc.) - Specifications and sources of some important materials, if applicable (such as lubricants,
cleaning agents, etc.) 4.3 Lists (3 Sets)
- Equipment and Instrument list with component descriptions - Electrical component parts list with descriptions - Spare parts list with appropriate identification nos., if any - Change parts list with appropriate identification nos., if any
4.4 Factory Acceptance Test Certificates (3 Sets) - Detailed list of modifications after contract &/or in final approved design - Material specifications and test certificates - Instrument Calibration certificates - Functional/ Factory acceptance certificates (such as weld inspection, passivation, pressure/
vacuum holds, etc.) - Warranty certificates - Surface finish test reports - Food grade material certificate
4.5 Site Acceptance Test (3 Sets) - Operational Qualification Protocol
5.0 PACKING
Equipment shall be dispatched to site packed in full wooden case (Sea Worthy). It shall be wrapped in polythene sheets before putting in cases and it shall be ensured that damage to the equipment does not occur during handling/transportation. Lifting hooks shall be provided for unloading at site.
-
TECHNICAL SPECIFICATION
HOT WATER GENEARTOR ( 10 M3/HR) PROJECT NO 21113 REVISION NO 00
DOCUMENT NO M-00-D07 PAGE NO . PAGE6 OF 12
File Location
Z:\PRJ1\API\NFIL 21113\PROCUREMENT\UTILITY\URS\Floated\Hot Utilities system\21113 M-00-D07 URS HOT WATER GENERATOR ( 10 m3)-R0.docx
Format No: SOP/ENG/005/02 Rev. 00 01/01/2013
6.0 SPARES
Commissioning Spares - The vendors shall include in the quoted price sufficient quantities of commissioning spares required for erection and commissioning of the equipment. These shall include such items as Bolts and other miscellaneous parts. Essential Spares - The vendor shall supply spares required for two years trouble free operation & furnish list of spare considered with offer.
7.0 DATASHEET
SR. NO. DESIGN PARAMETERS REQUIRED SPECIFICATIONS
1 GENERAL Tag No. HW-101
a Type Plate type Heat Exchanger with inbuilt condensate recovery unit
b Hot Water Application For process / in reactor jacket c Capacity 100,000 kcal/hr d Qty. 01 Nos. (1 Working ) e Hot Water flow required 10 m3/hr
f Cold water inlet temp. 75 deg C (At the first startup of system, temp. would be 30 deg C)
g Hot Water outlet temp. 85 deg C h Steam pressure available 3.5 Kg/cm2 i Input Water quality Soft water j Electrical supply 230 V / 1 phase + N / 50 Hz /AC k Steam Consumption Vendor to specify l Model No. Vendor to specify
m Design Code Vendor to specify
-
TECHNICAL SPECIFICATION
HOT WATER GENEARTOR ( 10 M3/HR) PROJECT NO 21113 REVISION NO 00
DOCUMENT NO M-00-D07 PAGE NO . PAGE7 OF 12
File Location
Z:\PRJ1\API\NFIL 21113\PROCUREMENT\UTILITY\URS\Floated\Hot Utilities system\21113 M-00-D07 URS HOT WATER GENERATOR ( 10 m3)-R0.docx
Format No: SOP/ENG/005/02 Rev. 00 01/01/2013
SR. NO. DESIGN PARAMETERS REQUIRED SPECIFICATIONS
2 Plate type Heat Exchanger
a Make Alfa laval / Tranter / IDMC/Spirex b Model No. Vendor to specify
c Type Semi welded type d Utility
Type Steam @ 3.5 kg/cm2 (g)
Flow Rate (kg/hr) Vendor to specify
Pressure Drop (kg/cm2(g)) 0.1 e Process
Type Water
Inlet Temp(C) 75C (At the first startup of system, temp. would be 30 deg C)
Outlet Temp(C) 85C
Inlet Nozzle Size(NB) Vendor to specify
Outlet Nozzle Size ( NB) Vendor to specify
Pressure Drop (Kg/cm2)(g) Vendor to specify f End Connection ANSI B 16.5, 150# g Heat Transfer Area (m2) Vendor to specify h No. of Plates Vendor to specify
i Plate Thickness Vendor to specify
j MOC
Plate SS 304
Gasket EPDM Clip on type
End Plates IS 2062
Studs & Bolts IS1367
Tie Rods & Bolts IS1367
-
TECHNICAL SPECIFICATION
HOT WATER GENEARTOR ( 10 M3/HR) PROJECT NO 21113 REVISION NO 00
DOCUMENT NO M-00-D07 PAGE NO . PAGE8 OF 12
File Location
Z:\PRJ1\API\NFIL 21113\PROCUREMENT\UTILITY\URS\Floated\Hot Utilities system\21113 M-00-D07 URS HOT WATER GENERATOR ( 10 m3)-R0.docx
Format No: SOP/ENG/005/02 Rev. 00 01/01/2013
SR. NO. DESIGN PARAMETERS REQUIRED SPECIFICATIONS
Upper & Lower SS 304
Carrying Bar SS 304
3 Steam Control Valve
a Type PID Based Pneumatic / Electrical actuated globe valve with Positioner b Make Vendor to specify
c MOC
Body CS (CARBON STEEL)
Trim SS 410
Packing PTFE
Size (NB) Vendor to specify d End Connection ANSI B 16.5, 150#
