2012 05 11 KAFD Program Rooms+Corridors

download 2012 05 11 KAFD Program Rooms+Corridors

of 23

Transcript of 2012 05 11 KAFD Program Rooms+Corridors

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    1/23

    ID Task Name Duration Start Finish

    1

    PROJECT SUMMARY:250.5 days Sat 5/12/12 Wed 2/27/13

    2 MATERIALS APPROVAL: 14 days Sat 5/12/12 Sun 5/27/123 Metal Works: 0 days Sat 5/12/12 Sat 5/12/12

    4 Galvanized Metal Tubes & Angles 0 days Sat 5/12/12 Sat 5/12/12

    5 Anchors &Screws 0 days Sat 5/12/12 Sat 5/12/12

    6 Gypsum Ceiling Work: 14 days Sat 5/12/12 Sun 5/27/12

    7 Metal Profiles for Suspension 0 days Sat 5/12/12 Sat 5/12/12

    8 Gypsum Board 14 days Sat 5/12/12 Sun 5/27/12

    9 Anchors & Screws 0 days Sat 5/12/12 Sat 5/12/12

    10 Wood Works: 14 days Sat 5/12/12 Sun 5/27/12

    11 Veneer&Solid Wood 14 days Sat 5/12/12 Sun 5/27/12

    12 MDF 14 days Sat 5/12/12 Sun 5/27/12

    13 Door Core 14 days Sat 5/12/12 Sun 5/27/12

    14 Accessories 14 days Sat 5/12/12 Sun 5/27/12

    15 Glass&Mirrors: 14 days Sat 5/12/12 Sun 5/27/12

    16 Glass 14 days Sat 5/12/12 Sun 5/27/12

    17 Mirrors 14 days Sat 5/12/12 Sun 5/27/12

    18 Glue & Sealant 14 days Sat 5/12/12 Sun 5/27/12

    19 accessories 14 days Sat 5/12/12 Sun 5/27/12

    20 Hardwares&Accessories: 14 days Sat 5/12/12 Sun 5/27/12

    21 Hardware 14 days Sat 5/12/12 Sun 5/27/12

    22 Accessories 14 days Sat 5/12/12 Sun 5/27/12

    23 Paint Work: 14 days Sat 5/12/12 Sun 5/27/12

    24 Fenomastic Emulsion Primer 14 days Sat 5/12/12 Sun 5/27/12

    25 Stucco Interior 14 days Sat 5/12/12 Sun 5/27/12

    26 Fenomastic Emulsion Matt Paint 14 days Sat 5/12/12 Sun 5/27/12

    27 Fenomastic Emulsion Silk Paint 14 days Sat 5/12/12 Sun 5/27/12

    28 Stucco Antica 14 days Sat 5/12/12 Sun 5/27/12

    29 Metalic Star light 14 days Sat 5/12/12 Sun 5/27/12

    30 Curtains Work: 14 days Sat 5/12/12 Sun 5/27/12

    31 Motor,Tubes&Brackets 14 days Sat 5/12/12 Sun 5/27/12

    5/12

    5/12

    5/12

    5/12

    5/12

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 1/23

    Project: KAFD HOTEL.Revision: Rev-02.Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    2/23

    ID Task Name Duration Start Finish

    32 Fabrics 14 days Sat 5/12/12 Sun 5/27/12

    33 Wall Covering Works: 14 days Sat 5/12/12 Sun 5/27/12

    34 Wall Cover 14 days Sat 5/12/12 Sun 5/27/12

    35 Backing 14 days Sat 5/12/12 Sun 5/27/12

    36 Glue 14 days Sat 5/12/12 Sun 5/27/12

    37 Carpet Work: 14 days Sat 5/12/12 Sun 5/27/12

    38 Underlay C-04 14 days Sat 5/12/12 Sun 5/27/12

    39 Carpet C-05 14 days Sat 5/12/12 Sun 5/27/12

    40

    41 SHOPDRAWINGS APPROVAL: 36 days Sat 5/12/12 Thu 6/21/1242 Wood Works&Others Typical rooms Drawings: 36 days Sat 5/12/12 Thu 6/21/12

    43 Entrance Door 28 days Sat 5/12/12 Tue 6/12/12

    44 Sliding Door 28 days Sat 5/12/12 Tue 6/12/12

    45 Connecting Door 28 days Sat 5/12/12 Tue 6/12/12

    46 Wardrobe cabinet 14 days Wed 6/6/12 Thu 6/21/12

    47 Vanity cabinet 6 days Wed 6/13/12 Tue 6/19/12

    48 Luggage bench cushions 6 days Wed 6/13/12 Tue 6/19/12

    49 TV wall unit 6 days Sat 5/12/12 Thu 5/17/12

    50 Glass partition & Mirror 14 days Sat 5/12/12 Sun 5/27/12

    51 Corridors doors 14 days Sat 5/19/12 Sun 6/3/12

    52 Corridors wooden Panel 14 days Mon 6/4/12 Tue 6/19/12

    53 Corridor Ceiling and wall Card Reader panels 14 days Mon 5/28/12 Tue 6/12/12

    54 Curtains 14 days Mon 5/28/12 Tue 6/12/12

    55

    56 PROCUREMENT: 144 days Sat 5/12/12 Thu 10/25/1257

    Metal Works: 45 days Sat 5/12/12 Mon 7/2/1258 Galvanized Metal Tubes & Angles including Fabrication 45 days Sat 5/12/12 Mon 7/2/12

    59 Anchors &Screws 12 days Sat 5/12/12 Thu 5/24/12

    60 Gypsum Ceiling Work:

    26 days Sat 5/12/12 Sun 6/10/12

    61 Metal Profiles for Suspension 12 days Sat 5/12/12 Thu 5/24/12

    62 Gypsum Board 12 days Mon 5/28/12 Sun 6/10/12

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 2/23

    Project: KAFD HOTEL.Revision: Rev-02.Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    3/23

    ID Task Name Duration Start Finish

    63 Anchors & Screws 12 days Sat 5/12/12 Thu 5/24/12

    64 Wood Works: 130 days Mon 5/28/12 Thu 10/25/12

    65 Veneer&Solid Wood 60 days Mon 5/28/12 Sun 8/5/12

    66 MDF 60 days Mon 5/28/12 Sun 8/5/12

    67 Door Core 60 days Mon 5/28/12 Sun 8/5/12

    68 Accessories 45 days Mon 5/28/12 Wed 7/18/12

    69 Doors Fabrication period till first Delivery 40 days Mon 8/6/12 Thu 9/20/12

    70 Joinery Fabrication till First Delivery 40 days Mon 8/6/12 Thu 9/20/12

    71 Corridors doors 30 days Sat 9/22/12 Thu 10/25/12

    72 Corridors wooden Panel 30 days Sat 9/22/12 Thu 10/25/12

    73 Glass&Mirrors: 120 days Mon 5/28/12 Sun 10/14/12

    74 Glass 120 days Mon 5/28/12 Sun 10/14/12

    75 Mirrors 60 days Mon 5/28/12 Sun 8/5/12

    76 Glue & Sealant 60 days Mon 5/28/12 Sun 8/5/12

    77 accessories 90 days Mon 5/28/12 Sun 9/9/12

    78 Hardwares&Accessories: 120 days Mon 5/28/12 Sun 10/14/12

    79 Hardware Fabrication 72 days Mon 5/28/12 Sun 8/19/12

    80 Hardware Delivery 42 days Mon 8/20/12 Sun 10/7/1281 Accessories 120 days Mon 5/28/12 Sun 10/14/12

    82 Paint Work: 14 days Mon 5/28/12 Tue 6/12/12

    83 Fenomastic Emulsion Primer 14 days Mon 5/28/12 Tue 6/12/12

    84 Stucco Interior 14 days Mon 5/28/12 Tue 6/12/12

    85 Fenomastic Emulsion Matt Paint 14 days Mon 5/28/12 Tue 6/12/12

    86 Fenomastic Emulsion Silk Paint 14 days Mon 5/28/12 Tue 6/12/12

    87 Stucco Antica 14 days Mon 5/28/12 Tue 6/12/12

    88 Metalic Star light 14 days Mon 5/28/12 Tue 6/12/12

    89 Curtains Work: 106 days Mon 5/28/12 Thu 9/27/12

    90 Motor,Tubes&Brackets 106 days Mon 5/28/12 Thu 9/27/12

    91 Fabrics 106 days Mon 5/28/12 Thu 9/27/12

    92 Wall Covering Works:

    90 days Mon 5/28/12 Sun 9/9/12

    93 Wall Cover 90 days Mon 5/28/12 Sun 9/9/12

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 3/23

    Project: KAFD HOTEL.Revision: Rev-02.Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    4/23

