2018 Annual Dam and Dike Inspection Report...Inspection photos are included in Attachement A....
Transcript of 2018 Annual Dam and Dike Inspection Report...Inspection photos are included in Attachement A....
-
2018 Annual Dam and Dike Inspection Report
Ash Pond Complex
Conesville Plant
AEP Generation Resources, Inc.
Coshocton County, Ohio
August 28, 2018
Prepared for: AEP Generation Resources – Conesville Plant
Conesville, Ohio
Prepared by: American Electric Power Service Corporation
1 Riverside Plaza
Columbus, OH 43215
GERS-18-037
-
---Page Intentionally Left Blank---
-
Pages 3 of 10
---Page Intentionally Left Blank---
-
Pages 4 of 10
Table of Contents 1.0 Introduction ............................................................................................................................................. 6
2.0 Description of Impoundment .................................................................................................................. 6
2.1 Definitions of Visual Observations and deficiencies .......................................................................... 6
2.2 Fly Ash Pond Complex ....................................................................................................................... 7
3.0 Review of Available Information (257.83(b)(1)(i)) ................................................................................ 7
4.0 Inspection (257.83(b) (1)(ii)) .................................................................................................................. 8
4.1 Metals Cleaning Waste Tank Dike (Non-CCR).................................................................................. 8
4.2 Ash Pond Complex ............................................................................................................................. 8
4.2.1 Changes in geometry since last inspection (257.83(b)(2)(i)) ....................................................... 8
4.2.2 Instrumentation (257.83(b)(2)(ii)) ............................................................................................... 8
4.2.3 Impoundment Characteristics (257.83(b)(2)(iii, iv, v)) ............................................................... 8
4.2.4 Visual inspection (257.83(b)(2)(i)) .............................................................................................. 9
4.2.5 Changes that effect stability or operation (257.83(b)(2)(vii)) ...................................................... 9
5.0 Summary of Findings .............................................................................................................................. 9
5.1 General Observations .......................................................................................................................... 9
5.2 Maintenance Items ............................................................................................................................ 10
5.3 Items to Monitor ............................................................................................................................... 10
5.4 Deficiencies (257.83(b)(2)(vi)) ......................................................................................................... 10
Attachments Attachment A – Pictures
Attachment B – Site Maps
Attachment C – Instrumentation Data
-
Pages 5 of 10
---Page Intentionally Left Blank---
-
Pages 6 of 10
1.0 Introduction This report was prepared by AEP- Geotechnical Engineering Services (GES) section, in part, to fulfill
requirements of 40 CFR 257.83 and the Ohio Department of Natural Resource (ODNR), Division of Water
Dam Inspection Section and to provide AEP Generation Resources and the Conesville Power Station with
an evaluation of the facility.
Ms. Beth Mullen, Plant Environmental Coordinator for the Conesville Plant provided onsite coordination
for inspection activities. The inspection was performed on August 28, 2018 by Brian Palmer of AEP
Geotechnical Engineering. Weather conditions were overcast with temperatures in low 70°s F to upper 80°s
F and 0.4-in of precipitation occurred in the preceding seven days prior to the inspection.
2.0 Description of Impoundment
2.1 Definitions of Visual Observations and deficiencies
This summary of the visual observations uses terms to describe the general appearance or condition of an
observed item, activity or structure. The meaning of these terms is as follows:
Good: A condition or activity that is generally better or slightly better than what is
minimally expected or anticipated from a design or maintenance point of view.
Fair or A condition or activity that generally meets what is minimally Satisfactory:
expected or anticipated from a design or maintenance point of view.
Poor: A condition or activity that is generally below what is minimally expected or
anticipated from a design or maintenance point of view.
Minor: A reference to an observed item (e.g., erosion, seepage, vegetation, etc.) where the
current maintenance condition is below what is normal or desired, but which is not
currently causing concern from a structure safety or stability point of view.
Significant: A reference to an observed item (e.g. erosion, seepage, vegetation, etc.) where the
current maintenance program has neglected to improve the condition. Usually,
conditions that have been previously identified in the previous inspections, but
have not been corrected.
Excessive: A reference to an observed item (e.g., erosion, seepage, vegetation, etc.) where the
current maintenance condition is above or worse than what is normal or desired,
and which may have affected the ability of the observer to properly evaluate the
structure or particular area being observed or which may be a concern from a
structure safety or stability point of view.
This document also uses the definition of a “deficiency” as referenced in the CCR rule section
§257.83(b)(5) Inspection Requirements for CCR Surface Impoundments. This definition has been
assembled using the CCR rule Preamble as well as guidance from MSHA, “Qualifications for
Impoundment Inspection” CI-31, 2004. These guidance documents further elaborate on the definition of
deficiency. Items not defined by deficiency are considered maintenance or items to be monitored.
