2011 CLINTON COUNTY ENGINEER’S ANNUAL REPORTclintoncountyengineer.org/News updates/2011 Annual...
Transcript of 2011 CLINTON COUNTY ENGINEER’S ANNUAL REPORTclintoncountyengineer.org/News updates/2011 Annual...
Inside this issue:
Engineer’s Review 1
Budget Breakdown 2
Bridge Replacements 2
Permit Summary 2
Tax Map Summary 2
Road Resurfacing 3
Bridge Ratings
3
Sight Distance Im-provements Project
3
Bypass Opening 4
2011 CLINTON COUNTY ENGINEER’S
ANNUAL REPORT Jeffrey B. Linkous, P.E., P.S.
Clinton County Engineer MARCH 31, 2012
three county roads with asphalt —Antioch Rd., Greene Rd. and Nelson Ave. This project is being funded using federal and Ohio Public Works monies. We also plan on sealing 30-35 miles of roads. We have received a $300,000 grant to install guard-rail at 98 locations and have a grant to stripe approximately 60 miles of roadway which will be in addition to the 50 miles we will complete with local funding.
Also in 2012, we plan to re-place the Port William Bridge with a new prestressed box beam bridge and have obtained both federal and Ohio Public Works funding to completely pay for this project. A new deck will be com-pleted on our Macedonia Road Bridge and new precast concrete boxes will be used for bridges on Dailey, Linkhart and Sabina Roads.
Our bridge and culvert inspec-tion program of all bridges and culverts over 5 feet is currently underway. A report will be sub-mitted to the Board of County Commissioners upon completion.
Our office and highway work-ers work very hard to improve our county highway system for the safety and welfare of the trav-eling public. I am proud of our many accomplishments and ap-preciate their support over the last year. I look forward to the challenges that face us in 2012.
In 2011 the Clinton County Engineer’s Office made signifi-cant advances in improving the safety of our roadways. We com-pleted two major safety up-grades. Center Road was low-ered and a new culvert installed at the intersection with Nelson Avenue, increasing visibility and providing a safer intersection. Cuba Road was lowered near the intersection with Berlin Road, also providing for better visibil-ity when entering the intersec-tion. Both were funded primarily using Ohio Public Works money.
Other safety measures in-cluded the installation of ap-proximately 2,000 of the 3,000 warning signs in the county. The new signs are more reflective to increase visibility for drivers, in accordance with new Federal Highway regulations. The re-maining 1,000 signs are ex-pected to be installed by late spring this year. New mile markers have also been installed along county roads, identifying the road number and mile loca-tion for first responders in case of an emergency.
We continue to widen berms and move ditches and obstruc-tions within the right-of-way. Our Wise Road project relocated ditches and replaced culverts to gain a safer stretch of road and eliminate the need for guardrail.
As part of our safety improve-ment focus, we have contracted Traffic Safety Analysis Systems & Services (TSASS) to provide a comprehensive county traffic safety program. This analysis is funded by a Federal Highway Administration (FHWA) grant. The Engineer’s Office already reviews accident reports on all county roads to determine loca-tions where safety can be im-proved. TSASS reports and
studies are in addition to our pro-gram and give further analysis which can help us obtain addi-tional funding for our safety im-provements. We also meet annu-ally with local law enforcement to review accident history and for-mulate necessary improvements as well as discuss enforcement issues.
During 2011, construction of major structures, including bridges and culverts totaled $528,199, which includes 5 bridge replacements and one large cul-vert. All of these replacements were constructed with our county forces. Portions of 17 roads were sealed using RS-2P by Miller-Mason Paving Co. at a cost of $403,774. Our crews also crack sealed several miles of roadway in an effort to prolong the life of our county roads. A summary of all maintenance and construction costs for 2011 has been included in this report for your review.
Snow and ice removal costs for the 2010-2011 winter season was $465,741, with the crews treating roads a total of 38 days. About $188,305 of this cost was for ma-terial applied to the road.
In 2012, we will be resurfacing
East Clinton Elementary Students
Learn About Signs Students in Mrs. Jones’s class learned that
signs help to protect people, and provide
necessary information to keep the roads
safer for everyone.