    ID Task Name Duration Start Finish

    94 Backing 90 days Mon 5/28/12 Sun 9/9/12

    95 Glue 90 days Mon 5/28/12 Sun 9/9/12

    96 Carpet Work: 90 days Mon 5/28/12 Sun 9/9/12

    97 Underlay C-04 90 days Mon 5/28/12 Sun 9/9/12

    98 Carpet C-05 90 days Mon 5/28/12 Sun 9/9/12

    99 EXECUTION: 238.5 days Sat 5/26/12 Wed 2/27/13100 LEVEL 4: 135 days Sat 5/26/12 Mon 10/29/12

    101 GUEST ROOMS(TOTAL 17 ROOMS) 117 days Mon 6/11/12 Wed 10/24/12

    102 Metal Works: 9 days Tue 7/3/12 Thu 7/12/12

    103 Installation of steel Bracket for Vanity, Shower & bathtub Acces 9 days Tue 7/3/12 Thu 7/12/12

    104 Installation of steel bracket for sliding door and TV Unit 9 days Tue 7/3/12 Thu 7/12/12

    105 Gypsum Ceiling: 10 days Mon 6/11/12 Thu 6/21/12

    106 Gypsum ceiling frame installation 8 days Mon 6/11/12 Tue 6/19/12

    107 Gypsum ceiling installation 8 days Wed 6/13/12 Thu 6/21/12

    108 Wood Works: 9 days Sat 9/22/12 Mon 10/1/12

    109 Doors(Entrance, Sliding, connecting) 9 days Sat 9/22/12 Mon 10/1/12

    110 Joinery(Wardrobe,TV Unit,Luggage,Vanity Cabinet) 6.75 days Sat 9/22/12 Sat 9/29/12

    111 Glass, Doors Hardware & Accessories: 69 days Mon 8/6/12 Wed 10/24/12112 Clear tempered shower partition 9 days Mon 10/15/12 Wed 10/24/12

    113 Metalic acid etch mirror 9 days Mon 8/6/12 Wed 8/15/12

    114 Toilet Access Panel 9 days Tue 10/2/12 Thu 10/11/12

    115 Doors Hardware 4 days Mon 10/8/12 Thu 10/11/12

    116 Bathroom accessories 4 days Mon 10/15/12 Thu 10/18/12

    117 Paint Work: 105 days Mon 6/18/12 Wed 10/17/12

    118 Paint Ceiling first coat 10 days Mon 6/18/12 Thu 6/28/12

    119 Paint Wall first coat 3.43 days Wed 9/26/12 Sun 9/30/12

    120 Paint Ceiling final Coat 8 days Thu 9/27/12 Sat 10/6/12

    121 Paint Wall final Coat 10 days Sun 10/7/12 Wed 10/17/12

    122 Curtains Work: 22 days Sat 9/29/12 Tue 10/23/12

    123 Brackets Installation 5 days Sat 9/29/12 Wed 10/3/12

    124 Motor&Tubes Installation 5 days Thu 10/4/12 Tue 10/9/12

    Steel Fixer[3]

    Steel Fixer[3]

    Gyp. Carp.[12]

    Gyp. Carp.[12]

    Wood Carp.[12]

    Wood Carp.[16]

    Glass Fixer[6]

    Glass Fixer[3]

    Gyp. Carp.[3]

    Wood Carp.[4]

    Wood Carp.[4]

    Painter[6]

    Painter[14]

    Painter[12]

    Painter[14]

    Curtain Installer[2]

    Curtain Installer[2]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 4/23

    Project: KAFD HOTEL.Revision: Rev-02.Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    5/23

    ID Task Name Duration Start Finish

    125 Fabric Tailoring 5 days Wed 10/10/12 Mon 10/15/12

    126 Fabrics Installation&Motor Programming 5 days Thu 10/18/12 Tue 10/23/12

    127 CORRIDOR (Type 1): 135 days Sat 5/26/12 Mon 10/29/12

    128 Gypsum Ceiling Works: 21 days Sat 5/26/12 Mon 6/18/12

    129 Gypsum ceiling frame installation 7 days Sat 5/26/12 Sat 6/2/12

    130 Gypsum ceiling Board installation 7 days Mon 6/11/12 Mon 6/18/12

    131 Wood Works: 1 day Sat 10/27/12 Sat 10/27/12

    132 Doors (Staircase, HVAC, Service, Shafts) 1 day Sat 10/27/12 Sat 10/27/12

    133 Joinery (Wood panelling for Elevator) 1 day Sat 10/27/12 Sat 10/27/12

    134 Wall Covering Works: 20 days Mon 9/10/12 Tue 10/2/12

    135 Fabrication 6 days Mon 9/10/12 Sun 9/16/12

    136 Panelling Fix 8 days Mon 9/17/12 Tue 9/25/12

    137 Shaft Door Fix 6 days Wed 9/26/12 Tue 10/2/12

    138 Paint Work: 18 days Tue 6/19/12 Mon 7/9/12

    139 Paint Ceiling first coat 6 days Tue 6/19/12 Mon 6/25/12

    140 Paint Ceiling final Coat P-01 4 days Tue 6/26/12 Sat 6/30/12

    141 Paint Ceiling final Coat SP-01 8 days Sun 7/1/12 Mon 7/9/12

    142 Glass, Doors Hardware & Accessories: 29 days Wed 9/26/12 Mon 10/29/12143 Wall Card Reader panel 4 days Wed 9/26/12 Sun 9/30/12

    144 Celing glass reader panel 4 days Mon 10/1/12 Thu 10/4/12

    145 Glass panelling in front of lift Lobby 3 days Sat 10/6/12 Mon 10/8/12

    146 Doors Hardware 2 days Sun 10/28/12 Mon 10/29/12

    147 Carpet Work: 9 days Mon 9/10/12 Wed 9/19/12

    148 Underlay C-04 Fixation 3 days Mon 9/10/12 Wed 9/12/12

    149 Carpet C-05 Fixation 3 days Mon 9/17/12 Wed 9/19/12

    150

    151 LEVEL 5: 133 days Sun 6/3/12 Sun 11/4/12

    152 GUEST ROOMS(TOTAL 17 ROOMS) 115 days Sun 6/24/12 Sun 11/4/12

    153 Metal Works: 9 days Sat 7/14/12 Mon 7/23/12

    154 Installation of steel Bracket for Vanity, Shower & bathtub Acces 9 days Sat 7/14/12 Mon 7/23/12

    155 Installation of steel bracket for sliding door and TV Unit 9 days Sat 7/14/12 Mon 7/23/12

    Curtain Installer[2]

    Curtain Installer[2]

    Gyp. Carp.[3]

    Gyp. Carp.[3]

    Wood Carp.[3]

    Wood Carp.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Painter[2]

    Painter[2]

    Painter[2]

    Glass Fixer[3]

    Glass Fixer[3]

    Glass Fixer[3]

    Wood Carp.

    Carpet inst.[2]

    Carpet inst.[2]

    Steel Fixer[3]

    Steel Fixer[3]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 5/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    6/23

    ID Task Name Duration Start Finish

    156 Marble Works: 20 days Sun 6/24/12 Tue 7/17/12

    157 Marble flooring 0 days Tue 7/17/12 Tue 7/17/12

    158 Marble cladding 0 days Thu 7/5/12 Thu 7/5/12

    159 Mosaic tiles 0 days Sat 6/30/12 Sat 6/30/12

    160 Marble vanity top 0 days Sun 6/24/12 Sun 6/24/12

    161 Marble sill at head board 0 days Tue 7/17/12 Tue 7/17/12

    162 Marble skirting 0 days Thu 7/12/12 Thu 7/12/12

    163 Grouting and protection 0 days Sat 7/7/12 Sat 7/7/12

    164 Gypsum Ceiling: 10 days Sat 6/30/12 Tue 7/10/12

    165 Gypsum ceiling frame installation 8 days Sat 6/30/12 Sun 7/8/12

    166 Gypsum ceiling installation 8 days Mon 7/2/12 Tue 7/10/12

    167 Wood Works: 11.25 days Sat 9/29/12 Thu 10/11/12

    168 Doors(Entrance, Sliding, connecting) 9 days Tue 10/2/12 Thu 10/11/12

    169 Joinery(Wardrobe,TV Unit,Luggage,Vanity Cabinet) 6.75 days Sat 9/29/12 Sun 10/7/12

    170 Glass, Doors Hardware & Accessories: 69 days Thu 8/16/12 Sun 11/4/12

    171 Clear tempered shower partition 9 days Thu 10/25/12 Sun 11/4/12

    172 Metalic acid etch mirror 9 days Thu 8/16/12 Sun 8/26/12

    173 Toilet Access Panel 9 days Sat 10/13/12 Mon 10/22/12174 Doors Hardware 4 days Sat 10/13/12 Tue 10/16/12

    175 Bathroom accessories 4 days Sat 10/20/12 Tue 10/23/12

    176 Paint Work: 99 days Sat 7/7/12 Mon 10/29/12

    177 Paint Ceiling first coat 10 days Sat 7/7/12 Tue 7/17/12

    178 Paint Wall first coat 8 days Sun 10/7/12 Mon 10/15/12

    179 Paint Ceiling final Coat 8 days Mon 10/8/12 Tue 10/16/12

    180 Paint Wall final Coat 10 days Thu 10/18/12 Mon 10/29/12

    181 Curtains Work: 27 days Thu 10/4/12 Sun 11/4/12

    182 Brackets Installation 5 days Thu 10/4/12 Tue 10/9/12

    183 Motor&Tubes Installation 5 days Wed 10/10/12 Mon 10/15/12

    184 Fabric Tailoring 5 days Tue 10/16/12 Sun 10/21/12

    185 Fabrics Installation&Motor Programming 5 days Tue 10/30/12 Sun 11/4/12

    186 CORRIDOR (Type 1): 130 days Sun 6/3/12 Wed 10/31/12

    7/17

    7/5

    6/30

    6/24

    7/17

    7/12

    7/7

    Gyp. Carp.[12]

    Gyp. Carp.[12]

    Wood Carp.[12]

    Wood Carp.[16]

    Glass Fixer[6]

    Glass Fixer[3]

    Gyp. Carp.[3]Wood Carp.[4]

    Wood Carp.[4]

    Painter[6]

    Painter[6]

    Painter[12]

    Painter[14]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 6/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    7/23

