5/14/2020 1 May 14, 2020 Updates • Phase 1.2 Construction activities Archaeological exploration • Phases 1.3 and 2 Design Activities Construction activities • Partner Coordination 2 1 2

Transcript of 20200514 spc Subcommittee KA...May 05, 2020  · Phase 1.3 and Phase 2 Construction • Early Work...

Page 1: 20200514 spc Subcommittee KA...May 05, 2020  · Phase 1.3 and Phase 2 Construction • Early Work Package 20: Heavy Civil – Construction started in Phase 1.3 • Early Work Package

5/14/2020

1

May 14, 2020

Updates

• Phase 1.2• Construction activities• Archaeological exploration

• Phases 1.3 and 2• Design Activities• Construction activities

• Partner Coordination

2

1

2

Page 2: 20200514 spc Subcommittee KA...May 05, 2020  · Phase 1.3 and Phase 2 Construction • Early Work Package 20: Heavy Civil – Construction started in Phase 1.3 • Early Work Package

5/14/2020

2

Phase 1.2 Construction

Phase 1.2 Construction• Houston to Commerce

– Utility installation

– Archaeological exploration

• Commerce to Dolorosa – Dolorosa street bridge

– Spanish Governor’s Palace wall

• Dolorosa to Nueva– Paseo/plaza paving

4

3

4

Page 3: 20200514 spc Subcommittee KA...May 05, 2020  · Phase 1.3 and Phase 2 Construction • Early Work Package 20: Heavy Civil – Construction started in Phase 1.3 • Early Work Package

5/14/2020

3

5

Archaeological Exploration• Coordination with

USACE, THC and COSA OHP ongoing

6

5

6

Page 4: 20200514 spc Subcommittee KA...May 05, 2020  · Phase 1.3 and Phase 2 Construction • Early Work Package 20: Heavy Civil – Construction started in Phase 1.3 • Early Work Package

5/14/2020

4

7

Phase 1.3 and Phase 2 Design

8

7

8

Page 5: 20200514 spc Subcommittee KA...May 05, 2020  · Phase 1.3 and Phase 2 Construction • Early Work Package 20: Heavy Civil – Construction started in Phase 1.3 • Early Work Package

5/14/2020

5

Phase 1.3 and Phase 2 Design

• Design ongoing

• 90% design submittal May 5

• 100% design submittal July 2020

9

10

9

10

Page 6: 20200514 spc Subcommittee KA...May 05, 2020  · Phase 1.3 and Phase 2 Construction • Early Work Package 20: Heavy Civil – Construction started in Phase 1.3 • Early Work Package

5/14/2020

6

11

12

11

12

Page 7: 20200514 spc Subcommittee KA...May 05, 2020  · Phase 1.3 and Phase 2 Construction • Early Work Package 20: Heavy Civil – Construction started in Phase 1.3 • Early Work Package

5/14/2020

7

13

14

13

14

Page 8: 20200514 spc Subcommittee KA...May 05, 2020  · Phase 1.3 and Phase 2 Construction • Early Work Package 20: Heavy Civil – Construction started in Phase 1.3 • Early Work Package

5/14/2020

8

Phase 1.3 and Phase 2 Construction • Early Work Package 20: Heavy

Civil– Construction started in Phase 1.3

• Early Work Package 21: SAWS Relocations– SAWS Board approved costs

• Phase 2 construction delayed– ROW acquisitions– USACE Permit– Century Link relocation

15

Partner Coordination

• Phases 1 and 2 Coordination ongoing– TPR/Alameda– Camaron Street– Commerce Street – GSA/Federal Courthouse– TxDOT– Linda Pace Foundation/Ruby City– UTSA downtown campus expansion– SAISD Administration building

16

15

16

Page 9: 20200514 spc Subcommittee KA...May 05, 2020  · Phase 1.3 and Phase 2 Construction • Early Work Package 20: Heavy Civil – Construction started in Phase 1.3 • Early Work Package

5/14/2020

9

Partner Coordination

• Executive Committee – David Smith, County Manager, Bexar County– Lori Houston, Assistant City Manager, City of San

Antonio– Razi Hosseini, Director, Public Works, City of San

Antonio– Suzanne Scott, General Manager, San Antonio River

Authority

• Meeting held May 13

17

18

QUESTIONS& COMMENTS