2012/13 Finance Report Month 9 - Dudley and Walsall · • The £300k contingency fund agreed at...
Transcript of 2012/13 Finance Report Month 9 - Dudley and Walsall · • The £300k contingency fund agreed at...
2012/13 Finance Report Month 9
1
2
2012/13 DWMH Finance Report Month 9 Page
• Key Messages 3
• Overall Summary and RAG Assessment 4-5
• Trust Income Statement including Functional Analysis 6
• Capital Programme 7
• Activity and Income 8
• Financial Performance Metrics 9-10
• Cash Flow Statement 11
• Debtor and Creditor Performance 12
• Workforce 13-15
• Cost Improvement Target Achievement 16
• Budget Reconciliation 17
• Statement of Financial Position (Balance Sheet) 18
Key Messages
Continued strong financial
performance
• Due to continued strong financial performance the Trust Board decided to revise the forecast
surplus outturn from £1,081k to £1,800k at Month 7. This report reflects this decision.
• The Trust is reporting a year to date surplus of £1,241k, £175k ahead of the revised Month 9 plan of
£1,066k
• This revenue position delivers a Monitor Metric score of 4.05 for Month 9, ahead of the overall
original 2012/13 plan of 3.65
• The surplus is driven in the main by a large number of substantive vacancies, lower than normal
non-pay spend, continued control over temporary staffing expenditure and recovery of income
budgets though block contracts and cost and volume arrangements
• The Trust also continues to fund non-recurrent expenditure solely through non-recurrent means
CIP identified and transacted in full –
time to continue to monitor the impact
and plan for future years
• The Trust transacted the remaining 2012/13 CIP target during Month 6
• Financial achievement of the CIP is contingent on delivering the expected financial position for the
Trust
• The Trust is now focusing on the detailed planning of the 2013/14 schemes and future years under
the management of the CIP PMO
Income – Cost and Volume
performance remains strong, block
contract impact
• Income is ahead of plan to date – mainly due to negotiated block contracts for 2012/13
• Two contracts remain on cost and volume and are performing well, Birmingham and Worcestershire
Bank, Agency and locum spend is
within manageable levels, but has
increased
• The £300k contingency fund agreed at budget setting is now reduced to £2k; the balance being
committed. The forecast of break even for medical budgets remains for Month 9, although some
additional non-recurrent funding has been required to manage operational demands
• Bank and Agency spend on the wards has increased in recent months and significantly during
Month 9, particularly on Holyrood ward. Although wards remain within budget overall due to the
level of funded vacancies, this requires close monitoring to ensure this remains under control
3
Overall Summary and RAG Assessment
Commentary
Revenue Position
• Another good month for the Trust with an in month
surplus of £160k (Month 8, £163k)
• The Trust is ahead of the revised budgeted plan by
£175k at Month 9.
• As a result of the sustained strong performance seen
this financial year the forecast was revised from
£1,081k to £1,800k at Month 7 and the Trust remains
on track to achieve this
CIP 2012/13 Delivery
• The Trust transacted the full balance of CIP during
Month 6, resulting in full delivery for 2012/13 and is now
concentrating on detailed planning for future years
Cash
• The cash balance reflects the strong revenue
performance, and remains significantly ahead of plan.
This reflects the principal fact that there remains
expenditure to be incurred on agreed Strategic Change
Reserve schemes
Capital
• Both of the major capital schemes for 2012/13, the
Canalside project, and the DPH Block 7 project, were
nearing completion as at 31st December 2012.
Budgetary Reserves
• The majority of the Strategic Change Reserve monies
have been devolved to Corporate and Operational
Services. The Trust’s recurrent reserve is now
committed.
