1802 Nuna BP Washington USA - Concrete Canvas

4
® © Concrete Canvas Ltd. 2017 The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express www.concretecanvas.com [email protected] +44 (0) 345 680 1908 www ® *Geosynthetic Cementitious Composite Mat i # OCT 27 Project Info CC5 TM Bulk Rolls Transverse layers CC5 TM was used as a hard armour capping for a secondary containment berm Western Refinery Service (WRS) Mount Vernon Washington, USA 5,200m² 27 / 10 / 14 Completed section of bund In October 2014, Concrete Canvas ® GCCM* (CC) was to protect and provide erosion prevention at a refinery site in Washington, USA. Industry safety protocols state that berms must maintain a minimum height in order to provide effective secondary containment. Previously, asphalt had been used to protect the berm, however this incurred high maintenance costs due to re-coating every 5-7 years to repair cracking, as well as patch repair work throughout the year. CC has a 50 year life-span and requires little to no maintenance, promising significant cost savings. Additionally, CC offers hydrocarbon resistance to BS:14414, as well as UV resistance and weed suppression characteristics which suppress growth, reduce maintenance costs, and prevent the fire hazards that vegetation can pose. The works were carried out by Western Refinery Services. Bulk rolls of CC5 TM were placed at the crest of the berm and unrolled down one side, and then the other. This process was repeated along the berm, with a 100mm overlap created between layers, which was sealed with Sika 1-A sealant, and screwed using 20mm self tapping screws at 300mm intervals. On the inside of the bund, the CC edges were placed into an anchor trench and captured with concrete paving. On the outer edges, masonry bolts were used to fix the CC to the existing concrete infrastructure.

Transcript of 1802 Nuna BP Washington USA - Concrete Canvas

Page 1: 1802 Nuna BP Washington USA - Concrete Canvas

®

© Concrete Canvas Ltd. 2017The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express

[email protected]+44 (0) 345 680 1908 www®

*Geosynthetic Cementitious Composite Mat

i

#

OCT

27

Project Info

CC5TM Bulk Rolls

Transverse layers

CC5TM was used as a hard armour capping for a secondary containment berm

Western Refi nery Service (WRS)

Mount Vernon Washington, USA

5,200m²

27 / 10 / 14

Completed section of bund

In October 2014, Concrete Canvas® GCCM* (CC) was to protect and provide erosion prevention at a refi nery site in Washington, USA.

Industry safety protocols state that berms must maintain a minimum height in order to provide eff ective secondary containment. Previously, asphalt had been used to protect the berm, however this incurred high maintenance costs due to re-coating every 5-7 years to repair cracking, as well as patch repair work throughout the year. CC has a 50 year life-span and requires little to no maintenance, promising signifi cant cost savings. Additionally, CC off ers hydrocarbon resistance to BS:14414, as well as UV resistance and weed suppression characteristics which suppress growth, reduce maintenance costs, and prevent the fi re hazards that vegetation can pose.

The works were carried out by Western Refi nery Services.

Bulk rolls of CC5TM were placed at the crest of the berm and unrolled down one side, and then the other. This process was repeated along the berm, with a 100mm overlap created between layers, which was sealed with Sika 1-A sealant, and screwed using 20mm self tapping screws at 300mm intervals. On the inside of the bund, the CC edges were placed into an anchor trench and captured with concrete paving. On the outer edges, masonry bolts were used to fi x the CC to the existing concrete infrastructure.

Page 2: 1802 Nuna BP Washington USA - Concrete Canvas

®

© Concrete Canvas Ltd. 2017The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express

[email protected]+44 (0) 345 680 1908 www®

Hydration from the watermainsSealing the overlap with Sika1-A sealant

Cracked asphalt

Using sandbags to increase the height of the berm

Spooling the CC down the bund

Cutting the CC to length with a utility knife

Page 3: 1802 Nuna BP Washington USA - Concrete Canvas

®

© Concrete Canvas Ltd. 2017The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express

[email protected]+44 (0) 345 680 1908 www®

The finished installationThe finished installation

Sealing around piping

Piping detail

Piping detail

CC accomodating infrastructure

Page 4: 1802 Nuna BP Washington USA - Concrete Canvas

®

© Concrete Canvas Ltd. 2017The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express

[email protected]+44 (0) 345 680 1908 www®

Stair detail Corner detail

In areas where the bund had eroded to the extent it no longer met the height requirements, sandbags were used to fill any voids before the CC was deployed. Infrastructure such as pipework was easily accommodated due to the flexibility of CC; holes were cut for the pipes, and where needed, an extra layer of CC was fitted around them and sealed. The CC was hydrated using a high volume mounted hose attached to a water hydrant.

5,200m2 of CC5TM were installed by a team of 8 in just 7 days. The completion of this project has resulted in drastically reduced maintenance costs, improved impermeability and improved fire resistance of the berm. Infrastructure, corner details and pipe protrusions were simple to accommodate resulting in an easy and rapid install. The client has said they are “very happy” with the outcome of the project and they are looking to install CC on other bunds in their vast oil and gas network.