หนวยที่ 15 บทบาทของภาครัฐกับการ ... · 2016-07-12 · 15.1 บทบาทของภาครัฐในภาพรวม
15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project...
Transcript of 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project...
![Page 1: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/1.jpg)
EIA Report Wan Chai Development Phase II
Volume 1 and Central-Wan Chai Bypass
97103_EIA9 (Dec07)
Maunsell 15-1
15 CONCLUSION
15.1 Introduction
15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which
specifies an “engineering feasibility study of urban development projects with a study area
covering more than 20 ha or involving a total population of more than 100,000”. The Project also
includes various individual designated projects defined in Schedule 2 of the EIAO including the
followings:
• DP1 - Central-Wanchai Bypass including its road tunnel (Items A.1 and A.7 of Part I of Schedule 2 of the EIAO)
• DP2 - WDII major roads (including Road P2) (Item A.1 of Part I of Schedule 2 of the
EIAO) • DP3 - Reclamation works including associated dredging works (Item C.1 of Part I of
Schedule 2 of the EIAO) • DP4 - Temporary typhoon shelter (Item C.5 of Part I, Schedule 2 of the EIAO) • DP5 - Wan Chai East Sewage Outfall (Item F.5 and F.6 of Part I of Schedule 2 of the
EIAO) • DP6 - Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui (Item C.12 of Part I
of Schedule 2 of the EIAO); and
15.1.2 This EIA Report has provided an assessment of the potential environmental impacts associated
with the construction and operation of the Project, with the consideration of the potential
cumulative impact from other projects including the Central Reclamation Phase III (CRIII) and
Hong Kong Convention and Exhibition Centre Atrium Link Extension projects. Since the details
of the potential future railway projects, i.e. Shatin to Central Link (SCL) and North Hong Kong
Island Line (NIL) were not available at the time of this EIA study, the cumulative impacts from
these two railway projects could not be addressed. Specific mitigation measures requirements for
the Project, as well as an environmental monitoring and auditing programme, have been
developed during the assessment of the proposed developments. The Implementation Schedule
of the recommendations is presented in Section 13. A summary of the environmental impacts
associated with the Project are present in Table 15.1. The key assessment assumptions, limitation
of assessment methodologies and all obtained relevant prior agreements with the EPD or other
authorities on individual environmental media assessment components are given in Appendix
15.1. The key environmental outcomes arising from the EIA study and the principal findings of
the study are summarized in Section 15.2.
![Page 2: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/2.jpg)
Wan C
hai D
evelo
pm
ent
Ph
ase I
I
EIA
Report
and C
entr
al-W
an C
hai B
ypass
Volu
me 1
9
71
03
_E
IA9
(D
ec0
7)
15-2
Maunsell
Tab
le 1
5.1
S
um
mary
of
En
vir
on
men
tal
Imp
act
s A
ssoci
ate
d w
ith
th
e P
roje
ct
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
Air
Qu
ali
ty
Co
nst
ruct
ion
Phas
e 4
8 a
sses
smen
t p
oin
ts
1-h
our
Aver
age
TS
P C
onc.
:
88
-43
4 µ
g/m
3
24
-ho
ur
Aver
age
TS
P C
onc.
:
82
-23
1µ
g/m
3
EIA
O-T
M a
nd
Air
Q
ual
ity O
bje
ctiv
e N
il
Fo
ur
tim
es
dai
ly w
ate
rin
g
wit
h c
om
ple
te c
over
age
of
acti
ve
con
stru
cti
on a
rea
Req
uir
em
ents
of
the
Air
P
oll
uti
on C
on
tro
l (C
onst
ruct
ion D
ust
) R
egula
tio
n
The
foll
ow
ing m
itig
ati
on
mea
sure
s, g
oo
d s
ite
pra
ctic
es a
nd
a
com
pre
hen
sive
dust
m
onit
ori
ng a
nd
aud
it
pro
gra
mm
e ar
e re
com
mend
ed t
o
min
imis
e cu
mula
tive
dust
im
pac
ts.
