![Page 1: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/1.jpg)
INTRODUCTION
Dr. Ahmed Elyamany
Construction Project Management (1)
![Page 2: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/2.jpg)
Lecture Contract
2
واجباتي نحوك حقوقي عليك
بالمواعيد ا�لتزام •المعلومات بطريقة مشوقة توصيل •إحترام عقلية ا خر •ا�جابة عن ا$سئلة •العدالة في التقييم •تشجيع المجدين •/ المسئولية/ا�حساس بالحرية•
المبادرة/عزة النفس/إتقان العمل
بالمواعيد ا�لتزام •ا.نصات بإھتمام •التكلم بذوق •ا�ستئذان قبل الك2م •مراعاة أداب الحوار •التفاعل في المحاضرة •/ المسئولية/ا�حساس بالحرية •
المبادرة/عزة النفس/إتقان العمل
![Page 3: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/3.jpg)
الغرض من التعليم الجامعي
3
. َتْھِيئة الط�ِب للمھِن الناجحةِ �
.الط�ب بالمعرفِة والمھاراِت ال�زمة للَتطورَتزويد�
.شخصية عق�نية وناجحة جعل الطالب ذو�
.اكساب الط�ب التثقيف من البيئات التي يعيشون فيھا�
.تنمية أدواَر الط�ب في المجتمعِ �
![Page 4: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/4.jpg)
Course Info
4
� Course Code:� CUE 321
� Course Title:
� Construction Project Management (1)
� Credit hours� Lecture: 3
� Tutorial: 1
� Total: 4
![Page 5: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/5.jpg)
Course Content Schedule
5
No. Session TitleInstructors*
1 2 3
1 Introduction �
2 Tendering �
3 Cost estimating & analysis �
4 Construction contracts �
5 Techniques of planning �
6 Techniques of planning �
7 Mid-Term Exam
8 Scheduling �
9 Scheduling �
10 Resource Management �
11 Resource Management �
12 Project time control �
13 Revision �
1) A. Prof Dr. Hany Abd Elshakour
2) Dr. Adel Gouda
3) Dr. Ahmed Elyamany
![Page 6: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/6.jpg)
Student Assessment Methods
6
Examination Marks
Total Exam Time (hrs)Course Work Practical/Tutorial Final Exam Oral
20% 10% 70% 0% 100% 3
Method Subject assessed Assessment schedule
Midterm Exam Subject covered in first 7 lectures Week no. 7
Quizzes Lecture subject Even Week
Sheets All subjects After finishing the subject by a week
Bonuses Students' interactions
Final exam All subjects Week no. 14
![Page 7: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/7.jpg)
Introduction to Management
7
![Page 8: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/8.jpg)
Management
8
Management
Engineering
Science
� Planning
� Organizing
� Commanding
� Coordinating
� Controlling
![Page 9: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/9.jpg)
PROJECT MANAGEMENT
9
![Page 10: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/10.jpg)
Project Management
10
ھو فن تنسيق و توجيه الموارد البشرية و الطبيعية إدارة المشروعات �باستخدام تقنيات ا2دارة الحديثة لتحقيق أھداف طوال عمر المشروع
:محددة سلفا مثل
.تشييد المشروعتحقيق الوظيفة المستھدفة من �
:ا8نتھاء من تنفيذه�.في الزمن المحدد �
.و في حدود الميزانية المخصصة له�
.و مطابقا للمواصفات�
.وذا مظھر جمالي�
![Page 11: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/11.jpg)
The Project Life Cycle
11
� The project life cycle consists of four phases
� Project Initiation تجھيز المشروع
� Project Planning تخطيط المشروع
� Project Execution تنفيذ المشروع
� Project Closure اقفال المشروع
![Page 12: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/12.jpg)
Develop a business case
Undertake a feasibility study
Establish the terms of reference
Appoint the project team
Setup a project office
1.PROJECT INITIATION
12
![Page 13: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/13.jpg)
Create a Project plan
Create a Resource plan
Create a Financial plan
Create a Quality plan
Create a Risk plan
Create a Acceptance plan
Create a Communication plan
Create a Procurement plan
Contract the suppliers
2.PROJECT PLANNING
13
![Page 14: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/14.jpg)
Create a project plan
14
� Document the project plan
� Identify ‘work breakdown structure’ (WBS)
� Allocate resources
� Form a detailed project schedule
![Page 15: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/15.jpg)
Create a resource plan
15
� Detailed resource plan is required to identify:
� Type of resource (labor, equipment and materials)
� Quantity of each type of resource
� Roles and skills of all human resource required
� Specifications of all equipment resource required
� Items and quantities of material resource required.
![Page 16: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/16.jpg)
Create a financial plan
16
� A financial plan is created to:
� Identify the quantity of money required for the project (the budget).
� An expense schedule is defined
![Page 17: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/17.jpg)
Create a quality plan
17
� The quality plan:
� Defines the term ‘quality’ for the project.
� Lists clear quality targets for each deliverable
� Provides a quality assurance plan.
� Provides a quality control plan.
![Page 18: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/18.jpg)
Create a risk plan
18
� Risk plan
� Documents all foreseeable project risks
� Identifies the actions required to prevent each risk from occurring
� Reduce the impact of the risk should it occur
![Page 19: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/19.jpg)
Create an acceptance plan
19
� To deliver the project successfully, you will need to gain full acceptance from the customer that the deliverablesproduced by the project meet or exceed requirements.
