The impact of Distributed Generation on network security ESRI EUC Madrid, 27 October 2011, Tomaso Bertoli
How Distributed Generation impacts network security? » Gruppo Dolomiti Energia
Network Security of Low Voltage Feeders STET Pergine
PESSE review 2012
Network Security and DG?
Gruppo Dolomiti Energia
6000 sqkm service area 500k inhabitants 8 service area + STET
3150 km 20kV 4470 MV>LV 6565 km 400V 140k service points 340k meters (En) + STET Pergine 18k
Gruppo Dolomiti Energia
6000 sqkm service area 500k inhabitants 8 service area + STET
3150 km 20kV 4470 MV>LV 6565 km 400V 140k service points 340k meters (En) + STET Pergine 18k
Gruppo Dolomiti Energia
6000 sqkm service area 500k inhabitants 8 service area + STET
3150 km 20kV 4470 MV>LV 6565 km 400V 140k service points 340k meters (En) + STET Pergine 18k
Gruppo Dolomiti Energia
6000 sqkm service area 500k inhabitants 8 service area + STET
3150 km 20kV 4470 MV>LV 6565 km 400V 140k service points 340k meters (En) + STET Pergine 18k
Gruppo Dolomiti Energia
6000 sqkm service area 500k inhabitants 8 service area + STET
3150 km 20kV 4470 MV>LV 6565 km 400V 140k service points 340k meters (En) + STET Pergine 18k
Gruppo Dolomiti Energia
6000 sqkm service area 500k inhabitants 8 service area + STET
3150 km 20kV 4470 MV>LV 6565 km 400V 140k service points 340k meters (En) + STET Pergine 18k
Gruppo Dolomiti Energia
6000 sqkm service area 500k inhabitants 8 service area + STET
3150 km 20kV 4470 MV>LV 6565 km 400V 140k service points 340k meters (En) + STET Pergine 18k
Gruppo Dolomiti Energia
6000 sqkm service area 500k inhabitants 8 service area + STET
3150 km 20kV 4470 MV>LV 6565 km 400V 140k service points 340k meters (En) + STET Pergine 18k
Gruppo Dolomiti Energia
6000 sqkm service area 500k inhabitants 8 service area + STET
3150 km 20kV 4470 MT>BT 6565 km 400V 140k service points 340k meters (En) + STET Pergine 18k
Integrated Information System
Network Information System
» ArcGIS \ ArcFM» Network topology» Geometric Network» Versioning Archiving» Feeder Manager
Device Locations
Customer Data and Work orders
» SAP IS-U» Clients Sales \ Users Distribution» Contracts» Devices» SAP GUI § Bapi
Device Location
» un-bundling
Like at home when the meter “trips” because oven and dryier and … are used together »
Network security for Low Voltage feeders
“ more a matter of probability than physics ”
Electric Analysis LV – V1 (2008)
• Trace Geometric Network return tree topology • Current Contract
Loads from SAP• Test Loads from
design
• Design Version
Electric Analysis LV – V1 (2008)
• Parameters• Contract Voltage• % of safe use• Power …• Paid for• Current contract• Available
• Probability concurrence• Probability \ Acceptable
Risk of black-out
Electric Analysis LV– V1 (2008)
• Output XLS• Max Current• Voltage Drop• Available power• Losses• Short Circuit Current
August 2010 – LV Feeder start tripping »
Managing Energy from renewable sources
Inversion of energy flowsLow Demand Max Production But how is it possible is DG is under 5% ? »
Current and future Electric Distribution
(source: EPRI, 2009 )
Emulation …
Clustering of Distributed Generation
Why clusters do not form?
PV (Photo Voltaic) Distributed Generation»
Clustering of Distributed Generation
• 50 MW total PV peak power• 6060 PV installations• 9000 LV Feeders
Average by feeder• < 0,7 installations• 9 kW
9000 total LVF
2890 LVF with PV
290 10° Percentile
29 1° Percentile
• 0,7 • 9 kW
• 2• 18 kW
• 6• 97 kW
• 10• 236 kW
• installations• Power kW
Average by feeder
PV (Photo Voltaic) Distributed Generation »
Clustering of Distributed Generation
• 50 MW PV total peak power• 1400 MW Contract power on LVF• On average PV 3% of Contract Power
But average values are missleading• Over 100 feeders have ratio PV / Contract power > 100%• 10° percentile of Feeders has PV / Contract power > 40%
Electric Analysis LV BT – V2 (2011)
• Generators • SAP IS-U• design
• Parameters• Power Modulation• Generation Modulation
Usual scenarios:• Late afternoon workday Winter• Weekend noon Summer
STET Pergine – PESSE review 2012
“small” multi utility in side valley
18k Electric meters Water\WasteWater Gas Garbage Street Lighting
PESSE, Emergency Plan for the safety of Electric SystemUnder the coordination of Terna (HV transmission) Distribution companies disconnect load in a planned and selective way, in order to avoid un-controlled black outs.
28 september 2003
PESSE – What ? Why ?
PESSE – How it works?
All residential and commercial customers are divided in groups For each group a rolling outage is planned for up to 1,5 hours per day.
PESSE – How it works ?
Optimize the groups » “domestic customers with life saving
equipment are excluded from the planned outages”
Distributed Generation – not only PV
PESSE Update 2012
PESSE Update 2012
GeoDataBase Versions to simulatedifferent PESSE plans \ groups »
PESSE Update 2012
ArcFM Feeder ManagerRecalculates MV and LV feeder »
PESSE update 2012
DBMS Server side SQL does all the group by \ sumNo Export, Fast and Reproduceable »
PESSE update 2012
Transforminga mountainof data inusefullusableInformation »
Data &Processes
data is trust worthy (updated and
complete) only as long as it is produced or used by a primary
company process
Robust Flexible
SoftwareAEEG releases each
year new rules, positive feed-back on
processes that can be managed and
optimized
Competent People on
Processes & Sw
dedication and (self)training to
exploit all the power in Sw (old and new) of the tech pyramid
3 key factors to “do more with less”
www.sinergis.it | [email protected]
www.dedagroup.it | [email protected]
Thank you for the attentionTomaso BertoliSolution Manager UtilitiesCoordinator of Multi Utility User Group
For more info: www.gismart.eu
Special thanks to Mariano Fronza, Dolomiti Reti (GDE)Stefano Silvestri, Dolomiti Reti (GDE)
Dario Dallepiatte, STET Pergine
To be Smart...
Smart Local Governments
Local GovernmentsUsing GIS-based Tax Solutions to be very effective in collecting real estate taxes and to fight tax elusion
Smart Multi Utilities
MultiutilitiesUsing GIS-based Solutions in order to better run the distribution network, reduce and manage power downwtime
Smart Provinces And Regions
Province e RegioniSoluzioni per il monitoraggio e il controllo permettono una gestione più efficace del traffico e una migliore manutenzione delle infrastrutture stradali
10 Regions 18 Provinces 3 Regional Environment Agencies
(ARPA) 2 Government Departments 10 Multi Utility Companies 15 Main Cities More than 50 Smaller Municipalities
and Associations of Smaller Cities
Smart Local Governments
Sinergis and Dedagrouphave been learning for morethan 20 years from:
Thank you for the attention
For more info: [email protected]