•
Str
ictl
y
lim
it
the
truck
sp
eed
on s
ite
to
bel
ow
1
0
km
p
er
ho
ur
and
w
ate
r
spra
yin
g t
o k
eep
the
hau
l ro
ads
in
wet
cond
itio
n;
Nil
![Page 3: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/3.jpg)
EIA
Report
W
an C
hai D
evelo
pm
ent
Ph
ase I
I
Volu
me 1
and C
entr
al-W
an C
hai B
ypass
97
10
3_
EIA
9 (
De
c0
7)
Maunsell
15-3
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
•
Wat
erin
g
duri
ng
exca
vati
on
and
mat
eria
l han
dli
ng;
•
Pro
vis
ion
of
veh
icle
wh
eel
and
b
od
y
wash
ing
faci
liti
es
at
the
exit
po
ints
of
the
site
, co
mb
ined
w
ith
clea
nin
g
of
pub
lic
road
s w
her
e
nec
essa
ry;
and
•
Tar
pau
lin
cover
ing
of
all
dust
y
vehic
le
load
s tr
ansp
ort
ed to
,
fro
m
and
b
etw
een
site
lo
cati
on
s.
Op
erat
ional
P
has
e 5
6 a
sses
smen
t p
oin
ts
1-h
our
Aver
age
NO
2 C
onc.
:
73
-25
5 µ
g/m
3
24
-ho
ur
Aver
age
NO
2 C
onc.
:
62
-13
5 µ
g/m
3
24
-ho
ur
Aver
age
RS
P C
onc.
:
56
-78
µg/m
3
Air
Qual
ity O
bje
ctiv
e N
il
No
t A
pp
lica
ble
N
il
![Page 4: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/4.jpg)
Wan C
hai D
evelo
pm
ent
Ph
ase I
I
EIA
Report
and C
entr
al-W
an C
hai B
ypass
Volu
me 1
9
71
03
_E
IA9
(D
ec0
7)
15-4
Maunsell
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
CW
B T
unnel
– a
chie
ve
EP
D
reco
mm
end
ed s
tand
ard
of
1 p
pm
N
O2 c
once
ntr
atio
n
EP
D T
unnel
Air
Q
ual
ity G
uid
elin
es
Nil
N
ot
Ap
pli
cab
le
Nil
A
ir q
ual
ity i
nsi
de
CW
B T
unnel
&
dec
ko
ver
fo
r p
lanned
HK
CE
C
Atr
ium
Lin
k
Dec
ko
ver
on A
triu
m L
ink –
th
e p
red
icte
d m
axim
um
NO
2
conce
ntr
atio
ns
(5 m
inu
tes
aver
age)
und
er n
orm
al t
raff
ic
flo
w a
nd
co
nges
ted
tra
ffic
flo
w
wo
uld
be
11
4µ
g/m
3 a
nd
13
0µ
g/m
3 re
spec
tivel
y.
Pla
nned
AS
R –
O
pen
sp
ace
wit
h
sen
siti
ve
use
at
the
west
of
HK
CE
C
and
No
rther
n
Bre
akw
ater
of
CB
TS
bre
akw
ater
, an
d w
ate
rfro
nt
rela
ted
co
mm
erci
al
and
lei
sure
use
s an
d W
ater
Sp
ort
s C
entr
e at
Wan
chai
The
pre
dic
ted o
do
ur
conce
ntr
atio
ns
ran
ge
fro
m 1
.5 t
o
29
ou/m
3 o
ver
aver
agin
g t
ime
of
5 s
eco
nd
s u
nd
er w
ors
t ca
se
cond
itio
n.
EIA
O-T
M
Exce
ed t
he
od
our
crit
erio
n u
p t
o 2
9
ou/m
3
The
Pro
ject
its
elf
wo
uld
no
t in
tro
duce
an
y
add
itio
nal
od
our
emis
sio
n
sourc
es w
ithin
the
stud
y
area
. O
do
ur
nuis
ance
as
soci
ated
wit
h t
he
Cau
sew
ay B
ay T
yp
ho
on
Shel
ter
is a
n e
xis
tin
g
env
iro
nm
enta
l p
rob
lem
an
d a
dver
se o
do
ur
imp
acts
in t
he
vic
init
y o
f C
BT
S w
ould
be
exp
ecte
d
duri
ng w
ors
t ca
se
cond
itio
ns.
