2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of...

80
Page 1 of I - ENGINEERING DATA TRANSMITTAL l.EDT 6243 11 3. From: (Originating Organization) CVDF Sub Project W441 2. To: (Receiving Organization) SNF CVDF Sub Project W441 4. Related EDT No.: N/A 5. Proj./Prog./Dept./Div.: DATA TRANSMITTED (F) (G) (H) Approval Reason Oriqi- nator rnittal sition (AI IC) NO. NO. NO. Item (8) DocumentIDrawinq No. Sheet 2 : ; . (E) Transmitted DeSCTiption Of miq- T:aOn:- ::;:- 1 HNF-2576 0 Cold Vacuum Drying N/A Facility: Phase I W-441 8. Originator Remarks: Release of FMECA (1) Receiv- Dizio- sition FMEA/FMECA Session Report 6. Design Authority/ Design 7. Purchase Order No.: Agent/Cog. Carol C Pitkoff Engr. : 9. Equip./Component No.: 10. System/Bldg./Facility: I CVDF 11. Receiver Remarks: 11A. Design Baseline Document? [I Yes [XI No 112. Major AsSm. DWg. NO.: 1. Approval 4. Review 2. Release 5. Post-Review 3. Information 6. Dist. (Receipt Acknow. Required) E, s, a, D or NIA (see hnc-CM-3-5, SBC.12.1) 13. Permit/Permit Application No.: 1. Approved 4. Reviewed no/coment 2. &proved wlco-nt 3. Disapproved wlcoment 5. Reviewed Wlcoment 6. Reoeipt acknowledged I 14. Required Response Date: 80-7400-172-1

Transcript of 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of...

Page 1: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

Page 1 of I - ENGINEERING DATA TRANSMITTAL

l.EDT 6243 1 1

3. From: (Originating Organization) CVDF Sub Project W441

2. To: (Receiving Organization) SNF CVDF Sub Project W441

4. Related EDT No.:

N/A

5. Proj./Prog./Dept./Div.:

DATA TRANSMITTED (F) ( G ) (H) Approval Reason Oriqi-

nator rnittal s i t i o n

(AI IC)

NO. NO. NO. Item ( 8 ) DocumentIDrawinq No. Sheet 2:;. (E) Transmitted DeSCTiption Of m i q - T:aOn:- ::;:- 1 HNF-2576 0 Cold Vacuum Drying N/A

Facility: Phase I

W-441

8. Originator Remarks: Release of FMECA

( 1 ) Receiv-

Dizio- s i t i o n

FMEA/FMECA Session Report

6. Design Authority/ Design 7. Purchase Order No.: Agent/Cog.

Carol C Pitkoff Engr. :

9. Equip./Component No.:

10. System/Bldg./Facility:

I

CVDF 11. Receiver Remarks: 11A. Design Baseline Document? [ I Yes [XI No 112. Major AsSm. DWg. NO.:

1. Approval 4 . Review 2. Release 5 . Post-Review 3. Information 6 . D i s t . (Receipt Acknow. Required)

E, s, a, D or NIA (see hnc-CM-3-5, SBC.12.1)

13. Permit/Permit Application No.:

1 . Approved 4 . Reviewed no/coment 2 . &proved wlco-nt 3. Disapproved wlcoment

5 . Reviewed Wlcoment 6 . Reoeipt acknowledged

I 14. Required Response Date:

80-7400-172-1

Page 2: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

0 HNF-2576, Rev. 0

Cold Vacuum Drying Phase I ENEA/FMECA

F a c i l i t y : Session Report

Carol P i t k o f f DELS Hanford, Inc., Richland, WA 99352 U.S. Department of Energy Contract DE-AC06-96RL13200

EDT/ECN: 6a43// uc: 7 2 1 Org Code: 2T360 Charge Code: LH302 B&R Code: Total Pages: 3 Key Words: Cold Vacuum Drying, FMECA, FMEA

Abstract: Report of the Failure Modes, Effect, and Criticality Analysis performed for the Cold Vacuum Drying process equipment and facility. designs, dresign requirments doument , and other baseline documentation.

The report summerized potential problems with the

TRADEMARK DISCLAIMER. Reference hereln to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise, does not necessarlly constitute or Imply its endorsement, recommendatlon, or favoring by the United States Government or any agency thereof or Its contractors or subcontractors.

Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O. Box 950, Mallstop H6- 08, Richland WA 99352, Phone (509) 372-2420; Fax (509) 376-4989.

&A/ Date Release Stamp

Approved for Public Release A-6400-073 (01/97) GEF321

Page 3: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

HNF-2576, Rev. 0

THIS PAGE INTENTIONALLY LEFT BLANK

2

Page 4: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

SPENT NUCLEAR FUEL COLD VACUUM DRYING FACILITY:

PHASE I FMEALFMECA SESSION

AUGUST 1997

Provided for: Carol C. F'itkoff DE&S Hanford Inc. Richland, Washington

Facilitated By: Richard A. Harrington, CVS Lockheed Martin Hanford Richland, Washington

Geoffrey E. Parker, CVS ARES Corporation Richland, Washington

Page 5: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

COLD VACUUM DRYING FACILITY: PHASE I FMEMMECA SESSION REPORT

TABLE OF CONTENTS

Sectionl-ExecutiveSu mmary ................................................... 1

Section 2 - Project Background and Introduction .................................... . 3

Section 3 - Conduct of Session .................................................. . 4

Appendices

A. Scope Statement Sheet

B.

