SYNERGY PROPERTY DEVELOPMENT SERVICES PVT LTD
Weekly progress report
Project Update
2nd May 2012
Divyasree NSL Orion- B7
(B+LG+G +14 + Terrace floor)
-
8/2/2019 20120502 Weekly Report B7
2/9
2FIRS
TTOL
A
ST
PROJECT MILESTONES
Sl. No. Milestone DescriptionRevised Target
DateProjected /Ach. Date
Status (RAG)
PM1 Project kick off 09-Aug-2011 09-Aug-2011 Completed
PM2 Lower Ground floor slab concreting 25-Feb-2012 28-Mar-2012 Completed
PM3 Sixth floor slab concreting 03-Sep-2012 03-Sep-2012 On track
PM4 Roof slab concreting 01-Apr-2013 01-Apr-2013 On track
PM5 Hand over to Fit out (6th & 7th Floor) 01-Jun-2013 01-Jun-2013 On track
PM6 Completion of Block work & plastering 20-July-2013 20-July-2013 On track
PM7 HSD installation 18-Aug-2013 18-Aug-2013 On track
PM8 Electrical High side testing & commissioning 05-Sep-2013 05-Sep-2013 On track
PM9 Plumbing works in Office floor toilets & Terrace 07-Sep-2013 07-Sep-2013 On track
PM10 HVAC Low Side Testing & commissioning 08-Sep-2013 08-Sep-2013 On track
PM11 Fire Fighting testing & commissioning 10-Sep-2013 10-Sep-2013 On track
PM12 Electrical Low side testing & commissioning 16-Sep-2013 16-Sep-2013 On track
PM13 Chiller commissioning 18-Sep-2013 18-Sep-2013 On track
PM14 DG commissioning 19-Sep-2013 19-Sep-2013 On track
PM15 Common area finishes 21-Sep-2013 21-Sep-2013 On track
PM16 Faade granite cladding & painting works 22-Sep-2013 22-Sep-2013 On track
PM17 External Development 24-Sep-2013 24-Sep-2013 On track
PM18 Faade / Structural Glazing works 26-Sep-2013 26-Sep-2013 On track
PM19 Passenger and service elevators 29-Sep-2013 29-Sep-2013 On track
PM20 Base building completion 30-Sep-2013 30-Sep-2013 On track
Toda
-
8/2/2019 20120502 Weekly Report B7
3/9
3FIRS
TTOL
A
ST
STATUS REPORT today
Project Manager: B. Sathyanarayana PM1 PM2 PM3 PM4
Cost Resource Schedule Content Plan: 09-08-2011 25-02-2012 03-09-2012 01-04-2013
Status: G G G G Act/LE: 09-08-2011 28-03-2012 03-09-2012 01-04-2013
Achievements (previous weeks): Targets (next weeks):
Works carried
JMC completed following in building foot print area:
Retaining wall from LGF to GF 99% completed.
Pour-1 & 2 FF Slab concreting completed.
Pour-3 FF Slab works 95% completed.
Pour-4 & 5 FF Slab shuttering work 70% and reinforcement30% completed.
Pour - 6 FF columns works in progress.
Pour -1 SF column works in progress.
South & East side retaining wall - External membrane waterproofing works 35% to complete.
2nd Tower Crane erection completed.
Schedule:
FF slab completion anticipated on 25th Apr 12 is deferred till10th May 12 due to insufficient manpower and outsourced
RMC. JMC to fulf ill resources and manpower as committed in
management meeting held on 27 th April 12.
Contractual: NA
Procurement:
Plumbing and fire fighting packages under review.
Team reviewed on Lift Vendors Technical specifications for
further process.
Works planned
JMC to complete following in building foot print area:
Lift core area GF slab concreting to complete.
Pour-3 & 4 FF Slab concreting to complete.
Pour- 5 FF Slab works 90% to complete.
Pour 6 FF columns to complete
Pour 1 SF columns to complete
Pour 2 SF columns 40% to completeSouth & East side retaining wall - External membrane
water proofing works 40% to complete.
Back filling works to re-start with outsourced Murrum.
Schedule:
JMC to submit Micro schedule as per the committeddates considering 14 days slab cycle.
Contractual: NA
Procurement:Batching plant equipment to be mobilized to site.
OTT for Electrical HT package to be scheduled.
STP package - Final recommendation to be shared.
-
8/2/2019 20120502 Weekly Report B7
4/9
4
CL
IENT
LIS
T
FIRSTT
OLAST
Achievements (previous weeks): Targets (next weeks):
Quality & Safety:
JMC submitted 7 days design mix report for Ultra tech cementand to share for 28 days for consultant review.
