2018, MARCH ““REJUVENATING THE CONTRACT...
Transcript of 2018, MARCH ““REJUVENATING THE CONTRACT...
2018, MARCH
““REJUVENATING THE CONTRACT ‘SPINE’ OF MEGAPROJECTS, PART 1” – BUSINESS
TRENDS, HYDROCARBON PROCESSING, HOUSTON
“LEARNING” PAGE
1
Ben Crossley - Singapore, and Gavin McLeod - Bahrain
Rejuvenating the Contract “Spine” of Megaprojects - Part 1 Current Contracts
Abstract. Executives and project managers are
grappling with challenging business environments and
a 20-year legacy of overrunning megaprojects. Billions
of dollars are wasted annually from execution
inefficiency, lost production and disputes. The
“medicine” applied over decades is not working. Two
respected consulting firms recently reported on causes
of project failure. They made valid observations.
However, they misdiagnosed symptoms of failure as
root causes. This article is based on understanding
what it takes to build megaprojects. It diagnoses the
failure root cause: business culture. Change is required
to empower competent project professionals, who
prepare well-designed contract “spines” to underpin
business governance and project management
discipline. This contract and related project
development is “preventative medicine” to cure the
reported symptoms, improve project outcomes, and
set in motion a flywheel of sustainable positive
momentum. Enlightened members of current
management circles are ready for change. This article
recommends currently trending actionable and
economic solutions requiring some time and relatively
inexpensive expertise: First, smart, strategic thinking.
Second, commitment to the disciplined work of
preparing usable and simple contracts. Simple is not
lazy, it is the opposite: comprehensive, and yet making
complex projects simpler to understand and execute.
FIG 1-1: Cut the “Gordian Knots” inhibiting contracts
from working, set in motion a positive flywheel
Contracts are not working as the “spine” of
projects. There is an old saying:
“The best place for contracts is in the bottom
drawer.”
Some projects work that way -- until a dispute arises.
Then, the contract is retrieved and interrogated for
favorable interpretations. Sound familiar? Contracts
are misused and misunderstood:
• Thought to have no relevance to the business of
building projects (medical analogy: “unnecessary
medicine”).
• Thought to have the narrow function of
“minimizing liability.” This important for
governance, but only required after the project has
gone wrong (“crisis medicine”).
• Some clients believe that simply by having EPC
lump sum contract terms “if the project fails the
contractor is responsible.“ In the real world, legal
words will not protect clients from failure
(“delusional medicine”) (Ref. Outcomes).
A contract’s purpose is “preventative medicine.” First,
to underpin project governance: high-level assurance
that a project will meet its objectives. This includes
allocation of sufficient time and resources, taking only
commercially prudent risks and liabilities, and setting
control measures. Poor governance in “toxic contracts”
causes bankruptcy (examples: Carillion 2018 UK, Shaw
Group 2012 US).
Second, to underpin project management
discipline: the contract form determines project
relationship, high-level performance obligations and
risk (Ref. FIG 1-5). The contract contents determine
scope, time and quality, HSE compliance, all execution
conditions, requirements and restraints (Ref. FIG 1-6).
These provisions in every major construction contract
mirror the required Body of Knowledge (BOK) of every
project manager (Ref. Project Management Institute
US, Association for Project Management UK).
Clearly, the place for contracts is not in the
bottom drawer.
What is wrong with contracts today? What can be
done? The purpose of contracts and consequences of
poorly designed contracts are rarely explained clearly,
let alone understood. Contracts focus too much on
who to blame and too little on how to get the job done.
An awareness of the current situation and the
2
imperative to improve contracts is trending within
innovative parts of the business the legal communities.
For example, General Counsel at GE Aviation recently
lamented:
“For the most part, the contracts used in
business are long, poorly structured, and full of
unnecessary and incomprehensible language.”
(Ref. Burton 2018).
The hypothesis of this article, is that after business
culture change, executives and project management
can restore their ownership over well-designed
contracts. They can empower competent project
professionals who, while taking good legal advice in
context, lead a rejuvenation of contracts, “to make
fresh or new again, to restore to youthful vigor” (Ref.