    ID Task Name Duration Start Finish

    187 Gypsum Ceiling Works: 21 days Sun 6/3/12 Tue 6/26/12

    188 Gypsum ceiling frame installation 7 days Sun 6/3/12 Sun 6/10/12

    189 Gypsum ceiling Board installation 7 days Tue 6/19/12 Tue 6/26/12

    190 Wood Works: 1 day Sun 10/28/12 Sun 10/28/12

    191 Doors (Staircase, HVAC, Service, Shafts) 1 day Sun 10/28/12 Sun 10/28/12

    192 Joinery (Wood panelling for Elevator) 1 day Sun 10/28/12 Sun 10/28/12

    193 Wall Covering Works: 22 days Mon 9/17/12 Thu 10/11/12

    194 Fabrication 6 days Mon 9/17/12 Sun 9/23/12

    195 Panelling Fix 8 days Wed 9/26/12 Thu 10/4/12

    196 Shaft Door Fix 6 days Sat 10/6/12 Thu 10/11/12

    197 Paint Work: 19 days Wed 6/27/12 Wed 7/18/12

    198 Paint Ceiling first coat 6 days Wed 6/27/12 Tue 7/3/12

    199 Paint Ceiling final Coat P-01 4 days Wed 7/4/12 Sun 7/8/12

    200 Paint Ceiling final Coat SP-01 8 days Tue 7/10/12 Wed 7/18/12

    201 Glass, Doors Hardware & Accessories: 23 days Sat 10/6/12 Wed 10/31/12

    202 Wall Card Reader panel 4 days Sat 10/6/12 Tue 10/9/12

    203 Celing glass reader panel 4 days Wed 10/10/12 Sun 10/14/12

    204 Glass panelling in front of lift Lobby 3 days Mon 10/15/12 Wed 10/17/12205 Doors Hardware 2 days Tue 10/30/12 Wed 10/31/12

    206 Carpet Work: 9 days Thu 9/13/12 Sun 9/23/12

    207 Underlay C-04 Fixation 3 days Thu 9/13/12 Sun 9/16/12

    208 Carpet C-05 Fixation 3 days Thu 9/20/12 Sun 9/23/12

    209

    210 LEVEL 6: 136 days Mon 6/11/12 Thu 11/15/12

    211 GUEST ROOMS(TOTAL 17 ROOMS) 112 days Mon 7/9/12 Thu 11/15/12

    212 Metal Works: 9 days Tue 7/24/12 Thu 8/2/12

    213 Installation of steel Bracket for Vanity, Shower & bathtub Acces 9 days Tue 7/24/12 Thu 8/2/12

    214 Installation of steel bracket for sliding door and TV Unit 9 days Tue 7/24/12 Thu 8/2/12

    215 Gypsum Ceiling: 10 days Mon 7/9/12 Thu 7/19/12

    216 Gypsum ceiling frame installation 8 days Mon 7/9/12 Tue 7/17/12

    217 Gypsum ceiling installation 8 days Wed 7/11/12 Thu 7/19/12

    Gyp. Carp.[3]

    Gyp. Carp.[3]

    Wood Carp.[3]

    Wood Carp.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Painter[2]

    Painter[2]

    Painter[2]

    Glass Fixer[3]

    Glass Fixer[3]

    Glass Fixer[3]Wood Carp.

    Carpet inst.[2]

    Carpet inst.[2]

    Steel Fixer[3]

    Steel Fixer[3]

    Gyp. Carp.[12]

    Gyp. Carp.[12]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 7/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    8/23

    ID Task Name Duration Start Finish

    218 Wood Works: 13.5 days Sun 10/7/12 Mon 10/22/12

    219 Doors(Entrance, Sliding, connecting) 9 days Sat 10/13/12 Mon 10/22/12

    220 Joinery(Wardrobe,TV Unit,Luggage,Vanity Cabinet) 6.75 days Sun 10/7/12 Mon 10/15/12

    221 Glass, Doors Hardware & Accessories: 69 days Mon 8/27/12 Wed 11/14/12

    222 Clear tempered shower partition 9 days Mon 11/5/12 Wed 11/14/12

    223 Metalic acid etch mirror 9 days Mon 8/27/12 Wed 9/5/12

    224 Toilet Access Panel 9 days Tue 10/23/12 Thu 11/1/12

    225 Doors Hardware 4 days Tue 10/23/12 Sat 10/27/12

    226 Bathroom accessories 4 days Sun 10/28/12 Wed 10/31/12

    227 Paint Work: 99 days Wed 7/18/12 Sat 11/10/12

    228 Paint Ceiling first coat 10 days Wed 7/18/12 Sun 7/29/12

    229 Paint Wall first coat 8 days Wed 10/17/12 Thu 10/25/12

    230 Paint Ceiling final Coat 8 days Thu 10/18/12 Sat 10/27/12

    231 Paint Wall final Coat 10 days Tue 10/30/12 Sat 11/10/12

    232 Curtains Work: 32 days Wed 10/10/12 Thu 11/15/12

    233 Brackets Installation 5 days Wed 10/10/12 Mon 10/15/12

    234 Motor&Tubes Installation 5 days Tue 10/16/12 Sun 10/21/12

    235 Fabric Tailoring 5 days Mon 10/22/12 Sat 10/27/12236 Fabrics Installation&Motor Programming 5 days Sun 11/11/12 Thu 11/15/12

    237 CORRIDOR (Type 1): 126 days Mon 6/11/12 Sun 11/4/12

    238 Gypsum Ceiling Works: 21 days Mon 6/11/12 Wed 7/4/12

    239 Gypsum ceiling frame installation 7 days Mon 6/11/12 Mon 6/18/12

    240 Gypsum ceiling Board installation 7 days Wed 6/27/12 Wed 7/4/12

    241 Wood Works: 1 day Mon 10/29/12 Mon 10/29/12

    242 Doors (Staircase, HVAC, Service, Shafts) 1 day Mon 10/29/12 Mon 10/29/12

    243 Joinery (Wood panelling for Elevator) 1 day Mon 10/29/12 Mon 10/29/12

    244 Wall Covering Works: 24 days Mon 9/24/12 Sun 10/21/12

    245 Fabrication 6 days Mon 9/24/12 Sun 9/30/12

    246 Panelling Fix 8 days Sat 10/6/12 Sun 10/14/12

    247 Shaft Door Fix 6 days Mon 10/15/12 Sun 10/21/12

    248 Paint Work: 24 days Thu 7/5/12 Wed 8/1/12

    Wood Carp.[12]

    Wood Carp.[16]

    Glass Fixer[6]

    Glass Fixer[3]

    Gyp. Carp.[3]

    Wood Carp.[4]

    Wood Carp.[4]

    Painter[6]

    Painter[6]

    Painter[12]

    Painter[14]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]Curtain Installer[2]

    Gyp. Carp.[3]

    Gyp. Carp.[3]

    Wood Carp.[3]

    Wood Carp.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 8/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    9/23

    ID Task Name Duration Start Finish

    249 Paint Ceiling first coat 6 days Thu 7/5/12 Wed 7/11/12

    250 Paint Ceiling final Coat P-01 4 days Thu 7/19/12 Mon 7/23/12

    251 Paint Ceiling final Coat SP-01 8 days Tue 7/24/12 Wed 8/1/12

    252 Glass, Doors Hardware & Accessories: 18 days Mon 10/15/12 Sun 11/4/12

    253 Wall Card Reader panel 4 days Mon 10/15/12 Thu 10/18/12

    254 Celing glass reader panel 4 days Sat 10/20/12 Tue 10/23/12

    255 Glass panelling in front of lift Lobby 3 days Thu 11/1/12 Sun 11/4/12

    256 Doors Hardware 2 days Tue 10/30/12 Wed 10/31/12

    257 Carpet Work: 15 days Thu 10/18/12 Sun 11/4/12

    258 Underlay C-04 Fixation 3 days Thu 10/18/12 Sun 10/21/12

    259 Carpet C-05 Fixation 3 days Thu 11/1/12 Sun 11/4/12

    260

    261 LEVEL 7: 137 days Tue 6/19/12 Sun 11/25/12

    262 GUEST ROOMS(TOTAL 17 ROOMS) 112 days Wed 7/18/12 Sun 11/25/12

    263 Metal Works: 9 days Sat 8/4/12 Mon 8/13/12

    264 Installation of steel Bracket for Vanity, Shower & bathtub Acces 9 days Sat 8/4/12 Mon 8/13/12

    265 Installation of steel bracket for sliding door and TV Unit 9 days Sat 8/4/12 Mon 8/13/12

    266 Gypsum Ceiling: 10 days Wed 7/18/12 Sun 7/29/12267 Gypsum ceiling frame installation 8 days Wed 7/18/12 Thu 7/26/12

    268 Gypsum ceiling installation 8 days Sat 7/21/12 Sun 7/29/12

    269 Wood Works: 15.75 days Mon 10/15/12 Thu 11/1/12

    270 Doors(Entrance, Sliding, connecting) 9 days Tue 10/23/12 Thu 11/1/12

    271 Joinery(Wardrobe,TV Unit,Luggage,Vanity Cabinet) 6.75 days Mon 10/15/12 Mon 10/22/12

    272 Glass, Doors Hardware & Accessories: 69 days Thu 9/6/12 Sun 11/25/12

    273 Clear tempered shower partition 9 days Thu 11/15/12 Sun 11/25/12

    274 Metalic acid etch mirror 9 days Thu 9/6/12 Sun 9/16/12

    275 Toilet Access Panel 9 days Sat 11/3/12 Mon 11/12/12

    276 Doors Hardware 4 days Sat 11/3/12 Tue 11/6/12

    277 Bathroom accessories 4 days Wed 11/7/12 Sun 11/11/12

    278 Paint Work: 99 days Mon 7/30/12 Wed 11/21/12

    279 Paint Ceiling first coat 10 days Mon 7/30/12 Thu 8/9/12

    Painter[2]

    Painter[2]

    Painter[2]

    Glass Fixer[3]

    Glass Fixer[3]

    Glass Fixer[3]

    Wood Carp.