C.

D. Session Flipcharts

Subsystem Final Pass, Actions, Potential Requirement and Design Changes

Failure Modes, Effects and Criticality Analysis, Phase I Matrices

i 4 ~ ~ 4 a 576 i FLUOR DANIEL HANFORD

Page 6: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

COLD VACUUM DRYING FACILITY: PHASE I FMEARMECA SESSION REPORT

SECTION 1

EXECUTIVE SUMMARY

The mission of the Spent Nuclear Fuel (SNF) Project is to remove the fuel currently located in the K-Basins 100 Area to provide safe handling and interim storage of the fuel. The spent nuclear fuel will be repackaged in multi-canister overpacks, partially dried in the Cold Vacuum Drying Facility (CVDF), and then transported to the Canister Storage Building (CSB) for further processing and interim storage.

The CVDF, a subproject to the SNF Project, will be constructed in the lOOK area. The CVDF will remove free water and vacuum dry the spent nuclear fuel , making it safer to transport and store at the CSB. At present, the CVDF is approximately 90% complete with definitive design.

Part of the design process is to conduct Failure Modes, Effects, and Criticality Analysis (FMECA). A four-day FMECA session was conducted August 18 through 21, 1997. The purpose of the session was to analyze 16 subsystems and operating modes to determine consequences of normal, upset, emergency, and faulted conditions with respect to production and worker safety. During this process, acceptable and unacceptable risks, needed design or requirement changes, action items, issues/concems, and enabling assumptions were identified and recorded. Additionally, a path forward consisting of recommended actions would be developed to resolve any unacceptable risks. The team consisted of project management, engineering, design authority, design agent, safety, operations, and startup personnel from DE&S Hanford Inc. (DESH), Numatec (NHC), Fluor Daniel Northwest (FDNW), Jason and Associates Co. (JAC), and Merrick Engineering. Technical facilitation was provided by Richard Harrington, CVS, Lockheed Martin Hanford Co. (LMHC), and Jeff Parker, CVS, ARES Corporation. The session successfully met the purpose as stated above.

Session Results

The session resulted in a Phase I FMECA Matrix, 37 Action Items, nine potential Design Requirement Document changes, and eight potential Design Changes. The most significant issues addressed, within the action items and potential design changes, were identified on the Heating Ventilation and Air Conditioning (HVAC), Process Water Conditioning (PWC), and the Helium (He) subsystems, as follows:

A. HVAC current design and controls for each bay could result in an upset condition that pressurizes the bays. Two action items and one potential design requirement change were identified to resolve this issue.

\.sur=- 357b FLUOR DANIEL HANFORD 1

P

Page 7: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

COLD VACUUM DRYING FACILITY: PHASE I FMEA/FMECA SESSION REPORT

B. The PWC system requires a significant redesign due to a factor of 1000 increase in the source term. This redesign, addressed in four action items, will mitigate the increase of potential operator exposure.

C. The He system requires a backup system for uninterrupted supply and in-field verification of He purity and miscellaneous gas constituents in the remaining 5%. Two action items and one potential design requirement change were identified to resolve this issue.

The process that developed the aforementioned results was an evaluation of 16 subsystems using a Phase I FMECA Matrix. In brief, the matrix was used to identify the likely failure modes (subsystem level), effects of those failures on production and worker safety, and actions required to minimize the likelihood of failure or effects of failures. The key to the worth of the matrix and the success of the session was the objective data known by the team members, or brought to light during the session, and the experience of the team members as they applied the matrix to each subsystem. After the Phase I FMECA Matrix was finished, it was reviewed and analyzed by subsystems to determine if a more detailed Phase II FMECA was needed by component and/or operating mode. As a result, it was recommended that five out of the sixteen subsystems should be subjected to a component level Phase 11 FMECA at a later date.

The five subsystems requiring a Phase 11 FMECA were: Vacuum & Purging System (VPS), PWC, HVAC-B, C, and D. While the entire PWC system was recommended for Phase II, only three operating modes on the VPS and one mode on the three HVAC systems were identified for component level analysis.

The balance of the action items, potential DRDs, and design changes, ranged from upgrading drawings to determining the need for additional instruments and/or components. Recommended design changes resulting from resolution of the action items, potential DRDs, and design changes, will need further evaluation to identify the impacts on capital, operations, and maintenance costs. Once cost is determined, the relative benefit to cost can be determined and a final decision made to make the change or not. That determination will be the subject of separate correspondence.

Due to time constraints the completion dates for actions, potential DRDs, and design changes, will be determined in subsequent meetings and tracked until closure in the on-going project status meetings.

