2018 Annual Dam and Dike Inspection Report...Inspection photos are included in Attachement A....

41
2018 Annual Dam and Dike Inspection Report Ash Pond Complex Conesville Plant AEP Generation Resources, Inc. Coshocton County, Ohio August 28, 2018 Prepared for: AEP Generation Resources Conesville Plant Conesville, Ohio Prepared by: American Electric Power Service Corporation 1 Riverside Plaza Columbus, OH 43215 GERS-18-037

Transcript of 2018 Annual Dam and Dike Inspection Report...Inspection photos are included in Attachement A....

  • 2018 Annual Dam and Dike Inspection Report

    Ash Pond Complex

    Conesville Plant

    AEP Generation Resources, Inc.

    Coshocton County, Ohio

    August 28, 2018

    Prepared for: AEP Generation Resources – Conesville Plant

    Conesville, Ohio

    Prepared by: American Electric Power Service Corporation

    1 Riverside Plaza

    Columbus, OH 43215

    GERS-18-037

  • ---Page Intentionally Left Blank---

  • Pages 3 of 10

    ---Page Intentionally Left Blank---

  • Pages 4 of 10

    Table of Contents 1.0 Introduction ............................................................................................................................................. 6

    2.0 Description of Impoundment .................................................................................................................. 6

    2.1 Definitions of Visual Observations and deficiencies .......................................................................... 6

    2.2 Fly Ash Pond Complex ....................................................................................................................... 7

    3.0 Review of Available Information (257.83(b)(1)(i)) ................................................................................ 7

    4.0 Inspection (257.83(b) (1)(ii)) .................................................................................................................. 8

    4.1 Metals Cleaning Waste Tank Dike (Non-CCR).................................................................................. 8

    4.2 Ash Pond Complex ............................................................................................................................. 8

    4.2.1 Changes in geometry since last inspection (257.83(b)(2)(i)) ....................................................... 8

    4.2.2 Instrumentation (257.83(b)(2)(ii)) ............................................................................................... 8

    4.2.3 Impoundment Characteristics (257.83(b)(2)(iii, iv, v)) ............................................................... 8

    4.2.4 Visual inspection (257.83(b)(2)(i)) .............................................................................................. 9

    4.2.5 Changes that effect stability or operation (257.83(b)(2)(vii)) ...................................................... 9

    5.0 Summary of Findings .............................................................................................................................. 9

    5.1 General Observations .......................................................................................................................... 9

    5.2 Maintenance Items ............................................................................................................................ 10

    5.3 Items to Monitor ............................................................................................................................... 10

    5.4 Deficiencies (257.83(b)(2)(vi)) ......................................................................................................... 10

    Attachments Attachment A – Pictures

    Attachment B – Site Maps

    Attachment C – Instrumentation Data

  • Pages 5 of 10

    ---Page Intentionally Left Blank---

  • Pages 6 of 10

    1.0 Introduction This report was prepared by AEP- Geotechnical Engineering Services (GES) section, in part, to fulfill

    requirements of 40 CFR 257.83 and the Ohio Department of Natural Resource (ODNR), Division of Water

    Dam Inspection Section and to provide AEP Generation Resources and the Conesville Power Station with

    an evaluation of the facility.

    Ms. Beth Mullen, Plant Environmental Coordinator for the Conesville Plant provided onsite coordination

    for inspection activities. The inspection was performed on August 28, 2018 by Brian Palmer of AEP

    Geotechnical Engineering. Weather conditions were overcast with temperatures in low 70°s F to upper 80°s

    F and 0.4-in of precipitation occurred in the preceding seven days prior to the inspection.

    2.0 Description of Impoundment

    2.1 Definitions of Visual Observations and deficiencies

    This summary of the visual observations uses terms to describe the general appearance or condition of an

    observed item, activity or structure. The meaning of these terms is as follows:

    Good: A condition or activity that is generally better or slightly better than what is

    minimally expected or anticipated from a design or maintenance point of view.

    Fair or A condition or activity that generally meets what is minimally Satisfactory:

    expected or anticipated from a design or maintenance point of view.

    Poor: A condition or activity that is generally below what is minimally expected or

    anticipated from a design or maintenance point of view.