    Carpet inst.[2]

    Carpet inst.[2]

    Steel Fixer[3]

    Steel Fixer[3]

    Gyp. Carp.[12]

    Gyp. Carp.[12]

    Wood Carp.[12]

    Wood Carp.[16]

    Glass Fixer[6]

    Glass Fixer[3]

    Gyp. Carp.[3]

    Wood Carp.[4]

    Wood Carp.[4]

    Painter[6]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 9/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    10/23

    ID Task Name Duration Start Finish

    280 Paint Wall first coat 8 days Sun 10/28/12 Mon 11/5/12

    281 Paint Ceiling final Coat 8 days Mon 10/29/12 Tue 11/6/12

    282 Paint Wall final Coat 10 days Sun 11/11/12 Wed 11/21/12

    283 Curtains Work: 32 days Tue 10/16/12 Wed 11/21/12

    284 Brackets Installation 5 days Tue 10/16/12 Sun 10/21/12

    285 Motor&Tubes Installation 5 days Mon 10/22/12 Sat 10/27/12

    286 Fabric Tailoring 5 days Sun 10/28/12 Thu 11/1/12

    287 Fabrics Installation&Motor Programming 5 days Sat 11/17/12 Wed 11/21/12

    288 CORRIDOR (Type 1): 122 days Tue 6/19/12 Wed 11/7/12

    289 Gypsum Ceiling Works: 21 days Tue 6/19/12 Thu 7/12/12

    290 Gypsum ceiling frame installation 7 days Tue 6/19/12 Tue 6/26/12

    291 Gypsum ceiling Board installation 7 days Thu 7/5/12 Thu 7/12/12

    292 Wood Works: 4 days Tue 10/30/12 Sat 11/3/12

    293 Doors (Staircase, HVAC, Service, Shafts) 1 day Sat 11/3/12 Sat 11/3/12

    294 Joinery (Wood panelling for Elevator) 1 day Tue 10/30/12 Tue 10/30/12

    295 Wall Covering Works: 26 days Mon 10/1/12 Tue 10/30/12

    296 Fabrication 6 days Mon 10/1/12 Sun 10/7/12

    297 Panelling Fix 8 days Mon 10/15/12 Tue 10/23/12298 Shaft Door Fix 6 days Wed 10/24/12 Tue 10/30/12

    299 Paint Work: 25 days Sat 7/14/12 Sat 8/11/12

    300 Paint Ceiling first coat 6 days Sat 7/14/12 Thu 7/19/12

    301 Paint Ceiling final Coat P-01 4 days Tue 7/24/12 Sat 7/28/12

    302 Paint Ceiling final Coat SP-01 8 days Thu 8/2/12 Sat 8/11/12

    303 Glass, Doors Hardware & Accessories: 13 days Wed 10/24/12 Wed 11/7/12

    304 Wall Card Reader panel 4 days Wed 10/24/12 Sun 10/28/12

    305 Celing glass reader panel 4 days Mon 10/29/12 Thu 11/1/12

    306 Glass panelling in front of lift Lobby 3 days Mon 11/5/12 Wed 11/7/12

    307 Doors Hardware 2 days Sun 11/4/12 Mon 11/5/12

    308 Carpet Work: 15 days Mon 10/22/12 Wed 11/7/12

    309 Underlay C-04 Fixation 3 days Mon 10/22/12 Wed 10/24/12

    310 Carpet C-05 Fixation 3 days Mon 11/5/12 Wed 11/7/12

    Painter[6]

    Painter[12]

    Painter[14]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Gyp. Carp.[3]

    Gyp. Carp.[3]

    Wood Carp.[3]

    Wood Carp.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]Wall Cover inst.[3]

    Painter[2]

    Painter[2]

    Painter[2]

    Glass Fixer[3]

    Glass Fixer[3]

    Glass Fixer[3]

    Wood Carp.

    Carpet inst.[2]

    Carpet inst.[2]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 10/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    11/23

    ID Task Name Duration Start Finish

    311

    312 LEVEL 8: 142 days Wed 6/27/12 Sun 12/9/12

    313 GUEST ROOMS(TOTAL 17 ROOMS) 116 days Sat 7/28/12 Sun 12/9/12

    314 Metal Works: 9 days Tue 8/14/12 Thu 8/23/12

    315 Installation of steel Bracket for Vanity, Shower & bathtub Acces 9 days Tue 8/14/12 Thu 8/23/12

    316 Installation of steel bracket for sliding door and TV Unit 9 days Tue 8/14/12 Thu 8/23/12

    317 Gypsum Ceiling: 10 days Sat 7/28/12 Tue 8/7/12

    318 Gypsum ceiling frame installation 8 days Sat 7/28/12 Sun 8/5/12

    319 Gypsum ceiling installation 8 days Mon 7/30/12 Tue 8/7/12

    320 Wood Works: 18 days Tue 10/23/12 Mon 11/12/12

    321 Doors(Entrance, Sliding, connecting) 9 days Sat 11/3/12 Mon 11/12/12

    322 Joinery(Wardrobe,TV Unit,Luggage,Vanity Cabinet) 6.75 days Tue 10/23/12 Tue 10/30/12

    323 Glass, Doors Hardware & Accessories: 69 days Mon 9/17/12 Wed 12/5/12

    324 Clear tempered shower partition 9 days Mon 11/26/12 Wed 12/5/12

    325 Metalic acid etch mirror 9 days Mon 9/17/12 Wed 9/26/12

    326 Toilet Access Panel 9 days Tue 11/13/12 Thu 11/22/12

    327 Doors Hardware 4 days Tue 11/13/12 Sat 11/17/12

    328 Bathroom accessories 4 days Sun 11/18/12 Wed 11/21/12329 Paint Work: 99 days Sat 8/11/12 Mon 12/3/12

    330 Paint Ceiling first coat 10 days Sat 8/11/12 Tue 8/21/12

    331 Paint Wall first coat 8 days Wed 11/7/12 Thu 11/15/12

    332 Paint Ceiling final Coat 8 days Thu 11/8/12 Sat 11/17/12

    333 Paint Wall final Coat 10 days Thu 11/22/12 Mon 12/3/12

    334 Curtains Work: 42 days Mon 10/22/12 Sun 12/9/12

    335 Brackets Installation 5 days Mon 10/22/12 Sat 10/27/12

    336 Motor&Tubes Installation 5 days Sun 10/28/12 Thu 11/1/12

    337 Fabric Tailoring 5 days Sat 11/3/12 Wed 11/7/12

    338 Fabrics Installation&Motor Programming 5 days Tue 12/4/12 Sun 12/9/12

    339 CORRIDOR (Type 1): 122 days Wed 6/27/12 Thu 11/15/12

    340 Gypsum Ceiling Works: 21 days Wed 6/27/12 Sat 7/21/12

    341 Gypsum ceiling frame installation 7 days Wed 6/27/12 Wed 7/4/12

    Steel Fixer[3]

    Steel Fixer[3]

    Gyp. Carp.[12]

    Gyp. Carp.[12]

    Wood Carp.[12]

    Wood Carp.[16]

    Glass Fixer[6]

    Glass Fixer[3]

    Gyp. Carp.[3]

    Wood Carp.[4]

    Wood Carp.[4]

    Painter[6]

    Painter[6]

    Painter[12]

    Painter[14]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Gyp. Carp.[3]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 11/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    12/23

    ID Task Name Duration Start Finish

    342 Gypsum ceiling Board installation 7 days Sat 7/14/12 Sat 7/21/12

    343 Wood Works: 12 days Wed 10/31/12 Tue 11/13/12

    344 Doors (Staircase, HVAC, Service, Shafts) 1 day Tue 11/13/12 Tue 11/13/12

    345 Joinery (Wood panelling for Elevator) 1 day Wed 10/31/12 Wed 10/31/12

    346 Wall Covering Works: 28 days Mon 10/8/12 Thu 11/8/12

    347 Fabrication 6 days Mon 10/8/12 Sun 10/14/12

    348 Panelling Fix 8 days Wed 10/24/12 Thu 11/1/12

    349 Shaft Door Fix 6 days Sat 11/3/12 Thu 11/8/12

    350 Paint Work: 26 days Sun 7/22/12 Mon 8/20/12

    351 Paint Ceiling first coat 6 days Sun 7/22/12 Sat 7/28/12

    352 Paint Ceiling final Coat P-01 4 days Sun 7/29/12 Wed 8/1/12

    353 Paint Ceiling final Coat SP-01 8 days Sun 8/12/12 Mon 8/20/12

    354 Glass, Doors Hardware & Accessories: 12 days Sat 11/3/12 Thu 11/15/12

    355 Wall Card Reader panel 4 days Sat 11/3/12 Tue 11/6/12

    356 Celing glass reader panel 4 days Wed 11/7/12 Sun 11/11/12

    357 Glass panelling in front of lift Lobby 3 days Mon 11/12/12 Wed 11/14/12

    358 Doors Hardware 2 days Wed 11/14/12 Thu 11/15/12

    359 Carpet Work: 15 days Thu 10/25/12 Sun 11/11/12360 Underlay C-04 Fixation 3 days Thu 10/25/12 Sun 10/28/12

    361 Carpet C-05 Fixation 3 days Thu 11/8/12 Sun 11/11/12

    362

    363 LEVEL 9: 145 days Thu 7/5/12 Thu 12/20/12

    364 GUEST ROOMS(TOTAL 17 ROOMS) 118 days Mon 8/6/12 Thu 12/20/12

    365 Metal Works: 9 days Sat 8/25/12 Mon 9/3/12

    366 Installation of steel Bracket for Vanity, Shower & bathtub Acces 9 days Sat 8/25/12 Mon 9/3/12

    367 Installation of steel bracket for sliding door and TV Unit 9 days Sat 8/25/12 Mon 9/3/12

    368 Gypsum Ceiling: 10 days Mon 8/6/12 Thu 8/16/12

    369 Gypsum ceiling frame installation 8 days Mon 8/6/12 Tue 8/14/12

    370 Gypsum ceiling installation 8 days Wed 8/8/12 Thu 8/16/12

    371 Wood Works: 20.25 days Tue 10/30/12 Thu 11/22/12

    372 Doors(Entrance, Sliding, connecting) 9 days Tue 11/13/12 Thu 11/22/12

    Gyp. Carp.[3]

    Wood Carp.[3]

    Wood Carp.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Painter[2]

    Painter[2]

    Painter[2]

    Glass Fixer[3]

    Glass Fixer[3]

    Glass Fixer[3]

    Wood Carp.