A “deficiency” is some evidence that a dam has developed a problem that could impact the structural
integrity of the dam. There are four general categories of deficiencies. These four categories are described
below:
-
Pages 7 of 10
1. Uncontrolled Seepage
a. Uncontrolled seepage is seepage that is not behaving as the design engineer has
intended. An example of uncontrolled seepage is seepage that comes through or
around the embankment and is not picked up and safely carried off by a drain. Seepage
that is collected by a drain can still be uncontrolled if it is not safely collected and
transported, such as seepage that is not clear. Seepage that is unable to be measured
and/or observe it is considered uncontrolled seepage. [Wet or soft areas are not
considered as uncontrolled seepage, but can lead to this type of deficiency. These
areas should monitored my frequently.]
2. Displacement of the Embankment
a. Displacement of the embankment is large scale movement of part of the dam. Common
signs of displacement are cracks, scraps, bulges, depressions, sinkholes and slides.
3. Blockage of Control Features
a. Blockage of Control Features is the restriction of flow at spillways, decant or pipe
spillways, or drains.
4. Erosion
a. Erosion is the gradual movement of surface material by water, wind or ice. Erosion is
considered a deficiency when it is more than a minor routine maintenance item.
2.2 Fly Ash Pond Complex
The fly ash pond complex is comprised of diked embankments on the north, southeast, and south sides.
County Road 273 runs along the toe of the north dike, a Plant haul road run along the top of the north dike,
and a coal haul road runs along the crest or exterior of the Southeast dike. The northwest side of the Ash
Pond Complex is located adjacent to a closed landfill area. There are three main ponds within the Ash
Pond Complex as listed below.
List of Main Ponds within the Ash Pond Complex
Fly Ash Pond
Bottom Ash Pond
Clearwater Pond
The Fly Ash Pond has internal splitter dikes that divide it into areas referred to as Ponds 1, 2, 3, and 4. The
Bottom Ash Pond has an internal splitter dike creating the Bottom Ash Pond and Pond 5. Water enters the
Ash Pond complex through either the Bottom Ash Pond or Pond 1. From the Bottom Ash Pond or Pond 1
water flows through the Ash Pond Complex in order from Pond 2, Pond 3, Pond 4, and Pond 5 before
reaching the Clearwater Pond where it is discharged to the Holding Pond.
The inspection included the dike for the Metals Waste Cleaning tank as it is adjacent to the South dike of the
Ash Pond complex
3.0 Review of Available Information (257.83(b)(1)(i)) A review of available information regarding the status and condition of the Ash Pond Complex, which
include files available in the operating record, such as design and construction information, previous
periodic structural stability assessments, previous 7 day inspection reports, and previous annual inspections
has been conducted. Based on the review of the data there were no signs of actual or potential structural
weakness or adverse conditions.
-
Pages 8 of 10
4.0 Inspection (257.83(b) (1)(ii))
4.1 Metals Cleaning Waste Tank Dike (Non-CCR)
A visual inspection of the dike for Metals Cleaning Waste Tank was conducted to identify any signs
of distress or malfunction of the secondary containment system. Overall the facility is in good
condition. The secondary containment is functioning as intended with no signs of potential structural
weakness or conditions which would be disruptive to the safe operation of the containment system.
Inspection photos are included in Attachement A. Additional pictures taken during the inspection can
be made available upon request.
4.2 Ash Pond Complex
4.2.1 Changes in geometry since last inspection (257.83(b)(2)(i))
No modifications have been made to the exterior geometry of the Ash Pond Complex since the 2017
annual inspection.
4.2.2 Instrumentation (257.83(b)(2)(ii))
The location and type of instrumentation is shown on Figure 2 in Attachment B. The maximum
recorded readings of each instrument since the previous annual inspection is shown in Table 1
below.
Table 1 – INSTRUMENTATION DATA
Ash Pond Complex
Instrument Type
Maximum Reading
since last annual
inspection
Date of reading
B7 Piezometer 729.53 2/27/2018
P-11 Piezometer 733.92 2/27/2018
P-12 Piezometer 747.82 2/27/2018
P-13 Piezometer 749.9 4/24/2018
B-0901 Piezometer 732.78 2/27/2018
B-0902 Piezometer 762.46 2/27/2018
B-0902R Piezometer 739.07 09/10/2018
B-0903 Piezometer 749.02 2/27/2018
B-0904 Piezometer 743.29 2/27/2018
NOTE: A review of the piezometer construction and locations identified issues with the construction of
B-0902 and B-0903 resulting in B-0902R replacing B-0902 in May 2018 and B-0903 was abandoned as
it is replicated by P-12.