T
he
po
tenti
al
od
our
imp
act
wo
uld
lik
ely
be
min
imiz
ed b
y t
he
foll
ow
ing
mit
igat
ion
mea
sure
s:
Res
idual
od
our
imp
act
is
pre
dic
ted
at
the
pla
nned
A
SR
s fo
r ar
ound
0.1
% t
o
0.2
% o
f ti
me
in a
yea
r,
und
er w
ors
t ca
se
met
eoro
logic
al a
nd
tid
al
cond
itio
ns.
F
or
the
oth
er
AS
Rs,
ther
e is
als
o a
0
.1%
pro
bab
ilit
y t
hat
the
actu
al o
do
ur
level
s as
p
erce
ived
at
the
AS
Rs
wo
uld
exce
ed t
he
pre
dic
ted
od
our
conce
ntr
atio
n (
takin
g i
nto
ac
count
of
0.1
%
pro
bab
ilit
y o
f exce
edin
g
the
pre
dic
ted
od
our
conce
ntr
atio
n i
nher
ent
in
the
calc
ula
tio
n
met
ho
d).
This
sit
uat
ion i
s no
t ex
pec
ted
to
res
ult
in
![Page 5: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/5.jpg)
EIA
Report
W
an C
hai D
evelo
pm
ent
Ph
ase I
I
Volu
me 1
and C
entr
al-W
an C
hai B
ypass
97
10
3_
EIA
9 (
De
c0
7)
Maunsell
15-5
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
�
Imp
lem
enta
tio
n o
f en
hance
ment
pac
kag
e fo
r ex
isti
ng
od
our
sourc
es
iden
tifi
ed a
t C
BT
S
as d
etai
ls i
n
Ap
pen
dix
15
.1
unac
cep
tab
ly a
dver
se
od
our
imp
act.
No
ise
Do
mes
tic
pre
mis
es:
7
5d
B(A
)
Do
mes
tic
pre
mis
es:
E
xce
ed t
he
no
ise
stan
dar
d b
y u
p t
o
26
dB
(A).
Co
nst
ruct
ion
Phas
e N
1,
N2
, N
3,
N6
, N
8,
N1
1,
N13
, N
15
, N
17
, N
18
, N
20
and
N2
2
Pre
dic
ted
no
ise
level
s w
ould
be
in t
he
range
of
57
to
101
dB
(A).
Ed
uca
tio
nal
in
stit
uti
on
s: 7
0 d
B
(A)
duri
ng n
orm
al
teac
hin
g p
erio
ds
&
65
dB
(A)
duri
ng
exam
inati
ons
Ed
uca
tio
nal
in
stit
uti
on
s: E
xce
ed
the
no
ise
stand
ard
by
20
dB
(A)
duri
ng
no
rmal
tea
chin
g
per
iod
and
up
to
25
d
B(A
) d
uri
ng
exam
inati
on p
erio
d.
Use
of
quie
t eq
uip
ment,
m
ovab
le/t
em
po
rary
no
ise
bar
rier
s an
d P
ME
gro
up
ing t
o m
inin
ise
const
ructi
on n
ois
e im
pac
t
Fo
r N
11
(M
ayso
n
Gar
den
), t
he
pre
dic
ted
no
ise
level
wo
uld
exce
ed
the
no
ise
stand
ard
of
75
d
B(A
) fo
r 1
mo
nth
by 1
0
dB
(A)
wit
h G
roup
2
PM
E.
Fo
r N
17
(H
arb
our
Hei
ghts
), t
he
pre
dic
ted
no
ise
level
wo
uld
exce
ed
the
no
ise
stand
ard
of
75
d
B(A
) b
y u
p t
o 5
dB
(A)
wit
h G
roup
1 o
r G
roup
2
PE
M f
or
a to
tal
of
8
wee
ks.