2 FLUOR DANIEL HAWORD

Page 8: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

COLD VACUUM DRYING FACILITY: PHASE I FMEAlFMECA SESSION REPORT

SECTION 2

PROJECT BACKGROUND and INTRODUCTION

The mission of the Spent Nuclear Fuel (SNF) Project is to remove the fuel currently located in the K-Basins 100 Area to provide safe handling and interim storage of the fuel. The spent nuclear fuel will be repackaged in multi-canister overpacks, partially dried in the Cold Vacuum Drying Facility (CVDF), and then transported to the Canister Storage Building (CSB) for further processing and interim storage. '

The CVDF, a subproject to the SNF Project, will be constructed in the lOOK area. Once constructed and turned over to operations, the CVDF will remove free water and vacuum dry the spent nuclear fuel, making it safe to transport and store at the CSB. At present, the CVDF is approximately 90% complete with definitive design.

Part of the design process is to conduct Failure Modes, Effects, and Criticality Analysis (FMECA). The purpose of a FMECA is to evaluate the system design at the component level to determine possible failure modes and their effects on production and worker safety. Mike Wiemers, Project Manager for the CVDF Project, determined that a facilitated team session would be a good approach for completing a phased approach. This session was limited to a Phase I FMECA on subsystems and some component levels. In addition, the team in this phase would recommend any subsystems and operating modes that would require a Phase II approach, at the component level.

Prior to the session, a blank matrix was developed by the facilitators and several team members for use as a tool prompt and to record information during the session. In addition, 16 subsystems were identified as safety significant and within scope for this Phase I session.

Page 9: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

COLD VACUUM DRYING FACILITY: PHASE I FMEA/FMECA SESSION REPORT

SECTION 3

CONDUCT OF SESSION

Appendix A contains the Scope Statement Sheet and Agenda developed prior to and followed throughout the four day session. The scope statement sheet identifies the team members, and the session scope, objectives, and deliverables. The session began on Monday morning, August 18, 1997, with a review of the agenda, scope statement sheet, process guidelines and expectations, and opening remarks from the project and deputy project managers. During opening remarks both Mike Wiemers and Carol Pitkoff stressed the importance of building a system that works through the entire life cycle. Specifically, the team was encouraged to remember the system must produce the product needed, at an acceptable rate, and minimizing downtime and any upset conditions. In addition, process emphasis was placed on “recovery thinking” &e., what must be done to recover from something that breaks or fails). Following opening remarks the team overviewed the system process and operation.

The Phase I FMECA began with the team reviewing the blank matrix and developing common definitions for each section of the matrix. Following definitions, the team reviewed the list of 16 subsystems and analyzed each subsystem based on failure modes within the subsystem. In some subsystems component failure was considered, but most subsystems were kept at the subsystem level. Typically, the failures were that the system stopped supplying something, supplied too much of something, over pressurized or under pressurized. Once the failure modes were identified they were analyzed using the matrix contained in Appendix C. During this process any action items, potential Design Requirement Document (DRD) changes, design changes, enabling assumptions, and issueskoncerns identified were recorded on corresponding flipcharts. Many of the action items identified will result in DRD or design changes. During this process the team was not certain whether an action was a potential DRD change, design change, or both. In the interest of time it was identified as an action item with impact to be determined later. Thus, a total of 37 actions were recorded. Potential impacts to capital, operation, andlor maintenance costs will be determined as actions are completed.

Once all 16 subsystems were analyzed with the FFiMCA matrix, the team reviewed each subsystem matrix for consistency in approach relative to severity class (taking mitigation into account) and to determine if a Phase II FEMCA would be required. Minor corrections were identified and recorded to ensure that the team’s analysis of severity class was consistent. In addition, any identified actions, DRDs, design changes, assumptions, and memory items were recorded. It was noted that a cost trade-off evaluation would be required at a later date based on the subsystem’s failure rate, severity class and benefit of a change. Appendix B contains the typed copy of the Subsystem Final PassReview, Action Items, Potential DRDs, and Potential Design Changes.

#NF a57G 4 FLUOR DANIEL HANFORD ..--

Page 10: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

COLD VACUUM DRYING FACILITY: PHASE I FMEAlFMECA SESSION REPORT

Finally, a path forward was developed by reviewing and validating the recorded assumptions, issuekoncerns, memories, potential DRD changes, potential design changes, and actions. Appendix D contains copies of the reduced Session Flipcharts developed during session and are backup reference to Appendix B and C..

The session ended with a round robin of each team member answering the questions of last minute items and meeting utility.

5 FLUOR DANIEL HANFORD c

f-

Page 11: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

COLD VACUUM DRYING FACILITY: PHASE I FMEA/FMECA SESSION REPORT

APPENDICES

A. Scope Statement Sheet And Agenda

B. Subsystem Final Passheview, Actions Items, Potential Design Requirements And Design Changes

C. Phase I FMECA Matrix

D. Session Flipcharts

WdF--a57b b o 6 FLUOR DANIEL miworn

in

Page 12: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

APPENDIX A

SCOPE STATEMENT SHEET AND AGENDA

Page 13: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

PROJECT SCOPE STATEMENT SHEET

Project Title: Cold Vacuum Drying Facilitv: Phase I FMEMMECA Session No. 001 Location of Session: Team Briefing Meeting: N/A Date: N/A

