2014-2015 - Tunisia Interim Country Strategy Paper · 4 Tunisia: Interim Country Strategy Paper -...
Transcript of 2014-2015 - Tunisia Interim Country Strategy Paper · 4 Tunisia: Interim Country Strategy Paper -...
TunisiaInterim Country Strategy Paper2014 - 2015
This strategy interim was prepared between June and September 2013. The interim strategy was approved by theBoard of the African Development Bank Group on March 5, 2014.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 3
A f r i c a n D e v e l o p m e n t B a n k
Country Strategy Paper Drafting Team
Design Team:
V. CASTEL, Chief Country Economist, ORNA
K. ABDERRAHIM-BEN SALAH, Economist, ORNA
P. TRAPE, Principal Country Economist, ORNA
M. CHAUVIN, Economist, ORNA
Team Members:
A. B. DIALLO, Chief Energy Engineer, ONEC1
A. KESSAB, Governance Expert, OSGE1
A. YAHIAOUI, Chief ICT Expert, ICT4D
A. CHOUCHANE, Chief Research Economist, EDRE1
B. BEN SASSI, Principal Water and Sanitation Officer,
OWAS
C. AMBERT, Senior Strategy Officer, OPSM.0
C. MOLLINEDO-TRUJILLO, Chief Strategist, STRG
F. BOUGAIRE, Principal Water and Sanitation Engineer,
AWF
H. CHAHBANI, Principal Infrastructure Expert, ONRI1
I. HAFSA, Assistant Statistician, ESTA
J. BANDIAKY, Senior Macro-economist, OSGE1
J. MURARA, Chief Socio-economist, OSHD1
K. HASSAMAL, Strategy Analyst, STRG
K. LUMBILA, Senior Economist, OSGE1
L. BOURKANE, Economist, OSHD.2
L. DADE, Regional Financial Management Coordinator,
ORPF.2
L. LANNES, Principal Health Economist, OSHD3
M.DAMAK, Principal Credit Risk Officer, FFMA2
M. GUEYE, Principal Education Economist, OSHD.2
M. OULD TOLBA, Chief Agronomist, OSAN1
S. DAH, Procurement Expert, ORPF1
S. OMAR ELMI, ICT Expert, ICT4D
T. MOURGUES, Consultant, OPSM0
W. DAKPO, Regional Procurement Coordinator, ORPF1
Regional Director:
Jacob KOLSTER, Director, ORNA
Peer Review:
K. MHIRSI, Chief Investment Officer, Mauritius Country
Office
M. NDONG NTAH, Chief Country Economist, ORNB
H. SAMER, Division Manager, OPEV2
S. LARBI, Senior Investment Officer, OPSM3
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 54
A f r i c a n D e v e l o p m e n t B a n k
Table of Contents
11 I Introduction
13 II Country Context and Prospects
13 2.1 Context
A. Political Situation B. Economic Context C. Social Situation D. Environment and Climate Change
25 2.2 Strategic Options
A. Country Strategic Framework B. Challenges and Weaknesses C. Strengths and Opportunities
31 2.3 AID Coordination/Harmonization and AfDB Positioning in the
Country
34 III Bank Group Strategy
34 3.1 Rationale for Bank Group’s Involvement40 3.2 Expected Outcomes and Targets 41 3.3 Risks and Mitigative Measures43 3.4 Implementation Arrangements44 3.5 Country Dialogue Issues
45 IV Conclusions and Recommendation
45 4.1 Conclusions45 4.2 Recommendation
List of Annexes
1. Endnotes
2. Results-Based Logical Framework – Tunisia’s CSP 2014-2015
3. I-CSP 2012-2013 Completion Report and Portfolio Performance Review (2013)
4. Tunisia’s Portfolio (UA) (September 2013)
5. Trends in Tunisia’s Sovereign Ratings
6. IMF: USD 1.74 Billion Standby Arrangement
7. Simulation in Terms of Loans
8. Poverty and Unemployment in the Regions
9. List of Economic and Sector Studies on Tunisia Carried out Since 2011
10. Status of Implementation of AfDB Budget Support Measures in 2011 and 2012
11. Civil Society Involvement in Strategy Preparation
12. Public Finance and Procurement Management Systems: Bank’s Risks and Fiduciary Strategy
12. Medium- and Long-Term Debt Sustainability Analysis
List of Figures
1. Contribution to the Growth of Key Sectors of the Economy
2. Macro-Economic Indicators
3. Distribution of FDI Flows by Sector (2012)
4. Governance Index 2012 – Tunisia’s Scores Compared to Africa
5. Freedom of Expression and Accountability and Corruption Perceptions Indices
6. Business Environment: Comparative Ranking with 183 Countries
7. Business Climate: Competitiveness Survey 2012 Results
8. Overall Factor Productivity Growth
9. GCI 2011-2012 Ranking
10. Tunisia’s Main Trading Partners
11. Main Destinations of Tunisian Exports and Complementarities
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 5
A f r i c a n D e v e l o p m e n t B a n k
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 56
A f r i c a n D e v e l o p m e n t B a n k
List of Tables
1. key Partners’ Active Portfolios by Sector (2013 - in USD Million)
2. Alignment with CSP-1 Analysis, Intervention Pillars and the Strategic Framework
3. Loan Scenarios
List of Boxes
1. Innovations in the Approach Adopted
2. Choice of the I-CSP Tool
Currency Equivalents - January 2014
CURRENCY UNIT = DINAR (TND)
UA 1 = TND 2.55
UA 1 = USD 1.54
UA 1 = EUR 1.12
FISCAL YEAR
1 JANUARY - 31 DECEMBER
12. Poverty, Inequality and Polarization in 2005 and 2010
13. Trends in the Overall Unemployment Rate Among University Graduates and Women
14. Trends in the Sophistication Index of Exports of Tunisia and Some ASIAN Countries
15. Indices of Regional Disparities in Terms of Wealth, Health and Education
16. Per Capita Investment in TND for the 1987-2010 Period
17. Rate of Youth Unemployment (Aged 18-30 years) by Type of Certificate (2010)
18. Share of Textile, Mechanical and Electronic Products in the Export Basket
Acronyms and Abbreviations
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 7
A f r i c a n D e v e l o p m e n t B a n k
AFD French Development Agency
AfDB African Development Bank
AMU Arab Maghreb Union
ANC National Constituent Assembly
AWF African Water Facility
B Billion
BCT Central Bank of Tunisia
CEDAW Convention on the Elimination of All Forms of Discrimination Against
Women
CPR Congress for the Republic
CSP Country Strategy Paper
I-CSP Interim Country Strategy Paper
DAC Development Assistance Committee
EBRD European Bank for Reconstruction and Development
EIB European Investment Bank
EU European Union
EUD European Union Delegation
FDI Foreign Direct Investment
FIPA Foreign Investment Promotion Agency
GAFTZ Greater Arab Free Trade Zone
GDP Gross Domestic Product
HDI Human Development Index
ICTs Information and Communication Technologies
IFI International Financial Institution
IMF International Monetary Fund
INS National Institute of Statistics
ITCEQ Tunisian Institute for Competitiveness and Quantitative Studies
JBIC Japan Bank for International Cooperation
KfW KreditanstaltfürWiederaufbau
KTOE Kiloton Oil Equivalent
MDCI Ministry of Development and International Cooperation
MENA Middle East and North Africa
MIC Middle-Income Country
MIC-TAF Middle Income Countries Technical Assistance Fund
NPLs Non-Performing Loans
OECD Organization for Economic Cooperation and Development
OFID OPEC Fund for International Development
OPSCOM Operations Committee
PDAI Integrated Agricultural Development Programme
PISA Programme for International Student Assessment
PISEAU Water Sector Investment Project
PPP Public-Private Partnership
SME Small- and Medium-size Enterprise
TND Tunisian Dinar
TNDB Billion Tunisian Dinars
TNDM Million Tunisian Dinars
UA Bank Group Unit of Account
UAB Billion Units of Account
UAM Million Units of Account
UNCTAD United Nations Conference on Trade and Development
USD United States Dollar
WAEMU West African Economic and Monetary Union
WB World Bank
WEF World Economic Forum
WGI World Governance Indicators
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 58
A f r i c a n D e v e l o p m e n t B a n k
Executive Summary
1. The previous Interim Country Strategy
Paper (I-CSP) was approved by the Bank’s
Board of Directors on 27 February 2012.
In view of political, economic and social
uncertainties in the wake of the Revolution,
the Bank opted for a two-year (2012-2013)
I-CSP. Two priority focus areas for the Bank
were adopted in agreement with Tunisian
authorities after broad consultations with civil
society and the private sector, namely: (i)
Growth and Economic Transformation and
(ii) Inclusion and Reduction of Regional
Disparities.
2. Political Context: In January 2014 the
adoption of the new constitution ended the
Tunisian political crisis that lasted more than
6 months. Indeed the national consensus
signed by the main political parties in October
2013 to end the political crisis resulted in
the appointment of new Prime Minister in
December, and the announcement of his
government in January 2014, following the
adoption of the new Constitution. These two
major political events have ended the lack of
political visibility affecting donors’ intervention
and impeding economic recovery. The transition
process in Tunisia remains one of the most
stable in the sub-region and the forthcoming
elections scheduled for end of 2014 could
establish a renewed virtuous circle.
3. Economic Context: After the Revolution,
the Tunisian economy has been affected by
social movements, political developments
and the fragile global economic context.
However, the relative resilience of the economy
to the two shocks of the 2011 Revolution and
the Euro zone crisis tends to prove that despite
economic uncertainties, Tunisia’s economic
fundamentals are still good. After a GDP
contraction of 1.9% in 2011, the Tunisian
economy recorded a 3.3% growth rate in
2012. This rate is estimated to 2.6% in 2013
(BCT estimate).
4. Government’s Objectives: In a context
of transition, the authorities have opted for a
flexible strategy aimed at appeasing social
and economic demands while preparing
necessary structural reforms. The I-CSP is
based on Government’s guidelines which
were presented in March 2013. This vision
provides for a series of medium- and long-
term structural reforms and investments
aimed at creating conditions for accelerated
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 9
A f r i c a n D e v e l o p m e n t B a n k
growth and job creation to ensure regional
balance and inclusive development.
5. Identification of Bank Group Operations:
the operations were identified on the basis
of the recommendations contained in the
I-CSP 2012-2013 completion report and the
discussions held with the Government and
development partners during missions fielded
in June and September 2013. Besides bilateral
meetings, a workshop was organized with
civil society in September 2013 to examine
the Government’s strategy. The document was
discussed with the new authorities in 2014.
6. Intervention Pillars: the I-CSP prioritizes
the principles of alignment with Government’s
priorities, particularly the creation of (higher
value added) jobs and the reduction of regional
disparities and to that end, it seeks to support
actions to develop an inclusive private sector.
The CSP is a continuation of the previous
I-CSP 2012-2013; however, it seeks to refocus
the Bank’s operation for the 2014-2015
period on two pillars, namely “governance”
and “infrastructure” - in line with the Bank’s
Ten-Year Strategy. Furthermore, in a context
of transition, support within the framework of
the pillars will be provided with a dual temporal
objective of carrying out (i) short-term actions
to ensure rapid achievements and (ii) medium-
/long-term actions to lay the foundations for a
new more inclusive and higher value-added
development model.
7. Instruments and Risks: in view of
challenges on the Bank’s financing, special
emphasis will be laid on technical assistance.
Trends in risk assessment at the regional
and national levels will influence the level
and type of Bank operation (technical
assistance, investment projects or budget
support). In this respect, three scenarios
have been developed to introduce various
possible levels of commitment. Furthermore,
in terms of loans, priority will be given to
the “infrastructure” pillar in the “low” and
“average” scenarios.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 510
A f r i c a n D e v e l o p m e n t B a n k
I. Introduction
1.1 Tunisia is a founding member of the
Bank and its second historic beneficiary.
The Bank’s portfolio in Tunisia, which is the
institution’s second largest portfolio, comprises
16 operations and 24 technical assistance
operations amounting to UA 1.3 billion.
Furthermore, the Bank contributed UA 659
million to the State budget in 2011 and 2012.
1.2 The previous Interim Country Strategy
Paper (I-CSP) was approved by the
Bank’s Board of Directors on 27 February
2012. In view of political, economic and
social uncertainties following the Revolution,
the Bank opted for a two-year (2012-2013)
I-CSP. Two priority areas for Bank intervention
were adopted in agreement with Tunisian
authorities after broad consultations with civil
society and the private sector, namely: (i)
Growth and Economic Transformation and (ii)
Inclusion and Reduction of Regional Disparities.
1.3 Since the approval of the 2012-2013
I-CSP, Tunisia’s transition has been cha-
racterized by a decline in political visibility
and growing economic uncertainty.
1.4 Social movements, particularly in
disadvantaged regions, have continued,
bringing to the fore issues related to (qualitative
and quantitative) employment, the situation
of youths, regional disparities and poverty.
In addition, the crises in Europe and Libya
profoundly affected economic recovery,
already weakened by the Revolution.
1.5 The lack of political visibility during
the period 2012-2013 also contributed to
slowing down economic recovery. Besides
the unrest that took place between February
and July 2013, political uncertainty stemmed
from delays in drafting the new Constitution
and holding new elections.
1.6 Nevertheless, the authorities have
maintained, at the same time, a dialogue
with key development partners on reforms
and investments, even without a 5 years
development plan.
1.7 The authorities are striving to remove
such uncertainties and the adoption of the
Constitution in January 2014 is a major
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 11
A f r i c a n D e v e l o p m e n t B a n k
step in this regard. In fact, all partners and
observers think that the transition in Tunisia
remains one of the most advanced and most
promising in the region.
1.8 In this context, the authorities
requested the Bank to formulate a new
interim strategy for the 2014-2015 period.
The aspects of this strategy were identified
through consultation with the authorities,
development partners, civil society and the
private sector.
1.9 The period covered by this I-CSP will
be aligned with the national agenda.
During this period, political events will be
organized and a new development plan
designed.
1.10 Though the I-CSP is a continuation
of the previous interim strategy, it takes
into account lessons learned by the Bank
regarding its commitment during the transition
period initiated in 2011 and the findings of
many studies carried out.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 512
A f r i c a n D e v e l o p m e n t B a n k
Box 1: Innovations in the ApproachAdopted
1. A commitment level that can be adjustedin the light of risks in order to mobilizemaximum resources.
2. Strong portfolio implementation supportthrough the establishment of an internalcoordination entity (Baobab) and the provision of technical support to accelerateprocurement.
3. Strong mobilization of technical assis-tance resources and advisory capacities tosupport transition and develop the futureportfolio.
4. Refocusing activities on (i) support to enhance the business climate and (ii) improvement of public service delivery andaccess to employment in disadvantagedregions.
5. Strong mobilization of partners and theprivate sector in all operations for leverageeffect.
6. Support in designing the new developmentplan, where appropriate.
7. The logical framework of designed projects should include indicators for monitoring the achievement of the Bank’s2013-2022 Strategy objectives.
II. Country Context and Prospects
2.1 Political, economic and socialcontext
A. Political Situation
2.1.1 After exercising power for over 23
years, President Ben Ali went into exile on
14 January 2011 following one month of
protests. Pressure exerted by demonstrators
and civil society led to the setting up of three
successive transitional governments (from
January to December 2011) to manage the
country’s economy and prepare free and
transparent Constituent Assembly elections.
2.1.2 The October 2011 Constituent
Assembly elections, though delayed, were
conducted in accordance with the electoral
process in place. To form a stable majority,
the Islamic Party, Ennahdha, which obtained
41.7% of the vote, formed a coalition with
the centre-left Party, CPR, and the Social
Democratic Party, Ettakatol. The initial aim
was to draft a new Constitution in one year.
2.1.3 The Troika, which won 63.6% of
seats in the National Constituent Assembly,
formed a government in December 2011
headed by the Secretary-General of Ennahda.
The office of President of the Republic is held
by the CPR Chairman and the Chairman of
Ettakatol is the ANC President.
2.1.4 However, the unrest that occurred
between end-2012 and November 20131
influenced the political process in 2012-
2013. In March 2013, tensions led to the
formation of a new government. Independent
personalities were appointed at the helm of
four key ministries2 to meet the expectations
of opposition parties. Security has become a
central issue and many actions have been
carried out to restore confidence.
2.1.5 In January 2014, the adoption of the
new constitution and the announcement
of a new government ended the Tunisian
political crisis that lasted more than 6 months.
Indeed, the national consensus signed by the
main political parties in October 2013 resulted
in the appointment of a new Prime Minister
in December, and the announcement of his
government in January 2014, the day following
the adoption of the new Constitution.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 13
A f r i c a n D e v e l o p m e n t B a n k
2.1.6 These two political events have
considerably lessened uncertainty and
lack of political visibility which had affected
donors’ intervention, and impeded economic
recovery. Following the vote of confidence
for the new government, the Tunisian Stock
Exchange closed on a positive note, the dinar
appreciated against the Euro and the U.S.
Dollar, and the IMF announced a disbursement
of $ 500 million of its support program.
2.1.7 In addition, the transition process in
Tunisia remains one of the most stable in
the region. The announcement of a new
government of technocrats and independents
as well as the holding of the forthcoming
elections scheduled for October 2014 could
husher a new positive impetus.
B. Economic Context3
2.1.8 Tunisia has for long been considered
as an economic success story in the region.
Since independence, the Tunisian economy
has undergone profound restructuring.
Its domestic production, which was initially
dominated by agriculture and raw materials
(phosphate, oil and gas), is directed towards
services and, to a lesser extent, the manu-
facturing industry.
2.1.9 The decade preceding the Revolution
was a period of transition for the Tunisian
economy plagued by many challenges. The
objectives of the reforms included in the
9th (1997-2001), 10th (2002-2006) and 11th
(2007-2011) Plans were to increase growth
from 4.8% to 6.1% and to reduce the unem-
ployment rate from 14.2% to 13.4% by 2011.