    Minor: A reference to an observed item (e.g., erosion, seepage, vegetation, etc.) where the

    current maintenance condition is below what is normal or desired, but which is not

    currently causing concern from a structure safety or stability point of view.

    Significant: A reference to an observed item (e.g. erosion, seepage, vegetation, etc.) where the

    current maintenance program has neglected to improve the condition. Usually,

    conditions that have been previously identified in the previous inspections, but

    have not been corrected.

    Excessive: A reference to an observed item (e.g., erosion, seepage, vegetation, etc.) where the

    current maintenance condition is above or worse than what is normal or desired,

    and which may have affected the ability of the observer to properly evaluate the

    structure or particular area being observed or which may be a concern from a

    structure safety or stability point of view.

    This document also uses the definition of a “deficiency” as referenced in the CCR rule section

    §257.83(b)(5) Inspection Requirements for CCR Surface Impoundments. This definition has been

    assembled using the CCR rule Preamble as well as guidance from MSHA, “Qualifications for

    Impoundment Inspection” CI-31, 2004. These guidance documents further elaborate on the definition of

    deficiency. Items not defined by deficiency are considered maintenance or items to be monitored.

    A “deficiency” is some evidence that a dam has developed a problem that could impact the structural

    integrity of the dam. There are four general categories of deficiencies. These four categories are described

    below:

  • Pages 7 of 10

    1. Uncontrolled Seepage

    a. Uncontrolled seepage is seepage that is not behaving as the design engineer has

    intended. An example of uncontrolled seepage is seepage that comes through or

    around the embankment and is not picked up and safely carried off by a drain. Seepage

    that is collected by a drain can still be uncontrolled if it is not safely collected and

    transported, such as seepage that is not clear. Seepage that is unable to be measured

    and/or observe it is considered uncontrolled seepage. [Wet or soft areas are not

    considered as uncontrolled seepage, but can lead to this type of deficiency. These

    areas should monitored my frequently.]

    2. Displacement of the Embankment

    a. Displacement of the embankment is large scale movement of part of the dam. Common

    signs of displacement are cracks, scraps, bulges, depressions, sinkholes and slides.

    3. Blockage of Control Features

    a. Blockage of Control Features is the restriction of flow at spillways, decant or pipe

    spillways, or drains.

    4. Erosion

    a. Erosion is the gradual movement of surface material by water, wind or ice. Erosion is

    considered a deficiency when it is more than a minor routine maintenance item.

    2.2 Fly Ash Pond Complex

    The fly ash pond complex is comprised of diked embankments on the north, southeast, and south sides.

    County Road 273 runs along the toe of the north dike, a Plant haul road run along the top of the north dike,

    and a coal haul road runs along the crest or exterior of the Southeast dike. The northwest side of the Ash

    Pond Complex is located adjacent to a closed landfill area. There are three main ponds within the Ash

    Pond Complex as listed below.

    List of Main Ponds within the Ash Pond Complex

    Fly Ash Pond

    Bottom Ash Pond

    Clearwater Pond

    The Fly Ash Pond has internal splitter dikes that divide it into areas referred to as Ponds 1, 2, 3, and 4. The

    Bottom Ash Pond has an internal splitter dike creating the Bottom Ash Pond and Pond 5. Water enters the

    Ash Pond complex through either the Bottom Ash Pond or Pond 1. From the Bottom Ash Pond or Pond 1

    water flows through the Ash Pond Complex in order from Pond 2, Pond 3, Pond 4, and Pond 5 before

    reaching the Clearwater Pond where it is discharged to the Holding Pond.

    The inspection included the dike for the Metals Waste Cleaning tank as it is adjacent to the South dike of the

    Ash Pond complex

    3.0 Review of Available Information (257.83(b)(1)(i)) A review of available information regarding the status and condition of the Ash Pond Complex, which

    include files available in the operating record, such as design and construction information, previous

    periodic structural stability assessments, previous 7 day inspection reports, and previous annual inspections

    has been conducted. Based on the review of the data there were no signs of actual or potential structural

    weakness or adverse conditions.