345 Hills Street, Conference Room 124 Dates:~ 08/18-21/97

NAME

J.J. (John) Irwin (TL) C.C. (Carol) Pitkoff R.I. (Dick) Whitehurst W.C. (Walt) Alaconis R.A. (Ray) Larson D.A. (Dan) Reny C. (Carole) Pili-Vincens K.J. (Kurt) McCracken J. (Jim) Robinson D. (David) Munger

TEAM MEMBERS

PHONE MSIN DISCIPLINE

376-1639 376-5655 376-4663 376-9390 373-1698 373-7518 373-1513 373-6653 783-7404 (505) 662-0606

R3-86 R3-86 R3-86 R3-85 R3-85 R3-15 R3-86 SO-04 _ _ _ _ _ _ _ _____--

Team Leader (TL)

FLOATERS

M.J. (Mike) Wiemers C.A. (Chris) Thompson G.P. (Gilles) Chewier C.R. (Curtis) Miska

NAME

R.A. (Richard) Harrington G.E. (Jeff) Parker

CVD Design Authority Project Management I&C Engineering Operations/Start-up Operations/Start-up Safety Engineering Safety Engineering HVAC Engineering Design Agent Design Agent

376-9516 R3-85 Project Manager 372-0598 R3-85 Operations/Start-Up 373-3609 R3-86 Project Management 376-7103 R3-86 HCS Design Authority

FACILITATORS

PHONE MSIN DISCIPLINE

376-2331 H8-71 Value Engineering 946-3300 _ _ _ _ _ _ _ _ Value Engineering

co. NHC DESH DESH DESH DESH JAC NHC FDNW Merrick Merrick

DESH DESH NHC NHC

co. LMHC ARES

Page 14: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

SCOPE

Cold Vacuum Drying (CVD) Process and Facility Systems: Phase I FMEAlFMECA

- Focus of Phase I is on sub-systems (i.e., CVDF Systems List) and some specific components, as required

Starting from the point a Multi-Canister Overpack is received with fuel, water, and sludge, and ending, after CVD processing, with the same MCO containing fuel and some water.

-

OBJECTIVES

Overview normal operating process and facility systems sequence

- Describe and list subsystems and/or operating modes to be analyzed.

0 Analyze subsystems andlor operating modes to determine consequences of normal, upset, emergency, and faulted conditions with respect to production and worker safety

- -

Identify acceptable and unacceptable risks, and their basis List needed design changes, spare parts, recovery procedures, and estimated recovery time.

0 Develop the path forward recommendations and actions to resolve unacceptable risks

DELIVERABLES

0 Draft Phase I FMECA Matrix

0 Listings of needed design changes, spare parts, recovery procedures and estimated recovery times.

0 Path Forward Recommendations and Actions

Page 15: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

Davl

7 ~ 3 0 -

8:OO -

9:30 - 9:40 - 11:30 - 12:30 - 2:30 - 2~40 - 4:OO -

7:30 - 8:OO - 9:30 - 9:40 - 11:30 - 1230 - 2 3 0 - 2:40 -

CVDF Phase I FMEAlFMECA Session

August 18 - 21,1997

AGENDA

Welcome/IntroductionslReview Agenda Guidelines and Expectations Review Scope Statement Sheet (Session Scope, Objectives, and Deliverables) Opening Remarks

Begin overview and sequencing of normal operating system

BREAK

Identifybist subsystems and/or modes on process and facility systems to be analyzed Utilize “parking-lot” sheets as required for running information

Conduct Phase I FMECA and matrix on C M A and HE sub-systems

LUNCH

Conduct Phase I FMECA.and matrix on FW, and DI sub-systems

BREAK

Continue FMECA on CHW and VPSCHW sub-systems

Finish Day 1 with review of status and Day 2 agenda

Review agenda and scope statement sheet

Continue FMECA on UPS and CraneJHoist sub-systems

BREAK

Continue FMECA on HVACD sub-system

LUNCH

Continue FMECA on HVACC sub-system

BREAK

Continue FMECA on HVACB sub-system

4:OO - Finish Day 2 with review of status and Day 3 agenda

Page 16: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

CVDF Phase I FMEUMECA Session August 18 - 21,1997

AGENDA

Dav3 7:30 - 8:OO -

Review agenda and scope statement sheet

Continue FMECA on DCS sub-system

9:30 - BREAK

9:40 - Continue FMECA on PWC sub-system

11~30- LUNCH

12:30 - Continue FMECA on TWC sub-system

2 3 0 - BREAK

240 - 4:OO -

Continue FMECA on TW sub-system

Finish Day 3 with review of status and Day 4 agenda

, 7:30 - Review agenda and scope statement sheet

8:OO - Continue FMECA on VPS sub-system

4 9:30 - BREAK

9:40 - Continue FMECA on EPD sub-system

- 11~30- LUNCH

12:30 - Conduct Subsystem Final Passmeview

i I I

Identify Phase I1 Component FMECA Areas

2 3 0 - BREAK

240 - Develop path forward

Finish session with a Round Robin Close-out

Last minute items

Meeting utility

Reviewmalidate running information on parking lot sheets

Identify actions needed resolve unacceptable risks and proceed forward

4:OO - I I

Page 17: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

APPENDIX B

Subsystem Final Passtreview

Action Items

Potential Design Changes

Potential Design Requirement Document Changes

Page 18: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

Sub-system Actions, DRDs, D.C.s, etc.