During this period, the country experienced
moderate, but steady, growth of 4.9% annually,
raising GDP (PPA) per capita to a little over
USD 4 200, despite the shock of the 2008
financial crisis. This growth contributed to
reducing poverty in rural and urban areas4
and improving health and education indicators.
Despite the global economic crisis, downswing
effects and the Recovery Plan helped to
implement a counter-cyclical policy without
worsening the budget deficit (less than 3% in
2009). However, despite the good perfor-
mance recorded, the set objectives in terms
of employment, social equality and regional
development were not achieved.
u Macro-economic Developments
2.1.10 After the Revolution, the Tunisian
economy has been affected by social
movements, political developments and
the fragile global economic context.
However, the economy was resilient to the
two shocks of the 2011 Revolution and the
Euro zone crisis, indicating that Tunisia’s
economic fundamentals are still good, despite
economic uncertainties. The impact of
the European crisis on the key sectors of
manufacturing and textile industries (-8%) and
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 514
A f r i c a n D e v e l o p m e n t B a n k
mechanical and electrical industries (-2%)
was offset by a strong rebound in refining
(+142.8%), chemical (+15.9%), agricultural
(+5.7%) and hotel and catering (12%) activities
(Fig. 1). FDIs which increased by almost 80%
compared to 2011 (thanks particularly to the
privatization of two seized assets), the vitality
of domestic demand and tradable (transport
and hotel and catering) services were the main
drivers of growth in 2012.
2.1.11 In fact, after recording a negative
growth (-1.9%) in 2011, the Tunisian economy
experienced an upswing in 2012 with a
3.3%5 growth rate which is expected to be
between 2.6% 3% in 2013 (Fig.2).
2.1.12 The budget deficit rose from 3.4%
of GDP in 2011 to 4.9% in 2012 and is
expected to stand at 6.5% in 2013. Tax and
non-tax revenues increased moderately in
2012.
2.1.13 The increase in public consumption
expenditure was relatively significant,
thus accelerating the deterioration of the
budget deficit. In particular, grants expenditure
increased sharply due to rising food and
oil prices, coupled with the depreciation of
the dinar6. Furthermore, the increase in civil
servants’ salaries and the recruitment of new
workers raised the public wage bill significantly
in 2013 (+40% compared to 2010). However,
this expenditure which has stimulated overall
demand partly explains the rapid cushioning
of the shock caused by the January 2011
Revolution. It should be noted that interest on
debt rose by 6.9% in 2012 and 4.9% in 2013.
2.2.1.14 Regarding investments, budget
execution in 2012 and 2013 was less
expansionary than envisaged. Development
expenditure included in the Supplementary
Finance Law increased by 18.7% in 2012.
However, constraints on implementation
capacity at the regional level and on procu-
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 15
A f r i c a n D e v e l o p m e n t B a n k
-40.0
-30.0
-20.0
-10.0
0.0
10.0
20.0
2008 2009 2010 2011 2012
Chemical
Hotel and catering
Transportation
Textile, clothing and leather
Mechanical and electrical
Figure 1: Contribution to the Growth of KeySectors of the Economy (MDCI)
Figure 2: Macro economics (AfDB)
rement led to a budget execution rate of
74.4% in 2012.
2.1.15 In 2014, debt will remain sustainable7,
provided the budget deficit is reduced and
growth is revived (Annex 13). According to
the standards of rating agencies and interna-
tional institutions, the debt/GDP ratio of mid-
dle-income countries like Tunisia must not
exceed 50%. The country’s public debt/GDP
ratio dropped from 44.6% in 2011 to 43.8%
in 2012 and is expected to stand at 46.8% in
2013. Sixty-three percent of public debt is
held abroad for a seven-year average repayment
period and a low average annual cost of
about 3.5%, excluding the repayment of the
principal before 2017. The budget deficit is
expected to fall to 4.3% in 2015.
2.1.16 However, the State’s financing
needs are huge and estimated at USD
3.9 billion in 2013 (8.5% of GDP) and USD
4.3 billion in 2014. Following development
partners’ interventions of, Tunisia has mana-
ged to bridge the financing gap in 2013.
Negotiations with the IMF on a precautionary
standby arrangement led to the approval –
on 7 June 2013 - by the IMF Executive Board
of a USD 1.7 billion programme for the 2013-
2015 period at a 1.07% interest rate (Annex
6) which is subject to the implementation
of reforms to restore macro-economic
stability.
2.1.17 The Central Bank of Tunisia (BCT)
has continued to implement a flexible
monetary policy to support the revival
policy. The structural liquidity deficit which
characterized the cash position of banks in
2011 continued in 2012, necessitating greater
BCT intervention on the money market
through the injection of about TND 5 billion
during the first 10 months of 2012. Total
deposits decrease by 7.8 in 2013 compared
to 10.7% in 2012 (5.1% in 2011), while
lending to the economy increased by only
8.7%, as against 13.4% in 2011.
2.1.18 Increasing inflationary pressures
prompted the BCT to gradually tighten its
monetary policy and implement a neutral
intervention strategy in line with changes in
autonomous bank liquidity factors. In fact, on
average, inflation stood at 6.4% in 2013 as
against 5.4% in 2012 and 3.5 % in 2011 due
mainly to8 : (a) rising world market prices of
some imported products; (b) the depreciation
of the dinar (from 0.52 dinars for TDN
1.90/EUR 1 on 1/12/10) to TDN 2.22/EUR 1
on 10/10/13); (c) increase in the wage bill; (d)
weakening price control, dysfunction of
distribution networks and the smuggling of
some products into neighbouring countries
(Libya).
2.1.19 The current account deficit rose
from 7.3% of GDP in 2011 to about 8.2%
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 516
A f r i c a n D e v e l o p m e n t B a n k
in 2012 and 8.3% in 2013, despite an
increase in revenue accruing from tourism
and remittances from Tunisian workers
abroad (34% and 22%) and the depreciation
of the exchange rate (12% against the Euro
in 20139 and 16% since 2010).
2.1.20 Hence, foreign exchange reserves,
though substantial, declined in 2013. The
agreement for the deposit of USD 500
million into the BCT by the National Bank
of Qatar at end-December 2013 helped to
stabilize the reserves at USD 7.1 billion,
representing 107 import days. Likewise,
foreign exchange reserves attained their
2010 level in 2012 (USD 8.5 billion) following
an increase in FDIs10 (Fig. 3) sustained parti-
cularly by the sale of ill-gotten property,
bilateral and multilateral loans and access to
financial markets (with the U.S. Treasury and
JBIC guarantee).
2.1.21 Tunisia’s sovereign rating was revised
downwards in this context marked by the
relative deterioration of macro-economic
balances. Since 2011, Standard & Poor’s
has progressively reduced Tunisia’s sovereign
rating by six notches from BBB to B in August
2013 (Annex 5). This has reduced Tunisia’s
sources of financing and increased their cost
at a time of growing needs. However, Tunisia
has never defaulted on its financial commitments
to the Bank or other donors and such scenario
is unlikely in the short- and medium-term
(Annex 13).
u Gouvernance
2.1.22 Before the Revolution, poor public
and private sector governance impeded
civil society participation in the running of
the country and also hampered private
sector development11. It is said that poor
governance cost the Tunisian economy two
growth points. In 2012, however, governance
indicators continued to portray Tunisia as the
most advanced country in Africa in terms of
HDI and sustainable economic development.
In contrasts, regarding the rule of law, Tunisia’s
score remained very close to the average of
African countries in 2012 (Fig. 4). Supplementary
and sustained efforts should be made to restore
the confidence of entrepreneurs and investors,
particularly in the judicial system.
2.1.23 During the post-Revolution period,
the authorities implemented several
initiatives to improve transparency and
good governance. This resulted in the
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 17
A f r i c a n D e v e l o p m e n t B a n k
1% 1% 5% 8%
4%
2%
36%3%
40%
Miscellaneous industries
Agro-food
Building materials
Mechanical-Electrical-Electronic Chemical, Rubber and Plastic
Textile, Clothing, Leather andFootwear
Energy
Tourism and Real Estate
Services and others
Figure 3: Distribution of FDI Flows by Sector, 2012 (IFAP)
creation of a Ministry in charge of Gover-
nance in 2012. An action plan was prepared
following the conduct of a governance
evaluation and a diagnosis of the extent of
corruption in Tunisia. This led to (i) the lifting
of reservations allowing the entry into force of
the United Nations Convention against
Corruption, 2003 and (ii) the revitalization of
the Independent National Anti-corruption
Authority in April 2012. In 2013, the Government
also carried out the OECD integrity scan
which constitutes an important milestone.
2.1.24 Tunisia has also made substantial
progress12 in establishing a legal and
institutional framework for public trans-
parency. The analysis of the Tunisian control
and audit system in 2013 underscored the
need to reform auditing as the basis for
corruption control. The reform of the financial
system is underway with the application of
objectives-based budget management which
ensures greater efficiency in resource mana-
gement. These achievements, whose impact
is still to be assessed, should be strengthened
by putting in place a robust legal framework.
2.1.25 Measures have also been taken to
improve Government’s accountability to
control institutions13. The Audit Office also
plans to reform its internal structures in order
to adapt the organization of its services,
particularly the pole centred around the
General Secretariat, and its operation to good
governance requirements. This structural reform
will therefore include the modernization of
tools placed at the disposal of magistrates
through the development of computerized
auditing and the use of computerized audit
techniques on the one hand, and the esta-
blishment of an information system adapted to
the needs of the Audit Office on the otherhand.
2.1.26 Corruption remains the centre of
attention. According to Transparency Inter-
national, Tunisia’s corruption perceptions
index declined in 2011 and 2012 compared
to 2010 and 2011 (Fig. 5). However, despite
the establishment of the National Corruption
and Embezzlement Investigation Commission
and the National Committee on the Recovery
of Ill-gotten Property Abroad, anti-corruption
measures are inadequate. Furthermore, the
report on the self-assessment of the national
procurement system conducted in 2012
highlighted a major weakness in the integrity
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 518
A f r i c a n D e v e l o p m e n t B a n k
62.7
81.7
54.1
68.6
51.2
56.7
53.3
47.3
0 10 20 30 40 50 60 70 80 90
Governance Index (Mo Ibrahim Index)
Human Development Index (HDI)
Security and Rule of Law
Sustainable economic development
Africa Tunisia
Figure 4: Governance Index 2012: Tunisia’sScore, Compared to Africa (AfDB)
and transparency of the Tunisian public
procurement system.
2.1.27 Since Revolution, major efforts
have been made to promote access to
information, civil society development and
greater citizen control14 (Fig. 5). These
include, for example, the enactment of the
2011 law on associations. The Tunisian
Government enacted a law on access to
information in May 2011 and also started
disseminating key statistical and financial
data such as budget implementation reports,
complete Audit Office reports, as well as
household and labour force surveys. This
is facilitated by the Bank’s support to
e-Government.
u Business Environment and
Competitiveness
2.1.28 Tunisia has become less attractive
to investors since the Revolution. It has
thus slipped 5 places in the Doing Business
2013 ranking (from 45th to 50th), declining in
all indicator rankings (Fig. 6). According to
the latest Global Competitiveness Report,
bureaucracy is the most problematic business
climate factor. Tunisia fell from the 23rd rank
in 2010 to 41st rank in 2011 in terms of the
quality of public institutions. According to
foreign investors, there are major disparities
among sectors, whether these sectors are
open or not to foreign investment, and
requests for prior authorization, particularly
in the service sector, are limiting factors.
Tunisia has become less attractive to investors
since the Revolution. It has thus slipped 5
places in the Doing Business 2013 ranking
(from 45th to 50th), declining in all indicator
rankings (Fig. 6). According to the latest Global
Competitiveness Report, bureaucracy is the
most problematic business climate factor.
Tunisia fell from the 23rd rank in 2010 to
41st rank in 2011 in terms of the quality of
public institutions. According to foreign
investors, there are major disparities among
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 19
A f r i c a n D e v e l o p m e n t B a n k
9.95
35.68
42.65
4.3 3.8 4.12010 2011 2012
Freedom of Expression andAccountability
Corruption Perceptions Index
Figure 5: Trends in Freedom of Expressionand Accountability and Corruption PerceptionIndices (IMG and Transparency International)
sectors, whether these sectors are open or
not to foreign investment, and requests for
prior authorization, particularly in the service
sector, are limiting factors.
2.1.29 ITCEQ’s Competitiveness Survey
2012 revealed that the business envi-
ronment is one of the main challenges
for corporate development, particularly
regarding corruption and insecurity
(Fig. 7).
2.1.30 Total factor productivity remains
low compared to those recorded in other
middle-income countries such as Morocco
and Romania, Tunisia’s main competitors
(Fig. 8). Although the country’s annual growth
rate rose from 1.2% (2000-2005) to 1.5%
(2006-2010), this performance is said to be
due only to a drop in the real effective exchange
rate owing to greater trade openness and
worsening terms of trade15.
2.1.31 A more knotty issue is that Tunisia
lost 43 places and was ranked 83rd in the
World Economic Forum’s Global Competi-
tiveness Report in August 201316 (Fig. 9).
Nevertheless, it has continued to honour its
commitment regarding the implementation of
reforms to improve the business environment
(new investment code, simplification of
administrative formalities and implementation
of administrative reforms). According to its
main partners, however, there is need to
accelerate the implementation of reforms.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 520
A f r i c a n D e v e l o p m e n t B a n k
10497
3130
39
8793
5466
4550
6470
7778
6062
4649
38
0 50 100 150
Ease of doing business
Starting a business
Obtaining building permit
Obtaining creditAcquisition of property
Investor protection
Taxation
International trade
Contact compliance
Closing a business
2012 2013
Figure 6: Business Environment: Comparative Ranking with 183 Countries
(Doing Business)
0.733
0.7190.7130.657
0.61
0.587
0.568
0.547
0.493
Infrastructure
Human resources
Macro-economic uncertainties Administrative procedures and system…
Contracting parties
Bank financing
Social security contributions Corruption
Insecurity
0 0.2 0.4 0.6 0.8
Figure 7: Business Climate:Competitiveness Survey 2012 Results
(ITCEQ)
1.2%1.5%1.4%
1.1%
2.7%
0.4%
5.5%
1.4%
2000-2005- 2006-2010-
Tunisia Morocco Turkey Romania
Figure 8: Overall Factor Productivity Growth for the 2000-2005 and 2006-2010
Periods (AfDB)
u Financial Sector
2.1.32 The already fragile financial sector
has been affected by the transition17. Before
the Revolution, it was already plagued by
structural vulnerabilities such as undercapita-
lization, poor asset quality, fragmentation,
poor banking supervision or underdeveloped
stock markets. The banking sector has been
affected by the Revolution owing to its
exposure to risks related to sensitive sectors
such as tourism as well as companies owned
by the former President’s family. Bad debts
have been maintained artificially at their
pre-Revolution levels and profits do not
reflect the low level of banks’ provisions and
equity. State banks are the most vulnerable
because they were used as economic policy
instruments. According to the BCT, the rate
of non-performing loans of State banks was
17.8% at end-2012 and would be more than
20% if rescheduled debts (in line with the
June 2011 BCT circular) are taken into
account18. Furthermore, the banking system
does not support SME and micro-enterprise
development.
2.1.33 The banking sector is at the core
of the reforms included in the IMF programme.
According to the recent assessment of financial
system soundness, the cost of restructuring
the public banking sector could reach 2.6%
of GDP over the next two years. The reforms
supported by the IMF include the improvement
of banking information, bank recapitalization,
the management of non- performing loans
(especially those related to tourism), improved
management of public banks, better banking
supervision and the establishment of a crisis
management system.
u Trade and Regional Integration
2.1.34 The Partnership Agreement between
the EU and Tunisia has enabled the country
to reach important milestones regarding
liberalization and integration. However, this
has been achieved at the expense of heavy
dependence on the European economy
which was the destination of 73% of Tunisian
exports in 2012. The top ten destinations
include Libya, Algeria, Morocco and the United
States which absorb 16.4% of Tunisian
exports (Fig. 10).
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 21
A f r i c a n D e v e l o p m e n t B a n k
0 50 100 150
Global Competitiveness Index 2011-…
Institutions
Infrastructure
Macro-economic environment
Health and primary education
Higher education and training
Contracting effectiveness
Technological maturity
Innovation
Turkey Brazil Tunisia
Figure 9: GCI 2012-2013 Ranking (WEF)
2.1.35 However, integration in the sub-
region and with sub-Saharan Africa is a
source of significant, but untapped,
potential growth. Tunisia exports much more
to France (26.3%) than to Cameroon (0.14%)
(Figure 11). Nevertheless, the merchandise
trade complementarity index shows that its
exports are more complementary with Came-
roonian (0.457) than French (0.433) exports
(Fig. 13). Thus, the Tunisian Government has
designed a roadmap in conjunction with the
private sector and market research consulting
firms to ease access to African markets. Tunisia
is also negotiating free trade agreements with
WAEMU and the establishment of free trade
zones with Libya and Algeria.
C. Social Situation
2.1.36 Transition is taking place in a social
environment marked by labour unrest. In
the first quarter of 2013 alone, the country
witnessed 23 strikes, of which only 11 were
legal (affecting 21 enterprises, 4 of them
public) that caused the loss of 4 000 working
days. Labour unrest has sometimes led to
acts of violence.
u Poverty, Inequality and Polarization
2.1.37 Wide socio-economic disparities
remain one of the main social challenges
faced by Tunisia, despite the alleviation of
poverty over the last decade (from 32.4% in
2000 to 15.5% in 2010)19. Global inequalities
have reduced, with a decline in the Gini Index
from 0.37 in 2000 to 0.35 in 2010 (Figure 12
– Annex 8). Despite the decrease in inequalities
at the national level, regional disparities have
continued to increase, further polarizing the
society.