Business Culture sections). Practical and relatively
inexpensive solutions are within reach (Ref.
Recommendations).
Project overruns are sinking business cases. Recent reports highlight low productivity concerns:
“The industry must confront internal
challenges. In most countries, over the past 50
years, productivity improvements in
construction have been meagre.” (Ref. World
Economic Forum, 2016 pg. 14)
Recent megaproject outcome data has a wide spread,
consistently pointing to major overruns in either cost,
time, or both:
• Average 80% cost overrun and 20 months
delay (overruns in 98% of cases): data on 60 oil
and gas and mining megaprojects (Ref.
McKinsey, 2015 pg. 2)
• Average 35% cost overrun and 25 months
delay (respectively 57% and 64% of cases):
data on 100 power megaprojects (Ref. Ernst &
Young Global, 2016 pg. 4)
Annual USD 29 billion global capital cost overruns are
estimated based on the lowest of the above reports
(35% overrun on 57% projects). The authors applied
that overrun to the forecast annual USD 144 billion
global capital spend for the hydrocarbon processing
industry (HPI) covering refining, petrochemical, gas
processing and LNG (Ref. “HPI Market Data 2018”).
Finally, based on an analysis of past project close-out
data, in FIG 1-2 the authors have quantified three
overrun components.
FIG 1-2: Annual USD 29 billion total global capital cost
overrun total, split into overrun components
Additional Work (10% of overrun total): “nice
to have changes”, due to enhanced functionality or
operating preference. Case example: change of plant
layout according to plant operator’s preference.
Under Estimate (50% of total): “must have
changes”, due to incomplete definition of design or
execution conditions. Case example: inaccurate sizing
of major vendor equipment requiring layout and
routing changes. Though, under estimate is not all
wasted, late change causes inefficiency, and under
estimate impacts the business case.
Execution Inefficiency (40% of total): “absolute
waste”, due to interruptions or deviations to the
planned work sequence and due to delays. Case
examples: client not set up for execution causes
engineering approval delays. And, contractor not set
up for execution causes lack of worksite sequencing
and low productivity.
Return on Investment (ROI) loss from delayed on-spec
production can be astronomical. Therefore, contract
terms include waivers of consequential loss, and limit
contractors’ liability to capped liquidated damages,
normally 10% of contract price. In addition to delayed
on-spec production, reported data shows nearly half
(47%) of projects suffering from significant output
guarantee shortfalls.
Disputes occur on most failed projects, including EPC
lump sum fixed price: Complex and poorly prepared
contracts are open to interpretation (Ref. Contents
section). The contractor seeks a way out of liquidated
damages and cost overruns (reported average 35% vs.
5% pre-tax margins). The client having compensated
expressly instructed changes, maintains that fixed
price, means fixed. The authors estimate
3
approximately 1% of project capital cost for low-
intensity disputes without third-party intervention
(USD 1.4 billion annually), and up to 5% in arbitration.
Legal words will not protect clients from failure
consequences. Some clients believe that simply by
having EPC lump sum contract terms:
“if the project fails contractor is responsible …
we won’t pay more than the contract.”
The lost output scenario and others above
show that in the real-world clients have most to lose.
Reported data shows major overruns on 62% of EPC
lump sum projects, which as explained above generally
leads to dispute. Clients should restrict EPC lump sum
contracts to appropriate cases (Ref. Contract Forms
below).
The global USD 12 billion annual capital cost
inefficiency, plus ROI production loss, plus dispute cost
is “absolute waste”. Clearly, both clients and
contractors have a compelling business case to seek
“preventative medicine.”
Overrun root causes and ‘Cobb’s Paradox’. 20 years ago, Martin Cobb advised the Canadian
Treasury investigating “IT” project failures. His well-
known paradox is still valid today. The “medicine”
applied over decades is not working:
“We know why projects fail; we know how to
prevent their failure—so why do they still fail?”
(Cobb, 1995)
Increasing scale, complexity and one-off nature of
megaprojects are not overrun root cause.
Megaprojects seem overwhelming at first sight: scores
of companies, hundreds of engineers, thousands of
documents, tens of thousands of workers. However,
understanding projects, it becomes clear that project
core drivers are repeated. Example: the largest
component of construction manhours (35% to 45%)
and the schedule critical path always involve piping
shop and field welding and installation. That is
standard technology unchanged over decades.