![Page 6: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/6.jpg)
Wan C
hai D
evelo
pm
ent
Ph
ase I
I
EIA
Report
and C
entr
al-W
an C
hai B
ypass
Volu
me 1
9
71
03
_E
IA9
(D
ec0
7)
15-6
Maunsell
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
Fo
r N
18
(C
ity G
ard
en),
th
e p
red
icte
d n
ois
e le
vel
w
ould
exce
ed t
he
no
ise
stan
dar
d o
f 7
5 d
B(A
) b
y
up
to
9 d
B(A
) w
ith G
roup
1
or
Gro
up
2 P
ME
fo
r a
tota
l o
f 1
6 w
eek
s.
Fo
r N
20
(H
ong K
ong
Bap
tist
Ch
urc
h H
enri
etta
S
eco
nd
ary S
cho
ol)
, th
e p
red
icte
d n
ois
e le
vel
wit
h
Gro
up
1 o
r G
roup
2 P
ME
w
ould
exce
ed t
he
no
ise
stan
dar
d o
f 6
5 d
B(A
) b
y
up
to
12
dB
(A)
duri
ng
exam
inati
on p
erio
ds
for
a to
tal
of
28
wee
ks
in 2
00
9,
20
13
and
20
15
. F
or
the
no
rmal
tea
chin
g p
erio
d,
th
e no
ise
level
wo
uld
ex
ceed
the
no
ise
stand
ard
o
f 7
0 d
B(A
) b
y 7
dB
(A)
wit
h G
roup
1 o
r G
roup
2
PM
E f
or
13.5
wee
ks.
![Page 7: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/7.jpg)
EIA
Report
W
an C
hai D
evelo
pm
ent
Ph
ase I
I
Volu
me 1
and C
entr
al-W
an C
hai B
ypass
97
10
3_
EIA
9 (
De
c0
7)
Maunsell
15-7
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
Op
erat
ional
P
has
e N
1 t
o N
23
and
P1
to
P3
D
om
esti
c p
rem
ises:
7
0 d
B(A
)
Ed
uca
tio
nal
in
stit
uti
on
s an
d a
ll
oth
ers
wher
e unai
ded
vo
ice
com
mu
nic
atio
n
is r
equir
ed:
65
dB
(A)
Do
mes
tic
pre
mis
es:
E
xce
ed t
he
no
ise
stan
dar
d b
y u
p t
o
17
dB
(A).
Ed
uca
tio
n i
nst
ituti
on:
Exce
ed t
he
no
ise
stan
dar
d b
y u
p t
o
12
dB
(A)
Pla
ces
of
pub
lic
wo
rship
: 6
5 d
B(A
)
Pla
ces
of
pub
lic
wo
rship
: E
xce
ed t
he
no
ise
stand
ard
by
7d
B(A
).
NS
Rs
N1
– N
5:
60
– 8
7 d
B(A
)
NS
Rs
N6
- N
8:
78
– 8
5 d
B(A
)
NS
Rs
N9
– N
17
and
P1
: 65
– 8
1
dB
(A)
NS
Rs
N1
8 –
N2
3, P
2 a
nd
P3
: 6
5 –
81
dB
(A)
1.
Ab
out
50
0m
leng
th o
f no
ise
sem
i-encl
osu
re
wit
h t
ransp
aren
t p
anel
co
ver
ing t
he
west
bo
und
sli
p r
oad
fr
om
the
IEC
2.
Ab
out
23
0m
leng
th o
f
no
ise
sem
i-encl
osu
re
wit
h t
ransp
aren
t p
anel
cover
ing t
he
mai
n
carr
iagew
ays
(eas
tbo
und
and
w
est
bo
und
) o
f th
e C
WB
and
IE
C
3.
Ab
out
13
5m
leng
th o
f 5
.5.m
hig
h
canti
lever
ed n
ois
e b
arri
er w
ith 3
m
canti
lever
wit
h
tran
spar
ent
pan
el
incl
ined
at
45
° o
n t
he
east
bo
und
sli
p r
oad
to
th
e IE
C.
Wit
h t
he
pro
po
sed
no
ise
mit
igat
ion m
easu
res
in
pla
ce,
the
‘New
’ ro
ad
no
ise
contr
ibuti
on
s to
the
over
all
no
ise
level
s at
all
re
pre
senta
tive
NS
Rs
wo
uld
be
less
than 1
.0
dB
(A)
and
the
‘New
’ ro
ad
no
ise
level
s w
ould
all
be
bel
ow
the
rele
van
t no
ise
crit
eria
. N
o a
dver
se n
ois
e im
pac
ts a
risi
ng f
rom
the
‘New
’ ro
ads
are
pre
dic
ted
at
rep
rese
nta
tive
NS
Rs.