2.1.38 The authorities are concerned
about the poor performance of social
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 522
A f r i c a n D e v e l o p m e n t B a n k
26%
16%
9%8%
4%
37%France
Italy
Germany
Libya
Spain
Rest of the World
Figure 10: Tunisia’s Main Trading Partners(% share of total exports) (INS)
0.14
26.28
0.15
9.39
0.062.99
0.11
0.457
0.433 0.4300.419
0,4100.405 0.401
0.3800.370
0.3900.4000.4100.4200.4300.4400.4500.4600.470
0.00
5.00
10.00
15.00
20.00
25.00
30.00 % Share of Total Export
Complementarity
Figure 11: Main Destinations of Tunisian Exports and Complementarities
(UNCTAD)
transfers20. In fact, to alleviate poverty and
preserve food security, Tunisia has implemented
social policies based on direct and indirect
transfers (food and energy subsidies) since
independence so as to promote inclusive
growth-driven development. However, analyses
of the efficacy of food subsidies have shown
that despite their significant redistributional
effects (without subsidies, the poverty rate
would have reached 19.1% in 2010), the uni-
versal nature of these subsidies undermines
the efficacy of this tool as a mechanism
for reducing inequalities and poverty. Poor
households which represented 15.5% of the
total population in 2010 receive only 12% of
food subsidies.
u Unemployment and Education
2.1.39 Despite the growth rebound in
2012, employment remains the major
preoccupation of Tunisian policy-makers.
During the third quarter of 2013, the average
unemployment rate and the unemployment
rate of graduates rose to 15.7% and 33.5%
respectively (Fig. 13). The effect of the recession
coupled with the massive influx of Tunisians
repatriated from Libya21 explain these rates
which remain high despite a slight decrease
compared with the previous year (particularly,
following recruitments in the public sector).
This structural unemployment, is a result
of a quantitative (between higher education
and private sector needs) and qualitative
(graduates lacking the required skills to enter
the labour market) mismatch. The distribution
of unemployment is also an important indicator
of regional and social disparities. The authorities
are also concerned about the informal sector
(36.8% of employment in 2007).
u Gender Issues
2.1.40 The Bank conducted a gender
diagnosis in 2012-2013. As regards gender
equity, the 1956 Personal Status Code
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 23
A f r i c a n D e v e l o p m e n t B a n k
23.3
34.8
61.9
15.5
32.7
62.5
Poverty rate Global inequality Polarization
2005 2010
Figure 12: Poverty, Inequality and Polarization in 2005 and 2010 (INS)
. . .
. . . . .
.. . .
.
..
..
.
.....
.
Figure 13: Trends in the Overall Unemployment Rate among University
Graduates and Women 2006-2012, in % (INS)
places Tunisia at the vanguard of the Arab
world with respect to the status of women in
society. Nevertheless, there are still reservations
at the CEDAW concerning the law of succession,
the Nationality Code and the concept of
patriarchy. During the transition period, there
were a lot of tensions during which achieve-
ments were sometimes threatened.
2.1.41 Concerning human capital,
Governments’ efforts have borne fruit,
although some disparities remain. There
is a higher female enrolment in universities
with a 62.3% rate in 2013. However, in basic
education, the illiteracy rate in 2010 was
26.4% for girls as against 11.5% for boys. In
rural areas, women sometimes lack access
to specific health (gynaecological) care.
2.1.42 Regarding economic inclusion,
women’s labour market participation is
irregular and declines from the age of 30
years. Women represent less than a quarter
of an active population of 3.2 million and their
unemployment rate is higher than that of
men. Sectors characterized by job insecurity,
underemployment and major differences in
remuneration are dominated by women. A
better women labour market positioning
would increase GDP by 0.7 percentage
points.
2.1.43 Women’s participation in the three
branches of government has improved
significantly. Women hold 22.6% of
positions in decision-making bodies. The
adoption of the gender equality principle
during the first ANC elections resulted in the
election of 49 women out of 217 seats and
the Vice-President of the ANC is a woman.
Although this representation seems is low in
absolute terms, it is remarkable in the sub-
region.
D. Environment and Climate Change
2.1.44 During the post-revolutionary
period, the management of environmental
issues has deteriorated. This degradation
is related to the difficulties encountered
by the government in applying the law22.
2.1.45 However, the renewed involvement
of civil society, which is clamouring for
better natural resource and environmental
management, is visible. The demands concern
improvement of the quality of life and natural
resource management, reduction of public
health disparities between regions and also
within towns through equitable access to
drinking water and sanitation and improved
waste management.
2.1.46 Like in most North African countries,
water is a precious commodity in Tunisia.
More than half of available water is surface
water and about 44% is derived from water
tables. Although all available water reserves
have not been harnessed, the excessive
consumption of groundwater is increasingly
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 524
A f r i c a n D e v e l o p m e n t B a n k
disquieting. On average, water reserves are
extracted at 146% of their recharge rate23.
2.1.47 Tunisia is implementing an aggressive
policy in the area of energy conservation
and new and renewable energy (wind,
solar, sludge from sewage treatment plants)
which should be encouraged. Energy intensity,
which is 0.08 ktoe per USD 1 000 of GDP,
is less than the world average of 0.13 as
well as the average of 0.18 in the MENA
region.
2.1.48 In addition, climate change may
have a significant impact in Tunisia. Tunisia
is expected to experience a warmer and
more variable climate by 2030. These expected
changes will have considerable impacts on
water resources, agriculture and natural
resources. In 2050, the impact is expected to
represent about 0.3% of GDP.
2.2 Strategic Options
A. Country Strategic Framework
2.2.1 Soon after the Revolution, Tunisia
stopped the preparation of five-year
development plans implemented since the
sixties. In a context of transition, the authorities
have opted for a flexible strategy aimed at
appeasing social and economic demands
while preparing necessary structural reforms.
The I-CSP is based on Government’s
guidelines which were presented in March
2013 and on (i) the September 2011 Jasmin
Plan and (ii) the October 2012 Letter of
Development Policy. These guidelines provide
for a series of structural reforms and investments
aimed at creating conditions for accelerated
growth and job creation to ensure regional
balance and inclusive development. They
build on five pillars, namely: (i) economic
reforms; (ii) infrastructure modernization; (iii)
strengthening of the social sectors of education
and employment; (iv) regional balance; and
(v) promotion of sustainable development.
There is, however, no detailed plan for its
operationalization.
2.2.2 The authorities intend to formulate
a development plan in 2014. In this
connection, the I-CSP proposed by the Bank
would cover the period of the formulation of
this new plan.
B. Challenges and Weaknesses
u Delays in the political agenda
and the sub-regional context
2.2.3 The relative slow pace of the political
transition process impedes the return to
a sustainable growth model. Economic
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 25
A f r i c a n D e v e l o p m e n t B a n k
actors are awaiting the implementation of a
clear political agenda, far-reaching structural
reforms and a coherent public investment
programme.
2.2.4 Geopolitical uncertainties in the sub-
region also weigh heavily on stability. The
Libyan crisis has had a direct impact on the
Tunisian economy resulting, inter alia, in the
return of workers, and heightened insecurity,
particularly in border regions24. The crisis in
Europe, Tunisia’s main trading partner, has
also affected the Tunisian economy.
u Need for more resources
2.2.5 The implementation of a recovery
policy and creation of conditions conducive
to democratic transition entail more financing
which calls for the mobilization of more
resources. However, the use of these
resources should not jeopardize macro-
economic stability. Besides the international
community’s role in providing such financing,
technical support should be intensified to
carry on the structural reforms presented
below.
u Accelerating the structural
transformation of the economy
2.2.6 The persistent dependence of the
economy on low-cost production and
export sectors with low value added make
it uncompetitive and vulnerable25. The
sophistication of Tunisian exports has not
improved since 1960 (Fig. 14). The structural
transformation of the economy should build
on: (i) the substantial contribution of exports
to growth; (ii) the greater contribution of
the service sector to growth26 (health27, air
transport or telecommunication28) and (iii)
the orientation of production towards
sectors with higher value added by moving
from a subcontracting to a co-contracting
economy29.
2.2.7 Furthermore and as indicated above
(2.1.30), the business climate should be
significantly improved. Micro-economic
policies and inefficient institutions hinder
investment, particularly foreign investment,
which offers a huge potential for bridging the
technological gap as well as enabling Tunisian
businesses to become competitive by supplying
export enterprises or exporting directly. Thus,
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 526
A f r i c a n D e v e l o p m e n t B a n k
Figure 14: Evolution Index sophistication of exports (EXP) for Tunisia
and some Asian countries
additional efforts should be made to improve
the business climate and strengthen the
competitiveness of businesses by simplifying
procedures. In this regard, regional consultations
on the Investment Code, which were initiated
on 25 May 2013, will be conducted before it
is tabled before the ANC for approval.
2.2.8 It is also necessary to continue
to develop infrastructure for economic
transformation30. The level of infrastructure
is relatively satisfactory. Good economic
performance was achieved over the last
decade thanks to investments in, and regular
upgrading of, new infrastructure. However,
Tunisia faces the challenge of maintaining,
during the transition period, an ambitious
public investment level to support economic
transformation (developing and improving the
management of trade infrastructure, particularly
ports31- or developing green energy).
2.2.9 It is necessary to redefine relation-
ships between the public and private
sectors. Although the outlines of public-
private partnerships (PPPs) are being defined,
it is obvious that the structural transformation
of the economy can only be achieved by
increasingly using them32.
u Reducing Regional Disparities
2.2.10 Regional disparities in Tunisia
primarily affect the quality of public
services33,34. As regards primary education,
tests conducted worldwide have shown that
schools in small towns are unable to give
their pupils the same level of skills acquired
by pupils of schools in big towns. In the same
vein, the knowledge index developed by the
authorities shows that the level of knowledge
is 30 times higher in Tunis than in Kasserine,
thus limiting the region’s participation in the
country’s economic transformation. Likewise,
the quality of health services is six times better
in Tunis than in Kairouan and eleven times
better than in Sidi Bouzid35. Citizens’ access
to water and sanitation, roads and energy in
disadvantaged regions is sometimes difficult
(Fig. 15).
2.2.11 These disparities are also reflected
in economic attractiveness36. Low levels
of private investment reflect imbalanced
development in terms of employment oppor-
tunities, underscoring the need to improve
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 27
A f r i c a n D e v e l o p m e n t B a n k
0.70
0.33
0.68
0.41
0.20
0.39
Wealth and employment Health and population Knowledge
Coastal Governorates Inland Governorates
Figure 15: Indices of Regional Disparities inTerms of Wealth, Health and Education
(MDCI)
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 528
A f r i c a n D e v e l o p m e n t B a n k
the business climate in regions with regard to
the quality of public services provided to
enterprises (Fig. 16).
2.2.12 There is need to continue to build
infrastructure to support regional integration.
Ambitious public investment will help to
reduce regional disparities by linking under-
served regions, thereby inducing a ripple
effect on the private sector so as to stimulate
growth while enhancing its inclusiveness.
Thus, besides providing support to techno-
logical hubs, special attention should be paid
to all basic infrastructure assets, be they
transport (including rural roads), logistics,
telecommunications, education or social
services.
2.2.13 However, these two components
can be achieved only by carrying on with
the reorganization of the State37. There is
need for Tunisia to implement urgent reforms
to make centralized State procedures more
flexible and upgrade institutions pending the
implementation of the necessary structural
reforms. In this regard, it is necessary to
strengthen the decentralization of the State
in regions and improve the implementation
of investment budgets in the short term.
Secondly, it is essential to formulate regional
development plans rapidly and to transfer
powers to councils, divisions and regions.
u Improving training-employment
dynamics in an inclusive manner
2.2.14 The reduction of unemployment
entails more efficient training-employment
dynamics38. Tunisia is suffering from major
structural unemployment, hence the need to
initiate the structural reform of the educational
and training system. Concerning basic
education, the aim should not only be to
undertake pedagogical reforms, but also to
ensure that these reforms have an impact on
learning. With regard to vocational training,
there is a threefold objective: (i) to build the
capacity of the vocational training system; (ii)
to improve its quality and adaptation to
the economic fabric; and (iii) to improve its
governance through increased private sector
involvement. Concerning higher education,
there is need to give a boost to the sub-
sector’s reform by focusing the reform
3323
7396
10619
4194 4358
8552
0
2000
4000
6000
8000
10000
12000
Public Private Total
Coastal Governorates Inland Governorates
Figure 16: Per Capita Investment in TNDfor the 1987 – 2010 Period (MDCI)
strategy on excellence, quality assurance and
managerial accountability of schools through
partnership with the private sector in terms of
research and innovation to meet economic
needs.
2.2.15 Lastly, it is necessary to ensure
coordination between training actors and
sectors so as to adopt a common human
capital development vision. New entrants
are trained and encouraged to join the public
sector, which is the main source of employment.
Thus, there is a mismatch between the skills
available on the labour market and corporate
needs (Fig. 17). Nevertheless, the quality of
training is put into question (OECD PISA
tests).
2.2.16 Furthermore, the growth diagnosic39
highlights the rigidities of the Labour
Code which do not facilitate transition from
training to formal employment and job creation.
These may be overcome only through the –
ongoing–renegotiation of the social contract40.
C. Strengths and Opportunities
u Strong central administration
2.2.17 Thanks to its strong central admi-
nistration, Tunisia still has the capacity
to formulate economic policies in the
context of transition. The authorities are
carrying on dialogue with key development
partners. Similarly, the central administration
continues to design investment projects in all
sectors.
2.2.18 However, the transition has slightly
affected the capacity of the central adminis-
tration. There are some slippages in the
implementation of projects. The effective
implementation of reforms, particularly within
the framework of multi-donor budget support
operations, is sometimes considered to be
timid (Annex 10)41. Delays are due to relative
political instability, occasional conflicting
visions of policy-makers (belonging to different
political parties) and schooling in participatory
decision-making.
u Diversified economy
2.2.19 Tunisia has a relatively diversified
economy. In 2011, agriculture accounted
for 8.8% of GDP, manufacturing industries
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 29
A f r i c a n D e v e l o p m e n t B a n k
9.6
12.4
32.4
26
26.1
25.4
27.4
10.5
5.7
13.9
6.3
15.9
Certificate before the Baccalauréat
Senior TechnicianBaccalauréat
Master’s degree in Letters and Social Sces Master’s degree in hard sciences
Master’s degree in hard sciences
Other certificate
Medicine or Pharmacy
Certificate in Engineering
Master’s Degree or equivalent certificate
Doctorate
Other certificate
Figure 17: Rate of Youth Unemployment(Aged 18 – 30 Years)by Type of Certificate
(2010) (INS)
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 530
A f r i c a n D e v e l o p m e n t B a n k
17.6%, non-manufacturing industries 12.9%,
tradable services 42.5% (tourism 6.3%) and
non-tradable services 18.2% (public adminis-
trative services 17.8%). Though Tunisia was
mainly an agricultural and mineral product
exporting country in the 1970s, textiles, elec-
tronics and chemicals now occupy the
largest share of its export basket. Since the
dismantling of the Multifibre Agreement, the
share of textiles in total exports has declined
over the past five years, while that of mecha-
nical and electronic products rose from
23.1% in 2005 to 36.6% in 2012 ( Fig. 18).
2.2.20 Tunisia has a number of sector
with huge potential (tourism, agriculture42,
manufacturing industries and services)
to support growth and employment. In this
regard, the current structure of the economy
provides a solid base for initiating economic
transformation.
u Sound international integration
2.2.21 Tunisia strengthened its integration
in the international economy in the late
1990s. Its openness to the external world has
made foreign trade and foreign investment the
engines of its growth. Its proximity to and
agreements concluded with the European
market are an asset for sustainable growth,
despite the tumultuous European economic
situation.
2.2.22 At the same time, Tunisia has
succeeded in exploiting export opportunities
in North Africa – although the Maghreb is
one of the world’s least economically integrated
regions43. Tunisia also benefits from numerous
bilateral trade agreements signed in 1999
and agreements concluded with GAFTZ
and AMU countries. It collaborates with sub-
Saharan African countries and develops
investments projects in the industrial and
service sectors (see 2.1.26).
2.2.23 However, Tunisia must find new
markets to reduce its heavy trade dependence
on a limited number of countries (France -
26.6% and Italy - 16.1% of total exports).
Greater integration with Africa and Asia could
create new sources of growth.
46.6
37.7
22.316.5
23.1
36.6
2000 2005 2012
Textiles, clothing and leather Mechanical and electronic industries
Figure 18: Share of Textile, Mechanical andElectronic Products in the export
Basket % (INS)
2.3. Aid Coordination/Harmonizationand AfDB Positioning in the Country
2.3.1 Tunisia signed up to the Paris
Declaration on Aid Effectiveness which
advocates, in particular, the conduct of a
survey on the monitoring of related indi-
cators. It did not participate in the global
surveys carried out by the OECD, but the
internal survey conducted by the Bank in
2012 shows that the aid provided is aligned
with national priorities. Concerning the har-
monization of procedures, projects financed
by the Bank and key partners in Tunisia are
implemented mainly by ministries and public
institutions, thus helping to limit the establish-
ment of parallel entities.
2.3.2 In 2012, the Government initiated,
with Bank and World Bank support, an
auto-evaluation of its national procurement
system by a national committee (open to
all public procurement stakeholders). This
auto-evaluation gave rise to an evaluation
report and an action plan which were validated
by the Government in August 2012. This
is the first step towards the use of country
systems by the Bank (Annex 12).
2.3.3 Given its adequate management
capacity, the Tunisian Government takes
responsibility for planning and coordinating
donor operations. Some attempts to formalize
the coordination framework have been made
without much success to date. These include
in particular an “employment and regional
development” group steered initially by the
Swiss Cooperation. However, coordination is
rather carried out on an ad-hoc basis, in the
form of information sharing and consultations
among the partners involved in similar
areas/operations. In this respect, the Bank
has prepared a series of distribution lists to
facilitate discussions among actors and
improve its dialogue with civil society.
2.3.4 Collaboration and coordination
with other donors are well-developed for
programmes co-financed in accordance
with the Paris Declaration. The partners: (i)
conducted joint budget support missions
giving rise to joint matrices of measures and
aide-memoires negotiated in a coordinated
manner; (ii) shared analytical works before
their publication; (iii) co-finance technical
assistance and investment programmes44.
