1PLANNING, ANALYSING(2).docx

download 1PLANNING, ANALYSING(2).docx

of 56

Transcript of 1PLANNING, ANALYSING(2).docx

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    1/561

    A MINI PROJECT REPORT

    Submitted by

    GEENA GEORGE

    RINCY SUNNY

    SONIJA T.

    TISNA THOMAS

    I n partial ful f il lment for the award of the degree

    of

    BACHELOR OF ENGINEERING

    IN

    CIVIL ENGINEERING

    MAHENDRA ENGINEERING COLLEGE NAMAKKAL

    ANNA UNIVERSITY: CHENNAI 600025

    NOVEMBER 2012

    PLANNING, ANALYSING AND

    DESIGNING OF A BANK

    BUILDING

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    2/562

    PLANNING, ANALYSING

    AND DESIGNING OF A BANK

    BUILDING

    A MINI PROJECT REPORT

    Submitted by

    GEENA GEORGE

    RINCY SUNNY

    SONIJA T.

    TISNA THOMAS

    (090104608012)

    (090104608046)

    (090104608051)

    (090104608055)

    I n partial ful fi llment for the award of the degree

    of

    BACHELOR OF ENGINEERING

    IN

    CIVIL ENGINEERING

    MAHENDRA ENGINEERING COLLEGE, NAMAKKAL

    ANNA UNIVERSITY: CHENNAI 600025

    NOVEMBER 2012

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    3/563

    ANNA UNIVERSITY: CHENNAI 600025

    BONAFIDE CERTIFICATE

    Certified that this project report on PLANNING, ANALYSING AND

    DESIGNING OF A BANK BUILDING is the bonafide work of

    GEENA GEORGE

    RINCY SUNNY

    SONIJA T.

    TISNA THOMAS

    (090104608012)

    (090104608046)

    (090104608051)

    (090104608055)

    Who carried out the project work under my supervision

    SIGNATURE

    Dr.K.JAGADESAN

    HEAD OF THE DEPARTMENT

    Department of Civil Engineering,Mahendra Engineering College

    SIGNATURE

    Dr.S.SAMSON

    SUPERVISOR

    Professor, Dept. of Civil Engg.Mahendra Engineering College

    Submitted for the practical examination held on--------------at----------------

    Internal Examiner External Examine

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    4/564

    ACKNOWLEDGEMENT

    The satisfaction and euphoria of successful completion of any task could

    be incomplete with mentioning the people who made it possible, whose constant

    guidance and encouragement crown our efforts with success.

    We take this opportunity to express our sincere gratitude to

    Shri.M.G.BHARATHUMAR, the chairman and Er.Ba.MAHENDRAN,Managing

    Director, Mahendra Engineering College, Mahendrapuri, Namakkal for their

    encouragement and granting permission to do this project.

    We are also express our gratitude to Dr.S.SAMSON RAVINDRAN,

    Principal, Mahendra Engineering college, for allowing us to use all facilities that are

    available in the college to complete our project.

    We express our sincere thanks to Dr.K.JAGADESAN, Head of the

    Department for this extended co-operation, persistent encouragement and support.

    We wish express our thanks and acknowledgement to our project guide

    Dr.S.SAMSON for this guidance and timely help to complete the project in time.

    We also thank all teaching and non teaching staff members of Civil

    Engineering Department for their valuable suggestion and co-operation in

    completing this project. Also we thank our friends for their support.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    5/565

    TABLE OF CONTENTS

    CHAPTER NO. TITLES PAGE NO.

    ABSTRACT

    i

    LIST OF SYMBOLS ii

    1. INTRODUCTION 1-4

    1.1 GENERAL 1

    1.2 PRACTICAL CONSIDERATIONS 1

    1.3 PLANNING CONSIDERATIONS 1

    1.4 SPECIFICATIONS 2

    1.4.1 FOOTING 2

    1.4.2 DAMP PROOF COARSE 2

    1.4.3 PLINTH 2

    1.4.4 FRAMES 2

    1.4.5 SUPER STRUCTURE 3

    1.4.6 ROOF 3

    1.4.7 FLOORING 3

    1.4.8 PLASTERING 3

    1.4.9 DOORS AND WINDOWS 3

    1.4.10 STAIRCASE 4

    1.4.11 WHITE WASHING ,COLOUR

    WASHING AND PAINTING4

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    6/566

    2. METHODOLOGY 5

    3. ANALYSIS 6-12

    3.1 INTRODUCTION 6

    3.2 ANALYSIS 8

    4. DESIGN 13-35

    4.1 INTRODUCTION 13

    4.1.1 DESIGN OF SLABS 14

    4.2.DESIGN OF BEAMS 22

    4.3 DESIGN OF COLUMNS 24

    4.4 DESIGN OF FOOTING 30

    4.5 DESIGN OF STAIRCASE 33

    5. REINFORCEMENT DETAILS 36

    6. PLANS 39

    7. CONCLUSION 44

    8. REFERENCE 46

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    7/567

    ABSTRACT

    The primary objective of this project is to gain sufficient knowledge in

    planning, analysis, and design of building.Our project deals with the plan and design of a Bank building. It is a

    reinforced concrete framed structure consisting of G +2 with adequate facilities.

