    SYNERGY PROPERTY DEVELOPMENT SERVICES PVT LTD

    Weekly progress report

    Project Update

    2nd May 2012

    Divyasree NSL Orion- B7

    (B+LG+G +14 + Terrace floor)

  • 8/2/2019 20120502 Weekly Report B7

    2/9

    2FIRS

    TTOL

    A

    ST

    PROJECT MILESTONES

    Sl. No. Milestone DescriptionRevised Target

    DateProjected /Ach. Date

    Status (RAG)

    PM1 Project kick off 09-Aug-2011 09-Aug-2011 Completed

    PM2 Lower Ground floor slab concreting 25-Feb-2012 28-Mar-2012 Completed

    PM3 Sixth floor slab concreting 03-Sep-2012 03-Sep-2012 On track

    PM4 Roof slab concreting 01-Apr-2013 01-Apr-2013 On track

    PM5 Hand over to Fit out (6th & 7th Floor) 01-Jun-2013 01-Jun-2013 On track

    PM6 Completion of Block work & plastering 20-July-2013 20-July-2013 On track

    PM7 HSD installation 18-Aug-2013 18-Aug-2013 On track

    PM8 Electrical High side testing & commissioning 05-Sep-2013 05-Sep-2013 On track

    PM9 Plumbing works in Office floor toilets & Terrace 07-Sep-2013 07-Sep-2013 On track

    PM10 HVAC Low Side Testing & commissioning 08-Sep-2013 08-Sep-2013 On track

    PM11 Fire Fighting testing & commissioning 10-Sep-2013 10-Sep-2013 On track

    PM12 Electrical Low side testing & commissioning 16-Sep-2013 16-Sep-2013 On track

    PM13 Chiller commissioning 18-Sep-2013 18-Sep-2013 On track

    PM14 DG commissioning 19-Sep-2013 19-Sep-2013 On track

    PM15 Common area finishes 21-Sep-2013 21-Sep-2013 On track

    PM16 Faade granite cladding & painting works 22-Sep-2013 22-Sep-2013 On track

    PM17 External Development 24-Sep-2013 24-Sep-2013 On track

    PM18 Faade / Structural Glazing works 26-Sep-2013 26-Sep-2013 On track

    PM19 Passenger and service elevators 29-Sep-2013 29-Sep-2013 On track

    PM20 Base building completion 30-Sep-2013 30-Sep-2013 On track

    Toda

  • 8/2/2019 20120502 Weekly Report B7

    3/9

    3FIRS

    TTOL

    A

    ST

    STATUS REPORT today

    Project Manager: B. Sathyanarayana PM1 PM2 PM3 PM4

    Cost Resource Schedule Content Plan: 09-08-2011 25-02-2012 03-09-2012 01-04-2013

    Status: G G G G Act/LE: 09-08-2011 28-03-2012 03-09-2012 01-04-2013

    Achievements (previous weeks): Targets (next weeks):

    Works carried

    JMC completed following in building foot print area:

    Retaining wall from LGF to GF 99% completed.

    Pour-1 & 2 FF Slab concreting completed.

    Pour-3 FF Slab works 95% completed.

    Pour-4 & 5 FF Slab shuttering work 70% and reinforcement30% completed.

    Pour - 6 FF columns works in progress.

    Pour -1 SF column works in progress.

    South & East side retaining wall - External membrane waterproofing works 35% to complete.

    2nd Tower Crane erection completed.

    Schedule:

    FF slab completion anticipated on 25th Apr 12 is deferred till10th May 12 due to insufficient manpower and outsourced

    RMC. JMC to fulf ill resources and manpower as committed in

    management meeting held on 27 th April 12.

    Contractual: NA

    Procurement:

    Plumbing and fire fighting packages under review.

    Team reviewed on Lift Vendors Technical specifications for

    further process.

    Works planned

    JMC to complete following in building foot print area:

    Lift core area GF slab concreting to complete.

    Pour-3 & 4 FF Slab concreting to complete.

    Pour- 5 FF Slab works 90% to complete.

    Pour 6 FF columns to complete

    Pour 1 SF columns to complete

    Pour 2 SF columns 40% to completeSouth & East side retaining wall - External membrane

    water proofing works 40% to complete.

    Back filling works to re-start with outsourced Murrum.

    Schedule:

    JMC to submit Micro schedule as per the committeddates considering 14 days slab cycle.

    Contractual: NA

    Procurement:Batching plant equipment to be mobilized to site.

    OTT for Electrical HT package to be scheduled.

    STP package - Final recommendation to be shared.

  • 8/2/2019 20120502 Weekly Report B7

    4/9

    4

    CL

    IENT

    LIS

    T

    FIRSTT

    OLAST

    Achievements (previous weeks): Targets (next weeks):

    Quality & Safety:

    JMC submitted 7 days design mix report for Ultra tech cementand to share for 28 days for consultant review.