    Carpet inst.[2]

    Carpet inst.[2]

    Steel Fixer[3]

    Steel Fixer[3]

    Gyp. Carp.[12]

    Gyp. Carp.[12]

    Wood Carp.[12]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 12/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    13/23

    ID Task Name Duration Start Finish

    373 Joinery(Wardrobe,TV Unit,Luggage,Vanity Cabinet) 6.75 days Tue 10/30/12 Wed 11/7/12

    374 Glass, Doors Hardware & Accessories: 69 days Thu 9/27/12 Sun 12/16/12

    375 Clear tempered shower partition 9 days Thu 12/6/12 Sun 12/16/12

    376 Metalic acid etch mirror 9 days Thu 9/27/12 Sun 10/7/12

    377 Toilet Access Panel 9 days Sat 11/24/12 Mon 12/3/12

    378 Doors Hardware 4 days Sat 11/24/12 Tue 11/27/12

    379 Bathroom accessories 4 days Wed 11/28/12 Sun 12/2/12

    380 Paint Work: 99 days Wed 8/22/12 Sat 12/15/12

    381 Paint Ceiling first coat 10 days Wed 8/22/12 Sun 9/2/12

    382 Paint Wall first coat 8 days Sun 11/18/12 Mon 11/26/12

    383 Paint Ceiling final Coat 8 days Mon 11/19/12 Tue 11/27/12

    384 Paint Wall final Coat 10 days Tue 12/4/12 Sat 12/15/12

    385 Curtains Work: 47 days Sun 10/28/12 Thu 12/20/12

    386 Brackets Installation 5 days Sun 10/28/12 Thu 11/1/12

    387 Motor&Tubes Installation 5 days Sat 11/3/12 Wed 11/7/12

    388 Fabric Tailoring 5 days Thu 11/8/12 Tue 11/13/12

    389 Fabrics Installation&Motor Programming 5 days Sun 12/16/12 Thu 12/20/12

    390CORRIDOR (Type 1): 124 days Thu 7/5/12 Mon 11/26/12

    391 Gypsum Ceiling Works: 21 days Thu 7/5/12 Sun 7/29/12

    392 Gypsum ceiling frame installation 7 days Thu 7/5/12 Thu 7/12/12

    393 Gypsum ceiling Board installation 7 days Sun 7/22/12 Sun 7/29/12

    394 Wood Works: 20 days Thu 11/1/12 Sat 11/24/12

    395 Doors (Staircase, HVAC, Service, Shafts) 1 day Sat 11/24/12 Sat 11/24/12

    396 Joinery (Wood panelling for Elevator) 1 day Thu 11/1/12 Thu 11/1/12

    397 Wall Covering Works: 30 days Mon 10/15/12 Sun 11/18/12

    398 Fabrication 6 days Mon 10/15/12 Sun 10/21/12

    399 Panelling Fix 8 days Sat 11/3/12 Sun 11/11/12

    400 Shaft Door Fix 6 days Mon 11/12/12 Sun 11/18/12

    401 Paint Work: 27 days Mon 7/30/12 Wed 8/29/12

    402 Paint Ceiling first coat 6 days Mon 7/30/12 Sun 8/5/12

    403 Paint Ceiling final Coat P-01 4 days Mon 8/6/12 Thu 8/9/12

    Wood Carp.[16]

    Glass Fixer[6]

    Glass Fixer[3]

    Gyp. Carp.[3]

    Wood Carp.[4]

    Wood Carp.[4]

    Painter[6]

    Painter[6]

    Painter[12]

    Painter[14]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Gyp. Carp.[3]

    Gyp. Carp.[3]

    Wood Carp.[3]

    Wood Carp.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Painter[2]

    Painter[2]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 13/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    14/23

    ID Task Name Duration Start Finish

    404 Paint Ceiling final Coat SP-01 8 days Tue 8/21/12 Wed 8/29/12

    405 Glass, Doors Hardware & Accessories: 13 days Mon 11/12/12 Mon 11/26/12

    406 Wall Card Reader panel 4 days Mon 11/12/12 Thu 11/15/12

    407 Celing glass reader panel 4 days Sat 11/17/12 Tue 11/20/12

    408 Glass panelling in front of lift Lobby 3 days Wed 11/21/12 Sat 11/24/12

    409 Doors Hardware 2 days Sun 11/25/12 Mon 11/26/12

    410 Carpet Work: 15 days Mon 10/29/12 Wed 11/14/12

    411 Underlay C-04 Fixation 3 days Mon 10/29/12 Wed 10/31/12

    412 Carpet C-05 Fixation 3 days Mon 11/12/12 Wed 11/14/12

    413

    414 LEVEL 10: 148 days Sat 7/14/12 Tue 1/1/13

    415 GUEST ROOMS(TOTAL 18 ROOMS) 120 days Wed 8/15/12 Tue 1/1/13

    416 Metal Works: 9 days Tue 9/4/12 Thu 9/13/12

    417 Installation of steel Bracket for Vanity, Shower & bathtub Acces 9 days Tue 9/4/12 Thu 9/13/12

    418 Installation of steel bracket for sliding door and TV Unit 9 days Tue 9/4/12 Thu 9/13/12

    419 Gypsum Ceiling: 10 days Wed 8/15/12 Sun 8/26/12

    420 Gypsum ceiling frame installation 8 days Wed 8/15/12 Thu 8/23/12

    421 Gypsum ceiling installation 8 days Sat 8/18/12 Sun 8/26/12

    422 Wood Works: 22.5 days Wed 11/7/12 Mon 12/3/12

    423 Doors(Entrance, Sliding, connecting) 9 days Sat 11/24/12 Mon 12/3/12

    424 Joinery(Wardrobe,TV Unit,Luggage,Vanity Cabinet) 6.75 days Wed 11/7/12 Thu 11/15/12

    425 Glass, Doors Hardware & Accessories: 69 days Mon 10/8/12 Wed 12/26/12

    426 Clear tempered shower partition 9 days Mon 12/17/12 Wed 12/26/12

    427 Metalic acid etch mirror 9 days Mon 10/8/12 Wed 10/17/12

    428 Toilet Access Panel 9 days Tue 12/4/12 Thu 12/13/12

    429 Doors Hardware 4 days Tue 12/4/12 Sat 12/8/12

    430 Bathroom accessories 4 days Sun 12/9/12 Wed 12/12/12

    431 Paint Work: 99 days Mon 9/3/12 Wed 12/26/12

    432 Paint Ceiling first coat 10 days Mon 9/3/12 Thu 9/13/12

    433 Paint Wall first coat 8 days Wed 11/28/12 Thu 12/6/12

    434 Paint Ceiling final Coat 8 days Thu 11/29/12 Sat 12/8/12

    Painter[2]

    Glass Fixer[3]

    Glass Fixer[3]

    Glass Fixer[3]

    Wood Carp.

