LOLEWG
9/11/2018
2019-2020 CIL/CEL Values
and Study Timeline
1
Updated
10/3/2018
• Purpose
• Inform stakeholders of Draft 2019-20
Capacity Import and Export Limits.
Key Takeaways (Limit changes)
• Limits have been impacted by the
FERC Locational filing changes
(MISO process change).
• Limits have been impacted by MISO
system changes including
transmission topology and generation
dispatch.
2
Purpose and Key Takeaways
Introduction
• Capacity Import and Export Limits (CIL and CEL) in this
presentation are calculated based on the FERC Locational
filing.
• The CIL and CEL results have been adjusted for exports to non-
MISO load.
• Coordinating Owner Resources and Border External Resources
are no longer treated as imports and instead treated as internal to
the zone which impacts base area interchange.
• CIL/ZIA for LRZs 1, 2, 3 and 4 along with CEL/ZEA for LRZs 4
and 5 have all been updated as of 10/03/18.
3
2019-2020 Capacity Import Limits
4
Zone
19-20
ZIA1
(MW)
19-20
CIL1
(MW)
18-19
CIL2
(MW)
18-19
Import in
Auction
1 3,747 4,078 4,546 Export
2 1,713 1,713 2,317 121
3 2,813 3,037 2,812 Export
43 5,210 6,845 6,278 1,133
5 5,013 5,013 3,580 606
6 6,924 7,066 7,375 Export
73 3,211 3,211 3,785 320
8 4,185 4,424 4,778 Export
9 3,631 3,950 3,679 1,513
10 3,792 3,906 2,618 120
1 Limits based on revisions made to the new Locational Tariff filing
2 Limits after applying changes due to December 31, 2015 FERC Order on exports 3 Denotes voltage limited transfers
Planning Year (2019-2020) CIL Results
Capacity Import Limits Zone 1: MN and ND
Limit: 4,078 MW
• Initial Limiting Element:
Colby to North Iowa Wind 161 kV Line
• Initial Contingency:
Adams to Barton 161 kV Line
Re-dispatch of 1,992 MW applied
10/3 update: Added two expedited
ComEd projects that we not included in
the regional model
• Final Limiting Element:
Sherman Street to Sunnyvale 115 kV
• Final Contingency:
Arpin to Rocky Run 345 kV
6
Capacity Import Limits Zone 2: WI and MI
7
735 kV
345 kV
115-161 kV
Limiting Element Map data ©2017 Google, INEGI
Limit: 1,713 MW
• Initial Limiting Element:
University Park to East
Frankfort 345 kV Line
• Initial Contingency:
Dumont to Wilton 765 kV
Line
Re-dispatch of 2,000 MW applied
10/3 update: Added two expedited
ComEd projects that we not
included in the regional model
• No change in limiting
element or contingency
Capacity Import Limits Zone 3: IA
8
Limit: 3,037 MW
• Initial Limiting Element:
Sub 3458 to Sub 3456 345 kV Line
• Initial Contingency:
Sub 3455 to Sub 3740 345 kV Line
Mitigation of the initial limiting element as
an RCF flowgate
10/3 update: Added two expedited ComEd
projects that we not included in the
regional model
Re-dispatch of 2,000 MW applied
• No change in limiting element or
contingency
Capacity Import Limits Zone 4 – IL: Voltage Constraint
9
Map data ©2017 Google, INEGI
Limit: 5,489 MW
• Limiting Voltage Element: Hallock138 kV Bus
• Limiting Contingency: Clinton unit
• Voltage constraint is more limiting than thermal constraint
• 10/3 update: A TO submitted a model correction that was applied after the 9/11/18 meeting that impacted this limit
345 kV 115-161 kV Limiting Element
Capacity Import Limits Zone 5: MO
10
500 kV 345 kV 230 kV 115-161 kV
Limiting Element
Map data ©2017 Google, INEGI
Limit: 5,013 MW
• Initial Limiting Element:
Heritage to Fredtown 161 kV Line