![Page 20: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/20.jpg)
Create a communications plan
20
� The communications plan identifies:
� The types of information to be distributed
� The methods of distributing the information
� The frequency of distribution
� Responsibilities of the project team for distributing the information.
![Page 21: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/21.jpg)
Create a procurement plan
21
� The procurement plan provides a detailed description of the:
� Goods and services to be obtained from suppliers,
� Justification for obtaining each product externally
� Schedule for product delivery
� Process for the selection of a preferred supplier
� Ordering and delivery of the products
![Page 22: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/22.jpg)
Contract the suppliers
22
� A formal tender process is undertaken
� Create a statement of work
� Request for proposal document
� Identify a short-list of capable suppliers
� Select the preferred supplier
� Agreement between the project team and the supplier.
![Page 23: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/23.jpg)
3.PROJECT EXECUTION
23
� Implementing the plans created during the project planning phase.
� While each plan is being executed, output is being monitored and controlled.
� Once all of the outputs have been produced, the project is ready for closure.
![Page 24: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/24.jpg)
4.PROJECT CLOSURE
24
� Project closure involves
� Releasing the final deliverables to the customer,
� Handing over project documentation
� Terminating supplier contracts
� Releasing project resources
� Communicating the project closure to stakeholders.
![Page 25: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/25.jpg)
CONSTRUCTION MANAGEMENT
25
![Page 26: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/26.jpg)
Construction Management
26
إدارة التشييد ھو ادارة الموارد ا:ساسية للتشييد من عمالة و مواد �:ومعدات و مقاولي باطن و نقود لتشييد منشأ ما بھدف
:المشروع ا8نتھاء من تنفيذ�
.في الزمن المحدد �
.و في حدود الميزانية المقدرة له�
و مطابقا للمواصفات�
![Page 27: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/27.jpg)
Construction Management Needs
27
:لحدوث تطور في مدخ�ت عملية التشييد
ظھور أنواع جديدة من المواد المستخدمة في التشييد�
تطور المعدات بتطور وقودھا وتعقد العمليات ا2نشائية�
زيادة حجم المشروعات ا2نشائية بتطور طرق التصميم و التنفيذ�
تعقد المشروعات مما تطلب عدد أكبر من العمال و المھندسين و ا2داريين�
![Page 28: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/28.jpg)
Main Construction Parties
28
� Client / owner
� Constructor/Contractor
� Designer / Consultant
Others:
� Project manager
� Users
� Public authorities
![Page 29: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/29.jpg)
Main Tasks of Project Participants
29
):Owner(المالك �.عمل دراسات الجدوي�
.إيجاد التمويل ال�زم�
.بحث نوع العقد المناسب للتعاقد�
.طربقة إختيار المقاول المناسب�
.وضع مواصفات التصميم�
وضع معايير تقييم الجودة�
![Page 30: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/30.jpg)
Main Tasks of Project Participants
30
):Designer(المصمم �
.تعريف المشروع علي لوحات�
.عمل الھيكل التنظيمي�
.عمل نظام المراقبة والجودة�
.عمل البرنامج الزمني للتسليم�
.عمل تقدير التكلفة�
![Page 31: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/31.jpg)
Main Tasks of Project Participants
31
):Contractor(المقاول �.مراجعة اللوحات و المواصفات�
.عمل الھيكل التنفيذي للمشروع�
.إختيار طرق التنفيذ�
.عمل البرنامج الزمني�
.عمل تقدير التكلفة�
.تنفيذ المشروع�
Constructor, General contractor, Prime contractor, Builder.
![Page 32: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/32.jpg)
Types of Construction Projects
32
� Residential projects
ا:براج السكنية -الفي�ت -مثل المساكن %)٤٥-٤٠(منشأت سكنية
� Building construction projects
-المنشأت الدينية -الجامعات -مثل المدارس%) ٣٠-٢٥( منشأت غير سكنيةالمستشفيات
� Heavy construction projects
المطارات -الطرق -الكباري -ا:نفاق -مثل السدود%) ٢٥-٢٠(منشأت ھندسية
� Industrial projects
منشأت بترولية -محطات الطاقة -مثل المصانع %)١٠-٥( منشأت صناعية
![Page 33: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/33.jpg)
Construction Project Cycle
33
� Preconstruction phase� Conceptual planning
� Schematic design
� Design development
� Contract documents preparation
� Procurement phase
� Construction phase
� Project Closeout
![Page 34: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/34.jpg)
Assignment 1
34
� Write a one page Curriculum Vita (CV) to present to the employers at the coming ZU Job Fair .
� Make sure to include:
� Your personal data including your photo, whenever possible.
� Show your academic grade.
� Explain your future goals in this career.
� Hint: Search the internet on how to write a resume.
![Page 35: 1.Introduction CUE321 2014 - Dr. Ahmed H. Elyamanydrahmedelyamany.weebly.com/.../1/0/7010103/1.introduction_cue321… · 4 Construction contracts 5 Techniques of planning 6 Techniques](https://reader034.fdocuments.net/reader034/viewer/2022051800/5ac22b997f8b9aca388ded07/html5/thumbnails/35.jpg)
Questions?
Dr. Ahmed Elyamany
Cell: 010-94-100-824
Email: [email protected]
Web page: http://drahmedelyamany.weebly.com/
35