    IS 456:2000 codes is the basic code for general construction in concrete

    structures, hence all the structural members are designed using limit state method in

    accordance with the IS 456:2000 code and design aids.

    The planning of any building in India will be recognized by National Building

    Code (NBC) , hence the building is planned in accordance with the National

    Building Code of India.

    The building includes the following:

    1. ATM Centre2. Safety locker room3. Conference hall4. Documentary room5. Manager room6. Power control room7. Assistant managers room8. Counters9. Toilet

    The bank building has proper ventilation, it is provided with sufficient doors,

    windows. Water supply and electrification are also provided.

    The ceiling height is provided as 3.2m, for assembly buildings as mentioned

    Building Code (NBC).

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    8/568

    LIST OF SYMBOLS

    SYMBOL DESCRIPTION

    D Effective depth in mm

    D Overall depth in mm

    ly Longer span length

    lx Shorter span length

    W Factored load

    x Bending moment coefficient along shorter direction

    y Bending moment coefficient along longer direction

    dreq Depth required

    Mu Bending moment

    Mulim Ultimate moment

    Ast Area of steel in tension

    Asc Area of steel in compression

    fy Grade of steel

    fck Grade of concrete

    Xu Depth of neutral axis

    B Breadth

    Ast(req) Reinforcement required

    Ast(pro) Reinforcement provided

    P Percentage of steel

    Diameter of bar used

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    9/569

    Peq Equivalent load

    v Nominal shear stress

    c Shear capacity of concrete

    D.L Dead load

    L.L Live load

    Lx Effective length in shorter span

    Ly Effective length in longer span

    Sv Spacing of stirrups

    V Shear force

    Vu Design Shear force

    Pu Ultimate axial load

    Ag Gross sectional area of column

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    10/5610

    CHAPTER-1

    INTRODUCTION

    1.1 GeneralThe main objective of our project is to know the various design aspects

    like planning, analysis and design etc.We have planned to design a bank

    building consisting of three floors (G+2).The planning is done as per the

    requirements and regulations given by the National Building Code (NBC).

    1.2 Practical considerationsBesides all the fundamentals of planning discussed, following practical

    points should be additionally considered:

    1) The elements of the building should be strong and capable to withstandthe likely adverse effects of natural agencies.

    2)

    Strength, stability, convenience and comfort of the occupants should bethe first consideration in planning.

    3) Elevation should be simple but attractive. The number of doors andwindows provided should be less for a bank building.

    4) The provisions of built in furniture at proper places are useful from thepoint of view of utility.

    5) Since the plan is for a bank building, the locker rooms must be securedwith thicker walls than usual.

    1.3Planning considerationsThe plan and detailing was drawn using Auto CAD. The proposed area

    of the bank is 324sq.m. The shape of the building is rectangular in plan. The

    building consists of ground floor, first floor and second floor.The parking

    space is provided around the building. The floor height of the building is

    3.2m.The height of the parapet wall is 1m.The staircase is provided with

    enough safe.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    11/5611

    Area of each floor is given below

    Ground floor = 108 sq.m

    First floor = 108 sq.m

    Second floor = 108 sq.m

    Total area = 324 sq.m

    1.4 Specifications1.4.1 Footing

    Earth work excavation for foundation is proposed to a depth of

    1.50m.below the ground level. For design, the safe bearing capacity of soil is

    assumed as 200KN/.Isolated footings are provided with a concrete grade ofM20. The maximum axial load 2210KN as arrived from analysis result is

    taken for the design of the footing.

    1.4.2 Damp proof coarseThe damp proof coarse is to be provided around the plinth level using

    C.M 1:3 with a thickness of 20mm. The column below the ground level are

    also provided with damp proof coarse of C.M 1:3

    1.4.3 Plinth

    The plinth beam will be at a level of 0.5m above the ground level. M20

    grade of concrete is used and Fe415 steel was used for plinth design.

    1.4.4 Frames

    All the R.C.C. structural components are designed using M20 grade

    steel. Each member is designed separately for its loading condition

    And its location as per the IS 456:2000 and SP 16 codes. The dimension of

    slab, beam, column and footing are designed according to the IS 456:2000

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    12/5612

    code. The column is designed as per the design principles given in SP-16 and

    the axial load was taken from the analysis results.

