(2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things...

36
Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering Manager (Retired) Bechtel Corporation - 01/28/2020 1

Transcript of (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things...

Page 1: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Project ManagementWhat Unique Things Must Be Considered

EPC Heavy Industrial Projects

By Bob StevensProject Engineering Manager (Retired)

Bechtel Corporation - 01/28/20201

Page 2: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

In my career:

Project Manager Small to Midsized Projects

Engineering Manager Mega Projects (> $10 Billion)

2

Page 3: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

After explaining to two young engineers why I could not approve their calculation; explaining their thermodynamics error, one said to the other, “I told you he is not the Pointy-Haired Boss in DILBERT.”

“Yes, and please close the door behind you. We are behind schedule and running over budget. I have to figure out how we get back on track.”

3

Page 4: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

4

Page 5: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Tonight – An Enjoyable Graduate Level Lecture• No Differential Equations• No Exam

Project Management >> Scheduling and Cost Analysis

No Confidential nor Secret Information

Safety is NO Accident!5

Page 6: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Project Manager

Engineering Manager

Procurement Manager

Construction Manager

Business Manager

6

Page 7: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Engineering Manager (The Conductor, Color in the Blank Spaces)

(ChE) - Process Engineering (Simulation, H&M Balance, PFD)

(ChE/ME) - Project Engineering (P&IDs, Equip. Data Sheets, Info. to Others)

(ME) - Mechanical Equipment Engineering – Equipment & Packages

Environment Engineering (Air, Water, Solid, Environmental Controls)

Materials Engineering (Selection, Specifications)

Geo Technical Engineering (Soil Conditions)

Civil Engineering (Concrete)

Architectural / Engineering (Buildings)

Structural Engineering (Steel)

Piping Design (Model/Layout, Stress Analysis, Piping Isometrics, Pipe Hangers)

Electrical Engineering (Power, Cathodic Protection)

Control Systems Engineering (Instruments, Software, DCS)

Etc.7

Page 8: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Engineering Manager (con’t)

Scheduling

• Most Common Tools - Primavera, MS Project

• Critical Path

• Staffing

Cost Analysis

• FORWARD LOOKING (Accounting is HISTORICAL)

• Estimating (Lang and More Detailed)

• Wage Rate Mix

• Contingency / Senior Management (or Owner) Allowance

• Trends (Non-Variance/ Variance)

• Progress/Performance – Cost/Commitment

8

Page 9: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Procurement Manager

Prime Contract AdministrationDirect Hire Administration Subcontract AdministrationPurchasing – Engineered EquipmentPurchasing – Bulk MaterialsExpeditingTraffic – (Ohio River Clearance, Highway and Rail Clearances)Logistics – (Permits for Shipments – Roads, Highways)

9

Page 10: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Construction Manager

SuperintendentsField EngineersRigging EngineersInspection / Quality Control & AssuranceLabor Agreements (NMA, GPA, Open Shop, etc.)Craft Availability / Travelers (Estimating and Construction) Craft Training (Especially in Developing Countries)

ALSO

CommissioningStartup

10

Page 11: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Business Manager

Accounting – (Backward Looking - HISTORICAL)Payroll / Timekeeper – (Allocation of Charges)Payment – Vendors (Engineered Equipment & Bulks)Management of the Money – “Cash Neutral”TaxesAdministrative Assistants / Document Control ClerksHuman Resources (Visas, as well)LegalHousing - (Especially International) – Pioneer and ConstructionFood - (Ditto)Emergency Response - (Evacuation, Fire, Medical, Snakes, etc.)Community Relations - (Government, Police, Community Relations)

11

Page 12: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

12

Page 13: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Contract Methodology

• Design Bid Build – Competitive – Less Expensive?

• Design Build – Cooperative – Less Expensive?