4
Statement of Comprehensive Income - Financial Position to 31st December 2012
Annual In Month Year To Date
Plan Plan Actual Variance Plan Actual Variance
Income £000 £000 £000 £000 £000 £000 £000
Revenue From Activities
Revenue-NHS Clinical 63,812 5,318 5,312 (6) 47,858 47,882 24
Revenue-Non NHS Clinical 174 15 17 2 134 147 13
Total Revenue From Activities 63,986 5,333 5,329 (4) 47,992 48,029 37
Other Operating Revenue
Revenue-Education & Training 1,473 120 131 11 1,106 1,177 71
Revenue NHS Non-Clinical 857 67 84 17 655 633 (22)
Other Revenue 613 51 50 (1) 460 560 100
Revenue-Employee Benefits 694 58 60 2 520 563 43
Total Other Operating Revenue 3,637 296 325 29 2,741 2,933 192
Total Revenue 67,623 5,629 5,654 25 50,733 50,962 229
Expenditure
Pay (49,545) (4,154) (4,041) 113 (37,020) (35,983) 1,037
Clinical Supplies and Services (1,917) (160) (156) 4 (1,438) (1,364) 74
Other Costs (11,081) (982) (1,032) (50) (7,895) (8,511) (616)
Expenditure Reserves (498) 147 (26) (173) (1,226) (1,776) (550)
Total Operating Expenditure (63,041) (5,149) (5,255) (106) (47,579) (47,634) (55)
EBITDA 4,582 480 399 (81) 3,154 3,328 174
Depreciation (1,238) (116) (113) 3 (929) (929) 0
Amortisation (219) (18) (18) 0 (164) (164) 0
Net Operating Surplus 3,125 346 268 (78) 2,061 2,235 174
PDC (1,350) (113) (113) 0 (1,013) (1,013) 0
Interest Receivable 25 2 2 0 19 19 0
Net Surplus /(Deficit) 1,800 237 160 (77) 1,066 1,241 175
Technical Adjustment 0 0
Technical Surplus 1,800 237 160 (77) 1,066 1,241 175
Overall Summary and RAG Assessment Continued
5
0200400600800
1,0001,2001,4001,6001,8002,000
£'0
00
Run Rate 2012/13Cumulative Budgeted Planned Run RateRevised Cumulative Budget
Actual Run Rate
Expected Run Rate
0
500
1,000
1,500
2,000
2,500
£'0
00
Capital Programme 2012/13
Cumulative Planned Spend
Cumulative Actual Spend
Revised Expenditure Profile
£2,781k
£2,804k
0 1,000 2,000 3,000
CIP Target
Transacted
£'000
CIP 2012/13
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Actual vs Forecast Cash 12/13 and Beyond
Actual Cash Forecast Cash 12/13 Cash Benchmark
Trust Income Statement Including Functional Analysis
Commentary
• Healthcare income continues to perform well,
despite a small under-performance in NCAs
against budget this month
• The IT network infrastructure costs are
reflected in the IT overspend to date. To be
reviewed through budget setting process. An
extension of IT Contract staff has been agreed
until March 2013, increasing the cost pressure
to the IT function
• Corporate Operations under spend includes
vacancies held within the Psychology
management structure
• Estates budgets are over spent due to
recurrent cost pressures in the Facilities
contract and Walsall Locality recharges from
NHS Dudley
• Estates costs are increasing due to the Estates
service SLA remaining constant despite taking
on posts internally in preparation for a full in-
house Estates service
• Within Acute & Older Adult services, a year to
date under spend has been generated from
vacancies in CRHT and in Older Adult CMHTs,
and lower than average ward costs in the early
part of the year
• Early Intervention services include high number
of vacancies in the Primary Care and CAMHS
teams
• Recovery under spend is due to vacant posts
within Day Services, pre-ST
• The YTD medical under spend is a timing issue
only, in particular training budgets are under
spent year to date. Medical services hold an
uncommitted contingency budget at Month 9 of
£2,000
• HR department is forecast to under spend due
to slippage on a non-recurrent Workforce
vacancy with a delay to recruitment
6
Annual Plan In Month Year to Date
Variance
Forecast I&E
2012/13 Plan Actual Variance Plan Actual Variance Outturn Outturn
£'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000
Revenue From Activities
NHS Dudley 28,550 2,379 2,379 0 21,412 21,412 0 0 28,550
NHS Walsall 30,400 2,534 2,534 0 22,799 22,786 (13) (13) 30,387
Birmingham contracts 483 40 41 1 362 429 67 75 558
Sandwell PCT 1,926 160 161 1 1,444 1,444 0 0 1,926
South Staffs PCT 391 33 33 0 293 293 0 0 391
Wolverhampton PCT 491 41 41 0 368 368 0 0 491
Worcestershire PCT 32 3 5 2 24 36 12 15 47
NCG 1,389 116 116 0 1,042 1,042 0 0 1,389
NCAs 150 13 3 (10) 113 72 (41) (50) 100
Total Revenue From Activities 63,812 5,319 5,313 (6) 47,857 47,882 25 27 63,839
Corporate Functions
Chief Executive (739) (64) (53) 11 (547) (527) 20 2 (737)
Corporate Affairs (1,152) (104) (84) 20 (842) (818) 24 14 (1,138)