    1.4.5 Super Structure

    The super structure is proposed in CM.1:6 using second class brick

    work. Brick partition walls of 110mm thick are also proposed using the C.M

    1:4 with a width of 300mm as a safety measure.

    1.4.6 Roof

    R.C.C Roof in M20 concrete is to be laid. A layer of weathering coarse

    using brick jelly lime mortar is to be used. Considering the future expansion

    of the structure, the roof slab is also designed as same as that of the floor

    slabs.

    1.4.7 FlooringIn each floor, all the rooms are to be provided with P.C.C. 1:5:10 as

    flooring base. The floors of entrance, toilet floors, staircase and entire flat are

    to be finished with granite tiles over the P.C.C. 1:2:4 flooring.

    1.4.8 Plastering

    All walls and structural members including the basement will be

    plastered smooth with C.M. 1:5 externally and internally, using 12mm thick

    plastering mortar.

    1.4.9 Doors and windows

    The main door will be of steel having a sliding shutter. The other doors

    inside the bank are to be provided with aluminium panel. The windows are to

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    13/5613

    be provided with steel and glazing is provided to supply a good light from

    outside.

    1.4.10 Staircase

    The stair will be of M20 grade concrete and Fe415 steel with a rise of

    150mm and tread of 300mm. The staircase is designed as spanning parallel to

    landing slab referring to IS 456-2000.

    1.4.11 White washing, Colour washing, Painting

    All the inner walls are to be finished with a first coat of white cement

    wash and then colouring as required. All the joiners and iron works are to be

    finished with two coats of synthetic enamel paint. The toilet walls are to be

    provided with mat finishing.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    14/5614

    CHAPTER2

    METHODOLOGY

    NBCPlanning

    Drawing

    Analysis

    Designing

    Collection of data

    NBC

    AUTOCAD

    BENDING MOMENT

    SHEAR FORCE

    SLABS

    BEAMS

    COLUMNS

    FOOTING

    STAIRCASE

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    15/5615

    CHAPTER-3

    ANALYSIS

    3.1 INTRODUCTION

    Structural analysis is the application of solid mechanics to predict the

    response (in terms of force and displacements) of a given structure (existing or

    proposed) subjected to specified loads.

    Based on degree of indeterminacy the structure will be classified as

    i. Determinate structureii. Indeterminate structure

    The determinate structure can be completely analyzed by using equilibrium

    equation. I.e.M =0;V=0; & H=0.

    Example: simply supported beam, cantilever beam, overhanging beam.

    In the indeterminate structure, cant be complete analyzed by equilibrium

    equations.

    Example: Fixed beam, continuous beam, and propped cantilever beam.

    Moment Area method:

    This method is used for analyzing cantilever and fixed beam.

    Theorem of three moment equation:

    It is more suitable for continuous beam.

    Moment distribution method:

    It is the iterative technique.

    Slope- deflection method:

    When the beam has more than four spans then the calculation is difficult.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    16/5616

    Stiffness method:

    Force and displacements play on important role in the structural

    analysis. In this method the force is measured to produce a unit displacement.

    Flexibility method:

    It is the inverse of stiffness. It is defined as the measure of displacement

    caused by the unit load. The moment distribution method for the analysis of

    beam is adopted in this project.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    17/5617

    3.2ANALYSIS

    FIXED END MOMENTS

    Type 1

    Span AB

    MFAB = KNmWl

    12.3612

    2)2.3(34.42

    12

    2

    MFBA = KNmWl

    12.3612

    2)2.3(34.42

    12

    2

    MFBC = MFCB

    Distribution factor (DF)

    @Joint B

    BCBA

    BA

    AB

    KK

    KDF

    = 5.03125.03125.0

    3125.0

    BABC

    BC

    BC

    KK

    KDF

    = 5.03125.03125.0

    3125.0

    Distribution factor (DF) is same as each member

    42.34KN/m

    3.2m

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    18/5618

    Table 3.1 Moment distribution method

    Span

    AB =

    KNmWl

    23.988

    4.595.26

    8

    22

    Span CE = KNmWl

    92.288

    37.25

    8

    22

    Type 2

    Span AB

    MFAB =KNm

    Wl

    33.4512

    2)2.3(13.53

    12

    2

    MFBA = KNmWl

    33.4512

    2)2.3(13.53

    12

    2

    MFBC = MFBC = MFCD

    MFBA = MFCB = MFDC

    Joint A B

    C

    Mem

    ber

    AB BA BC CB

    D.F 0.5 0.5

    I.M-

    36.12

    36.12 -

    36.12

    36.12

    B 0 0 0 0

    Net

    B.M

    -

    36.12

    36.12 -

    36.12

    36.12

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    19/5619

    Distribution factor (DF)

