2012 Program DesignDiscussion
Charlie Garrison, David Hill and Ron ReismanRenewable Energy Market Manager Team
Renewable Energy Committee MeetingSeptember 20, 2011
![Page 2: 2012 Program Design Discussion Charlie Garrison, David Hill and Ron Reisman Renewable Energy Market Manager Team Renewable Energy Committee Meeting September.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649dde5503460f94ad6baf/html5/thumbnails/2.jpg)
Process Timeline
Events to Date
June 7 – Initial presentation of 2012 plans
July 12 – Identification of key issues & focus areas / input requested
August 9 – Framing specific program changes / add’l input requested
September 16 – Discuss draft overview of program changes with OCE
September 20 – Final draft presentation to REC
![Page 3: 2012 Program Design Discussion Charlie Garrison, David Hill and Ron Reisman Renewable Energy Market Manager Team Renewable Energy Committee Meeting September.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649dde5503460f94ad6baf/html5/thumbnails/3.jpg)
Process Timeline
Events to Come
Sept. 26 – Complete draft of Compliance Filing submitted to BPU
October – BPU Solicits public feedback on filing
November – MM incorporates feedback into final filing as needed
December – BPU adopts MM’s plan
![Page 4: 2012 Program Design Discussion Charlie Garrison, David Hill and Ron Reisman Renewable Energy Market Manager Team Renewable Energy Committee Meeting September.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649dde5503460f94ad6baf/html5/thumbnails/4.jpg)
Reflecting EMPPolicy Priorities
• Continue transition of solar market from rebate-based programs to long-term financing options and power purchase agreements
• Continue market/financial analyses to determine appropriate initiatives for addressing market barriers and gaps
• Assist OCE in assessing market conditions and seeking ways to reduce the barriers to broad-based program participation
• Streamline processes to continue stimulating investment with lower costs
![Page 5: 2012 Program Design Discussion Charlie Garrison, David Hill and Ron Reisman Renewable Energy Market Manager Team Renewable Energy Committee Meeting September.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649dde5503460f94ad6baf/html5/thumbnails/5.jpg)
SREC Registration Program (SRP)Modifications
• Transitioning to electronic registration and processing• Need to assess scope of work and implementation timeframe
• New paperwork requirements for 2012• One recent EDC electric bill
• Site map
• Contract (key items)
• Construction schedule
• Maintain 10% rate of project verifications for SRP• Conduct meter verifications as requested by OCE
![Page 6: 2012 Program Design Discussion Charlie Garrison, David Hill and Ron Reisman Renewable Energy Market Manager Team Renewable Energy Committee Meeting September.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649dde5503460f94ad6baf/html5/thumbnails/6.jpg)
Solar Program Outreach
• Solar Technical Working Group• Ideal forum to address questions relating to rules, inspections, meter
placement and other technical issues.
• Fire safety training for firefighting community and solar industry
• Assess number of meetings needed and value of localized versus centralized sessions
• Financing webinars• Explore innovative financing options
• Use webinar format to reduce costs, maximize reach and archive content
• Outreach to realtors and appraisers (both RE and EE)• Assessing added value of solar on residential and commercial buildings
• Educate the public on importance of “Efficiency First”• Include in all presentations and public appearances
![Page 7: 2012 Program Design Discussion Charlie Garrison, David Hill and Ron Reisman Renewable Energy Market Manager Team Renewable Energy Committee Meeting September.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649dde5503460f94ad6baf/html5/thumbnails/7.jpg)
Wind Program
• REIP wind program still temporarily closed due to safety concerns stemming from blade failure and fire
• Need to assess the impact of the lengthy program shutdown
• MM provided draft recommendations to OCE revising 2011 program requirements and structure based on working group input and written comments
• Revised 2011 program will become 2012 program recommendation
• Small Wind Working Group meeting scheduled for 3rd week in Oct.
![Page 8: 2012 Program Design Discussion Charlie Garrison, David Hill and Ron Reisman Renewable Energy Market Manager Team Renewable Energy Committee Meeting September.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649dde5503460f94ad6baf/html5/thumbnails/8.jpg)
REIP Wind Program
Program revisions currently under review include:
• Turbine certification status to determine eligibility
• Contractor and manufacturer insurance and bonding requirements for participation
• More accurate estimated production calculation for rebate level determination
• Rebate levels and rebate payment structure
• MM reviewing alternative calculations to put more focus on performance-based incentives
![Page 9: 2012 Program Design Discussion Charlie Garrison, David Hill and Ron Reisman Renewable Energy Market Manager Team Renewable Energy Committee Meeting September.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649dde5503460f94ad6baf/html5/thumbnails/9.jpg)
Wind Program Outreach
Recommending more segment focus and outreach to the high wind target area and contractors
• More marketing and education
• Host quarterly small wind working groups
• Grow partnerships with NJ manufacturers and universities
• More proactive outreach to qualified contractors and manufacturers
• Municipality focus – small wind ordinance adoption
• Highlight incentive structure for Wind System Feasibility studies
![Page 10: 2012 Program Design Discussion Charlie Garrison, David Hill and Ron Reisman Renewable Energy Market Manager Team Renewable Energy Committee Meeting September.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649dde5503460f94ad6baf/html5/thumbnails/10.jpg)
REIP Biopower Program
• Program expected to remain similar to 2011 program
• Proactive outreach and industry engagement
• Target high potential industries (i.e., food processing, wastewater treatment, etc.) for project development
![Page 11: 2012 Program Design Discussion Charlie Garrison, David Hill and Ron Reisman Renewable Energy Market Manager Team Renewable Energy Committee Meeting September.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649dde5503460f94ad6baf/html5/thumbnails/11.jpg)
Biopower ProgramOutreach
Recommending more segment focus and outreach to high potential, high value industries and contractors:
• Partner with the Rutgers EcoComplex and other NJ universities and colleges to expand industry knowledge and opportunities for biopower systems in NJ.
• Review and update statewide feasibility studies that could serve as a basis for site- and project-specific feasibility studies
– Highlight Rutgers’ 2007 “Assessment of Biomass Energy Potential in NJ”
• Promote availability of funds for project and site-specific feasibility studies
![Page 12: 2012 Program Design Discussion Charlie Garrison, David Hill and Ron Reisman Renewable Energy Market Manager Team Renewable Energy Committee Meeting September.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649dde5503460f94ad6baf/html5/thumbnails/12.jpg)
Biopower Program Outreach (continued)
• More proactive outreach to qualified contractors and manufacturers
• Align biopower efforts with NJCEP’s EE programs for Industrial and Water/wastewater customers
• Re-establish biopower working group and schedule at least two MM-facilitated meetings
![Page 13: 2012 Program Design Discussion Charlie Garrison, David Hill and Ron Reisman Renewable Energy Market Manager Team Renewable Energy Committee Meeting September.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649dde5503460f94ad6baf/html5/thumbnails/13.jpg)
Preliminary 2012 RE New Funding
PROGRAM ($Million)
Offshore Wind $ .500
REIP $10.000
RE Direct Grid Supply (non-solar) $ 9.500
Total $20.000
NOTE: These amounts are in addition to any uncommitted carryover that will be identified by the end of year true-up during Q1, 2012.