Purpose of Phase 1: Screen systems and subsystems to determine which will be significant contributors to plant down time.

Component FMECA Required?

Voting for Phase 2 FMECA:

1. Is system a significant contributor to plant downtime 0 0

Failure rate - frequency of occurrences Restoration rate - mean time to restore

2. The "yes" designation indicates that the follow-on reviewers will use the tabulated information to more precisely select the components to do a detailed FMECA.

Page 19: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

ACTION ITEMS

li WHAT

1. Determine what the 25 psig service supplies (instrument air to HVAC). See Note #1

Finish thermo analysis to verify that shutdown system results in a safe plant condition and low corrosion environment (does design reflect results)

Determine system failure compressor PM rate vs. demand and plant outage schedule (can facility last that long [partime] during compressor maintenance). See Note #1

Develop an operator response to evacuate the bay on loss of HVAC (TSR consideration)

Verify the type of filters in compressed air dryer. See Note #1

Verify sight glasses exist for determination of liquid in the air lines (determine what is in dryer to help determine bad air). See Note #1

Review potential impact of bad air on safety class valve operators; review to determine if an LCO is required (reevaluate severity class if LCO required)

Determine minimum He purity requirement (Combine actions 8 and 9).

Develop method to verify & purity at site receipt and/or MCO

10. Switch to service water to supply DI water (design change)

1 1. Determine impact of glycol on MCO and develop recovery plan, if required; and failure detection method, if required

12. Develop recovery procedure(s) to

2.

3.

4.

5.

6.

7.

8.

9.

accommodate delays that violate technical specifications

13. Verify function and need for Damper DMP- 8060. See Note #1

WHOWHEN ~~ ~

WHO: Merrick - Dave Munger WHEN:

WHO: Project Team WHEN: Ongoing

WHO: Merrick - Dave Munger WHEN:

WHO: Operations -Walt Alaconis WHEN:

WHO: Merrick - Jim Robinson WHEN:

WHO: Merrick - Dave Munger WHEN:

WHO: Merrick on review; Dan RenyKarol Pili-Vincens on LCO

WHEN:

WHO: Johnirwin WHEN:

WHO: John Irwin WHEN:

WHO: J o h n h i n WHEN:

WHO: John InvinlLouie Goldman WHEN:

WHO: Walt Alaconis/George V. WHEN:

WHO: Jim RobinsodKurt

WHEN: McCracken

Page 20: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

ACTION ITEMS

WHAT

14. Reevaluate the approach to HVAC-D zone control (HVAC - all, not just D). See Note #1

15. Upgrade HVAC drawings to show condensate drain lines and seal pots

16. Upgrade HVAC P&Ds to show: 1. correct connection of Tank 4001 to

local exhaust system 2. correct connection of process skid

vent to local exhaust system 3. Show the isolation damper in the

process vent system at the bay walls

17. HVAC-D: 'delete fume hood callouts

18. Verify outside air damper interlock with general exhaust air flow. See Note #1

19. Evaluate the need to provide a "vacuum" break in the event of loss of air to HVAC-B (design a change, if required) [safe exit through door]. See Note #1

20. Evaluate need for local bay repeater a l m s (from problems in other bays). See Note #1

21. Determine needs of programming for MCS

22. Conduct a Design Review on programs/reprogramming

23. Do a dose study on the PWC; determine if design requires change; generate DRD or design change as required

24. Develop procedures to use installed backup pumps to recover from PWC loss of pumping flow (or use pressure control); requires a DRD change for recognition of requirement. See Notes 1 & 2.

WHOMHEN

WHO: Jim RobinsodKurt

WHEN:

WHO: Jim RobinsodKurt

WHEN:

WHO: Jim RobinsodKurt McCracken

WHEN:

McCracken

McCracken.

WHO: Merrick - Jim Robinson WHEN

WHO: Dave Munger/Kurt McCracken

WHEN:

WHO: Jim RobinsodKurt McCracken

WHEN:

WHO: Operations - Walt Alaconis WHEN:

WHO: Dick Whitehurst WHEN:

WHO: Dick Whitehurst WHEN:

WHO: Carol Pitkoff WHEN:

~ ~

WHO: Walt Alaconis/John Irwin WHEN:

Page 21: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

ACTION ITEMS

I WHAT

25. Reevaluatesource term for PWC and determine if DRD changes are required. (DRD to state different source term for design develop a criteria that results in a design that provides an operable PWC AT ALL TIMES) (Include worker safety and ALARA) (Include sampling needs also) (Include E M replacement). See Note #1

26. Establish design requirements to mitigate leaks on the PWC system. See Note #I

27. Develop a procedure for checking the inner seal of the MCO/cask annulus seal

28. Determine severity class to the "cask low water level" for TW. See Note #1

29. Ensure failure to drain recovery (unplugging) sequence is added to normal operations procedure In addition, add low level alarms on water and low level detectiodcorrection methods

30. Evaluate need for RGA. See Note #1

31. Review EPD for failure mode recovery procedures. See Note #I

32. Status and complete DRD changes (eight total), & any others resulting from actions and design changes.

33. Status and complete design changes 1-8, and any others resulting from actions and DRD changes.

34. Develop method to keep M M from going TRU. See Note #I

35. Identify new strategy for combined HVAC design, procurement, and installation for single oversight. See DRD #8 and Note #l.