    Carpet inst.[2]

    Carpet inst.[2]

    Steel Fixer[3]

    Steel Fixer[3]

    Gyp. Carp.[12]

    Gyp. Carp.[12]

    Wood Carp.[12]

    Wood Carp.[16]

    Glass Fixer[6]

    Glass Fixer[3]

    Gyp. Carp.[3]

    Wood Carp.[4]

    Wood Carp.[4]

    Painter[6]

    Painter[6]

    Painter[12]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 14/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    15/23

    ID Task Name Duration Start Finish

    435 Paint Wall final Coat 10 days Sun 12/16/12 Wed 12/26/12

    436 Curtains Work: 52 days Sat 11/3/12 Tue 1/1/13

    437 Brackets Installation 5 days Sat 11/3/12 Wed 11/7/12

    438 Motor&Tubes Installation 5 days Thu 11/8/12 Tue 11/13/12

    439 Fabric Tailoring 5 days Wed 11/14/12 Mon 11/19/12

    440 Fabrics Installation&Motor Programming 5 days Thu 12/27/12 Tue 1/1/13

    441 CORRIDOR (Type 1): 126 days Sat 7/14/12 Thu 12/6/12

    442 Gypsum Ceiling Works: 21 days Sat 7/14/12 Mon 8/6/12

    443 Gypsum ceiling frame installation 7 days Sat 7/14/12 Sat 7/21/12

    444 Gypsum ceiling Board installation 7 days Mon 7/30/12 Mon 8/6/12

    445 Wood Works: 28 days Sat 11/3/12 Tue 12/4/12

    446 Doors (Staircase, HVAC, Service, Shafts) 1 day Tue 12/4/12 Tue 12/4/12

    447 Joinery (Wood panelling for Elevator) 1 day Sat 11/3/12 Sat 11/3/12

    448 Wall Covering Works: 32 days Mon 10/22/12 Tue 11/27/12

    449 Fabrication 6 days Mon 10/22/12 Sun 10/28/12

    450 Panelling Fix 8 days Mon 11/12/12 Tue 11/20/12

    451 Shaft Door Fix 6 days Wed 11/21/12 Tue 11/27/12

    452 Paint Work: 28 days Tue 8/7/12 Sat 9/8/12

    453 Paint Ceiling first coat 6 days Tue 8/7/12 Mon 8/13/12

    454 Paint Ceiling final Coat P-01 4 days Tue 8/14/12 Sat 8/18/12

    455 Paint Ceiling final Coat SP-01 8 days Thu 8/30/12 Sat 9/8/12

    456 Glass, Doors Hardware & Accessories: 14 days Wed 11/21/12 Thu 12/6/12

    457 Wall Card Reader panel 4 days Wed 11/21/12 Sun 11/25/12

    458 Celing glass reader panel 4 days Mon 11/26/12 Thu 11/29/12

    459 Glass panelling in front of lift Lobby 3 days Sat 12/1/12 Mon 12/3/12

    460 Doors Hardware 2 days Wed 12/5/12 Thu 12/6/12

    461 Carpet Work: 15 days Thu 11/1/12 Sun 11/18/12

    462 Underlay C-04 Fixation 3 days Thu 11/1/12 Sun 11/4/12

    463 Carpet C-05 Fixation 3 days Thu 11/15/12 Sun 11/18/12

    464

    465 LEVEL 11: 159 days Sun 7/22/12 Tue 1/22/13

    Painter[14]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Gyp. Carp.[3]

    Gyp. Carp.[3]

    Wood Carp.[3]

    Wood Carp.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Painter[2]

    Painter[2]

    Painter[2]

    Glass Fixer[3]

    Glass Fixer[3]

    Glass Fixer[3]

    Wood Carp.

    Carpet inst.[2]

    Carpet inst.[2]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 15/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    16/23

    ID Task Name Duration Start Finish

    466 GUEST ROOMS(TOTAL 25 ROOMS) 130 days Sat 8/25/12 Tue 1/22/13

    467 Metal Works: 9 days Sat 9/15/12 Mon 9/24/12

    468 Installation of steel Bracket for Vanity, Shower & bathtub Acces 9 days Sat 9/15/12 Mon 9/24/12

    469 Installation of steel bracket for sliding door and TV Unit 9 days Sat 9/15/12 Mon 9/24/12

    470 Gypsum Ceiling: 16 days Sat 8/25/12 Tue 9/11/12

    471 Gypsum ceiling frame installation 12 days Sat 8/25/12 Thu 9/6/12

    472 Gypsum ceiling installation 12 days Wed 8/29/12 Tue 9/11/12

    473 Wood Works: 28.75 days Thu 11/15/12 Tue 12/18/12

    474 Doors(Entrance, Sliding, connecting) 13 days Tue 12/4/12 Tue 12/18/12

    475 Joinery(Wardrobe,TV Unit,Luggage,Vanity Cabinet) 9.75 days Thu 11/15/12 Mon 11/26/12

    476 Glass, Doors Hardware & Accessories: 73 days Thu 10/18/12 Thu 1/10/13

    477 Clear tempered shower partition 13 days Thu 12/27/12 Thu 1/10/13

    478 Metalic acid etch mirror 13 days Thu 10/18/12 Thu 11/1/12

    479 Toilet Access Panel 13 days Wed 12/19/12 Wed 1/2/13

    480 Doors Hardware 6 days Wed 12/19/12 Tue 12/25/12

    481 Bathroom accessories 6 days Wed 12/26/12 Tue 1/1/13

    482 Paint Work: 106 days Sat 9/15/12 Tue 1/15/13

    483 Paint Ceiling first coat 15 days Sat 9/15/12 Mon 10/1/12

    484 Paint Wall first coat 14 days Thu 12/13/12 Sat 12/29/12

    485 Paint Ceiling final Coat 12 days Sat 12/15/12 Thu 12/27/12

    486 Paint Wall final Coat 15 days Sun 12/30/12 Tue 1/15/13

    487 Curtains Work: 65 days Thu 11/8/12 Tue 1/22/13

    488 Brackets Installation 6 days Thu 11/8/12 Wed 11/14/12

    489 Motor&Tubes Installation 6 days Thu 11/15/12 Wed 11/21/12

    490 Fabric Tailoring 6 days Thu 11/22/12 Wed 11/28/12

    491 Fabrics Installation&Motor Programming 6 days Wed 1/16/13 Tue 1/22/13

    492 CORRIDOR (Type 2): 132.8 days Sun 7/22/12 Sun 12/23/12

    493 Gypsum Ceiling Works: 23.8 days Sun 7/22/12 Sat 8/18/12

    494 Gypsum ceiling frame installation 9.8 days Sun 7/22/12 Wed 8/1/12

    495 Gypsum ceiling Board installation 9.8 days Tue 8/7/12 Sat 8/18/12

    496 Wood Works: 40 days Sun 11/4/12 Wed 12/19/12

    Steel Fixer[3]

    Steel Fixer[3]

    Gyp. Carp.[12]

    Gyp. Carp.[12]

    Wood Carp.[12]

    Wood Carp.[16]

    Glass Fixer[6]

    Glass Fixer[3]

    Gyp. Carp.[3]

    Wood Carp.[4]

    Wood Carp.[4]

    Painter[6]Painter[6]

    Painter[12]

    Painter[14]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Gyp. Carp.[3]

    Gyp. Carp.[3]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 16/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    17/23

    ID Task Name Duration Start Finish

    497 Doors (Staircase, HVAC, Service, Shafts) 1 day Wed 12/19/12 Wed 12/19/12

    498 Joinery (Wood panelling for Elevator) 1 day Sun 11/4/12 Sun 11/4/12

    499 Wall Covering Works: 39.6 days Mon 10/29/12 Thu 12/13/12

    500 Fabrication 8.4 days Mon 10/29/12 Wed 11/7/12

    501 Panelling Fix 11.2 days Wed 11/21/12 Tue 12/4/12

    502 Shaft Door Fix 8.4 days Tue 12/4/12 Thu 12/13/12

    503 Paint Work: 29.4 days Sat 8/18/12 Sat 9/22/12

    504 Paint Ceiling first coat 8.4 days Sat 8/18/12 Tue 8/28/12

    505 Paint Ceiling final Coat P-01 5.6 days Tue 8/28/12 Mon 9/3/12

    506 Paint Ceiling final Coat SP-01 11.2 days Sun 9/9/12 Sat 9/22/12507 Glass, Doors Hardware & Accessories: 16.6 days Tue 12/4/12 Sun 12/23/12

    508 Wall Card Reader panel 5.6 days Tue 12/4/12 Mon 12/10/12

    509 Celing glass reader panel 5.6 days Mon 12/10/12 Mon 12/17/12

    510 Glass panelling in front of lift Lobby 4.2 days Mon 12/17/12 Sat 12/22/12

    511 Doors Hardware 2.8 days Thu 12/20/12 Sun 12/23/12

    512 Carpet Work: 16.2 days Mon 11/5/12 Sat 11/24/12

    513 Underlay C-04 Fixation 4.2 days Mon 11/5/12 Sat 11/10/12

    514 Carpet C-05 Fixation 4.2 days Mon 11/19/12 Sat 11/24/12

    515

    516 LEVEL 12: 164.2 days Wed 8/1/12 Sat 2/9/13

    517 GUEST ROOMS(TOTAL 25 ROOMS) 133 days Sat 9/8/12 Sat 2/9/13

    518 Metal Works: 9 days Tue 9/25/12 Thu 10/4/12

    519 Installation of steel Bracket for Vanity, Shower & bathtub Acces 9 days Tue 9/25/12 Thu 10/4/12

    520 Installation of steel bracket for sliding door and TV Unit 9 days Tue 9/25/12 Thu 10/4/12

    521 Gypsum Ceiling: 16 days Sat 9/8/12 Tue 9/25/12

    522 Gypsum ceiling frame installation 12 days Sat 9/8/12 Thu 9/20/12

    523 Gypsum ceiling installation 12 days Wed 9/12/12 Tue 9/25/12

    524 Wood Works: 32 days Tue 11/27/12 Wed 1/2/13

    525 Doors(Entrance, Sliding, connecting) 13 days Wed 12/19/12 Wed 1/2/13

    526 Joinery(Wardrobe,TV Unit,Luggage,Vanity Cabinet) 9.75 days Tue 11/27/12 Sat 12/8/12

    527 Glass, Doors Hardware & Accessories: 73 days Sat 11/3/12 Sat 1/26/13

    Wood Carp.[3]

    Wood Carp.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Painter[2]

    Painter[2]

    Painter[2]

    Glass Fixer[3]

    Glass Fixer[3]

    Glass Fixer[3]

    Wood Carp.