    @Joint B

    BCBA

    BA

    AB

    KK

    KDF

    = 5.03125.03125.0

    3125.0

    BABC

    BC

    BC

    KK

    KDF

    = 5.03125.03125.0

    3125.0

    Table 3.2 Moment distribution method

    Span AB = KNmWl

    23.988

    4.595.26

    8

    22

    Span CE = KNmWl

    92.288

    37.25

    8

    22

    Joint A B

    C

    Mem

    ber

    AB BA BC CB

    D.F 0.5 0.5

    I.M-

    45.32

    45.32 -

    45.32

    45.32

    B 0 0 0 0

    Net

    B.M

    -

    45.32

    45.32 -

    45.32

    45.32

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    20/5620

    Type 3

    Span AB

    MFAB = KNmWl

    50.4612

    2)2.3(49.54

    12

    2

    MFBA = KNmWl

    50.4612

    2)2.3(49.54

    12

    2

    MFBC = MFBC = MFCD

    MFBA = MFCB = MFDC

    Distribution factor (DF)

    @Joint B

    BCBA

    BA

    AB

    KK

    KDF

    = 5.03125.03125.0

    3125.0

    BABC

    BC

    BC

    KK

    KDF

    = 5.03125.03125.0

    3125.0

    Table 3.3 Moment distribution method

    Joint A B

    C

    Mem

    ber

    AB BA BC CB

    D.F 0.5 0.5

    I.M-

    46.50

    46.50 -

    46.50

    46.50

    Net

    B.M

    -

    46.50

    46.50 -

    46.50

    46.50

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    21/5621

    Type 4

    SPAN AB

    MFAB = KNmWl

    50.4612

    2)2.3(97.46

    12

    2

    MFBA = KNmWl

    50.4612

    2)2.3(49.54

    12

    2

    MFBC = MFBC = MFCD

    MFBA = MFCB = MFDC

    Distribution factor (DF)

    @Joint B

    BCBA

    BA

    AB

    KK

    KDF

    = 5.03125.03125.0

    3125.0

    BABC

    BC

    BC

    KK

    KDF

    = 5.03125.03125.0

    3125.0

    Table 3.4 Moment distribution method

    Joint A B

    C

    Mem

    ber

    AB BA BC CB

    D.F 0.5 0.5

    I.M-

    40.08

    40.08 -

    40.08

    40.08

    B 0 0 0 0

    NetB.M

    -40.08

    40.08 -40.08

    40.08

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    22/5622

    CHAPTER-4

    DESIGN

    Introduction

    Proper nomenclature of floors and storeys and also unified and improved

    methods of designating the structural members eliminate the possible confusion and

    led to less efforts and saving in time in the preparation of design calculation and

    drawings.

    There are two main methods to design the structural members, they are

    working stress method and limit state method. Here, we adopt the limit state method

    for designing all the structural members involved, in our project. The structures are

    designed to its elastic limit in the working stress method, whereas in the limit state

    method of design, the structural members are designed up to its plastic limits.

    Both the methods are having the safety value. But, the most economical

    method is the limits state method, which is adopted in every constructional design

    nowadays. Hence we planned to go for the limit state method of design. For our

    project work we took only for important structural members to design they are slab,

    beam, column and footing. The slab is designed by assuming it as simply supported

    with four edges discontinuous, for easier design calculation.

    The beam is designed by knowing its span and its location (inner and outer).

    The beam has to carry the self-weight of slab and live load of 4KN on its self-weight

    also. The live load on each beam will be calculated separately by considering the

    load transmission diagram. In some beams where the wall is constructed above it,the self-weight of wall has to be added.The column and footing design are made by

    knowing the maximum axial load on each column. The column alone is designed by

    following the SP16 codes.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    23/5623

    4.1 DESIGN OF SLAB

    4.1.1 Slab 1: Two adjacent edges discontinuous

    Data

    Dimension of slab = 3 m 3 m fck = 20 N/m2

    Support width = 230 mm fy = 415 N/m2

    Live load = 4 KN/m2

    Floor finish = 1 KN/m2

    Depth of slab

    Minimum depth = Span / B.V M.F

    B.V = 26 (For continuous slab)

    M.F = 1.4

    Minimum depth d = 3000/(26 1.2)

    = 96.15 mm 100 mm

    Assume effective cover = 25 mm, Using 10 mm diameter bars

    Effective depth = d = 100 mm

    Overall depth = D = 100 + 25 + (10/2)