  • Pages 8 of 10

    4.0 Inspection (257.83(b) (1)(ii))

    4.1 Metals Cleaning Waste Tank Dike (Non-CCR)

    A visual inspection of the dike for Metals Cleaning Waste Tank was conducted to identify any signs

    of distress or malfunction of the secondary containment system. Overall the facility is in good

    condition. The secondary containment is functioning as intended with no signs of potential structural

    weakness or conditions which would be disruptive to the safe operation of the containment system.

    Inspection photos are included in Attachement A. Additional pictures taken during the inspection can

    be made available upon request.

    4.2 Ash Pond Complex

    4.2.1 Changes in geometry since last inspection (257.83(b)(2)(i))

    No modifications have been made to the exterior geometry of the Ash Pond Complex since the 2017

    annual inspection.

    4.2.2 Instrumentation (257.83(b)(2)(ii))

    The location and type of instrumentation is shown on Figure 2 in Attachment B. The maximum

    recorded readings of each instrument since the previous annual inspection is shown in Table 1

    below.

    Table 1 – INSTRUMENTATION DATA

    Ash Pond Complex

    Instrument Type

    Maximum Reading

    since last annual

    inspection

    Date of reading

    B7 Piezometer 729.53 2/27/2018

    P-11 Piezometer 733.92 2/27/2018

    P-12 Piezometer 747.82 2/27/2018

    P-13 Piezometer 749.9 4/24/2018

    B-0901 Piezometer 732.78 2/27/2018

    B-0902 Piezometer 762.46 2/27/2018

    B-0902R Piezometer 739.07 09/10/2018

    B-0903 Piezometer 749.02 2/27/2018

    B-0904 Piezometer 743.29 2/27/2018

    NOTE: A review of the piezometer construction and locations identified issues with the construction of

    B-0902 and B-0903 resulting in B-0902R replacing B-0902 in May 2018 and B-0903 was abandoned as

    it is replicated by P-12.

    Piezometers readings were generally consistent since the last inspection. Piezometer well

    hydrographs are included in Attachment C. B-0902R is discretely screened in the embankment and

    better characterizes water elevations in the dike.

    4.2.3 Impoundment Characteristics (257.83(b)(2)(iii, iv, v))

    Table 2 is a summary of the minimum, maximum, and present depth and elevation of the impounded

    water & CCR based on the bathymetric survey conducted Nov. 9, 2017 and water elevation at time

    of inspection; the storage capacity of the impounding structure; and the approximate volume of the

    impounded CCR at the time of the bathymetric survey.

  • Pages 9 of 10

    Table 2 – IMPOUNDMENT CHARACTERISTIC DATA

    Impoundment Characteristics Ash Pond Complex

    Approximate Minimum depth of impounded water

  • Pages 10 of 10

    vegetation along the embankments was well established. The crest did not contain any ruts or

    other signs of instability.

    3) The Clearwater Pond hydraulic structure is in good condition. There were no signs of deterioration of the concrete or steel structures. The maximum pool elevation (762 ft. msl) is

    also clearly marked on the structure. Stop logs were available for use. Flow within the

    discharge pipe appeared unobstructed.

    5.2 Maintenance Items

    The following maintenance items were identified during the visual inspection, see inspection map for

    locations:

    Metals Cleaning Waste Tank Dike

    1) No specific items identified related to the Metals Cleaning Waste Tank Dike.

    Ash Pond Complex

    2) Continue work to clear the vegetation on the exterior embankment along the Coal Haul road to the toe of the embankment and groin ditch plus a minimum of 25 ft. along the opposite slope

    and ascertain the origin of the seepage observed within this area.

    3) Work on the removal of vegetation at the toe of the north dike along County Road 273.

    4) Continue monitoring and taking corrective actions related to groundhogs and other burrowing animals.

    5.3 Items to Monitor

    The following items were identified during the visual inspection as items to be monitored, see

    inspection map for locations:

    Metals Cleaning Waste Tank Dike

    1) No specific items identified related to the Metals Cleaning Waste Tank Dike.

    Ash Pond Complex

    2) The abandoned culverts under original coal haul road need to be inspected quarterly for seepage.

    3) Continue to monitor for areas of erosion and repair as necessary.

