200709 Falls Creek Report
-
Upload
tayfun-aykutlu -
Category
Documents
-
view
219 -
download
0
Transcript of 200709 Falls Creek Report
-
8/3/2019 200709 Falls Creek Report
1/12
Gustavus Electric Company
P.O. Box 102 Gustavus Alaska 99826 (907) 697-2299 fax (907) 697-2355
TO:
Pat Regan - Regional Engineer
Ofce of Energy Projects - FERCDivision of Dam Safety and Inspection
Portland Regional Ofce
101 Southwest Main Street - Suite 905
Portland, Oregon 97204
SUBJECT:
September 2007 Monthly Report for the Falls Creek Hydro-electric Project
FERC # P-11659
DATE SUBMITTED:
10/20/07
DISTRIBUTION LIST:
Project Personnel Position Contact E-mail
Richard Levitt Project Manager [email protected]
Steve Manchester Construction Superintendent [email protected]
Bob Christensen Environmental Compliance [email protected]
Recipients Aency Contact E-mail
Ron Wright FERC [email protected]
Jim Ferguson ADF&G [email protected]
Sean Johnson ADF&G [email protected]
Doug Jenkins USDARUS [email protected]
Richard Enriquez USFWS [email protected]
Tomie Lee NPS [email protected]
Jackie Timothy DNR [email protected]
-
8/3/2019 200709 Falls Creek Report
2/12
Falls Creek Hydroelectric Project (P-11659)
MONTHLY CONSTRUCTION REPORT TO FERC
September 2007
1) Progress of Work - PM
This month work continued on the intake/diversion
structure and the installation/backll of the
HDPE penstock. Further work was done on the
interconnecting powerline. Some progress was made
on erosion and sediment control work along the intake
road.
2) Status of Construction - PM
During the rst week of the month, 2,500 feet of
interconnecting transmission line was installed along
the side of the access road. In conjunction with the
transmission line work, some of the roadsides were
sloped to nal grade and progress was made on rock-
lining uphill side ditches.
The powerhouse road in the area of the clearcut gravel pit was
relocated to the east along the east edge of the pit. This is the
route of the original plan for the road. The road was relocated so
that more area of the gravel pit would be available for material
extraction. More material has been needed as the bedding and
backll for the penstock than was anticipated. The material is also
being used as bedding and backll for the powerline.
HDPE penstock was installed from station 27+00 to station
41+00 this month. An additional 300 feet of 30 HDPE was
installed in excess of what was called for in the original plan.
Thi i b f dditi l t t l l th f th t k d t
Sloping along the lower portions of the access
road where the transmission line is buried.
-
8/3/2019 200709 Falls Creek Report
3/12
-
8/3/2019 200709 Falls Creek Report
4/12
No work was done on the tailrace or in the
powerhouse area this month.
There were no inspections of the project this
month by FERC or any resource agencies.
3) Construction Difculties - PM
The additional length of 30 HDPE put the
reducer for connecting the 30 pipe to the
28 pipe in a curve of the pipe rather than a
straight section. This stressed the reducer
more than expected, so the reducer will beencased in concrete.
There were some minor equipment break-
downs this month which necessitated moving
from one phases of the job to another and then
back. Repair parts came quickly and the dif-
culties were minor.
5) Critical Events and Dates - PM
There were no critical events this month.
8) Sources of Major Construction Material - PM
All work done this month used material that has been described in previous reports.
9) Materials Testing and Results - PM
All backll material used this month was veried by the project manager as having been screened to remove
ll 1 i h l t i l C ti f th b kll t t d i th i th il b th d
Too much stress on this reducer damaged the connec-
tion. This joint will now be encased in a concrete block.
-
8/3/2019 200709 Falls Creek Report
5/12
11) Photographs - ECM
Ten photo vantage points have been
established throughout the project area to
document the progress of construction (see
Appendix 1). No visible changes occuredexcept at photo sites 7, 9, and 10. Precise
locations of photos were changed in some
locations to better display the new work.
12) Environmental Compliance Issues - ECM
Bob Christensen was on vacation during the
month of September. ECM duties were lledby Greg Streveler. This months ECM report
will be abbreviated for this reason.
Short-term pulses of high turbidity occured
a few times as a result of phase 2 intake
operations although recorded turbidiitys were
within acceptable parameters. In general,
the construction crew did an excellent jobof controlling sedimentation during phase 2
operations at the intake.
The foot print at the gravel pit expanded a bit
as a result of moving the powerhouse road
to the eastern side of the clearing. Efforts will
be made to work with the Project Manager to
insure that further impacts to important forest
habitats in this area are kept to an absolute
minimum.
13) C li I i N d f I di t
This cofferdam within a cofferdam was useful in control-
ling sedimentation of the creek.
-
8/3/2019 200709 Falls Creek Report
6/12
15) Biotic Monitoring - ECM
Salmon foot counts continued throughout the month. The peak pink salmon numbers observed for the year
came during the rst week of the month at 1,169. The rst cohos (very small numbers) showed up during the
very end of the month.
Some newly placed gravels in the engineered logjam area were lost downstream during higher ows. These
gravels will be replaced next year along with already scheduled gravel bed work and minor modications to the
woody structures next year.
The following sections are not yet applicable to the date of this report:
4) Contract Status6) Reservoir Filling
7) Foundations10) Instrumentation
-
8/3/2019 200709 Falls Creek Report
7/12
-
8/3/2019 200709 Falls Creek Report
8/12
APPENDIx 1: SEPTEMBER 2007 PHOTOS FROM vANTAgE POINTS
-
8/3/2019 200709 Falls Creek Report
9/12
-
8/3/2019 200709 Falls Creek Report
10/12
APPENDIx 2: qUALITY CONTROL ATTACHMENTS
-
8/3/2019 200709 Falls Creek Report
11/12
-
8/3/2019 200709 Falls Creek Report
12/12