    Carpet inst.[2]

    Carpet inst.[2]

    Steel Fixer[3]

    Steel Fixer[3]

    Gyp. Carp.[12]

    Gyp. Carp.[12]

    Wood Carp.[12]

    Wood Carp.[16]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 17/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    18/23

    ID Task Name Duration Start Finish

    528 Clear tempered shower partition 13 days Sat 1/12/13 Sat 1/26/13

    529 Metalic acid etch mirror 13 days Sat 11/3/12 Sat 11/17/12

    530 Toilet Access Panel 13 days Thu 1/3/13 Thu 1/17/13

    531 Doors Hardware 6 days Thu 1/3/13 Wed 1/9/13

    532 Bathroom accessories 6 days Thu 1/10/13 Wed 1/16/13

    533 Paint Work: 106 days Tue 10/2/12 Sat 2/2/13

    534 Paint Ceiling first coat 15 days Tue 10/2/12 Thu 10/18/12

    535 Paint Wall first coat 14 days Sun 12/30/12 Mon 1/14/13

    536 Paint Ceiling final Coat 12 days Sun 12/30/12 Sat 1/12/13

    537 Paint Wall final Coat 15 days Wed 1/16/13 Sat 2/2/13538 Curtains Work: 74 days Thu 11/15/12 Sat 2/9/13

    539 Brackets Installation 6 days Thu 11/15/12 Wed 11/21/12

    540 Motor&Tubes Installation 6 days Thu 11/22/12 Wed 11/28/12

    541 Fabric Tailoring 6 days Thu 11/29/12 Wed 12/5/12

    542 Fabrics Installation&Motor Programming 6 days Sun 2/3/13 Sat 2/9/13

    543 CORRIDOR (Type 2): 136 days Wed 8/1/12 Mon 1/7/13

    544 Gypsum Ceiling Works: 23.8 days Wed 8/1/12 Wed 8/29/12

    545 Gypsum ceiling frame installation 9.8 days Wed 8/1/12 Mon 8/13/12

    546 Gypsum ceiling Board installation 9.8 days Sat 8/18/12 Wed 8/29/12

    547 Wood Works: 52 days Mon 11/5/12 Thu 1/3/13

    548 Doors (Staircase, HVAC, Service, Shafts) 1 day Thu 1/3/13 Thu 1/3/13

    549 Joinery (Wood panelling for Elevator) 1 day Mon 11/5/12 Mon 11/5/12

    550 Wall Covering Works: 42.4 days Wed 11/7/12 Wed 12/26/12

    551 Fabrication 8.4 days Wed 11/7/12 Sat 11/17/12

    552 Panelling Fix 11.2 days Tue 12/4/12 Mon 12/17/12

    553 Shaft Door Fix 8.4 days Mon 12/17/12 Wed 12/26/12

    554 Paint Work: 30.8 days Wed 8/29/12 Thu 10/4/12

    555 Paint Ceiling first coat 8.4 days Wed 8/29/12 Sat 9/8/12

    556 Paint Ceiling final Coat P-01 5.6 days Sun 9/9/12 Sat 9/15/12

    557 Paint Ceiling final Coat SP-01 11.2 days Sat 9/22/12 Thu 10/4/12

    558 Glass, Doors Hardware & Accessories: 18.4 days Mon 12/17/12 Mon 1/7/13

    Glass Fixer[6]

    Glass Fixer[3]

    Gyp. Carp.[3]

    Wood Carp.[4]

    Wood Carp.[4]

    Painter[6]

    Painter[6]

    Painter[12]

    Painter[14]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Gyp. Carp.[3]

    Gyp. Carp.[3]

    Wood Carp.[3]

    Wood Carp.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Painter[2]

    Painter[2]

    Painter[2]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 18/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    19/23

    ID Task Name Duration Start Finish

    559 Wall Card Reader panel 5.6 days Mon 12/17/12 Sun 12/23/12

    560 Celing glass reader panel 5.6 days Mon 12/24/12 Sun 12/30/12

    561 Glass panelling in front of lift Lobby 4.2 days Sun 12/30/12 Thu 1/3/13

    562 Doors Hardware 2.8 days Sat 1/5/13 Mon 1/7/13

    563 Carpet Work: 16.2 days Sat 11/10/12 Wed 11/28/12

    564 Underlay C-04 Fixation 4.2 days Sat 11/10/12 Wed 11/14/12

    565 Carpet C-05 Fixation 4.2 days Sat 11/24/12 Wed 11/28/12

    566

    567 LEVEL 13: 162.9 days Mon 8/13/12 Tue 2/19/13

    568 GUEST ROOMS(TOTAL 25 ROOMS) 129.5 days Sat 9/22/12 Tue 2/19/13569 Metal Works: 9 days Sat 10/6/12 Mon 10/15/12

    570 Installation of steel Bracket for Vanity, Shower & bathtub Acces 9 days Sat 10/6/12 Mon 10/15/12

    571 Installation of steel bracket for sliding door and TV Unit 9 days Sat 10/6/12 Mon 10/15/12

    572 Gypsum Ceiling: 14 days Sat 9/22/12 Sun 10/7/12

    573 Gypsum ceiling frame installation 10 days Sat 9/22/12 Tue 10/2/12

    574 Gypsum ceiling installation 10 days Wed 9/26/12 Sun 10/7/12

    575 Wood Works: 33.25 days Sat 12/8/12 Tue 1/15/13

    576 Doors(Entrance, Sliding, connecting) 11 days Thu 1/3/13 Tue 1/15/13

    577 Joinery(Wardrobe,TV Unit,Luggage,Vanity Cabinet) 11 days Sat 12/8/12 Thu 12/20/12

    578 Glass, Doors Hardware & Accessories: 71 days Sun 11/18/12 Thu 2/7/13

    579 Clear tempered shower partition 11 days Sun 1/27/13 Thu 2/7/13

    580 Metalic acid etch mirror 11 days Sun 11/18/12 Thu 11/29/12

    581 Toilet Access Panel 11 days Sat 1/19/13 Wed 1/30/13

    582 Doors Hardware 5 days Thu 1/17/13 Tue 1/22/13

    583 Bathroom accessories 5 days Wed 1/23/13 Mon 1/28/13

    584 Paint Work: 99.5 days Sat 10/20/12 Tue 2/12/13

    585 Paint Ceiling first coat 12 days Sat 10/20/12 Thu 11/1/12

    586 Paint Wall first coat 10 days Tue 1/15/13 Sat 1/26/13

    587 Paint Ceiling final Coat 9.33 days Sun 1/13/13 Wed 1/23/13

    588 Paint Wall final Coat 8.5 days Sun 2/3/13 Tue 2/12/13

    589 Curtains Work: 76.5 days Thu 11/22/12 Tue 2/19/13

    Glass Fixer[3]

    Glass Fixer[3]

    Glass Fixer[3]

    Wood Carp.

    Carpet inst.[2]

    Carpet inst.[2]

    Steel Fixer[3]

    Steel Fixer[3]

    Gyp. Carp.[12]

    Gyp. Carp.[12]

    Wood Carp.[12]

    Wood Carp.[12]

    Glass Fixer[6]

    Glass Fixer[3]

    Gyp. Carp.[3]

    Wood Carp.[4]

    Wood Carp.[4]

    Painter[6]

    Painter[6]

    Painter[12]

    Painter[20]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 19/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    20/23

    ID Task Name Duration Start Finish

    590 Brackets Installation 6 days Thu 11/22/12 Wed 11/28/12

    591 Motor&Tubes Installation 6 days Thu 11/29/12 Wed 12/5/12

    592 Fabric Tailoring 6 days Thu 12/6/12 Wed 12/12/12

    593 Fabrics Installation&Motor Programming 6 days Tue 2/12/13 Tue 2/19/13

    594 CORRIDOR (Type 2): 137.2 days Mon 8/13/12 Sun 1/20/13

    595 Gypsum Ceiling Works: 23.8 days Mon 8/13/12 Mon 9/10/12

    596 Gypsum ceiling frame installation 9.8 days Mon 8/13/12 Sat 8/25/12

    597 Gypsum ceiling Board installation 9.8 days Wed 8/29/12 Mon 9/10/12

    598 Wood Works: 62 days Tue 11/6/12 Wed 1/16/13

    599 Doors (Staircase, HVAC, Service, Shafts) 1 day Wed 1/16/13 Wed 1/16/13600 Joinery (Wood panelling for Elevator) 1 day Tue 11/6/12 Tue 11/6/12

    601 Wall Covering Works: 45.2 days Sat 11/17/12 Tue 1/8/13

    602 Fabrication 8.4 days Sat 11/17/12 Tue 11/27/12

    603 Panelling Fix 11.2 days Mon 12/17/12 Sun 12/30/12

    604 Shaft Door Fix 8.4 days Sun 12/30/12 Tue 1/8/13

    605 Paint Work: 32.2 days Mon 9/10/12 Wed 10/17/12

    606 Paint Ceiling first coat 8.4 days Mon 9/10/12 Wed 9/19/12

    607 Paint Ceiling final Coat P-01 5.6 days Wed 9/19/12 Wed 9/26/12

    608 Paint Ceiling final Coat SP-01 11.2 days Thu 10/4/12 Wed 10/17/12

    609 Glass, Doors Hardware & Accessories: 18.2 days Sun 12/30/12 Sun 1/20/13

    610 Wall Card Reader panel 5.6 days Sun 12/30/12 Sun 1/6/13

    611 Celing glass reader panel 5.6 days Sun 1/6/13 Sat 1/12/13

    612 Glass panelling in front of lift Lobby 4.2 days Sat 1/12/13 Wed 1/16/13

    613 Doors Hardware 2.8 days Thu 1/17/13 Sun 1/20/13

    614 Carpet Work: 16.2 days Wed 11/14/12 Mon 12/3/12

    615 Underlay C-04 Fixation 4.2 days Wed 11/14/12 Mon 11/19/12

    616 Carpet C-05 Fixation 4.2 days Wed 11/28/12 Mon 12/3/12

    617

    618 LEVEL 14: 160.1 days Sat 8/25/12 Wed 2/27/13

    619 Typical Rooms: (TOTAL 15 ROOMS) 124.5 days Wed 10/3/12 Mon 2/25/13

    620 Metal Works: 9 days Tue 10/16/12 Thu 10/25/12

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[

    Gyp. Carp.[3]

    Gyp. Carp.[3]

    Wood Carp.[3]

    Wood Carp.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Painter[2]

    Painter[2]

    Painter[2]

    Glass Fixer[3]

    Glass Fixer[3]

    Glass Fixer[3]

    Wood Carp.