Corporate Medical (909) (84) (84) 0 (656) (666) (10) 4 (905)
Corporate Operations (2,020) (188) (173) 15 (1,456) (1,262) 194 124 (1,896)
Corporate Estates (2,757) (237) (251) (14) (2,045) (2,340) (295) (349) (3,106)
Corporate Finance (1,196) (101) (100) 1 (894) (900) (6) 6 (1,190)
Corporate Performance & IT (2,433) (223) (216) 7 (1,766) (2,014) (248) (228) (2,661)
Corporate Human Resources (1,342) (117) (104) 13 (964) (801) 163 17 (1,325)
Central Reserves (498) 147 (26) (173) (1,226) (1,776) (550) (366) (864)
Total Corporate Functions (13,046) (971) (1,091) (120) (10,396) (11,104) (708) (776) (13,822)
Operational Services
Acute and Older Adults
Management and Administration (937) (71) (49) 22 (639) (480) 159 195 (742)
Acute Services (8,837) (736) (676) 60 (6,626) (6,314) 312 371 (8,466)
Acute Estates (3,998) (332) (351) (19) (3,023) (3,071) (48) (55) (4,053)
Older Adults (6,319) (528) (588) (60) (4,736) (4,863) (127) (241) (6,560)
Total Acute & Older Adults (20,091) (1,667) (1,664) 3 (15,024) (14,728) 296 270 (19,821)
Community Services
Management and Administration (552) (65) (84) (19) (356) (386) (30) (91) (643)
Community Services (4,231) (358) (361) (3) (3,168) (3,126) 42 26 (4,205)
Early Intervention (6,873) (573) (523) 50 (5,155) (4,714) 441 477 (6,396)
Recovery Services (3,848) (320) (294) 26 (2,886) (2,769) 117 177 (3,671)
Community Estates (1,165) (109) (136) (27) (853) (897) (44) (110) (1,275)
Total Community Services (16,669) (1,425) (1,398) 27 (12,418) (11,892) 526 479 (16,190)
Medical Services (12,231) (1,021) (1,003) 18 (8,972) (8,937) 35 0 (12,231)
Psychology Services 0 0 0 0 0 0 0 0 0
Total Operating Services (62,037) (5,084) (5,156) (72) (46,810) (46,661) 149 (27) (62,064)
Sub Total 1,775 235 157 (78) 1,047 1,221 174 0 1,775
Interest Receivable 25 2 3 0 19 20 1 0 25
Net Surplus/(deficit) 1,800 237 160 (78) 1,066 1,241 175 0 1,800
Technical Adjustment 0 0 0 0 0
Technical Surplus 1,800 237 160 (78) 1,066 1,241 175 0 1,800
Capital Programme
7
Commentary
• Dorothy Pattison Block 7 –
VAT ruling received - 54% of VAT
to be recovered on Openspace
invoices (£40k to be recovered on
December VAT return)
All 3 valuations included in
expenditure to date – project to be
finished and account to be finalised
11/01/2013
• New Hill House –
Fences only to be funded from
2012/13 Capital Expenditure –
detail awaited
• Canal Side Capital Works –
Requested forecast final spend on
this project as substantially
complete as of 31st December 2012
Proposed Capital Funding April 12 – March 15 2012/13 2013/14 2014/15
£'000 £'000 £’000
MHPT depreciation 1,365 1,435 1,505
Proceeds from Sale of Non Current Assets 0 100 0
Proposed Cash to capital conversion 460 390 0
Total Funding Available 1,825 1,925 1,505
Expenditure YTD
Proposed Capital Schemes 2012/13 2012/13 Actual Accrued Total Variance
Priority £'000 £'000 £'000 £'000 £'000
Schemes not completed Prior Years
DPH Bathrooms Complete 34 34 0 34 0
BFH Aid Call Complete 11 12 0 12 -1
Kings Hill Refurbishment Complete 24 24 0 24 0
Schemes proposed for 2012/13
Dorothy Pattison Block 7 (Ambleside to Grasmere) Started 760 597 0 597 163
Canal Side Capital Works Started 600 415 2 417 183
BFH Entrance to Wards Complete 10 6 0 6 4
BFH Window Replacement (Kinver & Wrekin) Complete 108 108 0 108 0
Relocation of Modular Building to BFH Started 30 20 0 20 10
Blakenall Village Centre Added Space Started 60 46 0 46 14
BFH Sky Lights A/B
BFH Street Lights B 40 0 0 0 40
DPH Switchboard C 15 0 0 0 15
BFH Ventilation & Heating 30 0 0 0 30
BFH Sandringham Refurbishment Complete 5 5 0 5 0
New Hill House 0 0
Digital Dictation - Big Hand Started 67 0 0 0 67
Utensil Washer Complete 14 15 0 15 -1
Contingency 17 0 0 0 17
Total Cost of Proposed Schemes 1,825 1,282 2 1,284 541
Activity and Income
Commentary
• Activity recording continues to
rise, With quarter 3 being
marginally up on quarters 1 and
2. This is particularly
encouraging given that quarter 3
included the Christmas period.
• This suggests an underlying
increase in the levels of activity
recorded and reflects work
underway to improve this.
• Financial performance is also
strong as a result. Although the
majority of the Trust's income is
now on shadow cost and
volume (block), strong activity
recording will help safeguard
baseline income levels going
forward and will help during
contract negotiations
• Commissioners have indicated
that some services may be on
cost and volume contracts for
2013/14, specifically those
currently outside of care cluster
development.