Piezometers readings were generally consistent since the last inspection. Piezometer well
hydrographs are included in Attachment C. B-0902R is discretely screened in the embankment and
better characterizes water elevations in the dike.
4.2.3 Impoundment Characteristics (257.83(b)(2)(iii, iv, v))
Table 2 is a summary of the minimum, maximum, and present depth and elevation of the impounded
water & CCR based on the bathymetric survey conducted Nov. 9, 2017 and water elevation at time
of inspection; the storage capacity of the impounding structure; and the approximate volume of the
impounded CCR at the time of the bathymetric survey.
-
Pages 9 of 10
Table 2 – IMPOUNDMENT CHARACTERISTIC DATA
Impoundment Characteristics Ash Pond Complex
Approximate Minimum depth of impounded water
-
Pages 10 of 10
vegetation along the embankments was well established. The crest did not contain any ruts or
other signs of instability.
3) The Clearwater Pond hydraulic structure is in good condition. There were no signs of deterioration of the concrete or steel structures. The maximum pool elevation (762 ft. msl) is
also clearly marked on the structure. Stop logs were available for use. Flow within the
discharge pipe appeared unobstructed.
5.2 Maintenance Items
The following maintenance items were identified during the visual inspection, see inspection map for
locations:
Metals Cleaning Waste Tank Dike
1) No specific items identified related to the Metals Cleaning Waste Tank Dike.
Ash Pond Complex
2) Continue work to clear the vegetation on the exterior embankment along the Coal Haul road to the toe of the embankment and groin ditch plus a minimum of 25 ft. along the opposite slope
and ascertain the origin of the seepage observed within this area.
3) Work on the removal of vegetation at the toe of the north dike along County Road 273.
4) Continue monitoring and taking corrective actions related to groundhogs and other burrowing animals.
5.3 Items to Monitor
The following items were identified during the visual inspection as items to be monitored, see
inspection map for locations:
Metals Cleaning Waste Tank Dike
1) No specific items identified related to the Metals Cleaning Waste Tank Dike.
Ash Pond Complex
2) The abandoned culverts under original coal haul road need to be inspected quarterly for seepage.
3) Continue to monitor for areas of erosion and repair as necessary.
5.4 Deficiencies (257.83(b)(2)(vi))
There were no signs of structural weakness or disruptive conditions that were observed at the time of
the inspection that would require additional investigation or remedial action. There were no
deficiencies noted during this inspection or any of the periodic 7-day or 30-day inspections. A
deficiency is defined as either 1) uncontrolled seepage, 2) displacement of the embankment, 3)
blockage of control features, or 4) erosion, more than minor maintenance. If any of these conditions
occur before the next annual inspection contact AEP Geotechnical Engineering immediately
-
---Page Intentionally Left Blank---
-
ATTACHMENT A
Photos
-
---Page Intentionally Left Blank---
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 1
N40 11.366 W81 51.965
Photo #: 2
N40 11.351 W81 51.979
Description: Groin
Notes: Crest of SE dike haul road
Location: Looking SW
Notes: Exterior slope/crest of SE dike
Location: NE corner looking SW
Page: 01
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Crest
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 3
N40 11.362 W81 51.964
Photo #: 4
N40 11.332 W81 51.987
Description: Other
Notes: Left groin exterior slope of SE dike
Location:
Notes: Groundhog hole on slope, identified as part of plant inspection and flagged for repair. Groundhog removed
Location:
Page: 02
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Groin
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 5
N40 11.310 W81 52.014
Photo #: 6
N40 11.309 W81 52.016
Description: Toe
Notes: Toe of SE dike cleared at least 25ft from exterior toe
Location: Looking SW
Notes: Toe of SE dike needing additional work to clear exterior toe area
Location: Looking NE
Page: 03
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Toe
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 7
N40 11.200 W81 52.172
Photo #: 8
N40 11.200 W81 52.172
Description: Slope
Notes: General condition of exterior slope of SE dike
Location: Looking NE
Notes: General condition of exterior slope of SE dike
Location: Looking SW
Page: 04
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Slope
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 9
N40 11.143 W81 52.232
Photo #: 10
N40 11.146 W81 52.227
Description: Other
Notes: Old CMP culverts along exterior toe of SE dike
Location:
Notes: Old concrete culvert near old CMP pipes
Location:
Page: 05
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Other
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 11
N40 11.089 W81 52.302
Photo #: 12
N40 11.100 W81 52.299
Description: Culvert
Notes: General condition of of slope above access road to outfall pipe discharge
Location:
Notes: Outlet of discharge structure
Location:
Page: 06
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Slope