    SYN issued NCRs15 & 16 on 26th Apr 12 , JMC to take

    immediate action to rectify the same.

    SYN generated Internal Quality and safety Audit report -02 andfulfilled by site team .

    DNIPL shared material test certificates for cement .

    SYN highlighted on material stacking and safety measures onsite for JMC action.

    QS/Billing/Variations:

    SYN shared status on RA bills pending payment to DNIPL on27th Apr 12 for necessary action. DNIPL released payments for:

    RA-05 Adhoc for 54.73 lakhs RA-05 Final for 6.47 lakhs

    SYN shared the outsource Murrum quantities to DNIPL forapproval.

    Other Important :

    Meeting with JMC higher management was held on 27 th Apr 12

    for discussing slab concreting delays and insufficient resources.

    DNIPL shared interior layout, Conserve is planning IGBCdesign review submission on 2nd May 12.

    RSP team approved on 6th Floor Shuttering shared by PSC forfurther process.

    SYN shared comments on Atrium drawings for RSP review and

    incorporation.

    RSP services shared Basement ventilation as separatepackage for review on 26th Apr 12.

    RSP services shared hard copies for tender drawings of fire

    fighting, Electrical, plumbing and HVAC low side packages.

    Quality &Safety

    2nd Tower Crane 3rd party test certificate to besubmitted for operation.

    JMC to closed balance NCRs by 7th May 12.

    JMC to submit 3rd party design mix with 100% ROBO

    sand .

    JMC to increase team exclusively for housekeeping

    works at site.

    QS/Billing/Variations

    DNIPL to release payments for following:

    RA-06 Adhoc for 53.54 lakhs

    RA-06 Final for 24.11 lakhs

    NT-Item 02 for 3.64 lakhs

    DNIPL to approved the quantity of outsource Murrumsubmitted for the back filling works.

    Reinforcement steel indent 574MT, part PO to bereleased by DNIPL.

    Other Important:

    RSP services to review on design requirements forAtrium to share preliminary schemes.

    RSP Arch to share following:

    Revised elevations, sections, BOQ for faade by 5thMay 12

    Revised Common area presentation by 7 th May 12

    Updated architectural drawings for Atrium

  • 8/2/2019 20120502 Weekly Report B7

    5/9 5FIRS

    TTOL

    A

    STAchievements (previous weeks): Targets (next weeks):Status of Block work, Plastering and IPS at site:- Target for Block work, Plastering and IPS at site:-

    Floor Slab Block Work Plastering IPSBasement N.A

    LG 100%

    Ground 100%

    1st 60%

    2nd 2%

    3rd

    4th

    5th

    6th

    7th

    8

    th

    9

    th

    10th

    11th

    12th

    13th

    14th

    Terrace

    Floor Slab Block Work Plastering IPSBasement N.A

    LG 100%

    Ground 100%

    1st 80%

    2nd 8%

    3rd

    4th

    5th

    6th

    7th

    8

    th

    9

    th

    10th

    11th

    12th

    13th

    14th

    Terrace

  • 8/2/2019 20120502 Weekly Report B7

    6/96

    CL

    IENT

    LIS

    T

    FIRSTT

    OLAST

    Deviations and issues (previous weeks): Important Risks & Corrective Actions:

    Execution of Atrium columns at grid I11 & H11 as perproposed detail on anchoring to existing B6 footings. PSC

    to visit site on 2nd May 12 to inspect the existing footingsand review the site condition for advice.

    Insufficient man power, engineers to complete plannedworks at site by JMC.

    Corrective measure: Insufficient manpower for plannedworks. JMC to augment the manpower as committed on27thApr 12 for avoiding delays in slab concreting and to

    achieve fourth floor slab completion

    Batching plant production for B7 to be resolved by JMC.

    Corrective measure: Batching plant will be mobilized tocampus for erection by 7thMay 12 and production to startfrom 15th May 12. However, JMC to maintain requiredquantity of concrete for Orion B7 as agreed.

  • 8/2/2019 20120502 Weekly Report B7

    7/97F

    IRS

    TTOL

    A

    ST

    PROJECT STATUS PHOTOGRAPHS: 30-04-12 Vs 24-04-12

    View from South East side of site View from South East side of site

    View from South side of site View from South side of site

    Previous Week Present Week

  • 8/2/2019 20120502 Weekly Report B7

    8/98F

    IRS

    TTOL

    A

    ST

    PROJECT STATUS PHOTOGRAPHS: 30-04-12 Vs 24-04-12

    View from South West side of site View from South West side of site

    View from North West side of site View from North West side of site

    Previous Week Present Week

  • 8/2/2019 20120502 Weekly Report B7

    9/9

    9FIRS

    TTOL

    A

    ST

    PROJECT STATUS PHOTOGRAPHS: 30-04-12 Vs 24-04-12

    View from North East side of site View from North East side of site

    View from North side of site View from North side of site

    Previous Week Present Week