• Walsall's contract is showing an
underperformance of £12k
which represents
underperformance on 2011/12
CQUIN schemes.
8
Service name Currency Q1 Q2 Q3
Total Of
Recorded Value
Over/(Under) Performance
(£)
Consultant Services : Outpatient Setting : Adult Other : First Attend Appointment 244 254 320 818 (211)
Consultant Services : Outpatient Setting : Adult Other : Follow Up Attend Appointment 3,306 3,301 3,165 9,772 (27,579)
Consultant Services : Community Setting : Adult Other : First Appointment 1 2 6 9 (8,429)
Consultant Services : Community Setting : Adult Other : Follow Up Attend Appointment 22 21 18 61 (18,044)
Consultant Services : Outpatient Setting : Elderly : First Attend Appointment 64 53 50 167 (23,817)
Consultant Services : Outpatient Setting : Elderly : Follow Up Attend Appointment 306 263 309 878 9,679
Consultant Services : Community Setting : Elderley : First Attend Appointment 156 181 166 503 (4,445)
Consultant Services : Community Setting : Elderley : Follow Up Attend Appointment 458 543 495 1,496 17,237
Inpatients : Adult : Intensive Care ECA Bed Day 53 69 59 181 4,288
Inpatients : Adult : Acute Care Bed Day 7,685 7,466 8,338 23,489 (135,671)
Inpatients : Elderly Bed Day 4,898 4,937 4,976 14,811 (33,642)
Inpatients : Rehab Bed Day 724 717 709 2,150 (3,039)
Day Care Facilities : Regular Attendances : Adult Day Rate 1,254 1,264 1,070 3,588 (44,286)
Day Care Facilities : Regular Attendances : Elderly Day Rate 1,856 2,064 1,739 5,659 106,871
Memory Clinic Day Rate 657 726 737 2,120 108,197
Community Mental Health Team : Adult Face To Face Contact 11,010 11,862 12,037 34,909 188,695
Community Mental Health Team : Adult Non Face To Face Contact 1,068 1,202 1,390 3,660 19,940
Elderly Services Community Team Face To Face Contact 3,654 3,776 3,493 10,923 (138,341)
Elderly Services Community Team Non Face To Face Contact 679 992 950 2,621 29,142
Primary Care Team Face To Face Contact 10,566 10,461 11,418 32,445 416,874
Primary Care Team Non Face To Face Contact 169 202 331 702 1,829
Therapeutic Recovery Service Face To Face Contact 1,373 1,131 1,138 3,642 (89,778)
Therapeutic Recovery Service Non Face To Face Contact 25 23 21 69 (2,889)
AMH Employment Services Face To Face Contact 575 565 460 1,600 (5,075)
AMH Employment Services Non Face To Face Contact 313 315 338 966 1,871
Adult Eating Disorder Community Team Face To Face Contact 272 290 229 791 6,094
Adult Eating Disorder Community Team Non Face To Face Contact 6 3 11 20 (1,300)
Crisis Resolution Home Treatment Team: Adult Face To Face Contact 5,939 6,460 6,888 19,287 134,210
Crisis Resolution Home Treatment Team: Adult Non Face To Face Contact 1,485 1,445 1,688 4,618 69,286
Assertive Outreach Team : Adult Face To Face Contact 2,001 1,622 1,500 5,123 (442,478)
Assertive Outreach Team : Adult Non Face To Face Contact 111 141 149 401 (5,391)
Early Intervention in Psychosis Service: Adult Face To Face Contact 1,985 2,007 1,808 5,800 8,002
Early Intervention in Psychosis Service: Adult Non Face To Face Contact 109 83 163 355 2,129
Other Mental Health Specialist Teams: Child Face To Face Contact 4,320 4,353 4,530 13,203 76,802
Other Mental Health Specialist Teams: Child Non Face To Face Contact 167 307 246 720 12,589
Drug & Alcohol Teams: Adult Face To Face Contact 6,559 6,878 6,499 19,936 1,586
Drug & Alcohol Teams: Adult Non Face To Face Contact 2,321 2,691 2,341 7,353 12,537
Criminal Justice Liaison Team Face To Face Contact 506 353 244 1,103 45,674
Criminal Justice Liaison Team Non Face To Face Contact 70 116 70 256 10,386
Psychiatric Liaison Team Face To Face Contact 390 426 508 1,324 30,276
Psychiatric Liaison Team Non Face To Face Contact 195 195 210 600 9,871
Clinical Psychology Face To Face Contact 3,059 2,749 2,094 7,902 8,678
Clinical Psychology Non Face To Face Contact 135 263 105 503 2,112
Unadjusted Total before CQUIN 80,746 82,772 83,016 246,534 350,440
CQUIN 6,843
Unadjusted Total 357,282
Adjustment for Walsall Shadow as not on cost and volume (199,972)
Adjustment for Dudley Shadow as not on cost and volume 81,080
Adjustment for Sandwell Shadow as not on cost and volume (134,379)