2.3.5 Tunisia’s traditional donors’ speciali-
zation is based on their comparative
advantages and possible synergies and
complementarities. The IMF is supporting a
series of structural reforms helping particularly
to strengthen the financial sector and is coor-
dinating international support to stabilize the
macro-economic framework. The support of
AFD, JICA and KfW is focused on the private
sector, sanitation, local and agricultural develop-
ment and transport. For their part, multilateral
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 31
A f r i c a n D e v e l o p m e n t B a n k
donors provide multi-sector budget support45.
The WB and EIB give priority to the private and
transport sectors, while the EU is interested in
education and justice. Methods of intervention
have evolved and increased recourse to
technical cooperation is discernible. In this
respect, the Bank has continued to position
itself in sectors where its comparative advan-
tage is recognized in Tunisia (improvement of
basic infrastructure in the regions or vectors
of innovation and sophistication, the education
sector, governance support for private
sector development) or in sectors where it is
developing expertise such as PPP (Table 1).
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 532
A f r i c a n D e v e l o p m e n t B a n k
Table 1: Key Partners’ Active Portfolio by Sector (2013 - in USD million)46
Agr. HumanDev.
Transp. Ener./Env.
Reg.Int.
Private Water &San.
Loc. Dev.
Re-forms
Fin. Total %
AfDB 84 84 815 214 176 1013 138 2524 26,3
EIB 696 905 332 4 72 100 2109 22,0
WB 47 44 20 44 197 1059 54 1492 15,6
AFD 117 45 53 11 140 185 197 246 993 10,4
EU 115 63 40 73 75 79 545 990 10,3
AFESD 11 151 216 277 54 709 7,4
KfW 86 565 651 6,8
USAID 1 97 18 2 118 1,2
Total 286 440 1799 1600 40 696 1201 366 2865 292 9585 100,0
% 3 5 19 17 0 7 13 4 30 3 100
2.3.6 In addition, the Bank is coordinating
its activities together with other IFIs within
the framework of the Deauville Partnership.
In this connection, it hosted its secretariat in
2012. This partnership has helped to mobilize
additional resources in the form of grants,
share knowledge and coordinate operations.
2.3.7 The Bank has for long been a
preferred development partner of Tunisia.
The Bank’s portfolio (the institution’s second
largest) comprises 16 projects (of which four
non-sovereign) and 24 technical assistance
operations financed with grants to the tune
of UA 1.36 billion. Furthermore, in 2011 and
2012 UA 659.9 million was allocated for two
budget support operations. The road sector
represents 36% of the portfolio (in value),
followed by the multi-sector (26%) and the
private sector (16%) (Annex 4).
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 33
A f r i c a n D e v e l o p m e n t B a n k
2.3.8 The 2013 portfolio review showed
that the portfolio in Tunisia remains
efficient with a score of 2.6 (out of 3) and
a public portfolio financial performance of
71.8% in 2013. However, delays in loan
implementation have increased since the
Revolution and the good performance is
attributable to the presence of two aged projects
and the disbursement in a single tranche of
the budget support approved in November
2012. The level of grant disbursement, in
particular, remains modest with a rate of
40.1% (Annex 4).
2.3.9 The main recommendations of the
2013 portfolio review concerned audits,
disbursement timeframes and public
procurement procedures (Annex 3). The Bank
is continuing dialogue to enable the Audit Office
to implement projects with external financing. To
strengthen portfolio-related services, the Bank
has transferred three procurement experts to
the MDIC for an 18-month period to help speed
up disbursement for operations. Furthermore,
the Bank is supporting the public procurement
system reform which is a prerequisite for the use
of the country system47 (Annex 12).
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 534
A f r i c a n D e v e l o p m e n t B a n k
3.1 Rationale for Bank Group Involvement
3.3.1 The Tunisian authorities have
requested the preparation of a two-year
(2014-2015) I-CSP which is flexible and
adaptable to the changing political, eco-
nomic and social situation. This approach
will enable the organization of major political
events on the one hand and the preparation
of the new development plan on the other.
3.1.2 The operations will be a continuation
of previous operations, but will be well-
targeted to enhance their effectiveness
(Annexes 2 and 7). A flexible approach
based on a permanent dialogue with the
authorities and on the regular review of strategic
thrusts will be given priority.
3.1.3 The operations were identified
following discussions with the Government
and development partners during the
June and September 2013 missions. Since
2011, the Bank has organized monthly
meetings to exchange ideas with civil society,
private operators and the administration on
challenges of the country and the region. In
addition to bilateral meetings with the private
sector, a workshop was organized with civil
society in September 2013 to discuss the
strategy (Annex 11). External peer reviewers
(including development partners) were also
involved. The document was also discussed
with the new authorities in 2014.
3.1.4 Furthermore, the Bank’s strategic
positioning has been enhanced by the
growth diagnosis conducted with Tunisian
III. Bank Group Strategy
Box 2: Choice of the I-CSP Tool
1. The existence of sustained dialogue withthe authorities promotes the formulation ofa new strategy whereas the lack of visibilityunderpins its interim nature.
2. The lessons learned from achievementsin 2012-2013 encourage the refocusing ofactivities, necessitating the reformulation ofthe content of the two pillars.
3. Existing constraints on the level andtype of AfDB operation necessitated theestablishment of sustained dialogue duringconduct of the I-CSP preparation mission.
4. The authorities requested the design ofa I-CSP that gives a clearer signal to otherpartners and eases resource mobilization.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 35
A f r i c a n D e v e l o p m e n t B a n k
authorities and U.S. agencies . This diagnostic
underscores the importance of removing
micro-economic constraints to stimulate
growth driven by the private sector.
3.1.5 Despite a great deal of work to
improve knowledge done by the Bank
during the previous I-CSP (Annex 9),
huge knowledge gaps remain concerning
particularly the design of strategic frameworks
and reforms to support the transition process.
These gaps relate to the need to define condi-
tions for economic transformation (development
of an industrial strategy, agricultural sector
support, the selection of a deep-sea port and
the involvement of the private sector in educa-
tion) or conditions for the decentralization of
the State.
u Lessons learned from the previous
I-CSP
3.1.6 The recommendations of the I-CSP
2012-2013 completion report are as follows:
(i) Limit the Bank’s scope of intervention; (ii)
Strengthen the alignment of analytical works
with the I-CSP; (iii) Intensify the search for
co-financing; (iv) Improve the monitoring and
evaluation capacity of the I-CSP by identifying
simple and verifiable result indicators; and (v)
Combine budget support operations and
investments to maintain productive capacity
and create direct and indirect employment
opportunities in the regions.
3.1.7 The budget support mobilized 87%
of resources allocated during I-CSP 2012-
2013 implementation. This was justified (and
could be justified in the future) by the need to
support actions to revive demand while
preserving investment in order to guarantee
social peace and facilitate the transition
process. The budget support has enabled
achievements in local governance, support
to civil society, employment and public
finance whose scope may seem to be limited
but which, in the current context of transition,
should be considered as quite significant
(Annex 10). However, the examination of
public accounts during the 2011-2013 period
showed that constraints on financing led to
trade-offs in favour of recurrent expenditure,
to the detriment of public investment. To
avoid the loss of competitiveness related,
inter alia, to under-investment and strategic
infrastructure maintenance, special attention
should be paid to ensuring an optimal blend
between budget support operations and
investment projects during the implementation
of the I-CSP.
3.1.8 To take these recommendations
into account, it was resolved that: (i) the
Bank’s operation should be refocused on
governance and infrastructure; (ii) technical
assistance activities and studies should
underpin operations to ensure better
alignment; (iii) every project should include
external co-financing as much as possible;
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 536
A f r i c a n D e v e l o p m e n t B a n k
(iv) result indicators should be reviewed; and
(v) reform support and investment operations
should be combined.
u Approach and instruments
3.1.9 The I-CSP prioritizes the principles
of alignment with Government’s priorities,
complementarity with other partners and
consolidation of the achievements of
previous operations. The I-CSP focuses on
the Bank’s 2013-2022 Strategy, particularly
“governance” and “infrastructure” operational
priorities and incorporates the green dimen-
sion in their implementation. In accordance
with the Bank’s private sector development
strategy, the I-CSP will ensure permanent
dialogue between the Tunisian Government
and the private sector and promote PPPs.
3.1.10 In particular, the CSP recognizes
the key role played by the IMF in stabilizing
the macro-economic framework and the
financial system. Additionally, the I-CSP
focuses on two major challenges: (i) the
business climate and the competitiveness of
the economy and (ii) regional disparities.
3.1.11 In view of the transitional situation,
planned activities under the I-CSP will be
carried out within two time horizons: (i) a
short-term horizon for activities carried out to
meet urgent needs or to enable rapid economic
and social improvements (“quick wins”) and
(ii) a medium-/long-term horizon for activities
aimed at laying the foundations for a new
economic and social development model.
3.1.12 To support the transition process,
in particular and given financing challenges,
the Bank will lay special emphasis on tech-
nical assistance operations. The objectives
of such operations will be to conduct strategic
or pre-investment studies in order to enable the
authorities to focus on medium- and long-term
objectives during the transition period. The
technical assistance operations may also help
to identify reforms to support inclusive private
sector development in the short-term.
3.1.13 Depending on the development
of its commitment capacity, the Bank will
consider financing (public and/or private)
investment and budget support operations
(see section 3.2). In this connection, priority
will be given to investment operations that
promote public-private partnerships and
where the leverage effect of Bank resources
will be established. In this respect and in
order to facilitate progressive commitment
(in parallel with the development of its commit-
ment capacity), an approach based on the
financing of several small- and medium-size
operations (rather than a very small number
of large-scale operations) will be given
priority.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 37
A f r i c a n D e v e l o p m e n t B a n k
u 2014-2015 Intervention Component
3.1.14 To promote the creation of high
value added jobs for young graduates and
the economic attractiveness of regions,
emphasis will be laid on support for inclu-
sive private sector development within the
framework of this strategy. This support
entails the improvement of (i) private sector
output (by improving governance) and (ii) the
provision of production factors (by improving
infrastructure). Based on these factors and in
line with the I-CSP 2012-2013, the I-CSP
2014-2015 will focus on two pillars in keeping
with the Ten-year Strategy to obtain a blend
of governance and infrastructure domains.
3.1.15 Governance and infrastructure
improvement support helps to address
Tunisia’s major challenges (Table 2 –
Annex 2) while remaining consistent with
the Government’s policy framework. In
particular, Government’s thrusts: (i) Economic
Reforms and (ii) Infrastructure Modernization
are backed by actions carried out under the
I-CSP governance and infrastructure pillars
to: (a) improve the business climate and
competitiveness and (b) increase value
added. On the other hand, Government’s
thrusts: (iii) Regional Rebalancing and
(iv) Strengthening of the Social Sectors of
Education and Employment are supported
under the I-CSP governance and infra-
structure pillars through actions to (c) improve
public service delivery in the regions and
(d) ensure access to employment by
developing skills and opportunities in the
regions.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 538
A f r i c a n D e v e l o p m e n t B a n k
Table 2: Alignment with I-CSP Analysis, Intervention Pillars and the Strategic Framework
Country’s Context and Prospects
(Page 1)
Challeng
es and
Weaknesses (Pag
e 10)
Strengths and
Opp
ortunities (Page 12)
Instruments
Coun
try Strateg
ic
Framew
ork (P
age 9)
Political
Delays in the political agenda
and sub-regional context.
Uncertainties weigh on recovery
- return to stability depends
on a clear political agenda,
structural reforms and a coherent
investment programme. (Page
10)
A sound administration
capable of carrying on the
design of economic policies
in a context of transition.
(Page 12)
Flexible approach based
on the changing situation.
(Pages 15-18)
Tunisia is implementing one of the
most stable transition processes in
the region. However, the political
agenda (organization of elections) has
been delayed.(Page1)
Economique
Increased financial resource
need – however, macro-eco-
nomic balances should be
maintained.(Page 10)
Pillars
Macro-economics. Economic recovery
in 2012-2013. However, the budget
deficit widened with a decline in invest-
ment expenditure, a slight decrease
in foreign exchange reserves and a
deteriorating sovereign rating by rating
agencies.(Page 3)
Governance
Pillar
Infrastructure
Pillar
I. Economic
reforms
Governance, business climate and
competitiveness. There is a significant
improvement in public governance and
relations with citizens. However, the
business environment and competiti-
veness are considered as having
deteriorated.(Page 4)
Accelerating the structural
transformation of the econom
y.This necessitates the develop-
ment of sectors with higher
value added, strengthening the
business climate and infra-
structure support. (Page 10)
A diversified economy,
with huge sector potentials
.(Page 12)
II. Modernization of
infrastructure
Foreign trade and integration. There
is heavy dependence on the EU, which
slows down recovery.(Page 7)
An economy that is well
integrated internationally –
helping
to exploit new
opportunities.(Page 13)
Social
Reducing regional disparities.
These inequalities are reflected
in the quality of public services
and economic attractiveness.
(Page 11)
At the national level, achie-
vements in terms of the
attainment of Millennium
Development Goals are an
asset.
III.Regional rebalancing
Poverty and
inequality. Despite a
decline in poverty, disparities between
regions have increased. The authorities
are concerned about the poor perfor-
mance of social transfers.(Page 7)
IV. Strengthening the social
sectors of education
and
employment
Unemployment and education. Employ-
mentremains the main challenge
with high graduate unemployment,
reflecting poor training and employment
dynamics. (Page 9)
Improving the training and
employment dynamics in an
inclusive manner (Page 12).
Environm
ent
Including the green dimen-
sion in actions
V. Promotion of sustainable
development
The managem
ent of water rem
ains
the main challenge. Progress has
been made to promote renewable
energies.(Page 9)
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 39
A f r i c a n D e v e l o p m e n t B a n k
u “Governance” Pillar
3.1.16 Governance improvement will
entail the provision of support for reforms
and capacity building to improve the
business climate at the national level and in
the regions. This support will focus on the
“governance” operational priority of the Bank’s
2013-2022 Strategy. In this respect, the Bank
will continue to support the priority thrusts of
the reform programme at the national level,
namely: (i) the establishment of a transparent
process of reviewing regulations and adminis-
trative procedures for businesses so as to
simplify procedures and limit discretion in the
application of regulations; (ii) the improvement
of the performance of private sector support
entities by defining strategic studies; (iii) the
development of PPPs; and (iv) the improvement
of governance in institutions responsible for
education and vocational training to provide
skills necessary for the development of an
innovative private sector. At the local level, the
Bank will, in particular, support efforts to
upgrade and decentralize the administration in
order to improve public service performance
and, thus, attract investments to the regions
and promote more inclusive growth in Tunisia.
3.1.17 Regarding technical assistance,
“quick wins” may be carried out to improve
the business climate by supporting adminis-
trative reforms and implementing the Public
Procurement Reform Action Plan. Technical
assistance activities could also be carried out
to prepare the implementation of medium-term
actions by supporting the decentralization
strategy (including training), implementation
of the industrial strategy or involvement of the
private sector in higher education.
3.1.18 In terms of loans, budget support
could be considered to support the imple-
mentation of reforms identified in technical
assistance operations, if the Bank’s capacity
so permits (high scenario).
u Infrastructure” Pillar
3.1.19 This private sector development
support will require support for the formu-
lation and/or implementation of (public
and private) investment programmes
and strategies to improve the business
environment at the national level and in
the regions and to back the sophistication
of the economy. This support will focus on
the “infrastructure” operational priority of the
Bank’s 2013-2022 Strategy. At the regional
level, this will hinge on the upgrading of
basic infrastructure in order to promote the
development of productive activities in disad-
vantaged regions. This will help to firmly
establish growth in a context of enhanced
social cohesion and facilitate the implemen-
tation of reforms. At the national level, it will
require the provision of support to key
projects with a knock-on effect on the entire
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 540
A f r i c a n D e v e l o p m e n t B a n k
private sector or that serve as vectors of
innovation. Support to these investments will
be provided so as to include the “green”
dimension and promote PPPs.
3.1.20 Regarding technical assistance,
the conduct of a market research on the choice
and type of deep-sea port(s) in the short-term
could give a strong signal to investors, while
technical assistance operations for the prepa-
ration of the rural roads project, the develop-
ment of sanitation plans or an integrated
agricultural development programme would
allow for the rapid formulation of investment
operations in the regions and facilitate leverage
effects. In the medium term, the Bank could
support the development of a transport plan.
3.1.21 In terms of loans, where the Bank’s
capacity permits, priority will be given to
investment projects to upgrade basic infra-
structure in the regions (natural gas distribution,
rural and urban development and rural roads)
or highly innovative infrastructure with a high
leverage effect (solar energy). Where the
Bank’s resources permit (median and high
scenarios) other basic infrastructure develop-
ment operations in the regions (water and
sanitation, urban development, roads) and
strategic infrastructure development operations
(Rades Port) could be considered.
3.1.22 The quest for leverage effects
during the implementation of these two
pillars should lead to better coordination
of Bank actions and other donors and
private partners. A 1-to-4 leverage effect
will be sought. To that end, co-financing will
be considered before fielding the identification
mission and the Bank will first contact partners
without the same operational capacity in
Tunisia (OFID, GEF).
3.1.23 Furthermore, considering financing
constraints, priority will be given to the
“infrastructure” pillar in the case of “low”
and “median” loan scenarios. The “gover-
nance” pillar will be considered in terms of
loans only in the case of “high” scenario.
3.2 Expected Results and Targets
A. Monitoring and Evaluation
3.2.1 Dialogue will be held with the
authorities every two months to monitor
portfolio implementation status and
evaluate results. Like the previous I-CSP,
workshops will be organized to involve civil
society in the evaluation of results. This
monitoring process will be based on the
monitoring and evaluation system of the
country which has well-developed statistical
tools. However, the Bank will consider
providing support for the development of
regional statistics to facilitate the monitoring
of project impacts and public policies in the
regions.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 41
A f r i c a n D e v e l o p m e n t B a n k
3.2.2 The logical framework of future projects
will include indicators helping to monitor
the implementation of the 2013-2022
Strategy..