N
ois
e ex
ceed
ance
s at
the
rep
rese
nta
tive
NS
Rs,
if
any,
wo
uld
be
due
to t
he
exis
tin
g r
oad
s.
![Page 8: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/8.jpg)
Wan C
hai D
evelo
pm
ent
Ph
ase I
I
EIA
Report
and C
entr
al-W
an C
hai B
ypass
Volu
me 1
9
71
03
_E
IA9
(D
ec0
7)
15-8
Maunsell
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
4
. A
bo
ut
95
m l
en
gth
of
5.5
.m h
igh
canti
lever
ed n
ois
e b
arri
er w
ith 1
m
canti
lever
wit
h
tran
spar
ent
pan
el
incl
ined
at
45
° o
n t
he
east
bo
und
sli
p r
oad
to
th
e IE
C.
5
. A
bo
ut
35
0m
leng
th o
f 3
.5.m
hig
h v
erti
cal
no
ise
bar
rier
wit
h
tran
spar
ent
pan
el
on
the
east
bo
und
sli
p r
oad
to
the
IEC
.
6
. lo
w n
ois
e ro
ad
surf
acin
g f
or
the
tru
nk
road
(ex
cep
t tu
nnel
se
ctio
n a
nd
ben
eath
th
e la
nd
scap
ed d
eck a
t th
e ea
ster
n p
ort
al a
rea)
w
ith s
pee
d l
imit
of
70
k
m/h
our
![Page 9: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/9.jpg)
EIA
Report
W
an C
hai D
evelo
pm
ent
Ph
ase I
I
Volu
me 1
and C
entr
al-W
an C
hai B
ypass
97
10
3_
EIA
9 (
De
c0
7)
Maunsell
15-9
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
7
. T
he
op
enab
le w
ind
ow
s o
f th
e re
-pro
vis
ioned
T
in H
au T
emp
le,
if
any,
sho
uld
be
ori
enta
ted
so
as
to
avo
id d
irec
t li
ne
of
sig
ht
to t
he
exis
ting
Vic
tori
a P
ark R
oad
as
far
as p
ract
icab
le
Wa
ter
Qu
ali
ty
The
mo
del
res
ult
s in
dic
ate
exce
edan
ces
of
WS
D w
ater
q
ual
ity (
SS
) cr
iter
ion f
or
flush
ing w
ater
inta
kes
(at
K
enned
y T
ow
n,
Ko
wlo
on S
ou
th,
Quar
ry B
ay,
Sai
Wan
Ho
, S
heun
g W
an,
Tai
Wan
and
Wan
C
hai
) and
tar
get
SS
level
(at
A
dm
iral
ty C
entr
e an
d M
TR
C
coo
ling w
ater
inta
kes)
.
WS
D w
ater
qual
ity
crit
erio
n f
or
SS
: <
10
m
g/l
Res
tric
tio
n o
n t
he
maxim
um
dre
dgin
g r
ates
at
the
sew
age
pip
elin
es
zone,
wat
er m
ains
zone,
T
WB
, T
PC
WA
, H
KC
EC
S
tage
1 &
3 a
s w
ell
as
the
west
ern s
eaw
all
of
WC
R1
w
hic
h i
s cl
ose
to
the
WS
D i
nta
ke
at W
an C
hai
;
Co
nst
ruct
ion
Phas
e A
ll w
ater
se
nsi
tivit
y
rece
iver
s in
V
icto
ria
Har
bo
ur,
W
este
rn B
uff
er a
nd
E
aste
rn B
uff
er
WC
Zs
Full
co
mp
lian
ce w
ith t
he
asse
ssm
ent
crit
erio
n f
or
sed
imenta
tio
n r
ate
Tar
get
SS
lev
el a
t A
dm
iral
ty C
entr
e an
d
MT
RC
co
oli
ng w
ater
in
takes
: <
40
mg/l
Full
co
mp
lian
ce w
ith
the
asse
ssm
ent
crit
eria
w
ith t
he
imp
lem
enta
tio
n o
f m
itig
atio
n m
easu
res.