Adjustment for Wolverhampton Shadow as not on cost and volume 34,201
Adjustment for South Staffs Shadow as not on cost and volume 20,415
Sub Total 158,629
NCA Budget (112,500)
Walsall 11/12 Write Back - CQUIN (12,059)
Birmingham 11/12 Write Back (3,432)
NCAs 11/12 Write Back (5,209)
Roundings (13)
As Per Ledger Month 9 25,416
Financial Performance Metrics
9
Commentary – Financial Performance Metrics Slide 10
• These metrics represent Monitor’s Compliance Framework “early warning indicators” – measures that may indicate future financial difficulty, and have been adopted by
the SHA as part of their Provider Management Regime, which the Trust is required to report on monthly
• The analysis provided shows that this month the Trust is rated green against all criteria except for one relating to the Working Capital Facility (WCF). The Trust Board
made a decision to procure a Working Capital Facility at the Trust Board meeting in December. The agreement does contain a default clause, although the Trust has
worked extensively with the chosen provider on wording of this clause to ensure it meets the definition of a committed facili ty
• The Trust had previously reported spending less than 75% of planned capital expenditure year to date. As expected and reported, capital expenditure increased,
meaning that this criteria is also now rated green
• Regarding the <5% of debtors being over 90 days target, and Trust excludes those balances provided for in the I&E position already, and those balances where
payment has been agreed and is expected. The Trust has transparently informed the NTDA of this method of calculation
Commentary
• Strong Monitor metric performance
continues, reflected by the strong
revenue performance year to date
• The top table reflects the Trust’s original
plan, and the revised plan reflecting the
revised planned surplus, against which
Month 9 performance is measured
• All metrics have maintained scores from
last month, delivering an overall metric
of 4.05
• The new LTFM has brought with it a
change to the ROA metric; this is now
called NRAF and adjusts for any debt
used to fund the purchase of assets
Monitor Financial Risk Rating
Metric
Original
Plan
Original
Score -
Plan
PlanScore -
Plan
Weighted
FRR - Plan
Actual -
Month 09
Score - Actual
Month 09
Weighted FRR
- Actual Month
09
EBITDA margin 5.6% 3 6.8% 3 0.75 6.5% 3 0.75
EBITDA, % achieved 100.0% 5 100.0% 5 0.50 105.5% 5 0.50
Net Return after Financing 2.4% 4 3.9% 5 1.00 3.6% 5 1.00
I&E surplus margin 1.6% 3 2.7% 4 0.80 2.4% 4 0.80
Liquidity ratio 50.3 4 50.8 4 1.00 53.4 4 1.00
Weighted Average 3.65 4.05 4.05
Amended FRR Criteria Metric Weight 5 4 3 2 1
EBITDA margin 25% 11% 9% 5% 1% <1%
EBITDA, % achieved 10% 100% 85% 70% 50% <50%
Net Return after Financing 20% 3% 2% -1% -5% < -5%
I&E surplus margin 20% 3% 2% 1% -2% < -2%
Liquid ratio (Days) 25% 60 25 15 10 <10
10
Financial Performance Metrics Continued
Criteria Qtr to Mar-12 Qtr to Jun-12 Qtr to Sep-12 Oct-12 Nov-12 Dec-12Qtr to Dec-
12
1 Unplanned decrease in EBITDA margin in two consecutive quarters No No No No No No No
2Quarterly self-certification by trust that the financial risk rating (FRR) may be less than 3 in
the next 12 monthsNo No No No No No No
3 Working capital facility (WCF) agreement includes default clause Yes Yes
4 Debtors > 90 days past due account for more than 5% of total debtor balances No No No No No No No
5 Creditors > 90 days past due account for more than 5% of total creditor balances No No No No No No No
6 Two or more changes in Finance Director in a twelve month period No No No No No No No
7 Interim Finance Director in place over more than one quarter end No No No No No No No
8 Quarter end cash balance <10 days of operating expenses No No No No No No No
9 Capital expenditure < 75% of plan for the year to date No No Yes No No No No
Cash Flow Statement
11
Commentary
Cash Flow
• The Trust made an operat ing surplus of
£2,236k YTD, and received cash of £1,093k in
respect of depreciat ion and amort isat ion
• Trade and Other Receivables increased over
the period (a negat ive impact on cash)