Megaprojects are not destined to fail, they are big and
complex, requiring disciplined project development
and execution (Ref. Barron, 2015 pg. 221).
Respected consulting firms recently reported similar
overrun “root causes” (Ref. McKinsey, 2017 pg. 63,
Ernst & Young Global, 2016 pg. 6):
1. Unachievable cost and time commitments.
2. Incomplete definition of design or execution
conditions.
3. Execution team unprepared, inadequate skills.
Project not set up for delivery with appropriate
procedures and digital infrastructure.
4. Inadequate contract and commercial structures.
Poor supply-chain integration.
5. Inappropriate risk allocation and management.
All these causes are “internal” to the project,
could be cured by well-designed contracts (FIG 1-3),
and the related project development wrapped into the
contract. Overruns from unavoidable and external
events such as change in law are negligible in context.
FIG 1-3: Contract “spine” of governance and project
management
The reported causes are really “symptoms” of failure.
Like every good paradox, Cobb’s apparent
contradiction expresses a deeper truth. The reported
symptoms are valid. However, based on understanding
megaprojects, the following case examples show that
competent project professionals already know all the
reported symptoms, and they know the established
“preventative medicines” that should be applied.
Lessons are not learned: the root cause is deeper than
the reported symptoms.
Symptom and case example 1, unachievable
commitments: overruns occur from attempts to
compress schedule and cost, resulting in major re-work
and delay when attempting the impossible fails in the
real-world. Case example: a nuclear power plant which
was contracted with 5-year schedule v. historical best
7 years. Realistic contract schedules start with past
project references; then probabilistic analysis of an
integrated schedule.
Case example 2, incomplete design: overruns
occur from field changes requiring cut and re-weld of
4
fabricated or installed pipe and steel. Case examples:
show productivity falls by more than half during
months of field change (30% ~ 40%). Complete design
starts with client FEED to +/-10% and specifying
minimum engineering competence; contractor
allocating realistic contract allowances for “right first
time” detailed design.
Case example 3, inadequate preservation
execution: overruns occur from inadequate site
storage that causes re-work and start-up delays. Case
example: one project required re-surfacing of all 5,000
installed flanges. Preservation starts with specifying
minimum requirements, allocating realistic contract
allowances, implementing agreed measures.
The root cause of major overruns is “business culture”
characterized by prevailing behaviors and beliefs. This
finding has been neatly stated as follows:
“Modest project ‘screw-ups’ are mostly the
fault of project execution; Colossal ‘screw-ups’
are almost always caused by the business.”
When present, business culture failings, particularly on
client-side, that cause overruns include:
• Grasping short-term gains including perceived
“savings” on competent personnel or accepting
lowest commercial bids without sufficient
technical evaluation; over long-term foresight.
• Lacking the grit for getting down to the “devil in the
detail”, or for facing brutal realities of project
development and execution allowances.
• A “fear impulse” seeking insulation from blame or
responsibility, avoiding tough decisions, remaining
frozen to the perceived safety of the status quo.
When faced with challenging business environments
and contracting implications are not understood, these
cultural behaviors are in respects sane and rational.
The required business culture for successful projects
is long-term, smart, strategic thinking, collaborative,
innovative, tough-minded, brutally honest and down-
to-earth. It is hard but fair, which is more efficient in
the long-term. Example: unduly using market leverage
to impose undesirable contracting arrangements leads
to higher dispute costs. It incubates the single-minder
objective of preparing a robust business case at the
outset – if necessary, killing off unfeasible projects. It
remains relentless committed to achieving all project
success criteria. It understands what must happen,
why, and when. It gets down to the fundamentals
including well-designed contracts. Enlightened
members of current management circles already
practice the required culture and are ready for
widespread change.
Improved contract planning and preparation requires competent project professionals empowered
by the business, applying appropriate techniques.
Some fundamentals are summarized with a project
management emphasis (Broome and Lake, 2017).