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 13
N40 11.542 W81 51.863
Photo #: 14
N40 11.541 W81 51.862
Description: Groin
Notes: General condition of north dike exterior slope
Location: East end looking west
Notes: Right exterior groin and abutment north dike
Location:
Page: 07
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Slope
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 15
N40 11.560 W81 52.020
Photo #: 16
N40 11.543 W81 52.293
Description: Crest
Notes: General condition of exterior toe of north dike along county road
Location: Looking west
Notes: General condition of crest outside of fence
Location: Looking east
Page: 08
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Toe
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 17
N40 11.108 W81 52.350
Photo #: 18
N40 11.106 W81 52.317
Description: Slope
Notes: Crest SE dike above coal haul road
Location:
Notes: SE dike exterior slope above coal haul road
Location: SW corner looking NW
Page: 09
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Crest
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 19
N40 11.103 W81 52.392
Photo #: 20
N40 11.142 W81 52.443
Description: Slope
Notes: General condition of SW dike exterior toe and slope
Location: Looking west
Notes: General condition of SW dike exterior slope
Location: Looking east
Page: 10
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Toe
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 21
N40 11.140 W81 52.448
Photo #: 22
N40 11.128 W81 52.472
Description: —
Notes: Metal Cleaning Waste Tank (MCWT) east dike general condition
Location:
Notes: South MCWT dike general condition
Location:
Page: 11
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Other
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 23
N40 11.158 W81 52.474
Photo #: 24
N40 11.159 W81 52.470
Description: —
Notes: West MCWT dike general condition
Location:
Notes: North side of MCWT about SW dike of Ash Pond
Location:
Page: 12
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Other
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 25
N40 11.218 W81 52.547
Photo #: 26
N40 11.222 W81 52.544
Description: Crest
Notes: General condition of SW dike exterior toe and slope
Location: Looking east
Notes: General condition of SW dike crest
Location: Looking se
Page: 13
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Other
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 27
N40 11.224 W81 52.538
Photo #: 28
N40 11.235 W81 52.549
Description: Other
Notes: Interior slope of SW dike in bottom ash pond
Location: Looking SE
Notes: Bottom ash discharge pipes crossing top of berm at SW corner. Wood vegetation is starting to develop.
Location:
Page: 14
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Slope
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 29
N40 11.229 W81 52.513
Photo #: 30
N40 11.226 W81 52.517
Description: General
Notes: General condition of bottom ash outlet pipes
Location: Bottom ash pond
Notes: Bottom ash canal
Location: Bottom ash pond
Page: 15
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Other
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 31
N40 11.236 W81 52.542
Photo #: 32
N40 11.315 W81 52.446
Description: Crest
Notes: Toe and exterior slope on west side dike at bottom ash pond
Location: Looking north
Notes: Crest and interior slope of west side dike at bottom ash pond
Location: Looking southth
Page: 16
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Slope
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 33
N40 11.532 W81 52.213
Photo #: 34
N40 11.513 W81 51.919
Description: Slope
Notes: North dike haul road crest
Location: West end looking east
Notes: General condition of North dike interior slope
Location: Looking west
Page: 17
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Crest
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 35
N40 11.413 W81 51.909
Photo #: 36
N40 11.415 W81 51.909
Description: Slope
Notes: Overview of Ash Pond Complex
Location: Looking SW from NE corner
Notes: SE dike interior slope
Location:
Page: 18
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: General
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 37
N40 11.177 W81 52.245
Photo #: 38
N40 11.169 W81 52.253
Description: Other
Notes: SE dike above coal haul road
Location: Looking SW from clearwater pond
Notes: Outlet riser in clearwater pond
Location:
Page: 19
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Slope
-
Date: August 28, 2018
Inspector: B. Palmer
Photo #: 39
N40 11.155 W81 52.331
Photo #: 40
N40 11.148 W81 52.321
Description: Other
Notes: General condition of walkway to outlet riser
Location: Clearwater Pond
Notes: Discharge opening at outlet riser
Location: Clearwater Pond
Page: 20
AEP GES Dam Inspection
Plant Name: Conesville
Unit: Ash Pond
Description: Other
-
ATTACHMENT B
Inspection / Instrumentation Location Maps
-
---Page Intentionally Left Blank---
-
740 740
750
750
750
750
750
750
760
760
760
760
760
760
760
760
760
760
760
760
760
760
760
760
760
760
760
760
760
760
760
760
770
770
770
770
770770
770
770
770
770
770
770
770
770
780
780
780
780
780
790
790
790
790
800
800
800
810
810
DOCK
CONVEYOR
748.65
808.80
104
105
760.2W.E.