3.2.3 The I-CSP results monitoring frame-
work matrix is presented in Annex 2. It will
be revised depending on changes in the
commitment capacity. Given the short
duration of the I-CSP, two types of result
indicators were established, namely the: (i)
qualitative indicators by 2015 and (ii) quanti-
tative indicators over a longer period (2018).
B. Pillar Results and Targets
3.2.4 Structural and sector reforms will
have been supported under the “governance”
pillar to promote the qualitative transfor-
mation of the country’s institutional frame-
work. The Bank’s action, which was carried
out mainly through technical assistance ope-
rations, helped to improve regulations gover-
ning economic and training activities, resulting
in the creation of an environment that is more
conducive to private sector development at
the national and local levels (administrative
reforms, decentralization, development of
online services, application of the law on PPPs,
transparency in public procurement and
operation of the Stock Exchange, etc.) of
vocational training and education in the regions).
This support provided through technical
assistance will, where possible, be sustained
by a reform budget support (“high” scenario).
While enabling “quick wins”, all these actions
will have paved the way for private sector
development.
3.2.5 Under the “infrastructure” pillar,
investment projects to develop basic or
innovative infrastructure will have been financed,
if the Bank’s lending capacity permits. This
job-creating approach will improve the attrac-
tiveness of regions while reinforcing food
security (opening up of regions through the
construction of rural roads and roads, impro-
vement of sanitation and access to clean
energy in regions and the implementation of
the Integrated Rural and Urban Development
Programme) and support innovation and
national competitiveness (port and energy).
While enabling “quick wins” (project formulation
and leverage effect) the technical assistance
operations will have layed the necessary
basis for the development of a more inclusive
growth model.
3.3 Risks and Mitigative Measures
u Risk regarding the Bank’s
commitment capacity and financial
integrity
3.3.1 The relative uncertainty surrounding
political events could represent a short-
term risk. Developments in the regional context
could also impact the country’s security. To
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 542
A f r i c a n D e v e l o p m e n t B a n k
address this situation, the proposed flexible
approach will enable the Bank to adapt to all
major changes to protect its financial integrity.
3.3.2 Transition to democracy is often
accompanied by social instability with
attendant insecurity. Demands will cease
only if the transition period is completed as
soon as possible and if a new elected
government is put in place with a clear long-
term strategy to address social demands. In
this respect, the strategy proposed by the
Bank seeks to lessen social instability in a
lasting manner by reducing regional disparities
and supporting job creation.
3.3.3 The economic risk should also be
considered. Macro-economic imbalances
are manageable in the short term, but it is
difficult to predict the outlook over a three-year
period. The country suffered a successive
degradation of its sovereign credit rating by
rating agencies. In this context, the effective
implementation of the IMF-backed programme
should be of paramount importance to investors,
including the Bank. For the latter, changes in
the risk situation will significantly influence the
level and type of operation implemented in
Tunisia. In response, the Bank will adopt an
approach adaptable to the changing risk
situation and promote technical assistance
in the composition of its portfolio – where
necessary (Annexes 2 and 7).
3.3.4 Trends in risk assessment at the
regional and national levels will influence
the level and type of Bank operation (as
investment projects are preferred to budget
support operations in this respect). In this
connection, three scenarios are being
designed to introduce various possible levels
of commitment depending on changes in the
Bank’s financing constraints (with maximum
grants being: (i) low scenario: UA 50 million
and UA 13 million; (ii) median scenario:
UA 150 million and UA 10 million; (iii) high
scenario: UA 300 million and UA 10 million)
(Table 3 and Annex 2).
Table 3: Loan Scenarios
Scenario Grants (AT) inUAM per year
Maximum Loanin UAM per year
Triggers
Low 13 50 Level of concentration of Bank lending in NorthAfrica
Political, economic and social situation
Reports of rating agencies and the IMF
Median 10 150
High 10 300
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 43
A f r i c a n D e v e l o p m e n t B a n k
u Risks regarding ongoing operations
3.3.5. Implementation of operations. The
administration’s capacity to implement ope-
rations was slightly affected by the transition
(Annex 3). In response, the Bank will place
three procurement experts at the disposal of
MDCI for an 18-month period. In addition,
where the context is not conducive to the
design of reform budget support operations,
the Bank will promote direct investments.
3.3.6. Infrastructure maintenance. During a
period of budget constraints, infrastructure
maintenance could suffer. To address this
situation, technical assistance titled “Strategy
for Road Maintenance in Tunisia” will help to
sensitize the authorities.
3.4 Implementation Arrangements
3.4.1 During this transition period, the
Bank’s actions should be implemented
through arrangements that ensure consis-
tency and efficiency:
(i) The search for leverage effects should be
done as indicated in paragraph 3.1.18.
(ii) Communication on the Bank’s operations
should be permanent to strengthen their
ownership (in harmony with the policy on
access to information).
(iii) Project selection should be based on a
matrix of indicators reflecting strategy
objectives and the Bank’s 2013-2022
Strategy (in terms of impact on incomes,
employment, reduction of regional inequalities,
and improvement of the business climate and
sophistication of the economy). To this end,
a filter has been developed to select and
improve project quality.
(iv) Civil society will be involved in all stages
of the project cycle.
(v) The I-CSP implementation will be based
on sustained analytical works to strengthen
the Bank’s advisory role. These works will
contribute significantly to fostering dialogue
with the Government on reforms and innovative
operations.
(vii) The promotion of the “green growth”
objective of the Bank’s 2013-2022 Strategy
during the design of potential projects.
(viii) Gender mainstreaming in project design.
Employment-generating projects should pay
special attention to women’s employment
(such as the Agricultural Development Pro-
gramme), while projects that improve access
to basic services (energy and water) will
ensure that vulnerable and single-parent
households benefit from them as a matter of
priority. Furthermore, the gender perspective
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 544
A f r i c a n D e v e l o p m e n t B a n k
will be taken into account when designing
council investment programmes. Lastly, stra-
tegic studies on the development of training
and skills should take into account gender
mainstreaming to facilitate the transition from
training to employment among women.
3.5 Country Dialogue Issues
3.5.1 The I-CSP is part of an evolutionary
approach based on Tunisia’s political,
economic and social situation. The I-CSP
underpins the implementation of the Bank’s
support operations in a context of transition.
The political events of the next few months,
the macro-economic situation influenced by
an unstable global context and the changing
regional environment oblige development
partners to adopt a flexible approach.
3.5.2 Flexibility is reflected in the institution
of a permanent dialogue and convening
of meetings every two months with
Tunisian authorities to adapt the Bank’s
response. This flexibility will comply with the
framework of the pillars defined in the
strategy paper approved by the Bank’s top
management.
3.5.3 Issues related to climate change
and environmental conservation will be
discussed regularly in order to include this
strategy in the second pillar of the 2013-2022
strategy.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 45
A f r i c a n D e v e l o p m e n t B a n k
IV. Conclusions and Recommendation
4.1 Conclusions
4.1.1 As Tunisia is laying the last foundations
for its new economic, political and social-
model, financial and technicalassistance
needs are enormous. In this context, the
Bank plans to strengthen its support, in terms
of technicalassistance operations, for portfolio
implementation, while adapting the level of
investments to changes in risk assessment
at the regional and national levels.
4.1.2 It is proposed that the Bank’s operation
for the 2014-2015 period should be refocused
on two pillars, namely “governance” and
“infrastructure”.
4.2 Recommendation
4.2.1 The Board is requested to consider
and adopt the proposed I-CSP for the
2014-2015 period.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 546
A f r i c a n D e v e l o p m e n t B a n k
ANNEXES
Annex 1
ENDNOTES
1 Attack on the American Embassy, the killing of two political figures and the November 2013 suicide bombings
2 The Ministry of the Interior, Justice, Foreign Affairs and Defence
3 Requirement of a two-thirds majority for adoption
4Aide-memoire of the Recovery Support Programme Multi-donor Supervision Mission - March 2013(AfDB/WB/EU)
5 The data used is derived from the African Development Bank Statistics Department
6 AfDB, INS, WB, 2013. Measuring Poverty, Inequalities and Polarization in Tunisia 2000-2010, January 2013
7 2.7%, according to AfDB (ESTA)
8 Despite two successive increases in fuel and electricity prices9 According to analyzes carried out in 2013 by the AfDB, IMF and World Bank10 See AfDB Economic Brief: Inflation in Tunisia: Perception and Reality in a Context of Transition, July 201211 See AfDB Economic Brief: Trends in the Exchange Rate of the Tunisian Dinar and Economic Impacts12 See AfDB Economic Brief: Trends in Investment Flows (FDI) in 201213 See AfDB Economic Brief: The Revolution in Tunisia: Economic Challenges and Prospects
14
MPs, ministers and senior government employees henceforth have an obligation to declare their assets. In 2013,Tunisia is preparing its draft declaration of assets and the law on ill-gotten property and the protection of whistle-blowers. A code of conduct for public officials was prepared in 2013 and is presently the subject of anational consultation
15A series of legal (Constitution, Organic Law) and operational (reorganization) measures has been identified to consolidate the role of the Audit Office as a constitutional and legal institution and to strengthen its independence and that of its members
16 See AfDB Economic Brief: The Revolution in Tunisia - Economic Challenges and Prospects, March 201117 IMF, 2012
18Political stability and inefficient administrative bureaucracy appear to be particularly problematic for the businessworld as well as budget deficit, inflation and the efficiency of the labour market
19See AfDB Economic Brief: Capital Market Development in North Africa: Current Status and Future Potential,April 2013
20Through a Central Bank circular which authorized the non-classification of receivables whose counterpartieswere facing financial difficulties due to the Revolution. It is estimated that a classification of these receivables asbad debts would increase the ratio of bad debts in the system to 17%-18% as against 13.5% at end- 2012
21 AfDB, INS, WB 2013. Measuring Poverty, Inequalities and Polarization in Tunisia, 2000-2010, January 2013
22AfDB, INS CRES, 2013. Analysis of the Impact of Food Subsidies and Social Assistance Programmes on thePoor and Vulnerable Population
23 See ADB Economic Brief: Migration of Tunisians to Libya: Dynamics, Challenges and Prospects, January 2013
24Resurgence of the misuse of resources in nature reserves and deforestation as well as uncontrolled constructionin protected areas or poor waste management
25See report “Towards a New Economic Model for Tunisia: Identifying Tunisia’s Binding Constraints to Broad-Based Growth” AfDB, the Tunisian Government and various U.S. agencies (MCC – USAID – the StateDepartment)
26 See AfDB Economic Brief: Migration of Tunisians to Libya: Dynamics Challenges and Prospects, January 2013
27 See AfDB report: Comparative Study of Export Policies of Egypt, Tunisia and South Korea, October 2012
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 47
A f r i c a n D e v e l o p m e n t B a n k
28See AfDB Economic Brief: Open, Smart and Inclusive Development: ICT for Transforming North Africa, April2012.
29See AfDB Economic Brief: The Growth of International Trade in Health Services Export Prospects in North Africa,March 2013.
30 World Bank 2012 - Tunisia: From Revolutions to Institutions.
31Co-contracting enables the production of goods in partnership with another economy, helping to transfer technology and upgrade quality.
32 ILO - Infrastructure and Employment Creation in the Middle East and North Africa.
33 Comete Engineering - Evaluation of the Rades Port.
34 OECD. Strengthening Public-Private Dialogue on Economic Policy Reforms in Egypt, Morocco and Tunisia, 2011.
35 See ADB Economic Brief: Jobs, Justice and the Arab Spring - Inclusive Growth in North Africa, May 2012.
36 See AfDB Economic Brief: What Policies to Deal With Inequalities in Access to Healthcare in Tunisia?
37 See AfDB Economic Brief: Regional Development and Job Creation in Tunisia, Strategic Guidelines.
38OECD (2004), Development Centre Studies, “Institutional Efficiency and Its Determinants, The Role of PoliticalFactors in Economic Growth”.
39See report “Towards a New Economic Model for Tunisia: Identifying Tunisia’s Binding Constraints to Broad-Based Growth” AfDB, Tunisian Government and various U.S. agencies ( MCC- USAID - State Department).
40 See AfDB Economic Brief: Tackling Youth Unemployment in the Maghreb, July 2011.
41See report “Towards a New Economic Model for Tunisia: Identifying Tunisia’s Binding Constraints to Broad-Based Growth” AfDB, Tunisian Government and various U.S. agencies ( MCC- USAID - State Department).
42
See AfDB Economic Brief: Political Transitions and New Socio-economic Bargains in North Africa, May 2012.See report “Towards a New Economic Model for Tunisia: Identifying Tunisia’s Binding Constraints to Broad-Based Growth” AfDB, Tunisian Government and various U.S. agencies (MCC- USAID - State Department).
43Aide-memoire of the Recovery Support Programme Multi-donor Supervision Mission - March 2013(AfDB/WB/EU).
44 WB/AFD/FAO Report: Financing the Agricultural Sector in Tunisia.
45According to the gravity model of trade which best corresponds to empirical trends, the level of trade betweentwo countries is proportional to the product of their GDP and inversely proportional to the square of the distancebetween them (Anderson, 2011).
46Such as the Gabes-Ras Jedir Highway Project co-financed with JICA in 2011 or the Credit Line for SME Development co-financed with the World Bank.
47 Some major donors such as the IsDB and IFAD are not on this list.
48See AfDB/WB publication: Final Report on the Evaluation of the National Public Procurement System in Tunisia,May 2013: This report addresses the weaknesses of the current system and proposes concrete short- and medium-term actions to create conditions conducive to an efficient and transparent procurement system.
49Whose pillars are (a) Growth and Job Creation; b) Regional Development and Social Protection; and (c) Governance.
50See the report “Towards a New Economic Model for Tunisia: Identifying Tunisia’s Binding Constraints to Broad-Based Growth”, AfDB, Tunisian Government and various U.S. agencies (MCC- USAID - State Department).