4 On Off Valve Pneumatic /Electrical actuated valve with on- off Controller a Type Globe type b Make Vendor to specify
c MOC
Body CS (CARBON STEEL)
Piston SS 410
Packing PTFE
Size (NB) Vendor to specify d End Connection ANSI B 16.5, 150# 5 Safety Valve
a Type Spring loaded type with Screwed End BSPT b Make Vendor to specify
c Model Vendor to specify
d MOC
-
TECHNICAL SPECIFICATION
HOT WATER GENEARTOR ( 10 M3/HR) PROJECT NO 21113 REVISION NO 00
DOCUMENT NO M-00-D07 PAGE NO . PAGE9 OF 12
File Location
Z:\PRJ1\API\NFIL 21113\PROCUREMENT\UTILITY\URS\Floated\Hot Utilities system\21113 M-00-D07 URS HOT WATER GENERATOR ( 10 m3)-R0.docx
Format No: SOP/ENG/005/02 Rev. 00 01/01/2013
SR. NO. DESIGN PARAMETERS REQUIRED SPECIFICATIONS
Body Vendor to specify
Seat Vendor to specify
Spring Vendor to specify e Bonnet closed
f Cap Screwed g Size (NB)
Inlet (mm) Vendor to specify
Outlet (mm) Vendor to specify h Range (Psi) Vendor to specify i Back pressure Atmospheric 6 Steam Inlet Valve
a Type Piston Valve ASTM A 105 with SS internal b Make Vendor to specify
c MOC
Body CS (CARBON STEEL)
Piston BS 3605 304 S18 (SS 304)
Packing SS reinforce Graphite d Inlet valve Size (NB) Vendor to specify e End connections ANSI B 16.5, 150# 7 Strainer
a Type Y Type
b Make Vendor to specify
c MOC
Body CS (CARBON STEEL)
Element SS Perforated sheet & SS 304 Wire Mesh d Mesh 20 Mesh
-
TECHNICAL SPECIFICATION
HOT WATER GENEARTOR ( 10 M3/HR) PROJECT NO 21113 REVISION NO 00
DOCUMENT NO M-00-D07 PAGE NO . PAGE10 OF 12
File Location
Z:\PRJ1\API\NFIL 21113\PROCUREMENT\UTILITY\URS\Floated\Hot Utilities system\21113 M-00-D07 URS HOT WATER GENERATOR ( 10 m3)-R0.docx
Format No: SOP/ENG/005/02 Rev. 00 01/01/2013
SR. NO. DESIGN PARAMETERS REQUIRED SPECIFICATIONS
e Size (NB) Vendor to specify f End connections Flange End type ANSI 16.5,150# 8 Moisture Separator With Steam Trap
a Type Impingement plate type b Make Vendor to specify
c Model Vendor to specify
d MOC CS (CARBON STEEL)
Size (NB) Vendor to specify e End connections Flanged to BS 10 Table H (ANSI B 16.5, 150#) 9 Pressure Gauges
a Type Bourdon gauge b Make Vendor to specify
c Dial size (mm) 150 d Range (Kg/cm2 (g)) 0 - 6 e End connections BSPT (M) f MOC
Bourdon SS 304
Connection & Movement SS 304
Case SS 304
Syphon SS 304
g Accessories
Syphon Pig tail, BSPT (M)
Isolation valve Piston valve, Globe type BSPT 10 Pumping Trap
a Type Float type pumping trap b Make Vendor to specify
-
TECHNICAL SPECIFICATION
HOT WATER GENEARTOR ( 10 M3/HR) PROJECT NO 21113 REVISION NO 00
DOCUMENT NO M-00-D07 PAGE NO . PAGE11 OF 12
File Location
Z:\PRJ1\API\NFIL 21113\PROCUREMENT\UTILITY\URS\Floated\Hot Utilities system\21113 M-00-D07 URS HOT WATER GENERATOR ( 10 m3)-R0.docx
Format No: SOP/ENG/005/02 Rev. 00 01/01/2013
SR. NO. DESIGN PARAMETERS REQUIRED SPECIFICATIONS
c Model Vendor to specify
d Back Pressure (kg/cm2(g) Vendor to specify e Trapping capacity (kg/hr) Vendor to specify f MOC
Body IS 2062
Float Assembly SS 304
Studs & Nut IS 1367/A193/A194
Gaskets Asbestos free
Condensate valve Piston Valve - (ASTM A 105) with SS internal
Strainers Y type (ASTM A 105) with SS Perforated sheet & wire mesh
Motive steam inlet valve Piston Valve (ASTM A 105) with SS internal
Steam trap Thermodynamic type - (ASTM A 105) with SS internal
Check Valve Disc check Valve- (ASTM A 105) with SS internal g Nozzle Size (NB)
Condensate Outlet Vendor to specify
Drain Vendor to specify
h End connections Flanged to ANSI B 16.5, 150# 11 Piping
a Make Jindal / Tata b MOC SA 106 Gr.B
12 Bolts & Nuts
a Bolts A 193 Gr B7 b Nuts A 194 Gr 2H
-
TECHNICAL SPECIFICATION
HOT WATER GENEARTOR ( 10 M3/HR) PROJECT NO 21113 REVISION NO 00
DOCUMENT NO M-00-D07 PAGE NO . PAGE12 OF 12
File Location
Z:\PRJ1\API\NFIL 21113\PROCUREMENT\UTILITY\URS\Floated\Hot Utilities system\21113 M-00-D07 URS HOT WATER GENERATOR ( 10 m3)-R0.docx
Format No: SOP/ENG/005/02 Rev. 00 01/01/2013
SR. NO. DESIGN PARAMETERS REQUIRED SPECIFICATIONS
13 Temp Controller
a Make Radix
b Range Vendor to specify c Model Vendor to specify
14 Overall Dimensions (L x W x H) Vendor to specify
15 Accessories
a Piping with skid To include b Necessary Blind plugs To include
c Cabling with skid To include
d Electrical panel To include
e Insulator with Claddingwithin skid To include
f Ethernet port for communication with DCS To include