Creating awesome value proposition using Value Proposition Canvas
2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee...
Transcript of 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee...
![Page 1: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/1.jpg)
2006 Annual Report
on the Status of the Implementation of
Proposition 400
Management Committee9/6/06
![Page 2: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/2.jpg)
Report Requirements
ARS 28-6354. Status of Projects. Changes to the RTP and Plan Priorities. Project Financing. Public Hearing.
![Page 3: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/3.jpg)
Key Topics
Regional Transportation Plan. Revenues. Freeway/Highway Program. Arterial Street Program. Transit Program.
![Page 4: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/4.jpg)
Regional Transportation Plan
The Freeway/Highway, Arterial Street and Transit Life Cycle Programs were incorporated directly into the MAG Regional Transportation Plan.
MAG has initiated several transportation studies to serve as a resource for potential future RTP updates.
![Page 5: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/5.jpg)
Revenues
Fiscal Year 2006 receipts from the Prop. 400 half-cent sales tax were 11.4 percent higher than the estimate in the 2005 Annual Report.
Forecasts of future available regional revenues are largely unchanged from the 2005 Annual Report.
![Page 6: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/6.jpg)
Revenues Half-Cent Sales Tax - Receipts (FY 06)*
*Second Half
$77.1$85.7
$14.4$16.1
$45.7$51.5
$137.2
$152.9
$0.0
$20.0
$40.0
$60.0
$80.0
$100.0
$120.0
$140.0
$160.0
Millions
Fwy. Art. Transit Total
'05 Forecast
'06 Actual
![Page 7: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/7.jpg)
Revenues Half-Cent Sales Tax - Forecast (FY 07-26)
$7.97 $7.90
$1.49 $1.48
$4.72 $4.68
$14.18 $14.06
$0.00
$2.00
$4.00
$6.00
$8.00
$10.00
$12.00
$14.00
$16.00
Billions
Fwy. Art. Transit Total
'05 Forecast
'06 Forecast
![Page 8: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/8.jpg)
Revenues Other Sources - Forecast (FY 07-26)
$2.46$2.56
$3.12 $3.14
$2.43 $2.39
$0.00
$1.00
$2.00
$3.00
$4.00
Billions
15% Fed. Transit Fed. Hwy.
'05 Forecast
'06 Forecast
![Page 9: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/9.jpg)
Revenues
House Bill 2865 created the Statewide Transportation Acceleration Needs (STAN) Account. MAG’s share of the available funding will be approximately $184 million for projects on the State Highway System.
![Page 10: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/10.jpg)
Freeway/Highway Program
![Page 11: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/11.jpg)
Freeway/Highway Program
Major progress has been made on finishing the Prop. 300 program.- Santan Freeway completed.- Final Grand Ave. grade separation completed.- Red Mt. Freeway done by mid-2008.
Preliminary engineering and environmental analysis are proceeding on Prop. 400 corridors and widenings.
![Page 12: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/12.jpg)
Freeway/Highway Program
Projects on I-10 and I-17 were accelerated through HELP and GAN loans.
During FY 2006, approximately $58 million was expended on projects in the Prop. 400 freeway/highway program.
![Page 13: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/13.jpg)
Freeway/Highway Program FY 06 Project Expenditures
$26.8
$3.6
$25.3
$2.1
$57.8
$0.0
$10.0
$20.0
$30.0
$40.0
$50.0
$60.0
Millions
Design R/ W Const. Maint. Total
![Page 14: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/14.jpg)
Freeway/Highway Program
Approximately $540 million has been programmed for projects scheduled to go to bid for construction in FY 2007.
Cost increases totaling $252 million were experienced for projects in the Life Cycle Program.
![Page 15: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/15.jpg)
Freeway/Highway Program
Estimated future costs of the Freeway/Highway Life Cycle Program are in balance with projected revenues.- Future Revenues: $10,199 million- Future Costs: $10,145 million
During the coming fiscal year, significant additional project cost increases may be encountered in the Freeway/Highway Life Cycle Program, as detailed engineering studies are completed.
