2010 C&MS Summary Division of Construction Management.
-
Upload
chase-neal -
Category
Documents
-
view
220 -
download
3
Transcript of 2010 C&MS Summary Division of Construction Management.
2010 C&MS Summary
Division of Construction Management
2010 C&MS Distribution
• 2010 C&MS distributed 1/30/2010• Copies are available through
Office of Contracts – Tony Palka• 614/466-0387• [email protected]
2010 Conaway Conference 2
2010 Conaway Conference
Highlights of the 2010 C&MS
• Training for OCA• Tentatively scheduled for each Friday
in April
• Training for ODOT• Tentatively scheduled for May
• Highway Technician Classes updated for 2010 C&MS and 2009 MOP
3
2010 Conaway Conference
Highlights of the 2010 C&MS
• Updated 102.05/102.07 – – Examination of Bid Documents and
Project Site and Submission of PreBid Questions• New Policy and Standard Procedure for
Prebid questions and Addenda published
– Duty to Notify of Errors in Bid Documents
4
2010 Conaway Conference
Highlights of the 2010 C&MS
• Added 104.05 – Contractor Notification, Continuation
of Work, Disputes and Claims
• Added 105.19– Value Engineering Change Proposals– Changes that are only to MOT or
Sequence of Operation are not eligible as a VECP
5
2010 Conaway Conference
Highlights of the 2010 C&MS
• Updated 109.05 – Changes and Extra Work– New Policy and Standard Procedure
for Change Orders published
• SS800 will be published 4/16/210, and thereafter
6