51 See the AfDB Economic Brief: The Political Economy of Food Security in North Africa, November 2012.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 548
A f r i c a n D e v e l o p m e n t B a n k
Annex 2
RESULTS-BASED LOGICAL FRAMEWORK – TUNISIA’S CSP 2014-2015 – ADJUSTABLE TO CHANGES
Tunisia’s
Strategic
Objectives
Tunisia’s
Strateg
icChalleng
es
Problems
Imped
ing
the
Achievement
of Strateg
icObjectives
Expected
Long
-Term
Outco
mes
(that co
uld
be
expected in
2018)
Expected
outcomes
at the End
of the CSP
2015 Period
Outputs
(that could
be
expected at
the end of
the CSP
2015
period)
AfDB Operations that can be
implemented during the CSP period
Pillars (and
2013-2022
operational
strategy
priorities)
Potential
Technical
Assistance
Potential
Loans
I. Econo
mic
reform
s
II.Infrastructure
mod
ernization
Improving the
business
climate and
competitiveness
Infrastructure
and
upgrading of
transport
systems
25% increase
in container
traffic all over
the national
territory
The waiting
time at the
quay and time
spent at the
quay reduced
by 25%
The upgrading
of port i
nfrastructure is
initiated,
helping to
decongest
maritime t
raffic
The upgrading
project is
designed; the
contract is
concluded -
the use of
PPP is
prioritized
Infrastructure
Investment
project –
Support for
the
development
of the Rades
port (PPP)
(OITC/OPSM)
The deep-sea
port is
selected and
the search for
partners
initiated (by
prioritizing the
PPP method)
The public
sector
consulted the
private sector
on the
identification
of the
deep- sea port
Study -
Market
research on
the option
and type of
deep-sea
port(s),
conduct of
geological
studies
related to site
selection,
conduct of
feasibility
studies and
market
research,
preparation
of BOT or
PPP (OITC /
OPSM) files
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 49
A f r i c a n D e v e l o p m e n t B a n k
I. Econo
mic
reform
s
II.Infrastructure
modernization
Improving the
business
climate and
competitiveness
Complex admi-
nistrative proce-
dures do not
facilitate private
sector develop-
ment and entre-
preneurship
among citizens
Improvement of
Tunisia’s ranking
in Doing Busi-
ness by at least
15 places
Administrative
procedures are
simplified and
their use by the
private sector
and citizens is
facilitated
The diagnosis of
administrative
procedures is
carried out –
measures are
identified and
implemented
Governance
Technical
assistance –
Support for
administrative
reform
(OSGE/ICT4D)
Set of
measures that
can be included
in abudget
support
programme
(OSGE - OSHD)
The public
procurement
system requires
the initiation of
reforms to
comply with
international
standards
The time taken
to award a
contract is
reduced by
50% - 100% of
public contracts
are accessible
online
A more
transparent
regulatory f
ramework is put
in place and a
more efficient
public procure-
ment system
established
The implemen-
tation of the
Public Procure-
ment Reform
Action Plan is at
an advanced
stage and the
new procure-
ment code is
approved
Technical
assistance –
Support for the
implementation
of the Public
Procurement
Reform Action
Plan
(ORPF/ORNA)
The State
should ensure
the compliance
of its indepen-
dent audit
instruments with
standards to
evaluate public
policies in order
to improve the
business climate
and competiti-
veness
The Audit Office
can fully play its
role as a public
policy auditor
Budget support
measures
facilitate the
introduction of
ICTs into the
Audit Office’s
information sys-
tem and audit
instruments
Governance
Budget support
measures
facilitate the
training and
certification of
magistrates in
information
technology,
internal auditing,
computerized
auditing and
corruption
investigation
techniques
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 550
A f r i c a n D e v e l o p m e n t B a n k
I. Econo
mic
reform
s
II.Infrastructure
modernization
Improving the
business
climate and
competitiveness
The institutional
framework is
not conducive
to the
development of
PPPs
Five pilot
projects are
implemented -
helping to raise
TND 1.5 billion
worth of private
investment
The institutional
framework for
PPP formulation
is put in place. A
leverage effect
of at least [2.0 x]
is achieved
through private
sector
investment in
two pilot
projects
Budget support
measures
facilitate the
implementation
of a PPP
regulatory
framework and
a PPP Unit is
operational
Gouvernance
Set of
measures that
can be included
in abudget
support
programme
(OSGE - OSHD)
Increasing
value added
(sophistication)
Secondary
sector: the
industrial sector
lacks a clear
vision to guide
choices in terms
of public
policies and
attract FDIs that
support
innovation
20% increase
in industrial
exports
(in value)
Implementation
of the sector
industrial
strategy action
plan
The diagnosis
and benchmark
of industrial
sector outputs
are carried out;
New industrial
strategies are
approved by the
Government
Governance
Technical
Assistance –
Design of a new
industrial and
economic
transformation
strategy (ORNA)
Tertiary sector:
the
development of
quality private
higher education
that meets
private sector
needs lacks a
conducive
regulatory
framework and
strategic
vision
50% increase in
the number of
students trained
by private
education
(50 % of
women)
Increased
diversification
of private
education
courses
accredited by
the national
quality
assurance body
which meet
market needs
Completion of
diagnostic study
(2014);
Design of the
Integrated Pri-
vate Education
Development
Strategic Plan
(2014)
Study –
Preparation of
the diagnosis of
and prospects
for the
development of
private
higher
education
(OSHD)
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 51
A f r i c a n D e v e l o p m e n t B a n k
I. Econo
mic
reform
s
II.Infrastructure
modernization
Increasing
value added
(sophistication)
Secondary
sector: the
promotion of
green energy is
impeded by the
low mobilization
of concessional
financial
resources
Additional 50
MW for solar
energy
Continuation of
the diversifica-
tion of Tunisia’s
energy mix by
increasing the
share of rene-
wable energy
Start-up of
construction
works of the
Akarit 50 MW
power plant
Infrastructure
Investment
project -
Concentrated
Solar Project
(ONEC)
Tertiary sector:
the promotion of
health service
exports is impe-
ded by competi-
tion from other
countries and
the non- certifi-
cation of health
facilities
50% increase in
the share of
health services
in total service
exports
A health service
export action
plan is imple-
mented - PPP
projects are
identified
The strategic
study on the
export of health
services in
Tunisia is
validated and its
implementation
is ongoing
Infrastructure
and
governance
Investment
project -
Export of health
services -PPP
approach
(OSHD/OPSM)
III. R
egional
rebalancing
IV. S
trengthe-
ning
social,
education and
employm
ent
sectors
Improving
public service
delivery in
regions
The mobilization
of financial
resources is
necessary to f
acilitate access
to basic infra-
structure (water
and sanitation,
energy and
roads). This
mobilization is
affected by the
lack of a strate-
gic plan or
feasibility study
250 km of
additional rural
roads, resulting
in the creation
of 2 000
additional jobs
in the targeted
(40 % for
women)
The opening up
of regions is
accelerated and
infrastructure is
maintained
The feasibility
study is carried
out and the 500
km of Rural
Roads Project is
launched
Infrastructure
Technical
Assistance- for
the preparation
of the 500 km of
Rural Roads
Project (OSAN)
Investment
project -500
km of rural
roads (OSAN)
250 km of
additional
express high-
ways linking
interior governo-
rates to the
coast, resulting
in the creation
of 3 000 additio-
nal jobs in the
targeted regions
(40 % for
women)
The
Transportation
Plan and Road
Management
and
Maintenance
Strategy are
available - roads
are developed
Infrastructure
Technical
Support –
Design of a
transport
master plan and
the Road
Management
and Mainte-
nance Strategy
(OITC)
Investment
project – roads
in regions (OITC)
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 552
A f r i c a n D e v e l o p m e n t B a n k
III. R
egional
rebalancing
IV. S
trengthe-
ning
social,
education and
employm
ent
sectors
Improving
public service
delivery in
regions
4 000 additional
households
have access to
a source of
clean energy
(15%
for single
parents)
Improvement of
access to a
modern energy
source (natural
gas) in the
disadvantaged
areas of the
western region
The Project for
Secure and
Reliable Access
to Natural Gas
in the disadvan-
taged regions of
the Western
Region is
launched
Infrastructure
Investment
project - Project
for the
Development of
a Network for
the Transportation
and Distribution
of Natural Gas
in the Western
Region (ONEC)
95% of rural
dwellers have
access to
drinking water
Improving
access to
drinking water
and liquid and
solid sanitization
in regions
Feasibility
studies are
being finalized
with MIC grant
resources and
start-up of
RDWS project
Infrastructure
Technical
assistance for
the development
of sanitation
master plans by
governorate (12
disadvantaged
governorates)
and solid waste
management
(OWAS)
Investment
project - RDWS
Programme and
Sanitization
Programme of
30 councils with
less than 10
000 inhabitants
(OWAS)
Feasibility
studies are
available and
the start of the
Project to
Sanitize 30
Councils with
less than 10
000 inhabitants
is launched
The devolution /
decentralization
of government
services is
limited by an
inappropriate
institutional and
territorial
framework (one
third of the
Tunisian territory
is not divided
into councils)
and a great
need forinvest-
ment in some
areas in the
regions.
Creation of 5
regional urban
service agencies
(50%
of public
investments are
made at the
local level).
New councils
are established
from new
territorial
divisions, the
distribution of
the financial
resources
transferred to
local authorities
is improved and
the activities of
regional urban
service agencies
are initiated.
Studies on (i)
deconcentration
and its impact
on decentraliza-
tion; (ii) territorial
division and divi-
sion of the na-
tional territory
into councils;
and (iii) transfer
of financial re-
sources and
budgeting are
carried out and
reforms
Governance
(AT)
Infrastructure
(Investment)
Technical
assistance -
Support for the
implementation
of the
decentralization
strategy.
Establishment of
regional urban
service agencies
and joint
support for the
implementation
of investment
programmes
(OSHD / OSGE)
Investment
project -
Support to the
2014-2018
Council
Investment
Programme in
new councils
ensuing from
the creation of
new territorial
units (OSHD)
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 53
A f r i c a n D e v e l o p m e n t B a n k
III. R
egional
rebalancing
IV. S
trengthe-
ning
social,
education and
employm
ent
sectors
identified are
implemented.
The institutional
framework for
PPP projects is
defined for
councils.
Division of the
entire national
territory into
councils (100%)
Council
investment
programmes in
new councils
are launched
The Council
Investment
Programme
2014-2016 in
new councils is
launched
Access to
employm
ent by
developing
skills and
opportunities in
regions
The
decentralization
of government
services is
limited by lack of
capacity,
particularly in
the domain of
education
Reduction of
regional gaps in
PISA tests by no
less than 25%
(girls and boys
being at par)
Upgrading of
the human
resources in
charge of
management in
the 24 regional
education
offices to
enhanced the
decentralized
management of
education
All the 26
regional
education
offices are
equipped with
qualified human
resources;
partnerships are
developed with
specialized
capacity buil-
ding institutions;
decentralized
management
tools are
developed and
disseminated in
the regions
Governance
Technical
assistance –
Training regions
in decentralized
management of
education
(OSHD)
Set of measures
that could be
included in a
budget support
program
me
(OSHD - OSGE)
Youth
employability is
limited by access
to poor quality
vocational
training and a
mismatch
between job
offer and
demand
Reduction of the
unemployment
rate of new
entrants into the
graduate labour
market by 20%
(similar for
women and
men )
Access to
quality
vocational
training is
increased and
training meets
private sector
needs
Budget support
measures
facilitate the
creation of new
sectors in
regions
according to the
needs of the
economy and
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 554
A f r i c a n D e v e l o p m e n t B a n k
III. R
egional
rebalancing
IV. S
trengthe-
ning
social,
education and
employm
ent
sectors
Access to
employm
ent by
developing
skills and
opportunities in
regions
the strengthe-
ning of rotation
and learning in
companies -
and increased
communication
Gouvernance
Set of measures
that could be
included in a
budget support
program
me
(OSHD - OSGE)
20% reduction
in the
unemployment
rate of
graduates from
vocational
training schools
(similar for
women and
men )
The
employability of
graduates from
vocational
training schools
is being
improved
Budget support
measures
facilitate the
establishment of
a professional
integration
monitoring
system and an
institutional
ramework that
promotes the
involvement of
the productive
sector
The
development of
employment
opportunities in
rural areas is
limited by lack
of training,
agricultural
infrastructure
and opportuni-
ties outside the
agricultural
sector
15% reduction
in the
unemployment
rate in the
Zaghouane rural
area (similar for
women and
men )
An Integrated
Agricultural
Development
Programme is
launched in
Zaghouan
Region
The programme
has been
launched
Infrastructure
Investment
project -
Zaghouan
Integrated
Agricultural
Development
Programme
(OSAN)
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 55
A f r i c a n D e v e l o p m e n t B a n k
I-CSP 2012-2013 COMPLETION REPORT AND PORTFOLIO PERFORMANCE REVIEW (2013)
CONCLUSIONS AND RECOMMENDATIONS
Annex 3
I-CSP (2012-2013)
Restrict the number of pillars and be more selective about the expected out-comes of the next I-CSP to take into account the Bank’s resource constraintand Tunisia’s unstable environment.
Strengthen the alignment of analytical works with the objectives and expectedoutcomes of the interim strategy.
Strengthen strategic dialogue and communication with development partnersand the Government on the search for the co-financing of the implementation ofoperations and analytical works.
Improve the capacity to monitor and evaluate the I-CSP by developing resultindicators that are simple, verifiable and limited in number for CSP pillars.
Combine general budget support operations for structural reforms and sectorbudget support operations to increase strategic public investments in infra-structure (transport, energy and telecommunications) to preserve productivecapacity and create direct and indirect employment in the regions.
Portfolio (Provisional Review 2012)
For the Government
Auditing. Make adequate arrangements to meet the six-month deadline forsubmitting audit reports as from the 2012 financial year to the Bank and to ensure the verification of their quality by the CGF by indicating in particular thestatus of the recommendations of previous audits and appropriate measuresto implement them.Auditing. Pursue dialogue with the Audit Office and development partners toagree on a roadmap in 2013 to enable the Office to audit externally-funded projects.Reporting. Improve the regularity and quality of project progress reports bystrengthening ongoing project monitoring and evaluation units.Accelerate the effectiveness and fulfilment of conditions precedent to the firstdisbursement of non-performing loans (SME line of credit, Treated WastewaterQuality Improvement Project);Studies. Accelerate the award of delayed study contracts (BTS, health serviceexports, sanitation strategy) such as to enable the first disbursement of MICFgrants before end-December 2012. These grants are liable to cancellation ifnot disbursed.Public procurement. Adopt the Reform Action Plan before end-December2012.For the Bank
Supervision. Maintain an adequate rate of project supervision in 2013 (average greater than 1.5) with 2 missions for decentralized projects.Mid-term review. In 2013, programme the mid-term review of projectswhose implementation is at an advanced stage.Launching of new projects. In 2013, carry out at least one launching missionfor new projects with ORPF and FFCO assistance.Replenishment of the special account of decentralized projects. Coordinatepost-audit missions (FFCO) to build up of project working capital in 2013 withsupervision missions.Provide assistance (technical and financial) for the good governance reformsof the public sector initiated by the Government in 2013, which have directconsequences on the viability and performance of the Bank’s portfolio. (Publicprocurement, Auditing, Citizen Participation).
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 556
A f r i c a n D e v e l o p m e n t B a n k
Annex 4
TUNISIA’S PORTFOLIO (UA) (JANUARY 2014)
Dept. Name FinancingClosureDate
Approval Amount Disbur. Age
Private SectorOPSM3 ETAP corporate loan AfDB Private 29 Nov. 10 17 Mar. 10 97.64 100% 3.88
OPSM3 Enfidha Airport project AfDB Private 31 Mar. 10 14 Jan. 09 60.03 100% 5.05
OPSM3 Enfidha Airport (conditionaltranche) AfDB Private 31 Mar. 10 14 Jan. 09 1.83 0% 5.05
OPSM3 BH Tunisie AfDB Private 28 Feb. 06 27 Feb. 02 25.18 100% 11.93
OPSM3 BTEI- Line of credit AfDB Private 30 Apr. 07 20 Dec. 02 35.34 100% 11.12
OPSM APEX SME Line of Credit Facility AfDB Public 31 Dec. 16 13 Jul. 11 32.55 50% 2.56
Water and SanitationOWAS2 RDWS Programme AfDB Public 31 Dec. 17 12-oct-11 83.78 15% 2.31
OWAS2 Treated Wastewater Quality Improvement Project AfDB Public 31 Dec. 14 11 Jan. 12 28.67 1% 2.06
OWAS2 PCI Study – Grand Tunis MIC 31 Dec. 13 6 Oct. 09 0.58 12% 4.32
OWAS2 Study on Zaarat Seawater Desalination MIC 31 Dec. 14 5 Aug. 09 0.63 27% 4.49
OWAS2 Study on Tunisia’s SanitationStrategy MIC 30 june 14 4 Dec. 09 0.57 13% 4.16
AWF 2050 Water Vision and Strategy AWF 31 Dec. 14 10 Jan. 11 1.05 7% 3.06
AWF SINEAU AWF 31 Dec. 14 22 Dec. 09 1.74 71% 4.11
TransportOITC2 Gabes - Ras Jedir Highway AfDB Public 31 Dec. 17 21 June 11 121.35 17% 2.62
OITC2 Road Project - VI AfDB Public 31 Dec. 16 15 Sept.10 208.52 64% 3.38
OITC2 Road Project - V AfDB Public 31 Dec. 13 11 June 08 154.03 75% 5.64
Agriculture and Irrigation
OSAN1 Sector Investment Project AfDB Public 31 Dec. 14 11-Dec. 08 20.24 65% 5.14
OSAN1 North Gafsa PDAI AfDB Public TBC 13 Feb. 13 19.54 0% 0.96
OSAN1 Kairouan PDAI AfDB Public 31-Jul. 14 29 Mar. 06 15.73 71% 7.85
OSAN1 GDA Support MIC 31-Dec. 14 20 Oct 09 0.59 15% 4.28
OSAN1 Grant - Gabes and Gafsa PDAI MIC 31-Dec. 14 26 Jul. 12 0.38 48% 1.52
SocialOSHD2 Economic Recovery Support Project AfDB Public 31 Dec. 13 28 Nov. 12 342.48 100% 1.18
OSHD2 Sec. Education Support Project II AfDB Public 31 Dec. 13 28 Sept.05 52.84 89% 8.35
OSHD3 Study on Emerging Diseases MIC 31 Dec. 13 3 Nov. 09 0.58 100% 4.25
OSHD3 Export of Health Services MIC 31 Dec. 12 10 Sept.09 0.53 25% 4.32
OSHD2 Study on the Development of Cultural Industries MIC 31 Dec. 13 22 Nov. 10 0.27 15% 3.19
ORNA Humanitarian Assistance on theLibyan Border SRF 31 Dec. 11 11 Mar. 11 0.65 100% 2.90
Governance and Reforms
OSGE2 Preparatory Study on the Com-mercial Law Strengthening Project MIC 31 Dec. 13 24-sept-10 0.32 16% 3.36
OITC E-government and Open government MIC TBC 20 Dec. 12 0.68 0% 1.12
ESTA2 Statistical Capacity Building Programme II (SCB II) MIC 31 Dec. 14 30 Mar. 11 0.49 50% 2.84
ORNA Study on Micro-credit SystemEvaluation (BTS) MIC 31 Dec. 12 6 Jan. 10 0.14 0% 4.07
ORNA ITCEQ Support MIC 31 Dec. 11 3 Dec. 09 0.2 90% 4.16
EnergyONEC1 Sanitation Restructuring Project AfDB Public 31 Dec. 13 2 Sep. 09 42.03 78% 4.42
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 57
A f r i c a n D e v e l o p m e n t B a n k
Annex 5
TRENDS IN TUNISIA’S SOVEREIGN RATINGS
Date of modificationMoody’s ratings
Moody’s ratingsscale
Date of modificationof S&P’s ratings
S &P’s ratingsscale
Date of modificationFitch ratings
Fitch ratingsscale
Investment grade
Investmentgrade
Investmentgrade
Aaa AAA AAA
Aa1 / Aa2 / Aa3 AA+ / AA / AA- AA+ / AA / AA-
A1 / A2 / A3 A+ / A / A- A+ / A / A-
Baa1 BBB+ BBB+
17 April 2003 Baa2 21 March 2000 BBB 24 May 2001 BBB
April 199519 Jan. 2011
Baa3Sept. 1995
16 March 2011BBB-
Sept. 19952 March 2011
BBB-
Speculativegrade
Speculativegrade
Speculativegrade
28 Feb. 2013 Ba1 BB+ 11 Dec. 2012 BB+
30 May 2013 Ba2 23 May 2012 BB BB
25 Nov. 2013 Ba3 19 Feb. 2013 BB-30 Oct. 2013
BB-BB-
B1 / B2 / B3 16 Aug. 2013: B B+ / B / B- B+ / B / B-
Caa1/Caa2/Caa3CCC+/CCC/CCC
-CCC
Ca / C CC / C CC / C
SD / D RD / D
* This table does not include the dates of confirmation of ratings.*Bleu = Date of positive rating action; Red = Date of negative rating action.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 558
A f r i c a n D e v e l o p m e n t B a n k
1. Introduction
On 7 June, the Executive Board of the Interna-
tional Monetary Fund (IMF) approved a 24-
month standby arrangement of an amount
equivalent to SDR 1.146 billion (USD 1.74 billion)
for Tunisia to support its economic reform
programme for the 2013-2015 period intended
to strengthen budgetary and external flexibility
and foster more robust and inclusive growth.
The Executive Board’s decision helped to
ensure the immediate disbursement of USD
150 million. The disbursement of the remaining
amount will span the duration of the programme
and subject to eight reviews. The first review will
take place at end-September. As a reminder,
this is the third loan agreement between Tunisia
and the IMF (the preceding agreements were
concluded in 1964 and 1986).
The main objectives of the IMF-backed
programme are to: (i) strengthen budgetary
and external flexibility (through monetary and
budgetary policies); (ii) lay the foundations for
growth (by addressing the vulnerabilities of the
banking sector, facilitating better composition
of expenditure and implementing an ambitious
structural reform programme that promotes
private sector development and reduces regional
disparities and pervasive State intervention); (iii)
protect vulnerable groups (social assistance
mechanisms and systematic evaluation of the
social impact of proposed reforms). Thus,
they are a continuation of multi-donor budget
support programmes in which the AfDB
participated, thus underscoring the consistency
of the analysis of the various technical and
financial partners and the relevance of the
reforms encouraged.