![Page 16: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/16.jpg)
Arterial Streets Program
![Page 17: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/17.jpg)
Arterial Streets Program
The Arterial Street Life Cycle Program was refined and updated during FY 2006.
During FY 2006, $7 million in reimbursements were distributed to local governments and it is anticipated that $56 million will be distributed in FY 2007.
Work is proceeding on a broad range of arterial street projects over the next five years.
![Page 18: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/18.jpg)
Arterial Streets Program
Total estimated future regional reimbursements for projects in the Arterial Street Life Cycle Program are in balance with projected revenues.
- Future Revenues: $1,730 million- Future Disbursements: $1,630 million
![Page 19: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/19.jpg)
Arterial Streets Program
Given increasing construction costs, concerns are being raised regarding the ability of jurisdictions to provide full funding for all projects in the program.
The mandatory Federal approval process may pose schedule risks for projects receiving Federal funds.
![Page 20: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/20.jpg)
Transit ProgramBRT/Express
![Page 21: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/21.jpg)
Transit ProgramSuper Grid Bus
![Page 22: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/22.jpg)
Transit ProgramLight Rail Transit
![Page 23: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/23.jpg)
Transit Program
During FY 2006, funding began for 14 existing Express and 4 existing RAPID bus routes, ADA paratransit service, and customer service and marketing programs. Also, 62 new coaches and 20 used coaches were purchased.
Approximately $66 million was expended on the Transit Life Cycle Program, during FY 2006.
![Page 24: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/24.jpg)
Transit Program FY 06 Project Expenditures
$9.2 $11.4
$33.7
$11.5
$65.8
$0.0
$10.0
$20.0
$30.0
$40.0
$50.0
$60.0
$70.0
Millions
Bus Ops. Bus Fac. Bus Flt. LRT Sup. Total
![Page 25: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/25.jpg)
Transit Program
A broad range of bus planning studies were started to define service concepts in detail and provide improved future cost estimates.
During the next five fiscal years, 11 new BRT/Express routes and seven new Super Grid routes will be initiated. In July 2006, service began on the first regionally funded Super Grid route route on Scottsdale/Rural Road. Service is also now being provided on rural connector routes.
![Page 26: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/26.jpg)
Transit Program
Construction is continuing on the LRT Minimum Operating Segment (MOS) and service is scheduled to begin in December 2008.
Studies necessary to implement the 37.7 miles of LRT extensions have been initiated.
![Page 27: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/27.jpg)
Transit Program
Estimated future costs for the full Transit Life Cycle Program are in balance with projected revenues.
- Future Revenues: $5,940 million- Future Costs: $5,940 million
![Page 28: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/28.jpg)
Transit Program
Recent trends of escalating wages and fuel prices will increase the pressure on balancing bus service operations costs with available revenues. Similarly, recent increases for right-of-way and construction materials are likely to drive up costs for transit capital facilities.
![Page 29: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/29.jpg)
Key Summary Points
Regional Transportation PlanThe modal Life Cycle Programs were added to the Regional Transportation Plan.
Revenues Forecasts of future available regional revenues are largely unchanged from the 2005 Annual Report.
![Page 30: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/30.jpg)
Key Summary Points
Freeway/Highway Life Cycle ProgramDuring the coming fiscal year, significant additional project cost increases may be encountered in the Freeway/Highway Life Cycle Program, as detailed engineering studies are completed.
![Page 31: 2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.](https://reader036.fdocuments.net/reader036/viewer/2022062518/56649e915503460f94b97083/html5/thumbnails/31.jpg)
Key Summary Points
Arterial Street Life Cycle ProgramGiven increasing construction costs, concerns are being raised regarding the ability of jurisdictions to provide full funding for all projects in the program.
Transit Life Cycle Program As in the other modes, recent trends in of escalating wages, fuel prices, and construction costs will increase the pressure on balancing both service and capital costs with available revenues.