200709 Falls Creek Report

download 200709 Falls Creek Report

of 12

Transcript of 200709 Falls Creek Report

  • 8/3/2019 200709 Falls Creek Report

    1/12

    Gustavus Electric Company

    P.O. Box 102 Gustavus Alaska 99826 (907) 697-2299 fax (907) 697-2355

    TO:

    Pat Regan - Regional Engineer

    Ofce of Energy Projects - FERCDivision of Dam Safety and Inspection

    Portland Regional Ofce

    101 Southwest Main Street - Suite 905

    Portland, Oregon 97204

    SUBJECT:

    September 2007 Monthly Report for the Falls Creek Hydro-electric Project

    FERC # P-11659

    DATE SUBMITTED:

    10/20/07

    DISTRIBUTION LIST:

    Project Personnel Position Contact E-mail

    Richard Levitt Project Manager [email protected]

    Steve Manchester Construction Superintendent [email protected]

    Bob Christensen Environmental Compliance [email protected]

    Recipients Aency Contact E-mail

    Ron Wright FERC [email protected]

    Jim Ferguson ADF&G [email protected]

    Sean Johnson ADF&G [email protected]

    Doug Jenkins USDARUS [email protected]

    Richard Enriquez USFWS [email protected]

    Tomie Lee NPS [email protected]

    Jackie Timothy DNR [email protected]

  • 8/3/2019 200709 Falls Creek Report

    2/12

    Falls Creek Hydroelectric Project (P-11659)

    MONTHLY CONSTRUCTION REPORT TO FERC

    September 2007

    1) Progress of Work - PM

    This month work continued on the intake/diversion

    structure and the installation/backll of the

    HDPE penstock. Further work was done on the

    interconnecting powerline. Some progress was made

    on erosion and sediment control work along the intake

    road.

    2) Status of Construction - PM

    During the rst week of the month, 2,500 feet of

    interconnecting transmission line was installed along

    the side of the access road. In conjunction with the

    transmission line work, some of the roadsides were

    sloped to nal grade and progress was made on rock-

    lining uphill side ditches.

    The powerhouse road in the area of the clearcut gravel pit was

    relocated to the east along the east edge of the pit. This is the

    route of the original plan for the road. The road was relocated so

    that more area of the gravel pit would be available for material

    extraction. More material has been needed as the bedding and

    backll for the penstock than was anticipated. The material is also

    being used as bedding and backll for the powerline.

    HDPE penstock was installed from station 27+00 to station

    41+00 this month. An additional 300 feet of 30 HDPE was

    installed in excess of what was called for in the original plan.

    Thi i b f dditi l t t l l th f th t k d t

    Sloping along the lower portions of the access

    road where the transmission line is buried.

  • 8/3/2019 200709 Falls Creek Report

    3/12

  • 8/3/2019 200709 Falls Creek Report

    4/12

    No work was done on the tailrace or in the

    powerhouse area this month.

    There were no inspections of the project this

    month by FERC or any resource agencies.

    3) Construction Difculties - PM

    The additional length of 30 HDPE put the

    reducer for connecting the 30 pipe to the

    28 pipe in a curve of the pipe rather than a

    straight section. This stressed the reducer

    more than expected, so the reducer will beencased in concrete.

    There were some minor equipment break-

    downs this month which necessitated moving

    from one phases of the job to another and then

    back. Repair parts came quickly and the dif-

    culties were minor.

    5) Critical Events and Dates - PM

    There were no critical events this month.

    8) Sources of Major Construction Material - PM

    All work done this month used material that has been described in previous reports.

    9) Materials Testing and Results - PM

    All backll material used this month was veried by the project manager as having been screened to remove

    ll 1 i h l t i l C ti f th b kll t t d i th i th il b th d

    Too much stress on this reducer damaged the connec-

    tion. This joint will now be encased in a concrete block.

  • 8/3/2019 200709 Falls Creek Report

    5/12

    11) Photographs - ECM

    Ten photo vantage points have been

    established throughout the project area to

    document the progress of construction (see

    Appendix 1). No visible changes occuredexcept at photo sites 7, 9, and 10. Precise

    locations of photos were changed in some

    locations to better display the new work.

    12) Environmental Compliance Issues - ECM

    Bob Christensen was on vacation during the

    month of September. ECM duties were lledby Greg Streveler. This months ECM report

    will be abbreviated for this reason.

    Short-term pulses of high turbidity occured

    a few times as a result of phase 2 intake

    operations although recorded turbidiitys were

    within acceptable parameters. In general,

    the construction crew did an excellent jobof controlling sedimentation during phase 2

    operations at the intake.

    The foot print at the gravel pit expanded a bit

    as a result of moving the powerhouse road

    to the eastern side of the clearing. Efforts will

    be made to work with the Project Manager to

    insure that further impacts to important forest

    habitats in this area are kept to an absolute

    minimum.

    13) C li I i N d f I di t

    This cofferdam within a cofferdam was useful in control-

    ling sedimentation of the creek.

  • 8/3/2019 200709 Falls Creek Report

    6/12

    15) Biotic Monitoring - ECM

    Salmon foot counts continued throughout the month. The peak pink salmon numbers observed for the year

    came during the rst week of the month at 1,169. The rst cohos (very small numbers) showed up during the

    very end of the month.

    Some newly placed gravels in the engineered logjam area were lost downstream during higher ows. These

    gravels will be replaced next year along with already scheduled gravel bed work and minor modications to the

    woody structures next year.

    The following sections are not yet applicable to the date of this report:

    4) Contract Status6) Reservoir Filling

    7) Foundations10) Instrumentation

  • 8/3/2019 200709 Falls Creek Report

    7/12

  • 8/3/2019 200709 Falls Creek Report

    8/12

    APPENDIx 1: SEPTEMBER 2007 PHOTOS FROM vANTAgE POINTS

  • 8/3/2019 200709 Falls Creek Report

    9/12

  • 8/3/2019 200709 Falls Creek Report

    10/12

    APPENDIx 2: qUALITY CONTROL ATTACHMENTS

  • 8/3/2019 200709 Falls Creek Report

    11/12

  • 8/3/2019 200709 Falls Creek Report

    12/12