2012 TAX MAP SUMMARY
Total Property Transfers 2098
Deed Pre-approvals 1643
Existing deeds checked 907
Survey plats filed 115
Total Property Splits & Resurveys
Minor Splits< 20 ac. 27
Over 20 acres 10
Retracements 41
Exempt 18
Combinations 24
Total Parcels Reviewed
(include city) 120
Annexations reviewed 0
Major Subdivisions
Reviewed 0
Total Pay-in– Road/bridge $ 391,890
Total Pay-in—General
$ 2896
SNOW & ICE REMOVAL
Regular Hours 2259 hrs.
Overtime Hours 2079 hrs.
Grit (small stone) 4384 ton
Salt 2206 ton
Miles Driven 102,600 miles
Fuel Used 25,650 gals.
TOTAL COST: $ 465,741
(12/1/10 — 3/11/11)
2012 PERMITS & REVIEWS
Utility Permits Granted 66
House Numbers Assigned 31
Driveway Permits Issued 43
Accident Reports Reviewed 1230
Hauling/Overload Permits 38
MISC. MAINTENANCE
Trash Pickup
3/28/11—4/7/11 $ 40,296
Centerline Striping $ 30,134
Edgeline Striping $ 23,230
2011 REVENUE 2011 EXPENDITURES Motor Vehicle Tax (State) $ 1,364,978
Gas Tax $ 2,310,207
Reimbursements $ 391,890
Interest Income $ 1,932
Fines $ 172,485
Miscellaneous $ 2,553
Permissive Tax $ 68,885
TOTAL: $ 4,312,930
Salaries $ 1,564,631
Fringe Benefits $ 683,645
Road Resurfacing & Maint. $ 1,938,483
Bridge Constr. & Materials $ 228,218
Equipment $ 297,102
Miscellaneous $ 9,833
Unexpended Encumbrances $ (133,522)
TOTAL: $ 4,588,390
Road Name Bridge No. Type of Bridge Cost Est.
Macedonia 57-00.18 Cast In-Place Concrete Deck $130,000
Port William 05-09.81 Prestressed Box Beams w/Concrete Deck $673,400*
Dailey 145-00.58 Pre-cast Concrete Box $ 85,000
Linkhart 268-00.88 Pre-cast Concrete Box $120,000
Sabina 05-12.46 Pre-cast Concrete Box $ 75,000
TOTAL: $1,083,400
*80% Federal/20% Local (OPWC)
Road Bridge # Type of Bridge Cost
Beechgrove 17-02.440 Prestressed Box Beam $ 106,660
Second Creek 19-02.470 Prestressed Box Beam $ 110,151
Townsend 46-02.440 Pre-cast Concrete Box $ 79,827
Irvin 119-00.780 Pre-cast Concrete Box $ 85,771
Hornbeam 229-02.570 Pre-cast Concrete Box $ 88,348
Center 16-07.801 Reinforced Concrete Pipe $ 57,442
TOTAL: $ 528,199
Future... Past The Port William Rd. (Main St.)
Bridge is the focus of the federal
bridge project to be completed
in 2012. The aging superstruc-
ture on bridge will be replaced
with a new, pre-stressed com-
posite concrete box beam
bridge deck. The local share of
this project will be funded by
Ohio Public Works funds. December 1974 December 2002
Present
2011 Retiree’s Luncheon Those present were (left to right, starting in the back) Doug Smith, Donald Dalton, Paul Pollitt,
Marion Osborn, Larry Teboe, Ron Williamson, Bill Temple, Betty Graham, Ron Livingston, Aaron
Quigley, Jenny Brooks, Bob Brooks.