The Project Contracting Strategy (PCS) is the contract
planning and preparation keystone. The PCS defines
what scope is proposed in vertical and horizontal work
packages, how to motivate performance and manage
risks with “best fit” contract forms and incentives, who
is available in the market with necessary capabilities
Smart PCS starts in Phase-2 planning the Phase-3
contracts for FEED and technical requirements. These
are essential for delivering stable Phase-4 foundations:
“The quality of the FEED documents will
directly affect the quality of the EPC bids.”
(Baron, 2016)
The completed PCS output is used for Individual
Contracting Plans (ICP) for contracting each work
package.
FIG. 1-4: Project Contracting Strategy (PCS) covering
all project phases (simple example)
The Contract Development Schedule (CDS) manages
the PCS decision gate milestones. Second, it manages
contract preparation milestones for procurement
invitations to bid, and negotiation and award of
contracts. A robust CDS is critical to manage tensions
between the increasingly short times to market, the
time windows to leverage full procurement value from
the market, the internal resource availability, the
5
integration of contract preparation with the overall
project development.
The core of the Contract Development Team (CDT)
needs to form at the latest in Phase 2 to develop the
PCS. Full strength team is needed in Phase 3 to prepare
contract documents for bid packages. The CDT team
leadership comprises: the project manager as principal
stakeholder in a well-designed contract; contract
manager as specialist in contract strategy and content;
engineering and construction managers as specialists
in the technical requirements where most overrun
causes originate; project controls manager as specialist
in timelines; legal advisor and business manager as
specialists respectively in terms and conditions and
commercial requirements. Having CDT personnel
follow through into contract negotiation and worksite
execution delivers benefits of building the all-
important expert, committed and collaborative
“project team”.
Improved contract form choices are crucial. Some
senior professionals consider that first-order concerns
are a robust business case and complete design which
will be especially expensive if changed later; therefore:
“We tend to exaggerate the importance of
contracting approach…. Contracting is a
second-order concern.” (2011)
A robust business case is undoubtedly a priority.
Effective execution of that case requires a “best fit”
environment, and that will be determined the contract
form. Clients need to make smart “best fit” choices.
Project specific considerations include: work scope,
and risk factors described in the PCS above, the market
activity of providers, the required schedule, the client
team’s capability, the flexibility to optimize value
engineering or technology adoption potential.
Four fundamentally different contract forms; each
define four “attributes” of a business agreement:
different performance obligations; payment principles;
“first-order risk” allocation; and different working
relationships:
‘Traditional’ Unit Rate (UR): all client
engineering and decision making. Payment by actual
work quantities on BQ rates, or by man and equipment
hours on schedule of rates. Client takes most risk,
except BQ productivity risk.
Engineer, Procure and Construct Lump Sum
(EPCLS): contractor performs everything necessary to
meet defined end states, takes most risks under
defined execution conditions, for a fixed price.
Contractor has the right and the responsibility to
manage works most efficiently. Client maintains a
“hands-free” relationship.
Engineer, Procure and Construction
Management (EPCM), or EPC Reimbursable (PRCR):
Contractor performs the management of works as the
client’s agent, or contracts as EPC to suppliers. Under
both, payment is by cost-plus formula, client takes
most risks, and can maintain an active relationship.
Collaborative / Relational Contracting (IPD):
defines the relationships for parties to work together
to achieve mutual project or framework objectives.
Shared risks and opportunity for example saving on
target price underrun (Ref. Part 2).
FIG 1-5: Four fundamentally different contract forms
(high-level, multiple variants)
“First-order” risk allocation is achieved selecting the
contract form above. Specific “second-order risk”
allocation, for example change in law, is a specialist
topic; in summary: optimize contract allocation to
achieve lowest long-term cost; which generally means
assigning risk to “natural owners” best able to manage
and mitigate or take the benefit and save contingency
if risk does not occur.
Choice of EPC lump sum should be limited to projects
achieving all the following “EPCLS qualifying criteria”
for the potential benefits of this form to be delivered:
1. Clear and stable work scope. Preferably +/-10%
FEED design; at minimum unambiguous basic
engineering inputs (example: certified P&ID,
HAZOP), and end states (output guarantees).