Dep
loym
ent
of
silt
cu
rtai
ns
aro
und
sea
wal
l d
red
gin
g a
nd
sea
wal
l tr
ench
fil
lin
g i
n N
PR
, T
CB
R,
WC
R a
nd
H
KC
EC
are
as.
Nil
![Page 10: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/10.jpg)
Wan C
hai D
evelo
pm
ent
Ph
ase I
I
EIA
Report
and C
entr
al-W
an C
hai B
ypass
Volu
me 1
9
71
03
_E
IA9
(D
ec0
7)
15-1
0
Maunsell
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
Sed
imenta
tio
n r
ate
at
cora
ls:
<1
00
g/m
2/d
ay
Dep
loym
ent
of
silt
sc
reen
s at
sel
ecte
d
seaw
ater
inta
kes
Rel
evant
WQ
O f
or
mar
ine
wate
r:
TIN
lev
el:
<0
.4 m
g/l
fo
r an
nual
mea
n
UIA
level
: <
0.0
21
m
g/l
fo
r an
nual
mea
n
Dep
th-a
ver
aged
DO
le
vel
: >
4 m
g/l
fo
r 1
0th
per
centi
le
Bo
tto
m D
O l
evel
:
> 2
mg/l
fo
r 1
0th
p
erce
nti
le
Op
erat
ional
P
has
e A
ll w
ater
se
nsi
tivit
y
rece
iver
s in
V
icto
ria
Har
bo
ur,
W
este
rn B
uff
er a
nd
E
aste
rn B
uff
er
WC
Zs
Op
erat
ion o
f W
DII
and
CW
B
wo
uld
no
t ca
use
unac
cep
tab
le
imp
acts
up
on t
he
wate
r q
ual
ity
in V
icto
ria
Har
bo
ur
Tem
per
ature
in
crea
se:
< 2
oC
fro
m
bac
kgro
und
No
WQ
O e
xce
edan
ce
is i
nd
uce
d b
y t
he
Pro
ject
No
mit
igat
ion m
easu
res
are
consi
der
ed n
eces
sary
. N
il
![Page 11: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/11.jpg)
EIA
Report
W
an C
hai D
evelo
pm
ent
Ph
ase I
I
Volu
me 1
and C
entr
al-W
an C
hai B
ypass
97
10
3_
EIA
9 (
De
c0
7)
Maunsell
15-1
1
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
Wa
ste
Ma
na
gem
en
t Im
pli
cati
on
s
Co
nst
ruct
ion
Phas
e N
ot
app
lica
ble
M
ain
wast
e:
dre
dged
m
arin
e
sed
iment
wit
h a
to
tal
vo
lum
e o
f ap
pro
x.
1.1
5M
m3.
1.
Was
te D
isp
osa
l O
rdin
ance
(C
ap.
35
4)
No
t ap
pli
cab
le
Ref
er t
o T
able
14.4
N
il
2.
Was
te D
isp
osa
l (C
hem
ical
Was
te)
(Gen
eral
) R
egula
tio
n (
Cap
. 3
54
)
3.
Land
(M
isce
llan
eous
Pro
vis
ions)
O
rdin
ance
(C
ap.
28
)
Oth
er
wast
es:
gen
eral
re
fuse
fr
om
th
e w
ork
forc
e;
chem
ical
w
ast
e fr
om
pla
nt
and
eq
uip
men
t m
ainte
nan
ce;
and
C&
D m
ateri
al
fro
m exca
vat
ion
w
ork
s an
d th
e
dem
oli
tio
n o
f exis
ting s
truct
ure
s.
4.