• Trade and Other Payables increased over
the period (a posit ive impact on cash)
• Dividend w as paid for the first half of the
year in September (a negat ive impact on
cash in the month)
• The Trust received £18k of interest , and
spent £1,246k on capital. Capital
Expenditure w as therefore greater than the
cash received for depreciat ion and
amort isat ion (a negat ive impact on cash)
• The impact of all these movements w as to
increase the Trust ’s cash balance over the
period by £4,542k
Cash Benchmark for March 2013
• This figure assumes zero w orking capital
movements, a 12/ 13 financial surplus of
£1,800k and a cash to capital t ransfer of
£460k. This is a useful figure to compare
actual cash against as the year progresses
£'000
Cash Flows from Operating Activities
Operating Surplus/(Deficit) 2,236
Depreciation and Amortisation 1,093
(Increase)/Decrease in Trade and Other Receivables (368)
Increase/(Decrease) in Trade and Other Payables 3,491
Increase/(Decrease) in Provisions 25
Dividend Paid (707)
Net Cash Inflow/(Outflow) from Operating Activities 5,770
Cash Flows from Investing Activities
Interest received 18
(Payments) for Property, Plant and Equipment (1,246)
Net Cash Inflow/(Outflow)from Investing Activities (1,228)
Net Cash Inflow/(Outflow) before Financing 4,542
Cash Flows from Financing Activities 0
Net Increase/(Decrease) in Cash 4,542
Cash at the Beginning of the Period 6,932
Cash at the End of the Period 11,474
EBITDA at 31 December 2012 as per Summary Schedule 2 3,329
Deduct Depreciation and Amortisation (1,093)
Operating Surplus at 31 December 2012 2,236
Cash Benchmark
Opening cash 6,932
Planned surplus (updated to reflect increase at Month 7) 1,800
Planned cash to capital transfer (460)
Forecast Cash 31 March 2013 8,272
Payables Performance
12
Commentary
Better Payment Practice Code
• The Trust has paid over 95% of non
NHS invoices (by value) within 30
days YTD
• BPP performance improved across
all measures in December
• BPP performance may worsen in
January due to the fact that the last
payrun in December was processed
on the 18th of the month
• Performance has recovered to an
extent following poor performance
in November 2012
Aged Receivables Profile by Value
• Aged receivables have decreased
by £775k (69%) in December to
£344k. £500k relates to SCR
monies received in December
• The value of receivables aged
greater than 90 days has
decreased by 70% in the month,
from £449k to £133k. This is as a
result of the SCR monies being
paid by NHS Dudley.
Better Payment Practice Code
On Time Late Total On Time
(%)
Late
(%)
On Time
£
Late
£
Total
£
On Time
(%)
Late
(%)
Number Of Transactions Non-NHS Value Of Transactions Non-NHS Av days
Qtr 1 3,669 232 3,901 94.05% 5.95% 6,000,347 113,584 6,113,931 98.14% 1.86%
Qtr 2 3,148 397 3,545 88.80% 11.20% 5,829,693 146,861 5,976,554 97.54% 2.46%
Month 7 1,041 88 1,129 92.21% 7.79% 1,857,396 87,961 1,945,357 95.48% 4.52%
Month 8 1,237 231 1,468 84.26% 15.74% 2,099,559 167,229 2,266,787 92.62% 7.38%
Month 9 836 75 911 91.77% 8.23% 1,868,718 48,859 1,917,577 97.45% 2.55%YTD 9,931 1,023 10,954 90.66% 9.34% 17,655,712 564,493 18,220,206 96.90% 3.10% 15.83
Number Of Transactions NHS Value Of Transactions NHS
Qtr 1 85 4 89 95.51% 4.49% 926,129 65,433 991,562 93.40% 6.60%
Qtr 2 95 15 110 86.36% 13.64% 1,231,029 297,277 1,528,306 80.55% 19.45%
Month 7 33 6 39 84.62% 15.38% 386,329 79,434 465,763 82.95% 17.05%
Month 8 26 15 41 63.41% 36.59% 196,854 228,095 424,949 46.32% 53.68%
Month 9 24 7 31 77.42% 22.58% 266,001 40,984 306,986 86.65% 13.35%YTD 263 47 310 84.84% 15.16% 3,006,342 711,223 3,717,565 80.87% 19.13%
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
1,800,000
Jan
-12
Feb
-12
Mar
-12
Ap
r-1
2
May
-12
Jun
-12
Jul-
12
Au
g-1
2
Sep
-12
Oct
-12
No
v-1
2
Dec
-12
£
Month
Aged Receivables Profile by Value
Bal (120+)
Bal (91-120)
Bal (61-90)
Bal (31-60)
Bal (0-30)
13
Workforce
Commentary
• In Acute Services: w ard overt ime, bank and agency staff are less than funded vacancies
• In Older Adult Services: w ard overt ime, bank and agency staff exceed funded vacancies , to a larger extent than during Month 8