2. Clear and stable execution conditions,
requirements and restraints.
3. Project risks identified and commercially prudent.
6
4. Client wants “hands-free” relationship, not
intruding on contractor’s right to manage works.
5. Qualified EPCLS providers are interested in the
market.
6. Bid time is available and sufficient for stable and
competitive pricing.
EPCLS is be the predominant form reported to used on
53% of projects. Reported data showing 62% major
overruns indicates that on many megaprojects it is
unrealistic to meet all qualifying criteria. Alternatives
to EPCLS are required.
Fortunately, several alternatives to EPC lump sum are
available in regular use, as briefly outlined below:
• EPC Management (EPCM): is reportedly used on
25% projects with lower design definition and
higher risk. Experience shows that with smart-
design of cost-plus formula, contractor’s cost,
time, HSE motivations can be aligned with client.
Reported data showing 78% major overruns
indicates how difficult it is to design an effective
formula and use on higher risk cases.
• Early Contractor Involvement (ECI): use is trending
with innovative clients including a recent oil major
megaproject. Client employs one or more
contractors to develop design and execution plan,
as basis of second-stage execution. Efficiencies
result from leveraging execution expertise in value
engineering and advanced work planning in the
project shaping stage.
• Mixed engineering and procurement reimbursable
(EPR) and EPCLS: is reportedly used on 12%
projects with only 8% major overruns. Efficiencies
result from reimbursable work scope definition.
During EPR client risk is manageable by “open-
book” procurement and engineering is only 10%
project cost. Second stage EPCLS construction
contractors bid on work scope now clearly defined
in EPR phase.
International model contracts (FIG 1-5) offer
efficiency promoting advantages over many
specifically drafted contracts, including the following:
balanced “second-order risk” allocation, usable plain
language, less ambiguity after years of fine-tuning, user
familiarity, and available off-the-shelf. Collaboration
and a project management “spine” are built into some
models:
“NEC is designed to act as a definition of what
good project management around a group of
people should look like.” (Dr. Barnes,
Association of Project Management, Founding
Chairman, 2011)
Improved contract content needs to be usable by
the project team. Well-designed contracts are
comprehensive, and yet make complex megaprojects
easier to understand and implement. In essence,
contracts need a clear structure mirroring the project
activities and to satisfy two simple criteria:
1. For matters where there is certainty, they must
offer unambiguous instruction;
2. For matters that deal with uncertainty, they must
offer clear guidance on how it will be handled. It is
rarely practical to anticipate every incident or
uncertainty
FIG 1-6: Contract Pinnacle Structure
Contract Terms and Conditions (TC) whether
specifically drafted by legal or by a model contract
applied to the project will define the contract form (FIG
1-5). TC need project team oversight to ensure that the
PCS decisions on form, risk, payment principles and
relationship are correctly applied.
Contract Technical Requirements (TR) justify
the most focus and resource from CDT. Based on an
analysis of past project close-out data, most overruns
and disputes stem from TR. The biggest opportunity to
improve outcomes lies with better-designed TR.
Business people need practical business instruments
that support successful business outcomes. What
someone does not understand s/he will neither plan
nor implement. Practical guidelines for well-designed
content include following:
7
1. Contracts should be structured so that users know
where to find relevant information. An effective
technique is to mirror the main project activity
breakdowns and workflow, so it’s logical for
project people (FIG 1-6).
2. Concise so users don’t get lost or distracted.
Overdue “house-keeping” is required to clear out
unnecessary complexity and consolidate concise
standard documents. Case example: engineering
document specifications comprised five unlinked
sections, totaling hundreds of pages. The result is
abundant ambiguity. A series of mid-project
workshops are required to determine what is
required for hand-over, and what would be
burdensome inefficiency. Consolidation should be
a priority action:
“Both the volume and size of contracts have
grown dramatically over the last 30 years and
this has been accompanied by greater
complexity.” (Ref. Cummins, 2018)
3. Precise and complete for appropriately described
requirements. Requirements shall be expressed in
plain-language actionable terms: who does what,
when and where; not in abstract legalese.
