EMAS Procurement Case Study

TF Green Airport

Providence, RI

Runway 5 Extension

Page 3: 2016 ACC Airports Technical Workshop

#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC

Runway 5 Extension

• Runway 5 program

($87 million)

• Extension - $40 million

• Construction Safety and Phasing Plan including Safety Assessment

• ISI Envision Gold Award

• EMAS RSAEMAS

Runway Safety Area

Page 4: 2016 ACC Airports Technical Workshop

#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC

Runway 5 Extension Timeline

Page 5: 2016 ACC Airports Technical Workshop

#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC

Runway 5 Extension Timeline

Page 6: 2016 ACC Airports Technical Workshop

#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC

FAA PGL for EMAS Procurement

• Acknowledges two manufacturers meeting FAA AC

• Required for AIP projects less than 30% design

• Buy American

• 1-Year warranty

• Sole-source requires FAA approval

• Competitive procurement process (RFI/RFP)

• Proposal requirements

• Involves maintenance costs (life-cycle)

Page 7: 2016 ACC Airports Technical Workshop

#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC

How to select?

Stop at 70 knots

FAA PGL?

Maintenance

Sustainability

FAA ALSF-2

AIP vs. PFC

Buy American

New product?

Project constraints

How to evaluate?

How to contract?

Costs(Const,Life-Cycle)

Page 8: 2016 ACC Airports Technical Workshop

#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC

Procurement by RIAC

• Designs approved by FAA by both manufacturers

• FAA Region concurrence

• Separate RFP from runway – two alternate bids for furnish and install

• Price proposal – first time cost only

• Successful EMAS assigned to runway general contract

Page 9: 2016 ACC Airports Technical Workshop

#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC

Results

• Cardi construction (Runway 5 Extension contractor) submitted bid

• Bid both alternates (Zodiac and Runway Safe)

• Zodiac was lower price

• Saved more than $1 million from sole-source

• Construction progress currently on budget and ahead of schedule

• EMAS construction in 2017