    = 130 mm

    d = 100 mm D = 130 mm

    Effective span

    The least value of:

    (1)(Clear span + effective depth) = (3 + 0.1) = 3.1 m(2)(Centre to centre of supports = (3 + 0.23) = 3.23 m

    Hence L = 3.1 m

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    24/5624

    Loads

    Self weight of slab = (0.12 25) = 3 KN/m2

    Floor finish = 1 KN/m2

    Live load = 4 KN/m2

    Total service load = w=8 KN/m2

    Ultimate load = wu= 1.5 8 = 12 KN/m2

    Ultimate moments and shear forces

    Ly / Lx = 3 / 3 = 1< 2

    So it is a two way continuous slab

    The coefficients for the positive and negative moments are taken from IS 456

    2000

    +x = 0.035

    _ x = 0.047

    + y= 0.035

    _ y= 0.047

    Mux = x wuxx2

    Muy = ywuLy2

    Vux= 0.5 W lx

    (1)B.M along span ( +ve) = 0.035 12 3.12Mux = 4.036 KN.m

    (2)B.M along span ( -ve) = 0.047 12 3.12Muy = 5.420 KN

    (3)Shear force Vux = 0.5 12 3.1= 18.6KN

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    25/5625

    Check for depth

    Mmax = 0.138fckb d2

    d2 = 5.420 10

    6/ (.138 20 10

    3)

    d = 44.31mm < 100mm

    Reinforcements (Short and long span)

    Mu = .87fy Astd [1(fy Ast / b dfck)]

    Ast = 155.10mm2

    Adopt 10mm diameter bars at 400 mm centers (Ast=185.71mm2)

    Edge strip

    Minimum area of steel = 0.12% Ag

    = .12 /(100 1000 130)

    = 156mm2

    Provide 10mm diameter bars

    ast = /4 d2

    =78.5mm2

    Spacing = ast/ Ast 1000

    78.5/156 1000 = 509 mm

    So adopt 10 mm bar @ 500mm c/c

    Middle strip [+ve moment]

    Mu = .87 fy Astd [1(fy Ast / b dfck)]

    Ast = 201.44mm2

    Provide 10mm diameter bars

    ast = /4 d

    2

    ast = 78.5mm

    2

    Spacing = ast/ Ast 1000

    S = 300mm

    Provide 10 mm diameter bars @ 300mm c/c

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    26/5626

    Torsional reinforcement

    Single torsional reinforcement =l/5 ly/5

    Area of torsional steel = 3/4 maximum mid span

    = 3/4 201.44

    = 151.08mm2

    Provide 8mm bars

    Spacing = 50.26/151.08 1000

    = 332 mm c/c or 300 mm c/c.

    Check for deflection

    (Shorter span/depth)provided = 3000/130 = 23.07

    (Shorter span/depth)permissible = B.V M.F

    Fs = 0.58 415 (156/102)

    Fs = 368.12

    % Ast = 100 Ast/ bd

    = (100 156) / (100 130)

    = 1.2%

    M.F = 1.2

    (Shorter span/depth) = 26 1.2

    = 31.2

    Hence safe in deflection

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    27/5627

    4.1.2 Slab 2: One short edge discontinues

    Data:

    Clear dimension of slab =1.2Step 1: Check the ratio

    lx

    ly

    = 22.561.2

    3

    Hence it is one way slab

    Step 2 Effective dept

    d =

    26

    span

    =26

    3000

    = 115 mmD = d + 25 mm

    = 130+ 25+10/2 mm

    = 160 mm

    Step 3: Loads

    Self wt of slab = 0.16 Finishes =1KN/Total dead load =5 KN/

    Live load = 4 KN/The effective span = 3.2 mm

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    28/5628

    Step 4: ultimate Moment and SF

    Mu(-ve) =1.5( )

    =1.5( ) = 12.75 KN.m

    Mu(+ve) = ( )

    =

    (

    ) (

    )= 11.025 KN.m

    Vu = (1.5)(5+4) = 24.3 KN

    Step 5 : Limiting Moment of Resistance

    Mulimit = 0.138fckb.d2

    = 0.138 20 1000 1302 10-6

    = 46.64 KN.m

    Mu< Mulimit, Section is under reinforced.

    Step 7: Main reinforcement

    Mu = .87 fy Astd [1(fy Ast / b dfck)]

    A = 325 mm2

    Spacing

    a) Spacing = (ast/ Ast )1000

    Use 10mm bar

    Spacing = 1000325

    210/4

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    29/5629

    = 230mm

    Step 6 : distribution Reinforcement

    Ast =

    = 192 mm2

    Provide 10 mm bar at 300 mm c/c

    Step 7: Check for shear stress

    v =db.

    uV

    =1301000

    31092.25

    = 0.199N/mm2

    Pt =db.