SIGHT DISTANCE IMPROVEMENT PROJECTS MAKE
FOR SAFER COUNTY ROADS
Road Name Length Description Cost
Cox 3.490 Single Seal $ 34,072 Creek 2.473 Single Seal $ 26,529 Fairgrounds Lot 0.707 Single Seal $ 16,050 Fife Ave. 0.812 Single Seal $ 10,528 Gano 3.094 Single Seal $ 41,694 Gurneyville 2.737 Single Seal $ 28,392 Hamilton 1.914 Single Seal $ 17,652 Lynchburg 4.104 Single Seal $ 43,094 Moore 0.954 Single Seal $ 8,775 North Curry 1.818 Single Seal $ 18,656 Orchard 1.210 Single Seal $ 12,611 Sabina 6.971 Single Seal $ 69,506 Spring Hill 0.322 Single Seal $ 4,504 Stone 2.379 Single Seal $ 24,310 Terrell 3.089 Single Seal $ 30,292 Williams 1.543 Single Seal $ 14,747 Center 0.407 Reconstruction $332,419* Cuba 0.107 Reconstruction $123,772* Prairie 4.034 Mill, Asphalt, Berm $356,171** Starbuck 1.690 Mill, Asphalt, Berm $176,409** County Lot Dwy 0.156 Single Seal $ 2,362
TOTALS: 44.011 $1,392,545
Average Cost of Single Seal Per Mile—$10,689.48 (includes cost of stone)
*79% Ohio Public Works 21% Local Share
**ODOT funded for repairs needed due to Bypass Construction
SIGHT DISTANCE IMPROVEMENT PROJECTS
Center Road Approaching Nelson—Before
Center Road—Cutting Down Hill
Center Road —After
Cuba Road approaching Berlin—Before
Cuba and Berlin Intersection—After
Clinton County was able to obtain Ohio Public Works Commission
(OPWC) funding for the 2011 construction season in the amount of
$440,905 for sight distance improvement projects on Center Road and
Cuba Road. This project included total reconstruction of Center
Road to the west of the Nelson Road intersection by lowering Center
Road and replacing an existing culvert to create sight distance and
improve the safety of the Nelson Avenue intersection. In addition, re-
construction of Cuba Road and part of Berlin Road by lowering and
removing sight restrictions improved safety at this intersection.
Photos (to the right) show the progression of the work. Details of the
work are as follows:
Center Road—Approximately 1000 ft. of Center Road was recon-
structed, and the road was widened from 23 ft. to 24 ft. An existing
stone arch box culvert was also replaced by a new 60 inch reinforced
concrete culvert. By lowering the hill on Center Road, approximately
8 ft. in places, vehicles traveling on Nelson Road are now able to see
vehicles approaching them from the west on Center Road.
Cuba and Berlin Roads—Approximately 500 ft. of Cuba Road was
reconstructed and the road was widened from 20 ft. to 24 ft. Berlin
Road had approximately 250 ft. of road reconstruction and was wid-
ened from 18 ft. to 24 ft.
Although the majority of the work has been accomplished, finishing
touches will take place in the Spring of 2012. The project is scheduled
to be completed by the end of June, 2012.
Clinton County Engineer 1326 Fife Avenue
Wilmington, OH 45177 Phone: (937) 382-2078 Fax: (937) 382-5318
Coming together is a
beginning; keeping together is
progress; working together is
success.
- Henry Ford
Clinton County cele-
brated the opening of
the 7.5 mile Wilming-
ton Bypass! The Wilming-
ton High School marching
band provided the fan fare for the festivities as city, county
and state officials, along with
contractors, gathered to
share stories of the journey
from vision to reality. Stand-
ing on the pavement of the
relocated State Route 73 was
the result of years of planning
and teamwork.
The Engineer’s Office
served as a liaison for the
County, City and Ohio De-
VISIT US ON THE WEB! www.clintoncountyengineer.org
partment of Transportation (ODOT)
during the early planning stages. The
Engineer’s Office reviewed reports
and served as a technical advisor.
In 2004, the project was taken
over in its entirety by ODOT. The
majority of the $76.9 million cost of
the Bypass was funded by federal and
state dollars.
The bid for Phase I (SR 73S to US
22/SR 3E) was awarded to John R.
Jurgensen Co. and construction
started in 2007. Phase II (US 22/SR 3
E to US 68 N) and Phase III (US 68 N
to SR 73 W) bids were awarded to
E.S. Wagner and Co. and construc-
tion started in 2009, constructing
both phases concurrently.
The Bypass will reduce traffic
congestion through downtown Wil-mington and as Mayor David Raizk
said at the ceremony “the citizens
can reclaim city streets for local and
commercial traffic.”
SR 73 RELOCATION WAS COMPLETED AND OFFICIALLY OPENED NOVEMBER, 2, 2011
Wilmington Bypass Opens