13

Page 14: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Contract / Subcontract Types

• Lump Sum / Turn Key – (Hoover Dam)

• Well defined scope

• Grass Roots

• Lower Unknowns

• Cost Plus (Reimbursable) • Not well defined scope

• Unknown

• Existing Facilities

14

Page 15: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Contract / Subcontract Types - Variations

• Unit Rates (Air to Soil Interface)

• Lump Sump with Unit Rates for Extras

• Incentives

• Safety – Good – Risk – Taking Injuries Home in Your Pocket

• Quality – Rework – Customer Satisfaction

• Schedule – Permits, Long Lead Equipment (Pre-FID Work / Cancellations)

• Many Other Variations & Flavors

15

Page 16: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Contract / Subcontract – Risk Assessments

WHO CAN BEST MANAGE AT LEAST COST?Owner or Contractor / Subcontractor?

Construction Productivity

Asbestos / Lead Paint Abatement

Underground Surprises – Benzene Mitigation, U/G Obstuctions

Unknowns / Unknowables

Force Majeure

16

Page 17: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Choose Any 2 of the 3

17

Page 18: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

FAST / CHEAP / GOOD

• Good / Cheap – Well Defined Lump Sum (Grass Roots Plant)

• Good / Fast – A Lot of Unknowns and Little TimeRestore Rail Car Loading Facility – High Margin Specialty Chemical

Piping Isometrics – Design Review, SOE Review, Fabrication, Install

• Fast / Cheap – Temporary Facility (Run a Hose, Temp Piping)

18

Page 19: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

19

Page 20: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Regulatory / Permits• Expansion of Interstate 70 – Denver – 12 milesPermit work – 13 years

8,951 of Pages with 7,307 Pages of Appendices

Senior Government Officials Asked By the Cabinet Secretary

“Did you read all the pages of these documents?”

“No” was the emphatic answer

• Keystone XL PipelinePermit work – 12 years

Partial Approvals

Still not fully Approved

20

Page 21: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Environmental

• Existing Brownfield Site – Prospective Chemical PlantOpen Pit Quarries – Trees – Backfill

Fly Ash Pond – Old Coal Fired Power Plant

21

Page 22: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

External InfrastructurePermits – Work with Governmental Agencies

Corp of Engineers – River Locks and Dams

Coast Guard – River Traffic

Railroad

State Highway Expansion

Natural Gas

Electrical Power – Substation, Additional Power Plant Unit

Etc.

22

Page 23: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Ethics• Chemical Plant – 1 of 3 Proposed Locations - $5 Billion PlantHalf River Bottom, Half Up on Two Hills

Laydown

Parking

• Owner of the Site “How Much Will It Take to Recommend My Site?”

“May the Best Site Win”

“You are Such a Boy Scout. I Admire You. Not How I do Business, Though.”

23

Page 24: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Heuristics 1. Schedule – 2x As Long as First Appears2. Cost – 3x as Much as First Appears3. Cost & Schedule Contingency4. If you are just running on track, you will end up behind.

• There is always unforeseen items around the corner.5. The bitterness of poor quality remains long after the

sweetness of low price is long forgotten.

24

Page 25: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

QualityCorrective Action Report

Egypt – Pipe Welding Inspection Inspector – 6 months – Full Penetration Welds Error

Action: Reinspect all Shots, Grind out and Redo all Errors

Waste Treatment Plant – Misspelled Word – P&ID Notes Threatened – Whistleblower

40 Hours of Investigation and Resolution

Procedure Says – Red Pencil on Master Stick File25

Page 26: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

26

Page 27: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

27

Page 28: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Engineered Lifts

• Heavy Vessel Lift – (Vit Plant)

• Tight Clearances – (Low Sulfur Diesel Hydrotreater)

28

Page 29: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

29

Page 30: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Whatever it Takes…

30

Page 31: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Whatever it Takes…High Task, High People Relationships

31

Page 32: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

32

Page 33: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

General Jim Mattis

USMC (Ret.)

Sec of Defense (Former)

33

Page 34: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

34

Page 35: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

Whatever it Takes…

High Task, High People Relationships

Servant Leadership

Or

What the Project Manager does when his team is at his Christmas Dinner party

35

Page 36: (2020-01-28) Project Management presentation...2020/01/28  · Project Management What Unique Things Must Be Considered EPC Heavy Industrial Projects By Bob Stevens Project Engineering

What happened to my CAR?

36