• Initial Contingency:
Lutesville to St. Francois 345 kV line
Redispatch of 1,820 MW applied
• Final Limiting Element:
Joppa TS 345/161 kV Auto- transformer
• Final Contingency:
Shawnee 500/345 kV Auto- Transformer Line
Capacity Import Limits Zone 6: IN and KY
11
500 kV
345 kV
115-161 kV
Limiting Element
Map data ©2017 Google, INEGI
Limit: 7,066 MW
• Initial Limiting Element:
Benton 345/138 kV Auto
Transformer ckt. 1
• Initial Contingency:
Benton to Cook 345 kV Auto-
Transformer
Re-dispatch of 2,000 MW applied
• Final Limiting Element: Paradise
to BRTAP 161 kV
• Final Contingency:
Volunteer to Phillips B 500 kV
Line
Capacity Import Limits Zone 7 – MI: Voltage Constraint
12
345 kV 115-161 kV Limiting Element
Map data ©2017 Google, INEGI
Limit: 3,211 MW
• Limiting Voltage Element:
Pioneer 120 kV Bus
• Limiting Contingency: Wayne to
Monroe 345 kV Line
• Voltage constraint is more
limiting than thermal constraint
Capacity Import Limits Zone 8: AR
13
500 kV 115-161 kV Limiting Element
Map data ©2017 Google, INEGI
Limit: 4,424 MW
• Initial Limiting Element:
Colonial Orange to Cow 138 kV
Line
• Initial Contingency:
Sabine to Cow 138 kV Line
Re-dispatch of 2,000 MW applied
• Final Limiting Element:
Moonlake to Ritchie 230 kV
Line
• Final Contingency:
Cordova TN to Benton MS
500 kV Line
Capacity Import Limits Zone 9: TX and LA
14
500 kV 115-161 kV Limiting Element
Map data ©2017 Google, INEGI
Limit: 3,950 MW
• Initial Limiting Element:
Ray Braswell to Franklin 500 kV Line
• Initial Contingency:
Franklin to Grand Gulf 500 kV Line
Re-dispatch of 2,000 MW applied
• Final Limiting Element: Sterlington to Downsville 115 kV Line
• Final Contingency:
• Mt. Olive to El Dorado 500 kV Line
Capacity Import Limits Zone 10: MS
15
500 kV
230 kV
115-161 kV
Limiting Element
Map data ©2017 Google, INEGI
Limit: 3,906 MW
• Initial Limiting Element:
Cow to Colonial Orange 138 kV
Line
• Initial Contingency:
Sabine to Cow 138 kV Line
Re-dispatch of 2,000 MW applied
• Final Limiting Element:
Freeport to Twinkletown 230
kV Line
• Final Contingency:
Freeport to Hornlake 230 kV
Line
1 Limits based on revisions made to the new Locational Tariff filing
2 Limits determined as the excess capacity in the zone. It is the difference between maximum available generation in that zones and
the total generation dispatched.
2019-2020 Capacity Export Limits
16
Zone
19-20
ZEA1
(MW)
19-20
CEL1
(MW)
18-19
CEL
(MW)
18-19
Export in
Auction
1 3,379 3,048 516 516
2 979 979 2,017 Import
3 4,664 4,440 5,430 651
4 5,332 3,693 4,280 Import
52 2,122 2,122 2,122 Import
6 1,577 1,435 3,249 346
7 1,358 1,358 2,578 Import
8 5,328 5,089 2,424 2,299
9 2,224 1,905 2,149 Import
10 1,721 1,607 1,824 Import
Planning Year (2019-2020) CEL Results
Capacity Export Limits Zone 1: MN and ND
18
Map data ©2017 Google, INEGI
345 kV 115-161 kV Limiting Element
Limit: 3,048 MW
• Initial Limiting Element:
New Ulm South to New Ulm 69
kV Line
• Initial Contingency:
System Intact
Re-dispatch of 400 MW
GLT applied
• Final Limiting Element:
Seneca to Gran Grae 161 kV
Line
• Final Contingency:
Arpin to Eau Claire 345 kV Line
Capacity Export Limits Zone 2: WI and MI
19
345 kV
230 kV
115-161 kV
Limiting Element Map data ©2017 Google, INEGI
Limit: 979 MW
• Initial Limiting Element:
Wempletown 345/138 kV auto-
transformer
• Initial Contingency:
Cherry Valley 345/138 kV auto-
transformer
Cherry Valley 138/34.5 kV auto-
transformer
Cherry Valley 2M to Cherry Valley B 138
kV Line
Re-dispatch of 1,208.5 MW
GLT applied
• No change in limiting element or
contingency post re-dispatch
Capacity Export Limits Zone 3: IA
20
345 kV 115-161 kV Limiting Element Map data ©2017 Google, INEGI
Limit: 4,440 MW
• Initial Limiting Element:
Sub P Iowa City 161/69 kV
auto-transformer
• Final Contingency:
System Intact
GLT applied
• Final Limiting Element:
Fargo 345/138 kV Auto-
Transformer
• Final Contingency:
Mapleridge to Tazewell 345 kV
Line
Capacity Export Limits Zone 4: IL
21
345 kV
230 kV
115-161 kV
Limiting Element Map data ©2017 Google, INEGI
Limit: 3,693 MW
• Initial Limiting Element:
Pontiac to Brokaw 345 kV Line
• Initial Contingency:
Pontiac to Bluemond 345 kV Line
Re-dispatch of 350 MW applied
GLT applied
Implemented two expedited ComEd
projects that we not initially submitted
• No change in limiting element or
contingency post re-dispatch
Capacity Export Limits Zone 5: MO
22
Map data ©2017 Google, INEGI
Limit: 2,122 MW
• A valid constraint was not found.
• Initially, Capacity Export Limit was determined as the sum of
the Base Area Interchange and the excess capacity in LRZ 5.
• This was discussed at the 9/11/18 LOLEWG and the 9/12/18
RASC meetings and it was agreed that without any major
changes from last year within LRZ 5, the previous limits would
be utilized.
Capacity Export Limits Zone 6: IN and KY
23
500 kV
345 kV
115-161 kV
Limiting Element
Map data ©2017 Google, INEGI
Limit: 1,435 MW
GLT Applied
• Final Limiting Element:
University Park to East
Frankfort 345 kV Line
• Final Contingency:
Dumont to Wilton 765 kV
Line
Capacity Export Limits Zone 7: MI
24
345 kV
230 kV
115-161 kV
Limiting Element
Map data ©2017 Google, INEGI
Limit: 1,358 MW
• Initial Limiting Element:
University Park to East
Frankfort 345 kV Line
• Initial Contingency:
Dumont to Wilton 765 kV
Line
Re-dispatch of 1,400 MW applied
• No change in limiting
element or contingency
post re-dispatch
Capacity Export Limits Zone 8: AR
25
500 kV 115-161 kV Limiting Element
Map data ©2017 Google, INEGI
Limit: 5,089 MW
• Initial Limiting Element: Catherine
U4 to Arklahoma 115 kV Line
• Initial Contingency:
System Intact
GLT Applied
• Final Limiting Element:
Russelville South to Dardanelle
161 kV Line
• Final Contingency:
Arkansas Nuclear to Fort Smith
500 kV Line
Capacity Export Limits Zone 9: TX and LA
26
500 kV
230 kV
115-161 kV
Limiting Element Map data ©2017 Google, INEGI
Limit: 1,905 MW
• Initial Limiting Element:
Addis to Tiger 230 kV Line
• Initial Contingency:
Formosa to Enco kV Line
Re-dispatch of 800 MW applied
• Final Limiting Element:
Addis to Tiger 230 kV
• Final Contingency:
Dowmeter to Chenango 230
kV
Capacity Export Limits Zone 10: MS
27
230 kV 115-161 kV Limiting Element Map data ©2017 Google, INEGI
Limit: 1,607 MW
• Initial Limiting Element:
Batesville to Tallahachie 161
kV Line
• Initial Contingency:
Choctaw to Clay 500 kV
Line
Re-dispatch of 100 MW applied
GLT Applied
• No change in limiting element
or contingency post re-dispatch
Next Steps
28
• Next steps
• These results are final. However, if any updates are deemed
necessary, a conference call will be scheduled to discuss the revision.
• Results will be incorporated into the LOLE report