    Carpet inst.[2]

    Carpet inst.[2]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 20/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    21/23

    ID Task Name Duration Start Finish

    621 Installation of steel Bracket for Vanity, Shower & bathtub Acces 9 days Tue 10/16/12 Thu 10/25/12

    622 Installation of steel bracket for sliding door and TV Unit 9 days Tue 10/16/12 Thu 10/25/12

    623 Gypsum Ceiling: 12 days Wed 10/3/12 Tue 10/16/12

    624 Gypsum ceiling frame installation 8 days Wed 10/3/12 Thu 10/11/12

    625 Gypsum ceiling installation 8 days Mon 10/8/12 Tue 10/16/12

    626 Wood Works: 31.25 days Thu 12/20/12 Sat 1/26/13

    627 Doors(Entrance, Sliding, connecting) 9 days Wed 1/16/13 Sat 1/26/13

    628 Joinery(Wardrobe,TV Unit,Luggage,Vanity Cabinet) 9 days Thu 12/20/12 Mon 12/31/12

    629 Glass, Doors Hardware & Accessories: 69 days Sat 12/1/12 Mon 2/18/13

    630 Clear tempered shower partition 9 days Sat 2/9/13 Mon 2/18/13631 Metalic acid etch mirror 9 days Sat 12/1/12 Mon 12/10/12

    632 Toilet Access Panel 9 days Thu 1/31/13 Sun 2/10/13

    633 Doors Hardware 4 days Sun 1/27/13 Wed 1/30/13

    634 Bathroom accessories 4 days Thu 1/31/13 Mon 2/4/13

    635 Paint Work: 93.33 days Sat 11/3/12 Tue 2/19/13

    636 Paint Ceiling first coat 10 days Sat 11/3/12 Tue 11/13/12

    637 Paint Wall first coat 8 days Sun 1/27/13 Mon 2/4/13

    638 Paint Ceiling final Coat 8 days Wed 1/23/13 Sat 2/2/13

    639 Paint Wall final Coat 5.83 days Tue 2/12/13 Tue 2/19/13

    640 Curtains Work: 75.5 days Thu 11/29/12 Mon 2/25/13

    641 Brackets Installation 5 days Thu 11/29/12 Tue 12/4/12

    642 Motor&Tubes Installation 5 days Thu 12/6/12 Tue 12/11/12

    643 Fabric Tailoring 5 days Thu 12/13/12 Tue 12/18/12

    644 Fabrics Installation&Motor Programming 5 days Tue 2/19/13 Mon 2/25/13

    645 Presidential & Royal Suites: 118.5 days Sat 10/13/12 Wed 2/27/13

    646 Metal Works: 3 days Sat 10/27/12 Mon 10/29/12

    647 Supply and installation of steel brackets 3 days Sat 10/27/12 Mon 10/29/12

    648 Gypsum Ceiling: 10.5 days Sat 10/13/12 Wed 10/24/12

    649 Gypsum ceiling frame installation 6.5 days Sat 10/13/12 Sat 10/20/12

    650 Gypsum ceiling installation 6.5 days Wed 10/17/12 Wed 10/24/12

    651 Wood Works: 28.25 days Mon 12/31/12 Sat 2/2/13

    Steel Fixer[3]

    Steel Fixer[3]

    Gyp. Carp.[12]

    Gyp. Carp.[12]

    Wood Carp.[12]

    Wood Carp.[12]

    Glass Fixer[6]Glass Fixer[3]

    Gyp. Carp.[3]

    Wood Carp.[4]

    Wood Carp.[4]

    Painter[6]

    Painter[6]

    Painter[12]

    Painter[24]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installe

    Steel Fixer[6]

    Gyp. Carp.[12]

    Gyp. Carp.[12]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 21/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    22/23

    ID Task Name Duration Start Finish

    652 Doors(Entrance, Sliding, connecting) 6 days Sun 1/27/13 Sat 2/2/13

    653 Joinery(Wardrobe,TV Unit,Luggage,Vanity Cabinet) 5.67 days Mon 12/31/12 Mon 1/7/13

    654 Glass, Doors Hardware & Accessories: 66 days Tue 12/11/12 Mon 2/25/13

    655 Clear tempered shower partition 6 days Tue 2/19/13 Mon 2/25/13

    656 Metalic acid etch mirror 4 days Tue 12/11/12 Sat 12/15/12

    657 Toilet Access Panel 3 days Mon 2/11/13 Wed 2/13/13

    658 Doors Hardware 2 days Sun 2/3/13 Mon 2/4/13

    659 Bathroom accessories 2.5 days Tue 2/5/13 Thu 2/7/13

    660 Paint Work: 85.33 days Wed 11/14/12 Thu 2/21/13

    661 Paint Ceiling first coat 4.33 days Wed 11/14/12 Mon 11/19/12662 Paint Wall first coat 5.67 days Tue 2/5/13 Mon 2/11/13

    663 Paint Ceiling final Coat 1.5 days Sat 2/2/13 Sun 2/3/13

    664 Paint Wall final Coat 2 days Tue 2/19/13 Thu 2/21/13

    665 Curtains Work: 72.5 days Wed 12/5/12 Wed 2/27/13

    666 Brackets Installation 3 days Wed 12/5/12 Sat 12/8/12

    667 Motor&Tubes Installation 3 days Wed 12/12/12 Sat 12/15/12

    668 Fabric Tailoring 3 days Wed 12/19/12 Sat 12/22/12

    669 Fabrics Installation&Motor Programming 2 days Mon 2/25/13 Wed 2/27/13

    670 CORRIDOR (Type 1): 143.6 days Sat 8/25/12 Thu 2/7/13

    671 Gypsum Ceiling Works: 21 days Sat 8/25/12 Tue 9/18/12

    672 Gypsum ceiling frame installation 7 days Sat 8/25/12 Sun 9/2/12

    673 Gypsum ceiling Board installation 7 days Mon 9/10/12 Tue 9/18/12

    674 Wood Works: 70 days Wed 11/7/12 Sun 1/27/13

    675 Doors (Staircase, HVAC, Service, Shafts) 1 day Sun 1/27/13 Sun 1/27/13

    676 Joinery (Wood panelling for Elevator) 1 day Wed 11/7/12 Wed 11/7/12

    677 Wall Covering Works: 42.8 days Tue 11/27/12 Tue 1/15/13

    678 Fabrication 6 days Tue 11/27/12 Tue 12/4/12

    679 Panelling Fix 8 days Sun 12/30/12 Tue 1/8/13

    680 Shaft Door Fix 6 days Wed 1/9/13 Tue 1/15/13

    681 Paint Work: 31.8 days Wed 9/19/12 Sat 10/27/12

    682 Paint Ceiling first coat 6 days Wed 9/19/12 Wed 9/26/12

    Wood Carp.[6]

    Wood Carp.[6]

    Glass Fixer[3]

    Glass Fixer[3]

    Gyp. Carp.[3]

    Wood Carp.[4]

    Wood Carp.[4]

    Painter[6]Painter[6]

    Painter[12]

    Painter[12]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installer[2]

    Curtain Installe

    Gyp. Carp.[3]

    Gyp. Carp.[3]

    Wood Carp.[3]

    Wood Carp.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Wall Cover inst.[3]

    Painter[2]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 22/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.

  • 7/31/2019 2012 05 11 KAFD Program Rooms+Corridors

    23/23

    ID Task Name Duration Start Finish

    683 Paint Ceiling final Coat P-01 4 days Wed 9/26/12 Mon 10/1/12

    684 Paint Ceiling final Coat SP-01 8 days Wed 10/17/12 Sat 10/27/12

    685 Glass, Doors Hardware & Accessories: 11 days Sun 1/27/13 Thu 2/7/13

    686 Wall Card Reader panel 4 days Sun 1/27/13 Wed 1/30/13

    687 Celing glass reader panel 4 days Thu 1/31/13 Mon 2/4/13

    688 Glass panelling in front of lift Lobby 3 days Tue 2/5/13 Thu 2/7/13

    689 Doors Hardware 2 days Mon 1/28/13 Tue 1/29/13

    690 Carpet Work: 15 days Mon 11/19/12 Thu 12/6/12

    691 Underlay C-04 Fixation 3 days Mon 11/19/12 Thu 11/22/12

    692 Carpet C-05 Fixation 3 days Mon 12/3/12 Thu 12/6/12

    Painter[2]

    Painter[2]

    Glass Fixer[3]

    Glass Fixer[3]

    Glass Fixer[3]

    Wood Carp.

    Carpet inst.[2]

    Carpet inst.[2]

    Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 201

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    KOCACHE ENTERPRISES:KAFD HOTEL TENTATIVE PROGRAM .

    Page 23/23

    Project: KAFD HOTEL.Revision: Rev-02.

    Date: 11/05/2012.