    Ast100

    = 1301000

    314100

    = 0.241

    Permissible shear stress

    Kc = 1.27 0.35

    = 0.44 N/mm2

    Kc > v

    Hence the shear stresses are within safe permissible limits

    Step 8: Check for deflection

    maxdL = kfkckt

    basicdL

    Kt = 1.5

    Kc = 1

    Kf = 1 (Refer IS 4562000)

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    30/5630

    max/dL = =

    =34.5

    actualdL / =130

    3000

    = 23 < 34

    maxdL >

    actualdL

    Hence design is safe.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    31/5631

    4.2DESIGN OF BEAM

    Dimension:

    Shear force = 135 KN

    Moment Mu = 67 KN.m

    Beam size = 0.3 0.4m

    Limiting moment of resistance

    Mu limit = 0.138fckbd2

    Mu limit = [0.138203004002] 10-6

    = 132.48 KN.m

    Since Mu

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    32/5632

    Using 8 mm diameter 2 legged stirrups spacing

    Sv = [0.87 fy Asv d/Vus]

    = [(0.87 415 400 2 50)/(34.2 103)]

    = 221 mm

    Sv> 0.75 d = 0.75 450

    = 337.5mm

    Adopt spacing of 200mm near support, gradually increasing to 300mm towards

    center of span.

    Check For Deflection:

    pt = [100Ast/bd]

    = [(100 920)/(300 400)]

    = 0.76

    Neglecting bar in compression side

    [L/d]ma = [L/d]basic Kf

    = [2.6 1.2 1.2 0.92]

    = 34.44

    [L/d]actual = [3600/400]

    = 9 < 34.4

    Hence deflection control is satisfied.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    33/5633

    4.3 DESIGN OF COLUMN

    4.3.1 COLUMN TYPE - 1

    Data

    Size of column = 450mm 450mm

    Concrete mix = M20

    Characteristic strength of reinforcement = 415 N/mm2

    Factored load = 1660 KN

    Factored moment = 60.12 KN.m

    Assuming 25mm bars with 40mm cover,

    d = 40 + 12.5

    = 52.5mm

    = 5.25cm

    d/D = 5.25/45

    = 0.12

    By using SP16,

    Chart for d/D = 0.15 will be used.

    Pu /(fckbD) = (1660 103) / (20 45 45 102)

    = 0.409

    Mu/ (fck Bd2) = (60.12 106) / (20 45 45 45

    103)

    = 0.033

    a) Reinforcement on two sides.

    Refer Chart 33 of SP16,

    P/fck = .02

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    34/5634

    Percentage of reinforcement,

    P = .01 20

    = 0.4

    As = PbD / 100

    = 0.2 45 45 / 100

    = 8.1cm2

    b) Reinforcement on four sides.

    Refer Chart 45 of SP16,

    P/fck = 0.02

    P = 0.02 20

    = 0.4

    As = 0.4 45 45 /100

    = 8.1cm2

    Provide 6 bars of 20mm diameter

    Lateral Ties

    Diameter of lateral ties

    1 /4 of main bars = 1/4 x 20 = 5mm. Min diameter of bar = 6mm

    Follow 6# bars.

    Pitch of lateral ties

    16n times main bars = 16 x 20 = 320 mm. Lateral dimension = 450mm 300mm

    Provide 25mm diameter bars at 300mm c/c.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    35/5635

    4.3.2 COLUMN TYPE2

    Data

    Column = 450mm 450mm

    Axial load = 1660KN

    Unsupported length = 3.0mm

    Concrete mix = M20

    Characteristic strength of reinforcement = 415 N/mm2

    Slenderness Ratio

    (L/D) = (3000/450) = 6.7 < 12

    Therefore column is short column.

    Minimum Eccentricity

    emin = ( )emin = ( )= 21.0 > 20mmAlso .05 D = .05 450 = 22.5 > emin

    Factored Ultimate Load

    Pu

    = 1660KN

    Longitudinal reinforcement

    Pu = [.4fckAg+ (.6fy- .4fck )Asc]

    3000 103= [(.4 20 450 450) +{ (.67 415 ) - (.4 20)} A sc ]

    Asc = 5110.16mm2

    The area of reinforcement provided is greater than the minimum

    steel reinforcement of 0.08 percent = (.008 450 450) = 1620mm2.

    Provide 6 bars of 25mm diameter

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    36/5636

    Lateral Ties

    Diameter of lateral ties

    1 /4 of main bars = 1/4 x 25 = 6.25mm. Min diameter of bar = 6mm

    Hence provide 8mm diameter ties.