    5.4 Deficiencies (257.83(b)(2)(vi))

    There were no signs of structural weakness or disruptive conditions that were observed at the time of

    the inspection that would require additional investigation or remedial action. There were no

    deficiencies noted during this inspection or any of the periodic 7-day or 30-day inspections. A

    deficiency is defined as either 1) uncontrolled seepage, 2) displacement of the embankment, 3)

    blockage of control features, or 4) erosion, more than minor maintenance. If any of these conditions

    occur before the next annual inspection contact AEP Geotechnical Engineering immediately

  • ---Page Intentionally Left Blank---

  • ATTACHMENT A

    Photos

  • ---Page Intentionally Left Blank---

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 1

    N40 11.366 W81 51.965

    Photo #: 2

    N40 11.351 W81 51.979

    Description: Groin

    Notes: Crest of SE dike haul road

    Location: Looking SW

    Notes: Exterior slope/crest of SE dike

    Location: NE corner looking SW

    Page: 01

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Crest

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 3

    N40 11.362 W81 51.964

    Photo #: 4

    N40 11.332 W81 51.987

    Description: Other

    Notes: Left groin exterior slope of SE dike

    Location:

    Notes: Groundhog hole on slope, identified as part of plant inspection and flagged for repair. Groundhog removed

    Location:

    Page: 02

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Groin

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 5

    N40 11.310 W81 52.014

    Photo #: 6

    N40 11.309 W81 52.016

    Description: Toe

    Notes: Toe of SE dike cleared at least 25ft from exterior toe

    Location: Looking SW

    Notes: Toe of SE dike needing additional work to clear exterior toe area

    Location: Looking NE

    Page: 03

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Toe

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 7

    N40 11.200 W81 52.172

    Photo #: 8

    N40 11.200 W81 52.172

    Description: Slope

    Notes: General condition of exterior slope of SE dike

    Location: Looking NE

    Notes: General condition of exterior slope of SE dike

    Location: Looking SW

    Page: 04

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Slope

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 9

    N40 11.143 W81 52.232

    Photo #: 10

    N40 11.146 W81 52.227

    Description: Other

    Notes: Old CMP culverts along exterior toe of SE dike

    Location:

    Notes: Old concrete culvert near old CMP pipes

    Location:

    Page: 05

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Other

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 11

    N40 11.089 W81 52.302

    Photo #: 12

    N40 11.100 W81 52.299

    Description: Culvert

    Notes: General condition of of slope above access road to outfall pipe discharge

    Location:

    Notes: Outlet of discharge structure

    Location:

    Page: 06

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Slope

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 13

    N40 11.542 W81 51.863

    Photo #: 14

    N40 11.541 W81 51.862

    Description: Groin

    Notes: General condition of north dike exterior slope

    Location: East end looking west

    Notes: Right exterior groin and abutment north dike

    Location:

    Page: 07

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Slope

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 15

    N40 11.560 W81 52.020

    Photo #: 16

    N40 11.543 W81 52.293

    Description: Crest

    Notes: General condition of exterior toe of north dike along county road

    Location: Looking west

    Notes: General condition of crest outside of fence

    Location: Looking east

    Page: 08

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Toe

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 17

    N40 11.108 W81 52.350

    Photo #: 18

    N40 11.106 W81 52.317

    Description: Slope

    Notes: Crest SE dike above coal haul road

    Location:

    Notes: SE dike exterior slope above coal haul road

    Location: SW corner looking NW

    Page: 09

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Crest

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 19

    N40 11.103 W81 52.392

    Photo #: 20

    N40 11.142 W81 52.443

    Description: Slope

    Notes: General condition of SW dike exterior toe and slope

    Location: Looking west

    Notes: General condition of SW dike exterior slope

    Location: Looking east

    Page: 10

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Toe

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 21

    N40 11.140 W81 52.448

    Photo #: 22

    N40 11.128 W81 52.472

    Description: —

    Notes: Metal Cleaning Waste Tank (MCWT) east dike general condition

    Location:

    Notes: South MCWT dike general condition

    Location:

    Page: 11

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Other

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 23

    N40 11.158 W81 52.474

    Photo #: 24

    N40 11.159 W81 52.470

    Description: —

    Notes: West MCWT dike general condition

    Location:

    Notes: North side of MCWT about SW dike of Ash Pond

    Location:

    Page: 12

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Other

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 25

    N40 11.218 W81 52.547

    Photo #: 26

    N40 11.222 W81 52.544

    Description: Crest

    Notes: General condition of SW dike exterior toe and slope

    Location: Looking east

    Notes: General condition of SW dike crest

    Location: Looking se

    Page: 13

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Other

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 27

    N40 11.224 W81 52.538

    Photo #: 28

    N40 11.235 W81 52.549

    Description: Other

    Notes: Interior slope of SW dike in bottom ash pond

    Location: Looking SE

    Notes: Bottom ash discharge pipes crossing top of berm at SW corner. Wood vegetation is starting to develop.