758.1
758.1W.E.
W.E.
749.6W.E.
755.3W.E.
797.4760.3
801.1
770.9
803.2
764.9
806.6
806.7804.9
809.2
770.5
749.3
763.6
762.7
766.7
762.2
775.1
774.7
761.5762.6
773.2
759.3773.1773.5
759.3
760.9758.7
761.2758.9
761.3758.2
758.5
760.5757.3758.4
811.8
760.9758.3
760.3
760.3757.4
760.4815.6
760.5760.7
759.9759.1815.6
760.4759.1
813.4816.8
759.3
760.3
760.7815.9
760.5811.1
760.8814.9
761.3815.1
760.5761.1811.7
812.8
760.4760.8
766.9
760.9
760.7
762.9
763.5
765.5
763.8
763.1
763.1
775.4
775.9
759.6
771.4
751.6
750.9
747.3
760.6
758.7
750.9
751.3
752.7
752.7
764.4
747.5
797.3
796.5
761.6756.9
750.7
766.6
759.7
759.6
759.2
767.4
758.3
757.1
757.8
767.1
768.3
768.7
767.2
762.3
767.4
767.1
766.4
751.5
749.4
759.3
758.5
763.1
763.6
761.6
768.7
766.7
757.3
767.6
769.3
767.1
761.1
761.2
762.7
763.7
765.4
762.1
765.3
759.1
767.2
758.8
763.3
758.9
757.9
759.7
767.5
758.9
766.8
768.9
759.8803.6
805.3
755.2
761.5
766.4
770.5
777.3
784.4
789.1
793.4
797.4
807.2
809.5
740.7
774.5772.9773.1
767.4766.4
773.9773.3773.5773.7
773.9773.9
738.7737.8
737.8736.8736.5737.1
737.7737.5
764.5
762.3
762.3
762.4
767.0
766.2
774.4
751.4
768.9757.8
804.7
749.4762.7
747.5
747.1
752.2
774.8
774.1
755.6
750.7
768.2
759.6
757.8
765.1
765.6
764.2800.2
763.2759.4
769.4
755.7
763.8
762.3
766.7763.9
816.1
757.7
762.3 762.9
764.5
764.2
764.4
764.7
780.6
778.4
769.9
761.9
766.4
768.4
775.7
768.8
768.8
766.5
764.8
759.1
762.4
765.7
763.2
767.9
751.7
752.2
750.8
750.8
751.7
757.7
757.9
768.2
756.9
757.6
756.9
766.7
759.9
762.4
762.1
759.9
762.7
762.8
766.4
768.3
757.8
764.3
765.7
770.9
763.1
759.9
771.1
772.1806.1
774.3
761.2
IMAGERY DATE: MARCH 2006
UNIT: U.S. SURVEY FEET
ZONE: OHIO NORTHERN
DATUM: NORTH AMERICAN DATUM OF 1983 (NAD83)
HORIZONTAL CONTROL:
W E
N
21
44
00
02144000
2144500
2145000
21
44
50
0
2143000
21
42
50
0
21
43
00
0
21
43
50
02143500
21
45
00
0
2147000
21
46
50
0
21
47
00
0
21
47
50
02147500
21
45
50
02145500
2146000
2146500
21
46
00
0
190500
190000
190500
191000191000
189000189000
189500
190000
189500
191500
21
41
50
02141500
2142000
2142500
21
42
00
0
192000
191500
192000
192500192500
P13
P11
B-7
PZ-0901
PZ-0902
PZ-0903
PZ-0904
P12
DATE:
SCALE:1"=400'
DRN BY:AG
1 RIVERSIDE PLAZA
COLUMBUS, OH 43215
AEP SERVICE CORP.
DWG NO:FIGURE 2CONESVILLE POWER STATION
INSTRUMENTATION PLAN
ASH POND COMPLEX
PL
OT
DA
TE:
PL
OT
TI
ME:
BY:s279452
2:2
6:4
4
PM
9/21/2018
PZ-0902R
-
ATTACHMENT C
Instrumentation Data
-
---Page Intentionally Left Blank---
-
720
725
730
735
740
745
750
755
760
765
ELE
VA
TIO
N, F
EE
T
TIME, QUARTERLY
FIGURE 3 - INSTRUMENTATION DATA.
FAP CWP B-7 P-11 P-12 P-13 B-0901 B-0902 PZ-0902R B-0903 B-0904 BAP