Annex 6
IMF: USD 1.74 BILLION STANDBY ARRANGEMENT
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 59
A f r i c a n D e v e l o p m e n t B a n k
Annex 7
SIMULATION IN TERMS OF LOANS
PRE-IDENTIFIED PROJECTS (IN GREEN - LOW SCENARIO, IN ORANGE - MEDIANSCENARIO AND IN BLUE - HIGH SCENARIO)
Scenario Maximum Loan inUAM per year
Grant (AT)UAM per year
Triggers
Low 50 13 Level of concentration of Bank lending in NorthAfrica
Political, economic and social situation
Ratings of rating agencies
Median 150 10
High 300 10
TimeHorizon
Scenario Instrument Project Name Amount(UA million)
Department
Pilier - Infrastructure
2014
Low
Sector loanProject to Develop Natural GasTransportation and DistributionNetwork in the Western Region
30-40 ONEC
Sector loan Rural Development Project 22-30 OSAN
Median Sector loan Farm Road Project 40 - 60OITC - OSPM
ifi PPP
2015
Low
Sector loan Projet de pistes agricoles 27-43 OSAN
Sector loan
Concentre Solar Project (under leverage effect and shortterm economic viability condi-tions)
30-50 ONEC
Median
Sector loanRural Drinking Water Supply Programme
30 OWAS
Sector loan Road Project 30-50 OITC
High Sector loan Council Investment Project 75-100 OSHD
Pillar - Governance
2014 High Sector loan Health Service Export Project 68 OSHD
2014 HighBudget support
Budget Support Programme 100-250 OSGE and OSHD
2015 HighBudget upport
Budget Support Programme 100-250 OSGE and OSHD
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 560
A f r i c a n D e v e l o p m e n t B a n k
POVERTY AND UNEMPLOYMENT IN THE REGIONS
Annex 8
Governorate Unemployment Rate in 2010
Poverty in 2010
Governorate Unemployment Rate in 2010
Poverty in 2010
Ariana 10.4 5.8 Manouba 14.7 9.1
Beja 11.2 22.1 Mednine 13.8 18.8
Ben Arous 11.7 5.0 Monastir 5.7 5.5
Bizerte 12.3 19.4 Nabeul 11.1 3.6
Gabes 17.4 15.1 Sfax 7.1 9.4
Gafsa 28.5 22.2 Sidi bouzid 14.0 28.3
Jendouba 17.0 28.6 Siliana 15.3 20.3
Kairouan 10.2 23.9 Sousse 13.0 7.7
Kasserine 20.1 46.9 Tataouine 22.7 21.7
Kebili 17.1 21.8 Tozeur 16.8 18.8
Le Kef 11.5 30.4 Tunis 13.8 13.1
Mahdia 12.0 8.5 Zaghouan 4.8 11.1
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 61
A f r i c a n D e v e l o p m e n t B a n k
LIST OF ECONOMIC AND SECTOR STUDIES ON TUNISIA CARRIEDOUT SINCE 2011
Annex 9
Study Title Date of PublicationAfrican Economic Outlook 2013 - Structural Transformation and Natural Resources inAfrica
June 2013
Final Report on the Evaluation of the National Public Procurement System in Tunisia May 2013
Capital Market Development in North. Africa: Current Status and Future Potential April 2013
Trends in Investment Flows (FDI) in 2012 March 2013
Development of International Trade in Health Services: North Africa’s Export Prospects March 2013
Measuring Poverty, Inequalities and. Polarization in Tunisia, 2000-2010 January 2013
Identifying Tunisia’s Binding Constraints to Broad-Based Growth January 2013
Towards a New Growth Model for Tunisia. June 2012 Seminar Proceedings December 2012
The Political Economy of Food Security in North Africa November 2012
Could Oil Shine like Diamonds? How Botswana Avoided the Resource Curse and its Im-plications for a New Libya
November 2012
Unlocking North Africa’s Potential through Regional Integration October 2012
Comparative Study on Export Policies in Egypt, Tunisia and South Korea October 2012
Forecasting the Costs and Benefits of Implementing Basel III for North African EmergingEconomies: An Application to Egypt and Tunisia
September 2012
Tunisia: Economic and Social Challenges Beyond the Revolution September 2012
Inflation in Tunisia: Between Perception and Reality in a Context of Transition July 2012
Political Transitions and New Socio-economic Bargains in North Africa May 2012
Jobs, Justice and the Arab Spring: Inclusive Growth in North Africa May 2012
African Economic Outlook 2012 - Promoting Youth Employment May 2012
The African Development Bank Group in North Africa 2012 - A Year of Transition May 2012
Open, Smart and Inclusive Development: ICTs for Transforming North Africa April 2012
Tunisia - Interim Strategy Paper 2012-2013 January 2012
New Libya, New Neighbourhood: What Opportunities for Tunisia? January 2012
Islamic Banking and Finance in North Africa December 2011
Libya: Post-war Challenges October 2011
Distortions to Incentives and Agricultural Policy in Tunisia: A Preliminary Analysis September 2011
Poverty and Inequality in Tunisia, Morocco and Mauritania August 2011
Tackling Youth Unemployment in the Maghreb July 2011
Impact of Libya’s Conflict on the Tunisian Economy: A Preliminary Assessment July 2011
The African Development Bank Group in North Africa - 2011 April 2011
The Revolution in Tunisia: Economic Challenges and Prospects March 2011
Chinese Investments and Employment Creation in Algeria and Egypt January 2011
The BRICs in North Africa: Changing the Name of the Game? January 2011
Alleviating Poverty in Rural Tunisia: An Integrated Approach to Agriculture July 2010
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 562
A f r i c a n D e v e l o p m e n t B a n k
STATUS OF IMPLEMENTATION OF AfDB BUDGET SUPPORT MEASURES IN 2011 AND 2012
Annex 10
Measures Status of Implementation Remarks
Economic Recovery and Inclusive Development Support Programme - 2012
Lifting the ceiling of the tax on industrial, commercial or professionalestablishments
Implemented.Very satisfactory
TND 60 million collected in2012
Adoption of a circular on the establishment of an information system forsocial protection programmes
Adopted. Unsatisfactory
The implementation of theplan has been delayed
Adoption of a decree establishing a national health care accreditationbody and defining its functions and laying down its administrative,scientific and financial organization as well as functioning
Adopted. Unsatisfactory
The appointment of members has delayed theoperationalization of thisbody
Adoption of a decree establishing a participatory process for theevaluation and review of the administrative procedures governingthe conduct of economic activities
Adopted. Unsatisfactory
The review is ongoing
Adoption of a decree laying down procedures for the functioning ofthe microfinance control authority
Adopted. The authority is operational.
Adoption of Decrees No. 2012-890 and No. 2012-891 of 24 July2012 to amend the law relating to venture capital and mutual invest-ment fund companies and relax the terms and conditions of theiroperation
Adopted. Satisfactory
Ongoing
Adoption of a decree to amend and supplement Decree No. 349-2009 of 9 February 2009 establishing National Employment Fundprogrammes and the terms and conditions of their benefit
Adopted. Satisfactory
New employment programme and the reorganization of ANETIare underway
Adoption of a decree defining the composition of the National Evaluation, Quality Assurance and Accreditation Authority and itsfunctioning
Adopted. Unsatisfactory
The operationalization ofMES has been delayed
Adoption of a note on the publication of public finance-related dataAdopted. Satisfactory
Budget information is published on MF’s website
Approval by the Government of the report on the evaluation of thenational procurement system according to OECD/DAC methodologyas well as the ensuing action plan
Adopted. Satisfactory
The implementation of theAction. Plan is ongoing. Anew procurement code isbeing finalized.
Adoption of a circular issued by the Head of Government outliningthe provisions of Decree-Law No. 2011-41 of 26 May 2011 governingaccess to the administrative documents of public bodies
Adopted, but notapplied.
Some past laws governing the administrationare contradictory andshould be amended.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 63
A f r i c a n D e v e l o p m e n t B a n k
Governance and Inclusive Development Support Programme 2011
Improvement of targeting quality and extension of the coverage ofthe Needy Families Support Programme
Ongoing Targeting quality is beingimproved
Review of criteria for the allocation of investments to disadvantagedregions
Completed
Besides human development indicators,criteria should be improved
Adoption of a comprehensive programme for the active support ofjob-seekers (AMAL)
Adopted. Satisfactory
Grants have been awarded to 200 000 unemployed
Issuing of a Presidential decree transferring the management of theNational Employment Fund (Fund 21/21) to the Ministry of VocationalTraining and Employment
Completed. Satisfactory
Increased transparency inthe allocation of funds
Adoption of the roadmap on microfinance reformsOngoing. Unsatisfactory
The action plan has beenimplemented; orders relating to accounting andexternal audit standardsshould be issued
Setting up of special delegations with the participation of civil societyin lieu of municipal councils
Completed. Satisfactory
Special delegations have been set up in 236 delegations
Strengthening mechanisms for the evaluation of public services bycitizens
Partly implemented
The process has beenlaunched in three regions,but it is yet to be institutionalized
Adoption of a decree-law on access by the public to informationheld by the Government
Decree adopted,but not implemented.Unsatisfactory
Its implementation is impeded by lack of awareness and poor dissemination among actors and the population
Adoption of a decree establishing the National Public ProcurementReform Coordination and Monitoring Committee (NPPCMC)
Adopted. Satisfactory
The Committee managesthe entire public procurement system reform process
Publication of annual Audit Office reports in fullImplemented.Satisfactory
The reports of 2005 2006,2007, 2008, 2009, 2010and 2011 have been published
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 564
A f r i c a n D e v e l o p m e n t B a n k
On 14 January 2011, Tunisian civil society
which, hitherto, was virtually absent from the
national public scene, entered an intense
development phase resulting in the creation
of numerous organizations. This unprecedented
development also gave an opportunity to
technical and financial partners in the country,
including the African Development Bank, to
renew their relationships with this now inevitable
actor in Tunisia. In this context, the dialogue
initiated during the preparation of the previous
I-CSP was consolidated through five work-
thrusts.
(i) Conduct of an in-depth study and survey
on “Participatory Governance: How to
Improve Public Service Delivery through
State-Citizen Partnership”. The identification
work initiated after the Revolution gave rise
to genuine literature review. The report was
prepared on the basis of interviews with key
stakeholders (citizens, civil society organizations
(CSOs) and public authorities) and a survey of
256 Tunisian associations in 24 governorates
to analyze the present context of participatory
governance in Tunisia and the capacity of
Tunisian associations. The African Development
Bank now has a genuine qualified database as
well as an accurate assessment of the sector,
its potential and needs. Meetings held during
this exercise also helped the Tunisian civil
society to better understand the role and
operations of the AfDB. The relations developed
have subsequently been maintained.
(ii) Holding of regular meetings with civil
society to discuss issues of common
interest. During the past two years, the AfDB
has sought to involve CSOs in many events
relating to political, financial, economic and
social challenges in North Africa, particularly
monthly conferences organized within the
framework of the North Africa Policy Series. In
fact, besides building their capacity through
the direct dissemination of information from
this research, their contribution to debates
helps to understand certain field realities
which could be reflected in the Bank’s strategy
and operations in North Africa. During these
meetings, the Bank also serves as a catalyst
by promoting dialogue between the public
sector, the world of research and other tech-
nical and financial partners. This dialogue has
been complemented by the organization of
quarterly national conferences (in collaboration
with the administration, in most cases) where
civil society has played a very active role to
share their views with those of institutions,
CIVIL SOCIETY PARTICIPATION IN STRATEGY PREPARATION
Annex 11
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 65
A f r i c a n D e v e l o p m e n t B a n k
including the AfDB (this includes, among
others, a workshop on employment strategy,
the presentation of the findings of the study
on poverty, etc.).
(iii) The participatory approach adopted for
the design of AfDB projects in Tunisia. At
the operational level, the direct involvement of
civil society has been strengthened through:
(i) the consultation of civil society during the
identification and formulation of the Bank’s
operations and (ii) the involvement of civil
society in the evaluation of activities. The best
example of this approach is perhaps the
fruitful exchange of ideas on priority reforms
needed in Tunisia during the preparation of
the 2012 budget support. These discussions
contributed significantly to fine-tuning proposals
and helped to better meet the expectations
of the Tunisian population. This exercise
should be maintained and its mechanisms
institutionalized.
(iv) The Souk At-tanmia Project which is a
partnership involving civil society as an
actor and a beneficiary. Souk At-tanmia is
inspired by the Bank’s reflections on its new
framework of commitment with civil society,
particularly its desire to “involve more CSOs
and beneficiaries in local projects aimed at
reducing poverty with potential large-scale
impacts”. Souk At-tanmia is a partnership
incorporating several dimensions capable of
stimulating development and promoting job
creation. Its main objective is to encourage
and support ideas from a wide range of
participants such as young entrepreneurs or
civil society organizations by providing them
with necessary financing and support. Colla-
boration with TOUENSA, Souk’s partner and
civil society representative, was instrumental
in involving more associations in promoting
entrepreneurship in Tunisia, thus facilitating
contact with the target public thanks to the
close ties established with the population.
TOUENSA facilitated the dissemination of
information and helped candidates to prepare
and submit their applications by establishing
10 focal points and mobilizing a network of
50 associations.
(v) Consultation workshop on the new
interim Country Strategy Paper 2014-2015
and bilateral meetings. The consultation
workshop on the new interim Country Strategy
Paper 2014-2015, which took place on the
Bank’s premises on 24 September 2013 at
the end of the evaluation mission, helped to
reap the benefits of partnership with civil
society developed over the last two years.
Some fifteen participants from various
backgrounds discussed the relevant needs
and priority areas of the I-CSP 2014-2015
in Tunisia with Bank staff. Discussions with
Bank staff and associations helped not
only to promote dialogue and strengthen
diagnosis, but also to increase the visibility
and legibility of the Bank’s action amongst
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 566
A f r i c a n D e v e l o p m e n t B a n k
key opinion relays. The majority of organi-
zations dwelled on the importance of such
meetings while civil society representatives
reiterated their interest in developing a long-
term strong and direct commitment with the
AfDB to achieve tangible impacts. This
workshop completed a series of bilateral
meetings on specific topics such as public-
private partnerships with public and private
sector representatives.
Though the Bank has demonstrated the
capacity to devise a new form of relationship
with Tunisian civil society over the last two
years, efforts are still needed. The identification
of entities should be continuous and progressive
like the changing sector. The frequency of
meetings should not wane and new interactions
could be developed. Special attention could
be paid to regional associations which are
more difficult for the Bank to access.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 67
A f r i c a n D e v e l o p m e n t B a n k
1. Introduction
The Bank’s Department of Fiduciary Services
carried out an evaluation of the framework
and fiduciary risks in Tunisia (March 2012) as
part of the preparation of the CSP in September
2013.
2. Overview of National Systems and Fiduciary Risks
2.1. Public Finance Management:
the evaluation of Tunisia’s public finance
using PEFA methodology (June 2010)
showed that the Tunisian public finance
management system sufficiently supports the
implementation of fiscal discipline, the strategic
allocation of resources and the provision of
services to citizens. The strengths are the
preparation and strict implementation of the
annual budget, internal controls and checks
and a non-accrual, but reliable accounting
system. However, priority areas remain,
namely: ensuring the efficiency of the entire
budget system through multi-year budget
planning and functional budget classification,
rationalizing internal audit bodies, establi-
shing a modern accounting system that
complies with international standards, impro-
ving time frames for submitting accounts and
strengthening the external audit system.
Thus, performance budgeting (PB) has been
on the drawing board in Tunisia since June
2010. It includes several components,
namely: (1) multi-year budgeting and results-
based management; (2) the review of budget
nomenclature; (3) the reform of the system of
control and accountability of authorizing
officers; (4) the reform of the accounting
system to upgrade it to IPSAS standards and
accrual accounting; and (5) the modernization
of information systems. Several ministries
and cross-cutting departments have tested
the budget system and performance indicators.
It should be noted that in 2012 the Bank’s
PARDI programme supported the adoption
of a decision by the Ministry of Finance
to publish detailed budget information at
end-2012. To date, the implementation of
several performance budgeting components
has been delayed due to the transition
period. Concerning external audits, the Audit
Office is preparing a reform proposal whose
key orientations are a series of legal and
operational measures needed to consolidate
the role of the Audit Office as a constitutional
and legal institution, strengthen the indepen-
PUBLIC FINANCE AND PROCUREMENT MANAGEMENT SYSTEMS: BANK’SRISKS AND FIDUCIARY STRATEGY
Annex 12
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 568
A f r i c a n D e v e l o p m e n t B a n k
dence of the Office and its members and
institute better monitoring by Parliament.
Since the issuing of the Decree of 7 May 2011
authorizing the full publication of the latest
annual reports of the Audit Office, the Office
was reorganized and it recruited 40 new
magistrates. It has also submitted to the
Constituent Assembly a proposal relating to
its status and guarantees of independence for
possible inclusion in the draft Constitution. An
analysis of the Tunisian control and audit
system carried out in 2013 with the assistance
of OECD re-emphasized the need to reform
the audit system.