    Location:

    Page: 14

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Slope

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 29

    N40 11.229 W81 52.513

    Photo #: 30

    N40 11.226 W81 52.517

    Description: General

    Notes: General condition of bottom ash outlet pipes

    Location: Bottom ash pond

    Notes: Bottom ash canal

    Location: Bottom ash pond

    Page: 15

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Other

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 31

    N40 11.236 W81 52.542

    Photo #: 32

    N40 11.315 W81 52.446

    Description: Crest

    Notes: Toe and exterior slope on west side dike at bottom ash pond

    Location: Looking north

    Notes: Crest and interior slope of west side dike at bottom ash pond

    Location: Looking southth

    Page: 16

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Slope

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 33

    N40 11.532 W81 52.213

    Photo #: 34

    N40 11.513 W81 51.919

    Description: Slope

    Notes: North dike haul road crest

    Location: West end looking east

    Notes: General condition of North dike interior slope

    Location: Looking west

    Page: 17

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Crest

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 35

    N40 11.413 W81 51.909

    Photo #: 36

    N40 11.415 W81 51.909

    Description: Slope

    Notes: Overview of Ash Pond Complex

    Location: Looking SW from NE corner

    Notes: SE dike interior slope

    Location:

    Page: 18

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: General

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 37

    N40 11.177 W81 52.245

    Photo #: 38

    N40 11.169 W81 52.253

    Description: Other

    Notes: SE dike above coal haul road

    Location: Looking SW from clearwater pond

    Notes: Outlet riser in clearwater pond

    Location:

    Page: 19

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Slope

  • Date: August 28, 2018

    Inspector: B. Palmer

    Photo #: 39

    N40 11.155 W81 52.331

    Photo #: 40

    N40 11.148 W81 52.321

    Description: Other

    Notes: General condition of walkway to outlet riser

    Location: Clearwater Pond

    Notes: Discharge opening at outlet riser

    Location: Clearwater Pond

    Page: 20

    AEP GES Dam Inspection

    Plant Name: Conesville

    Unit: Ash Pond

    Description: Other

  • ATTACHMENT B

    Inspection / Instrumentation Location Maps

  • ---Page Intentionally Left Blank---

  • 740 740

    750

    750

    750

    750

    750

    750

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    760

    770

    770

    770

    770

    770770

    770

    770

    770

    770

    770

    770

    770

    770

    780

    780

    780

    780

    780

    790

    790

    790

    790

    800

    800

    800

    810

    810

    DOCK

    CONVEYOR

    748.65

    808.80

    104

    105

    760.2W.E.

    758.1

    758.1W.E.

    W.E.

    749.6W.E.

    755.3W.E.