SYN issued NCRs15 & 16 on 26th Apr 12 , JMC to take
immediate action to rectify the same.
SYN generated Internal Quality and safety Audit report -02 andfulfilled by site team .
DNIPL shared material test certificates for cement .
SYN highlighted on material stacking and safety measures onsite for JMC action.
QS/Billing/Variations:
SYN shared status on RA bills pending payment to DNIPL on27th Apr 12 for necessary action. DNIPL released payments for:
RA-05 Adhoc for 54.73 lakhs RA-05 Final for 6.47 lakhs
SYN shared the outsource Murrum quantities to DNIPL forapproval.
Other Important :
Meeting with JMC higher management was held on 27 th Apr 12
for discussing slab concreting delays and insufficient resources.
DNIPL shared interior layout, Conserve is planning IGBCdesign review submission on 2nd May 12.
RSP team approved on 6th Floor Shuttering shared by PSC forfurther process.
SYN shared comments on Atrium drawings for RSP review and
incorporation.
RSP services shared Basement ventilation as separatepackage for review on 26th Apr 12.
RSP services shared hard copies for tender drawings of fire
fighting, Electrical, plumbing and HVAC low side packages.
Quality &Safety
2nd Tower Crane 3rd party test certificate to besubmitted for operation.
JMC to closed balance NCRs by 7th May 12.
JMC to submit 3rd party design mix with 100% ROBO
sand .
JMC to increase team exclusively for housekeeping
works at site.
QS/Billing/Variations
DNIPL to release payments for following:
RA-06 Adhoc for 53.54 lakhs
RA-06 Final for 24.11 lakhs
NT-Item 02 for 3.64 lakhs
DNIPL to approved the quantity of outsource Murrumsubmitted for the back filling works.
Reinforcement steel indent 574MT, part PO to bereleased by DNIPL.
Other Important:
RSP services to review on design requirements forAtrium to share preliminary schemes.
RSP Arch to share following:
Revised elevations, sections, BOQ for faade by 5thMay 12
Revised Common area presentation by 7 th May 12
Updated architectural drawings for Atrium
-
8/2/2019 20120502 Weekly Report B7
5/9 5FIRS
TTOL
A
STAchievements (previous weeks): Targets (next weeks):Status of Block work, Plastering and IPS at site:- Target for Block work, Plastering and IPS at site:-
Floor Slab Block Work Plastering IPSBasement N.A
LG 100%
Ground 100%
1st 60%
2nd 2%
3rd
4th
5th
6th
7th
8
th
9
th
10th
11th
12th
13th
14th
Terrace
Floor Slab Block Work Plastering IPSBasement N.A
LG 100%
Ground 100%
1st 80%
2nd 8%
3rd
4th
5th
6th
7th
8
th
9
th
10th
11th
12th
13th
14th
Terrace
-
8/2/2019 20120502 Weekly Report B7
6/96
CL
IENT
LIS
T
FIRSTT
OLAST
Deviations and issues (previous weeks): Important Risks & Corrective Actions:
Execution of Atrium columns at grid I11 & H11 as perproposed detail on anchoring to existing B6 footings. PSC
to visit site on 2nd May 12 to inspect the existing footingsand review the site condition for advice.
Insufficient man power, engineers to complete plannedworks at site by JMC.
Corrective measure: Insufficient manpower for plannedworks. JMC to augment the manpower as committed on27thApr 12 for avoiding delays in slab concreting and to
achieve fourth floor slab completion
Batching plant production for B7 to be resolved by JMC.
Corrective measure: Batching plant will be mobilized tocampus for erection by 7thMay 12 and production to startfrom 15th May 12. However, JMC to maintain requiredquantity of concrete for Orion B7 as agreed.
-
8/2/2019 20120502 Weekly Report B7
7/97F
IRS
TTOL
A
ST
PROJECT STATUS PHOTOGRAPHS: 30-04-12 Vs 24-04-12
View from South East side of site View from South East side of site
View from South side of site View from South side of site
Previous Week Present Week
-
8/2/2019 20120502 Weekly Report B7
8/98F
IRS
TTOL
A
ST
PROJECT STATUS PHOTOGRAPHS: 30-04-12 Vs 24-04-12
View from South West side of site View from South West side of site
View from North West side of site View from North West side of site
Previous Week Present Week
-
8/2/2019 20120502 Weekly Report B7
9/9
9FIRS
TTOL
A
ST
PROJECT STATUS PHOTOGRAPHS: 30-04-12 Vs 24-04-12
View from North East side of site View from North East side of site
View from North side of site View from North side of site
Previous Week Present Week