2.2. Procurement:
Tunisia’s legal and regulatory framework for
procurement is governed by the 17 Decem-
ber 2002 Decree (and subsequent instru-
ments, the last of which dates back to May
2011). The Bank evaluated this framework in
2011 and concluded that its risk was mode-
rate. This evaluation helped to conclude that
all national LCB procedures are compatible
with the Bank’s fiduciary obligations, excep-
ting some differences identified. Although it
guarantees globally acceptable procedures,
the system is characterized by (i) a problem
of efficiency, with long contract cycle time
frames; (ii) a need to improve the access of
foreign contractors to public procurement; (iii)
a redress and complaint management
system that is not independent; and (iv) a
confused institutional framework, with the
non-separation of some functions which are
incompatible. To address these problems, in
accordance with commitments made within
the framework of PARDI, the Government
carried out an overall evaluation of the procu-
rement system to initiate the structural
reforms necessary for its modernization. The
system was evaluated using the OECD/DAC
methodology (internationally accepted tools)
during the first half of 2012, with AfDB and
World Bank technical support. It gave rise to
a report and an action plan approved by the
Government in August 2012. The implemen-
tation of the actions contained in this plan will
complete the structural reform of the national
procurement system initiated by the Govern-
ment and help to: (i) increase efficiency in
order to reduce delays in the implementation
of contracting cycles; (ii) strengthen
2.3. Summary of fiduciary risks and mitigative measures:
the fiduciary risk as a whole is deemed
moderate, based on the most recent diag-
noses of public finance management and
corruption perception. However, this risk can
be reduced by: (i) initiating far-reaching reforms
of external auditing to guarantee its adminis-
trative and financial independence and
professionalism; (ii) ensuring good prospects
for continuing and completing the reform
initiated in 2010 in order to improve budget
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 69
A f r i c a n D e v e l o p m e n t B a n k
management and introduce management by
objectives; (iii) fostering and pursuing the
implementation of the action plan to reform
the public procurement system adopted in
August 2012; (iv) developing the national anti-
corruption strategy and establishing the legal
anti-corruption framework; (v) the willingness
and efforts of TFPs and the Government
to rapidly reach a lasting and satisfactory
consensus on the external auditing of projects
implemented through external financing and
provide the Audit Office with the means to
fulfil this mandate; and (vi) the consideration
by the Tunisian Government of the possibility
of establishing a unified framework for
planning, coordinating and monitoring
reforms related to public finance manage-
ment in order to ensure synergy and better
information dissemination.
3. Bank’s Fiduciary Strategy in Tunisiafor the I-CSP 2013-2014 period
3.1. Recommended level of use of the NationalPublic Finance Management System
In accordance with the provisions of the
Paris Declaration and the Accra Forum, the
Bank’s decision to use the national public
finance management system was examined.
This examination showed a moderate
fiduciary risk, enabling the Bank to maintain
an approach based primarily on national
procedures and systems, while continuing
its support for the reform of the system.
However, the approach could be adapted
and revised during the period. Hence:
Budget support using the entire public
expenditure chain could continue, subject
to the implementation, in the medium term, of
the mitigative measures recommended above
(2.3). The use of budget support resources will
be audited through the examination of
Settlement Laws by the Audit Office, which
laws will be published within the statutory
deadlines. The Bank reserves the right to
request any auditing of the financial flows of
support operations and/or the performance of
programmes it deems necessary.
Public investment projects/programmes
will use most of the existing execution and
control procedures of the public system,
though with restrictions on external auditing.
Thus, besides systematically including external
financing in the State budget, priority will be
given to the use of the existing capacity and
resources of public entities, the opening of
project accounts in the Central Bank of Tunisia,
disbursements that are consistent with the
Bank’s procurement rules as well as with
public expenditure authorization and control
rules, the internal auditing of projects by public
entities, systematic inclusion in the ADEB
(budget execution) system and in the local
accounting system of pay masters. Where
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 570
A f r i c a n D e v e l o p m e n t B a n k
the local public system is limited, separate
accounts will be kept in order to have
accounts by financing and by component
and the necessary financial reports. Each
evaluation will propose appropriate measures
to mitigate specific fiduciary risks and justify,
where necessary, the need for alternative
arrangements. Regarding the external auditing
of investment projects/programmes, arran-
gements will continue to be considered
on a case by case basis, pending the
outcome of the dialogue initiated with
Tunisian authorities. For long, project auditing
was entrusted to the General Financial
Controller (GFC). However, given his/her
position, the GFC does not meet INTOSAI’s
criteria for independence of supreme audit
institutions. Thus, it is necessary to extend
ongoing dialogue with the authorities to other
partners and to find solutions to support the
Audit Office and give it the means to perform
its task of ensuring the external auditing of
projects financed by the State and TFPs.
Where independent implementing agencies
that already have a private external auditor
are used, the same auditor will be proposed
for the project.
One of the elements of the Bank’s strategy
in Tunisia is continuous support for the
continuation of the reform of the public
finance management system. This support
could be reflected in increased dialogue with
the authorities to improve consultation with
other TFPs on the one hand and through
assistance for strengthening the capacity and
technical resources of the Audit Office, imple-
menting one or more components of the
reform of Objectives-based Budget Mana-
gement as well as support for the reform of
external auditing, on the other hand.
3.2. Recommended Level of the Use of the National Procurement System
To ensure harmonization, the Bank will
continue to implement its strategy for the
use of the Tunisian national system. This
strategy will be consistent with the chosen
approach to be implemented by the Bank in
its RMCs. It comprises the following distinct
phases: (a) Phase 1: strengthening of the use
of national procedures in the LCBs specified
in Bank operations; and (b) Phase 2: use of
the entire national procurement system,
together with its legal and regulatory frame-
work, institutional framework, purchasing
practices and control and redress mechanism.
Under Phase 1 of its strategy, the Bank will
soon initiate discussions with the Tunisian
Government to carefully examine the major
differences contained in its regulatory frame-
work. Once agreement is reached on the
report submitted to the Tunisian party,
Tunisian procedures may be used for all
LCBs financed by the Bank during the period
covered by this CSP. Phase 2 of the Bank’s
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 71
A f r i c a n D e v e l o p m e n t B a n k
initiative is expected in the medium/long
term. It will entail (according to modalities
to be determined and approved by Bank
authorities) using the entire national system.
This stage, which must be preceded by a
system performance evaluation using the
OECD/DAC methodology, will be feasible
only after the implementation of the Action
Plan activities.
During this CSP period, the Bank will s
upport Tunisia to address the challenges
identified and presented above. Specifically,
the Bank’s procurement operation will seek
to: (i) carry on dialogue with the Government
(to overcome the differences observed
following the evaluation of the national
procedures by the Bank) so as to sign a letter
of understanding for the use of the existing
national procedures for LCBs and (ii) provide
support to revitalize the implementation of
the actions identified and included in the
action plan ensuing from the evaluation of
the national procurement system (using the
OECD/DAC methodology) approved by the
Government.
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 572
A f r i c a n D e v e l o p m e n t B a n k
TABLE OF DETAILED ANALYSIS OF COUNTRY RISKS BY PILLAR
Pillars
Indicators
Risk Factors
Initial
Risk
Mitigative Measures
Residual
Risk
PEFA 201
0, interview
with M
in. F
inance,
DGRE, CGABE,
DGCPR
➢Credibility PI 1-4
➢Com
prehensiveness
PI 5-7
➢Transparency
PI 8-10
➢Policy-based
budgeting PI 11-12
➢Efficacy
(predictability and
monitoring of
implementation)
PI 13-21
➢No multi-year budget
➢Non-functional classification of the budget
➢Large number of internal control bodies and
missions, related high costs, risk of duplication
or conflict
Low
i.Ongoing or planned measures
➢Implementation of a comprehensive objectives-
based budget management project, including:
-budget reform incorporating multi-year
budgeting and results-based management
-revision of budget nomenclature
-reform of the system of control and
accountability
of authorizing
officers,
incorporating performance auditing
-reform of the accounting system to upgrade
it to ISPAS standards and accrual accounting
-modernization of information systems
The implementation of objectives-based budget
management has been delayed since 2011
due to the ongoing transition process.
➢Measure on budget transparency and more
information disclosure (Open Government)
contained in the PARDI 2012 programme
ii.(Other Bank recommendations
➢The Government should complete the
reforms
of objectives-based budget
management which will help to establish
multi-year budget planning and functional
budget classification and streamline internal
audit bodies
Low
PEFA 201
0, interview
with DGCRP and
the
Aud
it Office
➢Comprehensiveness
➢Efficacy
➢Quality
➢Opportunity
➢PI 22-25
➢PI 26-28
examination
➢Reliable management, but not accrual,
accounting: risk relating to the exhaustiveness
and relevance of financial information
➢Still long delays in tabling the Settlement Bill
before the Audit Office
➢Previous reports of the Audit Office were
published in 2011, but their future publication
is not yet guaranteed by instruments
➢The scope of external auditing is inadequate,
but changing
➢Insufficient independence safeguards for the T
unisian Audit Office
➢Limited content of parliamentary scrutiny
➢The auditing of external financing entrusted by
the Government to the GFC which does not
meet all INTOSAI’s criteria: there is still an
audit risk on operations controlled solely by
the GFC
Moderate
Low
1- Budget: Preparation, Execution, Control 2- Financial information and auditing
i.Ongoing or planned measures
-Accounting System Reform Project within
the framework of objectives-based budget
management to upgrade to accrual accounting
and comply with IPSAS accounting standards.
Design slowed in 2011
-The deadline for submission of accounts by
the DGCRP has improved; 1.5 years in 2
009 and 2010. The statutory period may
be reduced within the framework of objectives-
based budget management
-Permanent change in the scope of auditing
of the Audit Office (CDC), with a risk-based
approach in the sampling of units. The
capacity building plan for the year is submitted
-New guidelines presented by the Audit Office:
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 73
A f r i c a n D e v e l o p m e n t B a n k
➢Increased delays in submitting project audit reports over
the past three years
Low
Rep
ort o
n the evaluation
of national procurement
proced
ures fo
r LC
Bs
unde
r projects financed
by th
e Bank; CPA
R 200
4;PEFA 201
0 Interviews
with CSM
➢Prohibition of the access (or prerequisites) of foreign
contractors to CBs
➢Uncontrolled participation of public enterprises in CBs
➢The bid opening mechanism contains provisions impeding
transparency
➢Possibility of modifying the content of bids after they have
been opened
➢Possibility of using specific evaluation criteria for local
contractors (fair treatment)
➢The current redress and complaints management me
chanism is not independent (subject to political control)
and is hampered by a conflict of interest (COSEM and
MSC fall under the same authority)
Moderate
Low
-Consolidation of the Constitution and legal
framework - organizational and financial
autonomy vis-à-vis the executive – Consolidation
of the independence of members and functional
independence – Abolition of presidential
discretion on the publications in the Organic
Law – institution of review and monitoring
sessions by Parliament – expansion of
competences. Ten sub-committees have
been set up to prepare the revision of the
organic law of the Audit Office (CDC)
-The CDC has tabled before the Constituent
Assembly a bill relating to its status and
guarantees of independence in the new
Constitution being drafted
ii.Other Bank recommendations
➢The Government should prioritize the far-reaching
reform of the external auditing system to enhance
the independence of the Audit Office, improve
its scope and means and monitoring of reports
by Parliament
➢Similarly, dialogue between TFPs and the
authorities on the external auditing of projects
financed with external resources was expected
to help find solutions to enable the Audit Office
to fulfil its mandate
➢The Government should complete the reform
of objectives-based budget management to
upgrade it to a modern accrual accounting
system that is consistent with international
standards and to improve the time frame for
auditing accounts
i.Ongoing or planned measures
➢In the short term, the Bank and Government
should initiate a dialogue to satisfactorily
address the differences that are incompatible
with the Bank’s fiduciary obligations and
contained in the report on the evaluation of
national LCB procedures
➢The Government should take support measures
(training of actors) enabling the smooth
implementation of interim measures which
are the subject of revision of procurement
regulations carried out in May 2011
➢The Government should revitalize and pursue
the implementation of the action plan of the
measures identified through the evaluation of
the national procurement system carried out
using OECD/DAC methodology
3- Procurement
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 574
A f r i c a n D e v e l o p m e n t B a n k
3 - Procurement - This pillar has been the subject of a separate assessment ORPF.1
Transparency International,
interview with
Min. F
inance, interview
with M
inistry GAC
➢Corruption Perceptions Index 2012, 41/100
(43/100 in 2011)
➢Anti-corruption measures initiated, but to be pursued
Moderate
i.Ongoing or planned measures
➢A ministry in charge of Governance and
Corruption Control (at the SG of Government)
has been established
➢An independent anti-corruption body will be
reviewed and institutionalized
➢Tunisia carried out an integrity scan in 2013
➢MPs, ministers and
senior government
employees are obliged to declare their assets
➢Bills on the declaration of assets and legislation
on ill-gotten property being prepared in 2013
➢The Code of Conduct for Public Officials is
prepared in 2013 and is the subject of a national
consultation. Still to come into force
ii.Other Bank recommendations
➢Develop a national anti-corruption strategy
➢Continue to reform objectives-based budget
management to ensure accountability and
efficiency in resource management
➢Reform external auditing to combat corruption
Low
PEFA 201
0, interview
with M
in. F
inance
➢Lack of a unified framework for planning, coordination
and monitoring public finance management-related
reforms: risk of low synergy and sequencing and
inadequate dissemination of reforms and monitoring
of their progress (also identified by PEFA 2010)
Moderate
i.Ongoing or planned measures
➢Point brought to the attention of the Ministry of
Finance
ii.Other Bank recommendations
➢The Government should consider empowering
a body of the Ministry of Finance to: (i) design
a strategy and a unified and sequenced public
finance management system action plan, in
consultation with the departments of the Ministry
of Finance, sector ministries and audit bodies;
(ii) coordinate and report on the status of
implementation; (iii) establish a framework for
dialogue and partnership with TFPs for the
implementation of this strategy
Low
Overall assessment of fiduciary risk
Moderate
Low
4- Corruption Adequate Reform Plan andMonitoring
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 5 75
A f r i c a n D e v e l o p m e n t B a n k
1. Trend. Although debt represented 60% ofGDP on average in the 1990s, the drastic
debt reduction strategy implemented by
Tunisian authorities helped to reduce public
debt ratio to 40.4% of GDP in 2010. This
adjustment mainly concerned external debt
which rose from 65% of GDP in 2002 to 48%
of GDP at the end of 2011 after a drastic
budget adjustment accompanied by a mode-
rate current account deficit. The authorities
have also adopted shrewd borrowing policies
by prioritizing recourse to concessional loans
from multilateral development banks and EU
grants rather than borrowing on the interna-
tional market. However, the expansionary
fiscal policy implemented by the Government
after the January 2011 Revolution, coupled
with a fall in GDP (-1.6%) and a growing
current account deficit, has contributed to
increasing the public debt ratio to 44.6% in
late 2011.
In 2012, a return to growth (+3.8%) helped to
maintain the debt-to-GDP ratio at about 44%,
despite growing budget deficits. However, the
projections made by the IMF within the frame-
work of the preparation of the USD 1.78 billion
standby agreement approved on 7 June 2013
confirmed that the public debt ratio will
increase steadily by 5% in the short term to
attain 49% of GDP by 2015 and decline
again progressively in the medium term to
about 44% in 2018. This expected increase
in the public debt ratio is expected to stem
mainly from an increase in the estimated
budget deficit needed to continue to meet
sustained social demands while providing the
resources required to recapitalize public
sector banks (cost estimate: 3% of GDP ) as
well as strengthen public enterprises (cost
estimate: 7% of GDP) and the social protection
system. This favourable debt dynamics,
however, calls for the streamlining of public
finance based on an overall deficit reduced
to 2.3% of GDP in 2018 and maintaining
continued real growth rates (4.6% on average)
during the 2013-2018 period as against
3.2% during the 2008-2013 period.
2.Structure and outstanding debt.As at 30 June2013, Tunisia’s nominal outstanding public
debt stood at TND 33.275 billion, as against
TND 31.418 billion in June 2012, representing
a 6% increase. In terms of GDP, the nominal
outstanding public debt during the same
period was 44.5% of GDP, as against 43.8%
of GDP at end-2012. External debt represents
the largest share of public debt. As at 30
Annex 13
MEDIUM- AND LONG-TERM DEBT SUSTAINABILITY ANALYSIS
T u n i s i a : I n t e r i m C o u n t r y S t r a t e g y P a p e r - 2 0 1 4 - 2 0 1 576
A f r i c a n D e v e l o p m e n t B a n k
June 2013, external debt represented
58.1% of total outstanding debt and 41.9%
of domestic debt. Domestic debt is financed
mainly through the issuance of short- and
medium-term treasury bills, while external
debt is financed through borrowings from
multilateral financial institutions (mainly the
African Development Bank and the World
Bank) and from foreign countries (France,
USA and Japan). However, Tunisia’s debt
is mainly in Euros and its current and future
debt servicing is denominated in that currency,
representing 52.3% of the outstanding debt
to be paid at maturity in 2025.
3.Debt sustainability in the medium term. Tunisia’sdebt strategy, which was defined within the
framework of the IMF-backed programme,
presupposes the transfer of the bulk of public
debt to foreign debt. The latter should therefore
increase to 55% of GDP in 2015 as against
29.5% expected in 2013, before declining to
49.2% by 2018 owing to a favourable current
account balance. Sensitivity tests show that
the external debt ratio is resistant to most
negative external shocks, except a major
exchange rate depreciation. The relatively
low level and profile of Tunisia’s debt (low
average interest rate and relatively long
maturity) will, however, enable it to resist
most shocks, excepting a major real
exchange rate depreciation. The external
debt ratio will remain below 58% of GDP in
all scenarios during the projection period.
Thus, a lasting negative shock on growth or
current account would increase the debt ratio
to 55%-58% of GDP, while an increase in the
average interest rate would have a much
lesser impact. However, a potential significant
real depreciation of 30% of the exchange rate
in 2013 compared to the benchmark would
increase the debt ratio to around 80%
of GDP.
Furthermore, public debt seems to be highly
vulnerable to negative shocks. Public debt
could reach 60% of GDP by 2018 under a
scenario in which public finance management
is streamlined in the medium term. The debt
dynamics is also very sensitive to actions
aimed at maintaining the primary deficit to the
current and historic level. Lastly, over 60%
of public debt is denominated in foreign
currency. An occasional depreciation of 30%
would increase the public debt-to-GDP ratio
in the short term to about 63% and then
decline to 56% by 2018. However, the
dynamics of public debt will resist fairly well
to an interest rate shock and stand at a
sustainable level of 50% in the medium term.