WHOlWHEN

WHO: JohnIrwin WHEN:

WHO: John Irwin WHEN:

WHO: JohnIrwin WHEN:

WHO: John Irwin WHEN:

WHO: Merrick WHEN:

WHO: Dick Whitehurst WHEN:

WHO: JohnIrwin WHEN:

WHO: JohnIrwin WHEN:

WHO: JohnIrwin WHEN:

WHO: Carol Pitkoff WHEN:

WHO: JohnIrwin WHEN:

WHO: Carol Pitkoff WHEN:

Page 22: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

WHAT

36. Incorporate "plugging of flow meter" in PWC design. See Note #1

37. Define normal operating modes for the VPS in the re-cycle mode, and include in DRD. 'See Note #1

1. Using the resulting information, identify any design changes that would minimize the likelihood of failure and/or the effects of the failure. Identify the cost impact and benefit of any recommended design changes. Finally, recommend that change or no change be made. In either case, identify the resulting risk that management is accepting.

WHO/WHEN

WHO: John Irwin/Dave Munger WHEN:

WHO: John Irwin WHEN:

2. Consider remote replacement for PWC replacement pump.

Page 23: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

POTENTIAL DRD CHI

WHAT

1. Project philosophy on spare parts.

2. This item was deleted

3. Include capability to put the MCO in a cold shutdown condition (production consideration--not safety consideration).

Investigate the dryness criteria on

for the cask annulus area. Based on investigation develop requirement statement and revise DRD.

Add: “continuous supply of He” requirement. -

4. . instrument to determine required dew point

5. Ensure overpressure or loss of He does not effect redundant supply trailer.

Add: Requirements for crane & rigging (detect imbalance).

Establish and add minimum DP requirements for zone control and alarm in HVAC systems.

Potential change - Require a stand alone HVAC control system with interfaces to MCS (HVAC- B). See Action Item #35.

Identify requirement for MCO block values with respect to particulates in water streams

6.

7.

8.

9.

(GES

WHONHEN

WHO: Walt Alaconis WHEN

NIA

WHO: JohnIrwin WHEN:

WHO: Kurt McCracken WHEN:

WHO: John Irwin WHEN:

WHO: JohnIrwin WHEN:

WHO: Kurt McCracken WHEN:

WHO: Kurt McCracked

WHEN:

WHO: JohnIrwin WHEN:

Dick Whitehurst

Page 24: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

(I POTENTIAL DE:

II WHAT

1. Investigate maximum allowable connection pressure in cask (quick disconnects attached to cask). See Note #1

2. Ouerating secpence: close MCO block valve - when?? (identify

Potential Design Change - Install check valve in air line to seal ring

On Drawing H-1-82222, add 100 psig service to rm 132; check if 25 psig service is needed

timing)

3.

4.

Verify alarm type (PAL 5008) change as required (need high &

5. Potential Design Change - Allow the use of IA for formal purge of cask annulus. See Note #1

Add PT or switch upstream of He pressure regulator to detect He supply pressure

Global Change - Review all P&Ds for change from PAL to PI

6.

7.

8. 82164 - Change EJR to EDR

Notes:

GN CHANGES

WHONHEN

WHO: Andy Kee/John Irwin WHEN:

WHO: Dick Whitehursman Reny WHEN:

WHO: MerricWJohn Irwin WHEN:

WHO: MerricWJohn Irwin WHEN:

WHO: Dick Whitehurst WHEN:

WHO: JohnIrwin WHEN:

WHO: MerrickDick Whitehurst WHEN:

WHO: MerrickDick Whitehurst WHEN:

WHO: MerrickDick Whitehurst WHEN:

1. Using the resulting information, identify any design changes that would minimize the likelihood of failure andor the effects of the failure. Identify the cost impact and benefit of any recommended design changes. Finally, recommend that change or no change be made. In either case, identify the resulting risk that management is accepting.

Page 25: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

APPENDIX C

COLD VACUUM DRYING: FAILURE MODES, EFFECTS AND CRITICALITY PHASE I

MATRICES

Page 26: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

I I

SNF - Cold Vacuum Drying Project Failure Modes, Effects and Criticality Analysis, Phase I

Subcomponent/ Sub. Sys.. Sub. sys..l Failure Alpha Subsystem No./ Compl Mode Rank

Failur

Local Effects

Uncontrolled H.P. air, noise, & flying debris

H.P air & noise

Inaccurate I & C & unreliable valves

Effects

End Effects

@ 80 PSIG dampers close (supply & exhaust is isolated, recurc. still operable)

*@ 50 PSIG all GOVs go to fail position

@ 45 PSIG lose seal ring pressure

Below 15 PSIG begin to lose HVAC cooling control - Loss of air balance - Loss of fresh air to bays

* Process shutdown to safe conditions

None

Same as local effect

I I I I Failure

Method Detection of Cause Class Action(s) Required?

