Due Diligence and Contamination Management on Design Build Projects
Cyrus Parker, LG, PE, CPM
North Carolina Department of Transportation
Lesson Learned
Reduce Risk
Maintain Accountability
Meaningful Bids
And
Successful Projects
5/5/2015
2
NC Design Build Project History
102 Projects
39 Low Bid and Others
4 Turnpike Projects
59 Conventional
Projects
NC Design Build History
Conventional Projects With GeoEnvironmental Scopes of Work
40%
60%
Yes
No
5/5/2015
3
Due Diligence by the Department
• Identify Sites of Concern• Estimate Risk Level of Each Site
Related to the Project
Phase I
Planning
• Design Recommendations• Right of Way Recommendations
Phase II Investigation
• Remove Underground Storage Tank• Remove Contaminated Soil
Phase III Remediation
IIIIII
5/5/2015
4
First Design Build Scope of Work
Department Design Build Team
Design Build Teams’ Response
Questions
How can we bid a
Lump Sum
Too Many UnknownsConcerns
Very High Risk
5/5/2015
5
First Design Build Scope of Work
Department Design Build Team
Final Scope of Work
Department Design Build Team
5/5/2015
6
Adjusted Low
BidderManagement
Responsiveness
Long Term Maintenance
Schedule And Milestones Innovation
Quality
Aesthetics
Warranty
5/5/2015
7
5/5/2015
8
5/5/2015
9
5/5/2015
10
5/5/2015
11
5/5/2015
12
5/5/2015
13
5/5/2015
14
1978 Aerial
5/5/2015
15
1987 Aerial
2007Aerial
5/5/2015
16
5/5/2015
17
5/5/2015
18
5/5/2015
19
5/5/2015
20
5/5/2015
21
5/5/2015
22
5/5/2015
23
5/5/2015
24
5/5/2015
25
Contamination Management
Landfill
5/5/2015
26
5/5/2015
27
Reduce Risk
Maintain Accountability
Meaningful Bids
and
Successful Projects