• In Medical Services there w ere 10.20 high cost agency locums (6.20 in Dudley & 4 in Walsall) plus 2.20 agency medical secretaries
• Corporate movements in agency WTE are due to changes in consultancy & agency t reatment
• Month on month, funded establishment remains stable
Function Funded WTE
Actual Worked
WTE
(substantive staff)
Actual Worked
WTE
(bank staff)
Estimated WTE
(agency staff)
Total Actual
WTE
Variance
WTE
Variance WTE
Month 8
Acute Management 24.34 20.92 0.00 1.73 22.65 1.69 1.54
Acute Services 250.94 203.12 28.35 7.39 238.86 12.08 5.27
Acute Estates 21.13 21.56 0.18 0.00 21.74 (0.61) (1.08)
Older Adult Services 188.75 160.10 25.91 29.20 215.21 (26.46) (14.69)
Medical Services 114.40 100.79 0.00 12.40 113.19 1.21 1.06
Community Services 104.26 99.19 1.05 2.79 103.03 1.23 0.72
Community Management 6.00 5.36 0.00 6.31 11.67 (5.67) (5.96)
Early Intervention Services 174.54 143.03 0.00 13.56 156.59 17.95 17.84
Recovery Services 105.74 94.66 1.76 0.49 96.91 8.83 6.96
CEO 7.87 8.85 0.00 1.00 9.85 (1.98) (2.34)
Corporate Affairs 16.14 14.88 0.00 2.00 16.88 (0.74) 0.20
Corporate Medical 6.20 2.00 0.00 0.00 2.00 4.20 4.20
Corporate Ops (incl Gov) 55.36 48.86 0.00 0.00 48.86 6.50 6.82
Finance 15.32 16.60 0.00 2.00 18.60 (3.28) (3.53)
IT 1.00 0.00 0.00 1.00 1.00 0.00 0.00
Estates 5.72 4.58 0.00 2.00 6.58 (0.86) 0.14
Performance 13.91 14.15 0.00 2.00 16.15 (2.24) (2.00)
HR 39.36 32.83 0.00 2.00 34.83 4.53 4.13
1,150.98 991.48 57.25 85.88 1,134.61 16.37 19.27
14
Workforce Continued (1)
Commentary
Current posit ion
• This month the presentat ion has
changed to reflect changing
operat ional circumstances and the
subsequent impact on the current
forecast versus the original plan
• Dudley had 6.2 agency locums and 1
Trust -paid locum against 6 vacant
posts and 2 staff on maternity leave
• Walsall had 4 agency locums covering
3 vacant posts plus 2 instances of sick
leave
• Year to date costs exceed forecast due
to the t iming of locum leave and
unplanned sick leave
• Temporary staff usage on inpat ient
areas relates to cover of vacancies,
long term sick or maternity leave
cover, high observat ion levels
• Acute w ards under spent by £42k on
staffing overall in-month, including a
£15k under spend on Langdale
result ing from low usage of ECA and
low er than average observat ion levels
£0
£5,000
£10,000
£15,000
£20,000
£25,000
£30,000
£35,000
£40,000Temporary Staffing Analysis - Adult Acute Wards
Clent
Kinver
Wrekin
Ambleside
Langdale
0
50000
100000
150000
200000
250000
300000
Oct
-11
No
v-1
1
Dec
-11
Jan
-12
Feb
-12
Mar
-12
Ap
r-1
2
May
-12
Jun
-12
Jul-
12
Au
g-1
2
Sep
-12
Oct
-12
No
v-1
2
Dec
-12
Jan
-13
Feb
-13
Mar
-13
Medical Locum Spend Analysis and Forecast
Original Forecast at M2
Actual
Current Forecast
15
Workforce Continued (2)
Commentary
• Temporary staff usage on
inpat ient areas relates to cover of
vacancies, long term sick or
maternity leave cover, and special
observat ions (the high costs at
Bloxw ich in recent months result
from a combinat ion of all of these
factors occurring simultaneously)
• Older adult w ards overspent by
£79k in-month, but this w as
part ially mit igated by £18k of
savings against other OA budgets
(e.g. vacancy savings in OA
CMHTs, day centres, psychology)
• The sharp increase in Holyrood
temporary staffing in Mth 8-9
mainly relates to a number of
pat ients present ing w ith
challenging behaviours (result ing
from lack of alternat ive
provision), requiring unusually
high observat ion levels,
combined w ith higher than
average w ard occupancy
£0
£10,000
£20,000
£30,000
£40,000
£50,000
£60,000
£70,000
£80,000
£90,000
Temporary Staffing Analysis - Older Adult Wards
Holyrood
Malvern
Cedars
Linden
16
Cost Improvement Target Achievement
Commentary
• The Trust has transacted all CIP for 2012/13
• Total transacted to date is £2,764k against a revised target (after taking last year’s over-achievement into account) of £2,740k. The extent to which
these identified schemes are considered delivered will be measured through achievement of the Trust’s forecast surplus as the year progresses.