Production Worker

alarm B No No

Manual

Date: 848-21/97

Sheet No: 1

Remarks

Acceptable risk

I - I

Page 27: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

I SNF - Cold Vacuum Drying Project Date: 8/18-21/97

1 Failure Modes, Effects and Criticality Analysis, Phase I Sheet No: 2

I I I I I I I I I I Acceptable risk I Overflowtodrain I None I PI-7031 & I SRV-7050 I H I A I None None I I I

I II

701 1

EL Water leaks Overflow to drain Overflow rank LT-9035 Manual isolation M A None None Acceptable risk a W A C (contaminated water tank)

I I None Water leaks I E L I b. Process I None I None I None II I NIA I NIA I None I None I Acceptablerisk

I I I I- I

Page 28: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

SNF - Cold Vacuum Drying Project Failure Modes, Effects and Criticality Analysis, Phase I

Date: 8/18-21/97

Sheet No: 3

I I

I (1 mic restraints

7076 I EL Leaks Overflow to floor drain Loss of cooling Fl-7078 None N/A B None None Acceptable risk

- External TT-7077

maintenance

EL Drop load - Equipment damage Delay in process Visual audio Procedures (O&M) H C See DRD #6 No additional Acceptable risk - Personnel injury

I None

L

Effluent to VPS & Potentially None potential contamination of I RGA MCO fuel I

Seismic #1 failed to None Delay in process Visual None NIA B SeeAI#12 None Acceptable risk engage/disengage

SeeAI#11

93-3 EL Loss ofpower with None Total loss (MCS (process Plant goes dead Periodic lesting of H B None None Acceptable risk 480V AC unavailable stops) battery (fallure of baneries)

1 11 Craneshoistslseis I 14 I L I Fail to operate I I none I Delay in process I stops I periodic I H I B I SeeA#12 I None I Acceptable risk II

r n

Page 29: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

SNF - Cold Vacuum Drying Project Failure Modes, Effects and Criticality Analysis, Phase I

Date: W18-2 1/97

Sheet No: 4

I I

Page 30: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

SNF - Cold Vacuum Drying Project Failure Modes, Effects and Criticality Analysis, Phase I

Date: 8118-21197

Sheet No: 5

I I

Alpha 1 Rank ( T W

I R I I I I I I I I I I I I I Failure Effects Failure Mitigation Reliability Severity . Action(s) Required? Remarks

Detection I ofcause I of 1 Class Method Mitigation

Local Effects End Effects Production Worker

Subcomponent/ Sub. sys.. I Subsystem I iV; I s"y"sp:/ I Component Comp.

Failure

MCS

Failure Mode

Rate Safety

93 -2 M Panial loss of control at YO None Componentlsubsystem shut PLC has self- None NIA B None None Acceptable risk down, possible process diagnosncs (assumphons 4 and 5) shutdown

Componentlsubsystem position continuing, possible process detcchon shutdown

Component

System parameter detection

VO self- diagnoshcs

L Panel fails None Process shutdown in bay or Same as above None NIA B None PWC or mech roam

None Acceptable risk

II I L I YO card fails I I None I Same as above I Same as above I None I NIA I B I None I None I Acceptable risk I s'l I

Communications errors

Program to go to safe Computer Redundant H condition of process after 60 generated alarm computers and second time out I I cables I

PLC generated

Loss of communications between the PLC and computers I E L I

EL

alarm

Total loss of MCS System goes down every- All processes are stopped in Visual and UPS and redundant H B None None Acceptdble risk thing black safe (failed) condition audible (quiet) systems NOTE thls is an

adminlstrative nightmare

I B M I

I SeeAI#21 I None

Bad programming False indication(s) or Process upsetkhutdown Direct and/or Independent safety H B Yes, see AI #'s TBD; see Al control indirect alarms controls ; multiple H 22 and 21 #22

alarms,; and a QA M software program

Acceptable risk

Page 31: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

SNF - Cold Vacuum Drying Project Failure Modes, Effects and Criticality Analysis, Phase I

Date: 8/18-21/97

Sheet No: 6

I I

Failure Mitigation Reliability Severity Action@) Required? Remarks * Detection of Cause of Class - Subcomponent/ Sub. sys.. Sub. sys..l Failure Alpha Failure Effects

Subsystem No./ Comp. Mode Rank Production Worker Method Mitigation (TED) Local Effects End Effects Component Failure

ID Rate .S*fetV t I-.-.