    797.4760.3

    801.1

    770.9

    803.2

    764.9

    806.6

    806.7804.9

    809.2

    770.5

    749.3

    763.6

    762.7

    766.7

    762.2

    775.1

    774.7

    761.5762.6

    773.2

    759.3773.1773.5

    759.3

    760.9758.7

    761.2758.9

    761.3758.2

    758.5

    760.5757.3758.4

    811.8

    760.9758.3

    760.3

    760.3757.4

    760.4815.6

    760.5760.7

    759.9759.1815.6

    760.4759.1

    813.4816.8

    759.3

    760.3

    760.7815.9

    760.5811.1

    760.8814.9

    761.3815.1

    760.5761.1811.7

    812.8

    760.4760.8

    766.9

    760.9

    760.7

    762.9

    763.5

    765.5

    763.8

    763.1

    763.1

    775.4

    775.9

    759.6

    771.4

    751.6

    750.9

    747.3

    760.6

    758.7

    750.9

    751.3

    752.7

    752.7

    764.4

    747.5

    797.3

    796.5

    761.6756.9

    750.7

    766.6

    759.7

    759.6

    759.2

    767.4

    758.3

    757.1

    757.8

    767.1

    768.3

    768.7

    767.2

    762.3

    767.4

    767.1

    766.4

    751.5

    749.4

    759.3

    758.5

    763.1

    763.6

    761.6

    768.7

    766.7

    757.3

    767.6

    769.3

    767.1

    761.1

    761.2

    762.7

    763.7

    765.4

    762.1

    765.3

    759.1

    767.2

    758.8

    763.3

    758.9

    757.9

    759.7

    767.5

    758.9

    766.8

    768.9

    759.8803.6

    805.3

    755.2

    761.5

    766.4

    770.5

    777.3

    784.4

    789.1

    793.4

    797.4

    807.2

    809.5

    740.7

    774.5772.9773.1

    767.4766.4

    773.9773.3773.5773.7

    773.9773.9

    738.7737.8

    737.8736.8736.5737.1

    737.7737.5

    764.5

    762.3

    762.3

    762.4

    767.0

    766.2

    774.4

    751.4

    768.9757.8

    804.7

    749.4762.7

    747.5

    747.1

    752.2

    774.8

    774.1

    755.6

    750.7

    768.2

    759.6

    757.8

    765.1

    765.6

    764.2800.2

    763.2759.4

    769.4

    755.7

    763.8

    762.3

    766.7763.9

    816.1

    757.7

    762.3 762.9

    764.5

    764.2

    764.4

    764.7

    780.6

    778.4

    769.9

    761.9

    766.4

    768.4

    775.7

    768.8

    768.8

    766.5

    764.8

    759.1

    762.4

    765.7

    763.2

    767.9

    751.7

    752.2

    750.8

    750.8

    751.7

    757.7

    757.9

    768.2

    756.9

    757.6

    756.9

    766.7

    759.9

    762.4

    762.1

    759.9

    762.7

    762.8

    766.4

    768.3

    757.8

    764.3

    765.7

    770.9

    763.1

    759.9

    771.1

    772.1806.1

    774.3

    761.2

    IMAGERY DATE: MARCH 2006

    UNIT: U.S. SURVEY FEET

    ZONE: OHIO NORTHERN

    DATUM: NORTH AMERICAN DATUM OF 1983 (NAD83)

    HORIZONTAL CONTROL:

    W E

    N

    21

    44

    00

    02144000

    2144500

    2145000

    21

    44

    50

    0

    2143000

    21

    42

    50

    0

    21

    43

    00

    0

    21

    43

    50

    02143500

    21

    45

    00

    0

    2147000

    21

    46

    50

    0

    21

    47

    00

    0

    21

    47

    50

    02147500

    21

    45

    50

    02145500

    2146000

    2146500

    21

    46

    00

    0

    190500

    190000

    190500

    191000191000

    189000189000

    189500

    190000

    189500

    191500

    21

    41

    50

    02141500

    2142000

    2142500

    21

    42

    00

    0

    192000

    191500

    192000

    192500192500

    P13

    P11

    B-7

    PZ-0901

    PZ-0902

    PZ-0903

    PZ-0904

    P12

    DATE:

    SCALE:1"=400'

    DRN BY:AG

    1 RIVERSIDE PLAZA

    COLUMBUS, OH 43215

    AEP SERVICE CORP.

    DWG NO:FIGURE 2CONESVILLE POWER STATION

    INSTRUMENTATION PLAN

    ASH POND COMPLEX

    PL

    OT

    DA

    TE:

    PL

    OT

    TI

    ME:

    BY:s279452

    2:2

    6:4

    4

    PM

    9/21/2018

    PZ-0902R

  • ATTACHMENT C

    Instrumentation Data

  • ---Page Intentionally Left Blank---

  • 720

    725

    730

    735

    740

    745

    750

    755

    760

    765

    ELE

    VA

    TIO

    N, F

    EE

    T

    TIME, QUARTERLY

    FIGURE 3 - INSTRUMENTATION DATA.

    FAP CWP B-7 P-11 P-12 P-13 B-0901 B-0902 PZ-0902R B-0903 B-0904 BAP