This remains on revised plan
• Schemes planned for 2012/13 that have not delivered to date are still expected to do so and will contribute towards future years targets
• It is vital that the Trust continues to identify and deliver CIP two years in advance, in accordance with requirements relating to performance
management and identifying the impact of service change on quality and safety. A CIP Project Management Office is now in place
Operations Medical Estates Corporate Inflation Productivity Total
2011-12 CIP Carried Forward (389,152) 348,424 (40,728)
2012-13 CIP Target 2,781,000
Revised CIP Target 2,740,272
CIP 12 -13 Transacted Month 1 457,955 687,000 - 420,476 625,000 200,000 2,390,431
CIP 12 -13 Transacted Month 2 - - 23,600 - - - 23,600
CIP 12 -13 Transacted Month 4 57,373 - - - - - 57,373
CIP 12 -13 Transacted Month 6 163,036 - - 60,173 69,000 - 292,209
Total CIP Identified 678,364 687,000 23,600 480,649 694,000 200,000 2,763,613
Planned full year over-achievement (678,364) (687,000) (23,600) (480,649) (694,000) (200,000) (23,341)
17
Budget Reconciliation – Expenditure Budget Movement
Commentary
• Small funding of cost
pressure movements and
budget virements during
Month 9
Contract
Income
Corporate
Costs
Acute & Older
Adult
Community
Services
Medical
Services
Psychology
ServicesReserves Dep'n & PDC
Interest
ReceivableSurplus
Budgets approved by Trust Board (61,689,684) 9,450,835 17,684,952 15,280,224 12,018,167 1,544,270 2,022,619 2,632,000 (25,000) (1,081,617)
Adjustment for Depn.& PDC (210,000) (2,069,000) (349,000) (4,000) 2,632,000 0
Net Budgets (61,689,684) 9,660,835 19,753,952 15,629,224 12,018,167 1,548,270 2,022,619 0 (25,000) (1,081,617)
Total - Month 08 (63,810,871) 12,663,268 20,090,927 16,642,975 12,220,912 0 417,790 0 (25,000) (1,799,999)
SCR Adjustments -30,000 30,000 0
Medical appointment - Dr Das 10,439 (10,439) 0
Walsall CRS South Appointment 5,870 (5,870) 0
Funding of Depreciation (Canalside) 19,118 (19,118) 0
Trf of Estates Budgets -80,000 80,000 0
Miscellaneous movement -453 453 0
Total - Month 09 (63,810,871) 12,583,268 20,140,474 16,668,416 12,231,351 0 412,363 0 (25,000) (1,799,999)
Statement of Financial Position
18
Commentary
Non Current Assets
• Capital expenditure is higher than the depreciat ion
and amort isat ion charges YTD. This has led to an
increase in total non current assets of £192k since 31
March 2012. Progress against capital schemes is
review ed in Slide 7
Current Assets
• Receivables are £369k greater than at 31 March 2012
• Cash is £4,542k higher than the balance at 31 March
2012. An analysis of cash flow s can be seen elsew here
in this report
Current Liabilities
• Payables have increased significant ly YTD by £3,836k.
This is part ly due to accrued commit ted expenditure
against Strategic Change Reserve schemes
Provisions
• This balance is made up of provisions for consultant
contracts and staff on fixed term contracts
Tax Payers’ Equity
• The only change from March 2012 is the addit ion of
the YTD surplus of £1,241k
31 March 2012 31 December
2012
Movement
£000 £000 £000
Non-Current Assets
Property, Plant and Equipment 41,535 41,891 356
Intangible Fixed Assets 929 765 (164)
Total Non-Current Assets 42,464 42,656 192
Current Assets
Receivables less than one year 1,488 1,857 369
Cash (OPG and Other) 6,932 11,474 4,542
Total Current Assets 8,420 13,331 4,911
Current Liabilities
NHS Payables less than one year (393) (1,491) (1,098)
Payables less than one year (4,867) (7,605) (2,738)
Provisions less than one year (33) (58) (25)
Total Current Liabilities (5,293) (9,154) (3,861)
Net Current Assets less Liabilities 3,127 4,177 1,050
Provisions greater than one year (476) (476) 0
Total Assets less Current Liabilities 45,115 46,357 1,241
Financed by Tax Payer Equity:
Public Dividend Capital (48,321) (48,321) 0
Revaluation Reserve (96) (96) 0
I&E Reserve b/f 3,302 3,302 0
Current Year I&E 0 (1,241) (1,241)
Total Taxpayers' Equity (45,115) (46,357) (1,241)