46-1 L Loss of pumping flow Increased radiation MCO process delay, Pump status None NIA B Yes YeS increased radrahon & indication See AI tf23 & See AI#23 potential exposure FT-4050 24, and

memories # 8 FT-4038 FT-4039 & $9 FT-4037 PT-4031

-1 , ----I

l H Loss of IXM capability Increased radiation MCO process delay, PDISH-4044 Sampling increased radiation & I or4041 I potential exposure Sampler results

1 EL I B 1 Yes 1 Yes I Assumption#6 See AI #25 See AI #25

FT-4039

M LXMS GO TRU None Delay process Sampling Sampling & EL B Yes Yes Assumption #6 analysis kequency S e e d #25 See A l # 2 5

Page 32: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

SNF - Cold Vacuum Drying Project Failure Modes, Effects and Criticality Analysis, Phase I

Date: 8/18-21/97

Sheet No: 7

I

L 5 Badwater Potential radiation None None None NIA A None None Acceptable risk

I 6. Loss of temperature None I I I I E L I control (highhow)

S.C. prevention and H B I None I None I Acceptablerisk I I TT-3 * 05 I Process delays I S.C.TSH I normal prevention

07 Valves I Loss of water drain path Increased radiation Fuel conosion FI-4050, Valves-nonc NIA B Yes None L (valve llneup or plugging) Production delay LI-4033, etc Plugging-conecr H See AI #29

H hydrogen) Plugging (strainer screen) (More sludge & more loading I vps

I I None I Process delay (long, long See AI #29 Fully plugged-none Yes; see drying time) I slow drain-multiple I :p I A I AI#29 1 I None I M I lailxcessiverehlmed

drain cycles

EL 2 Loss o f purge path None Hydrogen buildup PDT-1 * 13 Nonc NIA B See remarks See remarks On-going effort to detetmint filter plugging likelihood (HEPA plug sub sys or Process delay PDT-I * 34 and my actions

MCO) Potential S C shutdown PT-l * 08 FE-I 19 PE-2 * 12 sc flow switches

B I Yes; see DRD None EL 3. Loss of DI rinse Increased radiation Process delay Valve position None NIA (valves) alarms #9 (and issue)

MCO plug valve seal damaged or not reseating

I I- I

*S.C. - safety class

n\

Page 33: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

I I

SNF - Cold Vacuum Drying Project Failure Modes, Effects and Criticality Analysis, Phase I

Date: 8/18-21/97

Sheet No: 8

5 Loss of condenser

Page 34: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

I I

Subcomponent/ Subsystem

EPD

SNF - Cold Vacuum Drying Project Failure Modes, Effects and Criticality Analysis, Phase I

Date: W18-21/97

Sheet No: 9

ID Failure

Failure Mode

Remarks I Alpha Failure Effects I Rank (TBD) Method Mitigation

End Effects Production Worker Local Effects

ommunications,

EL Loss of equipment MCC Loss of HVAC, chilled Process delays Alarms None NIA B None None Acceptable risk water, CARA

I I I I I I I I I- I

Page 35: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

APPENDIX D

SESSION FLIPCHARTS

I I

I I i I I I I I

Page 36: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

. . . . ........... ................ ...__....I . ... _ ..............

, ’ . ’ . I : . . , I i ! . .

........ ..... . -. -

. . . . . . . . . s , ,

.....

.. - . . . . . . ! , ; i /

....... i... I.

i;”

u l l r - . - ? O , n I,

Page 37: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

. . . ____ . . .. -

Page 38: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

..... . -. ... ._

n 7

Page 39: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 40: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

. . .. . . . ._ .. - . . ..

Page 41: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

. -. lll"_ . .

Page 42: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

_. ___ . . .. .. ._ .. . . . . _. .

Page 43: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

. . . . .I .. .

Page 44: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 45: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

.. . . ..

Page 46: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 47: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

. . . . . .. .- -... - . ~

I \ .

Page 48: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

..I.. .

I \2

Page 49: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 50: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

.. . . ^ . i . . . - , . _.I-_..“ ..

I I C 4

Page 51: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

.. .. . .... . - ..... .I__ . _ _

3

Page 52: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 53: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 54: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 55: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

CLi

Page 56: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 57: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

. . . . .. .. , . . .. . .- . .. . . - ..

Page 58: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 59: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 60: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 61: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 62: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

. .. - . .... . . .

Page 63: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

. - I - .- . .- . . .. - ... ....... -_-- ..-..,---.-

Page 64: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

. ... . . .. . _>,.._ .... ; ....- ". , .... . -:. . ,

1

Page 65: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 66: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

I i

Page 67: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

3 1 I I

3 1 I I I 1

I

I

Page 68: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 69: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 70: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

I G

Page 71: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

.. _. . . . I . . . .. . . . . . . ... . . .

Page 72: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

I . . ..

I I

1 I I I ! I I I I I I I I

Page 73: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

. - ..: -

Page 74: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

........

3 I

Page 75: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

~ . -. . .. . . . . . . .. - . . .~ .~. - .-

a

Page 76: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

_ _ _ ~ . . . . . ........ - ... - .

__ .... ___ ... -. .................

. . . ._ .. .. __ ...........

__ ....... ... .... . . . .

............... _.___ . . __ . .... ...... - . . . . . . . . _-

...... ._ ___ . . . . . . __ ............ -

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . _ _ .. . . . . . . . . . . . .

Page 77: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

.. .

. . .

. ... -

...

Page 78: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.
Page 79: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.

._. € b

. .~ ..

. . . -. . . . E

Page 80: 2:;. Of T:aOn:- Dizio-/67531/metadc683849/m2/1/high_res... · Printed in the United States of America. To obtain copies of this document, contact: Document Control Services, P.O.