The business case for simple plain-language contracts
is trending within innovative parts of the business the
legal communities. The case includes: Saving time to
market and costs of needlessly dragging negotiations;
Project execution team who are often multinational
can use the contact down to supervisor level (most
times it understandably stays in the “bottom drawer”);
Reducing disputes caused by ambiguity in complex and
poorly managed technical requirements, meaning that
each side can normally find one interpretation
supporting their position. Case example: GE Aviation
recently completed a three-year program changing
terms and conditions to usable plain-language, and
reported the following results:
“The contract was then presented to the
leaders of the digital-services business. It was
well received, to say the least…. Plain language
has saved significant amounts of time and
money” (Ref. Burton 2018).
Simple does not mean incomplete or lazy. In fact, it’s
the continued use of unmanaged performance
inhibiting complex contracts that are lazy and
constitute a bigger business risk.
Takeaways and Recommendations. The estimated
annual USD 12 billion global capital cost inefficiency,
plus ROI production loss, plus dispute cost is “absolute
waste”. Rejuvenating contracts and the related project
development, is key to improved outcomes. Use of
well-designed contracts is trending. After the current
overruns, potential benefits, and the solutions have
been clearly explained and understood; enlightened
members of current management circles are already
for widespread business culture change:
"No problem can be solved until it is reduced to
some simple form” - J. P. Morgan (1837 - 1913)
Recommended practical improvements steps are
neither difficult nor expensive in relative terms:
1. Client organisations need to buy-in as primary
drives in their supply chain. Starting by analyzing
causes of any existing or potential overruns. After
consultation, design appropriate improvements.
2. Implement improvements with stakeholders,
including, as applicable:
a) Core personnel and capabilities: establish or
train company centers of competence in line
with in current trends and techniques.
Replenishing competencies lost over the past
decades is a top priority for many clients.
b) Contract form: familiarize project
management with current options. Implement
smart “best fit” forms applicable to specific
project circumstances
c) Contract content: Overdue “house-keeping” is
required to clear out unnecessary complexity
and consolidate concise standard documents.
Prepare usable plain-language contracts with a
focus on the technical requirements.
FIG 1-7: Economic and practical “preventative
medicine”
8
Part 2 Continues with: Contracting trends and
revolutionary new strategies examines the
potential of collaborative contracting, described in the
foreword to a new book as follows: “The goal of
everyone in the industry should be better, faster, more
capable project delivery created by fully integrated,
collaborative teams” (Ref. ‘Integrating Project Delivery’
- Fischer, Ashcroft, Reed, Khanzode, 2017).
Literature Cited - listed by publication date
‘Why simplify your contracts?’ - Tim Cummins, CEO of the International Association for Contract & Commercial Management (IACCM), January 2018
‘The Case for Plain-Language Contracts – Shawn Burton, General Counsel GE Aviation, Harvard Business Review, January 2018
‘Guide to Contracts and Procurement’ - Broome and Lake, Association for Project Management, 2017
‘Reinventing Construction: A Route to Higher Productivity’ - McKinsey Global Institute, February 2017
‘Shaping the Future of Construction - A Breakthrough in Mindset and Technology’ – World Economic Forum, 2016
‘Power and Utilities Megaprojects: Formulas for Success’ - Ernst & Young Global, Power & Utilities, 2016
‘The Oil and Gas Engineering Guide’ – Hervé Baron, Dec 2015
Further reference is available to online subscribers at
http://www.hydrocarbonprocessing.com/magazine/archive
Authors
Ben Crossley is Director and founder of
Energy Contract Solutions specializing in contracts and
procurement in Singapore. Ben provides front-line advice to
clients and EPC contractors on downstream oil and gas and
power generation megaprojects. Ben facilitates regular
training on ‘Project Development and EPC Contract
Management’.
Gavin McLeod is Senior Staff Operations
Specialist at Chevron Inc. specializing in commissioning and
systems completion, currently on assignment to Bapco
Refining Company in Bahrain. Gavin’s expertise and
specialist interests include hydroprocessing technology,
project implementation efficiencies, team development and
organizational dynamics.
Disclaimer: The views, information, and opinions expressed
in this article are solely those of the individual authors and
do not necessarily represent the official policy or position of
any third party, including an author's employer.