    Pitch of lateral ties

    16n times main bars = 16 x 25 = 400 mm. Lateral dimension = 450mm 300mm

    Provide 25mm diameter bars at 300mm c/c.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    37/5637

    4.3.3 COLUMN TYPE3

    Data

    Size of column = 450mm 450mm

    Concrete mix = M20

    Characteristic strength of reinforcement = 415 N/mm2

    Factored load = 1660 KN

    Factored moment MUX = 46.50 KN.m

    MUY = 36.12KN.m

    Moments due to minimum eccentricity are less than the values given above.

    Reinforcement is distributed equally on four sides.

    As a first trial assume the reinforcement percentage, P = 1.2

    P/fck = 1.2/20 = 0.06

    Uniaxial moment capacity of the section about XXaxis:

    d/D = 5.25/45 = 0.117

    Chart for d/D = 0.1 will be used.

    Pu/fckbD = (1660x103) / (20 450 405)

    = 0.409

    Referring to chart 44

    Mu /fckbD2

    = 0.09

    Mux1 = 0.09 20 45 452 103/106

    = 164.02KN.m2

    Uniaxial moment capacity of the section about YY-axis:

    d/D = 5.25/45 = 0.117

    Chart for d/D =0.15 will be used.

    Referring to chart 45

    Mu/fckbD2 = 0.083

    Muy1 = 0.083 20 45 45

    2 10

    3/10

    6

    = 151.26KN.m

    2

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    38/5638

    Calculation of Puz:

    Referring to chart 63 corresponding to

    P = 1.2

    fy = 415

    fck = 20

    Puz /Ag = 10.3N/mm2

    Puz = 10.3 45 45 102/10

    3

    = 2085.7KN

    Pu / Puz = 1660/2085.7 = 0.79

    Mux/ Mux1 = 46.50/164.02 = 0.28

    Muy/ Muy1 = 36.12/151.26 = 0.23

    Referring to chart 64, the permissible value of Mux/ Mux1

    Corresponding to the above Muy/ Muy1 and Pu / Puz is equal to 0.61

    Hence the section is ok.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    39/5639

    4.4 DESIGN OF FOOTING

    Data

    Factored axial load Pu = 1660KN

    Size of Column = 450 450 mm

    Safe Bearing Capacity = 200 KN/m2

    Assume self weight of footing 10% of load

    Self weight of footing = 166 KN

    Area of footing required = Total Load / SBC

    = 1826/(2001.5)

    =6.08m2

    Side of square footing = 2.46m

    Assume breadth of square footing = 3m

    Provide a square footing of 3m3m = 9m2

    Net upward design pressure W =1660/33

    = 184.4

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    40/5640

    Over all depth = 480+10+20+40

    = 550mm

    Tension Reinforcement

    Mmax = 449.74

    106

    Mu = 0.87fyAstd[1-(Astfy/bdfy)]449.74106= 0.87 415 480[1-(Ast 415/20 480 3000)]

    Ast = 2700mm2

    Minimum Astto be provided = (0.15/100) 3000 550

    = 2475 < 2700mm2

    Provide 20 mm diameter bars,

    Number of bars = 2700/314.15

    = 8.59 10nos

    Provide 10 numbers of 20mm bars (Actual Ast= 3141mm2)

    Check for one way shear

    The critical section for traverse shear (section yy) is at distance of 480mm (effective

    depth).

    Length of critical section = 1.2750.48= 0.795m or 795mm

    Vu = 184.430.795

    Vu = 439.79 KN

    Nominal shear stress

    v = Vu/bd

    = 439.79/(3000550)= 0.26 N/mm2

    From the table -19 of IS456-2000

    100Ast/bd = 0.24 for M20.

    v = 0.34

    c > v , Hence safe.

    Checking for punching shearThe critical section for shear is at distance of ( deff)

    ie , 240mm around the face of the column.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    41/5641

    Side of the section = 450 + (2240)

    =930mm

    Punching shear across section zz

    Vz = 184.4( 330.940.94 )

    = 1496.99 KN

    Nominal shear stress across section zz

    v = (1496.66103)/(4940480)

    v =0.82N/mm2

    As per clause 31.6.31 of IS456:2000

    Permissible shear stress in concrete = kc

    For square column,

    k = 1.0, c = 0.33

    kc = 0.33

    Check for Safe bearing capacity

    Column of load = 1660 KN

    Self weight of footing =330.5525

    =123.75 KN

    Total = 1783.75 KN

    Pressure = 1783.75/(33)

    =198.3< 300 (200 1.5)

    Hence safe.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    42/5642

    4.5 DESIGN OF STAIRCASE

    DATA:

    Spanning parallel to landing slab (stair-1)

    Type: dog-legged

    Number of steps in the flight = 11 per flight

    Thread T = 300 mm

    Rise R = 150 mm

    Width of landing beam = 300 mm

    Width of landing slab = 1850 mm

    M-20 grade concrete (fck= 20 N/mm2)

    Fe-415 hysd bars (fy= 415 N/mm2)

    Solution:

    Design of first flight

    Effective span = (11 x 300) + 300/2 + 1850/2

    = 4375 mm = 4.375 m

    Thickness of waist slab = (span/20) =4375 /20)

    = 218.75 mm

    overall depth (D) = 218.75 mm

    Assume using 25mm cover and 10mm diameter bars

    Effective depth (d) = 188.75 mm

    LOADS:

    Dead loads of slab on slope (ws) = (0.188x1x25)= 4.717KN/m

    Dead load of slab on horizontal span (w)

    =[ws(R2+ T

    2)]/T

    = [4.717(1502+ 3002)]/300

    = 5.28 KN/m

    Dead load of one step = (0.5x0.15x0.3x25)

    = 0.56 KN/m

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    43/5643

    Load of step per meter length =[(0.56x1000)/300]=1.875KN/m

    Finishes etc, = 0.6 KN/m

    Total dead load = ( 4.72+1.86+0.6)

    = 7.18 KN/m

    Service live load = 5 KN/m2

    Total service load = (7.18+5) = 12.18 KN/m

    Factored load (wu) = (1.5x12.18) = 18.27 KN/m

    BENDING MOMENTS:

    Maximum bending moment at centre of span ( (Mu) = 0.125wuL2

    = 0.125x18.27x4.32

    = 42.235 KNm

    CHECK FOR DEPTH OF WAIST SLAB

    (d) = [Mu/(0.138fckb)]

    = [(42.23x106)/(0.138x20x103)]

    = 123.69 mm < 188.7mm Hence safe.

    MAIN REINFORCEMENTS

    Mu = (0.87fyAstd)[1-(Astfy/bdfck)]

    42.23x106

    = (0.87x415Astx188.75)[1-(415Ast/103x188.75x20)

    Ast = 668 mm2

    Provide 12 mm diameter bars at 150 mm centres (Ast= 678.6 mm2) as main

    reinforcement.

    DISTRIBUTION REINFORCEMENT

    Distribution reinforcement = 0.12 per cent of cross section= (0.0012x1000x188.75)

    = 226.5 mm2

    Provide 8mm dia bars at 220 mm centres (Ast= 251.3mm2)

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    44/5644

    Design of second flight

    The design of the second flight loading above the landing slab will be the

    same as that of the flight below the landing slab and that design is shown above.

    There is only one change the landing beam and landing slab will be reversed.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    45/5645

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    46/5646

    5.3 BEAM- REINFORCEMENT DETAILS

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    47/5647

    5.4 COLUMNREINFORCEMENT DETAILS

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    48/5648

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    49/5649

    150

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    50/5650

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    51/56

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    52/5652

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    53/5653

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    54/5654

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    55/5655

    CHAPTER -7

    CONCLUSION

    In this project, PLANNING DESIGNING AND ANALYSING OF A

    BANK BUILDING. We all the members of our team has learned to plan a building

    with referring to National Building Code of India -2005.

    This bank building project has made us to learn Drawing and drafting the

    building plans using Auto cad software.

    In this bank building project we learnt to create the models by giving nodes

    and property to the structural elements using analysis and also we learnt to the same

    structure with corresponding loads as givenIS 875 part 1&2 using analysis.

    This project is very useful in making us learn the design by referring to the IS

    456:2000 for each slab and beam. SP: 16 codes alone are used for easier design of

    columns yet we learned to design the columns.

    The important thing that we done was referring to a lot of books for designing

    and we are very much satisfied with exposing to field of design.

  • 8/14/2019 1PLANNING, ANALYSING(2).docx

    56/56

    CHAPTER -8

    REFERENCES

    1. Arul Manickam A.P (2004) Structural Engineering Pratheeba publishers.2. Is 456: 2000 Plain and Reinforced concrete code of practice (Fifth

    revision).

    3. SP 16 Design for reinforced concrete to 456 19784. Krishna raju (2002) Design of reinforced concrete structures5. Murugan.M (2007) Structural Analysis Samuthira Publications.6. Varghese P.C (2002) Limit state Design of Reinforced concrete second

    Edition.

    7. Vaidyanthan. R. Perumal. P (2005) Structural Analysis Volume I LaxmiPublications.

    8.NBCNational building of India , Bureau of Indian Standards ,New Delhi.