Pub
lic
Hea
lth a
nd
M
un
icip
al
Ser
vic
es
Ord
inan
ce (
Cap
. 1
32
) -
Pub
lic
Cle
ansi
ng a
nd
P
reven
tio
n o
f N
uis
ance
s R
egula
tio
n
5
. A
nnex
es
7 &
15
o
f E
IAO
TM
![Page 12: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/12.jpg)
Wan C
hai D
evelo
pm
ent
Ph
ase I
I
EIA
Report
and C
entr
al-W
an C
hai B
ypass
Volu
me 1
9
71
03
_E
IA9
(D
ec0
7)
15-1
2
Maunsell
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
La
nd
Co
nta
min
ati
on
Im
pa
ct
So
urc
e o
f la
nd
co
nta
min
atio
n
fro
m p
ast
land
use
s o
f A
Kin
g
Mar
ine
Ship
yar
d.
Po
tenti
al l
and
co
nta
min
atio
n i
mp
acts
mig
ht
occ
ur
as a
res
ult
of
hand
lin
g
conta
min
ated
so
il b
y
const
ructi
on w
ork
ers
duri
ng t
he
rem
edia
tio
n w
ork
s at
A K
ing
Mar
ine.
Co
nst
ruct
ion
Phas
e C
onst
ruct
ion
Wo
rker
s via
dir
ect
inges
tio
n o
f an
d
der
mal
co
nta
ct
wit
h c
on
tam
inat
ed
soil
s.
It i
s ex
pec
ted
that
land
co
nta
min
atio
n i
mp
acts
wo
uld
be
min
imal
if
the
pro
po
sed
m
itig
atio
n m
easu
res
wer
e p
rop
erly
im
ple
mente
d.
Pro
PE
CC
PN
3/9
4 -
“
Co
nta
min
ate
d L
an
d
Ass
ess
men
t a
nd
R
em
ed
iati
on
”
“G
uid
an
ce N
ote
s fo
r In
vest
iga
tio
n a
nd
R
em
ed
iati
on
of
Co
nta
min
ate
d S
ites
of:
Petr
ol
Fil
lin
g
Sta
tio
ns,
Bo
aty
ard
s,
an
d C
ar
Rep
air
/D
ism
an
tlin
g
Wo
rksh
op
s
Fiv
e co
nta
min
ated
ar
eas
(One
area
wit
h
hea
vy m
etal
s and
TP
H
and
4 a
reas
wit
h h
eav
y
area
s o
nly
) w
ere
iden
tifi
ed.
The
esti
mat
ed q
uan
tity
of
soil
co
nta
min
ati
on i
s 6
33
m3
Ref
er t
o T
able
14.5
A
fter
ap
pro
pri
ate
rem
edia
tio
n a
ctio
ns
(if
req
uir
ed)
hav
e b
een
com
ple
ted
, A
Kin
g
Mar
ine
wil
l b
e cl
eaned
up
to
acc
epta
ble
sta
nd
ard
s an
d n
o a
dver
se i
mp
act
wo
uld
be
envis
aged
.
Ma
rin
e E
colo
gic
al
Imp
act
s
Co
nst
ruct
ion
Phas
e E
colo
gic
al
reso
urc
es i
n t
he
asse
ssm
ent
area
Hab
itat
lo
ss
- P
erm
anen
t: 1
2.7
ha
soft
b
ott
om
ben
thic
& s
ub
tid
al
hab
itat
& 1
km
art
ific
ial
inte
rtid
al h
abit
at
No
t ap
pli
cab
le
No
t ap
pli
cab
le
Avo
idan
ce
- R
evis
ed d
esig
n o
f al
tern
ativ
e T
runk
Ro
ad c
onst
ruct
ed i
n
tunnel
to
avo
id
per
manent
loss
of
larg
e ar
ea o
f m
arin
e
hab
itat
s
No
ad
ver
se r
esid
ual
im
pac
t as
lo
ss o
f ap
pro
xim
ate
ly 1
2.7
ha
of
soft
bo
tto
m b
enth
ic a
nd
su
bti
dal
hab
itats
due
to
per
manent
recl
am
ati
on
wo
rks
are
of
ver
y l
ow
ec
olo
gic
al v
alue
![Page 13: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/13.jpg)
EIA
Report
W
an C
hai D
evelo
pm
ent
Ph
ase I
I
Volu
me 1
and C
entr
al-W
an C
hai B
ypass
97
10
3_
EIA
9 (
De
c0
7)
Maunsell
15-1
3
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
Min
imiz
atio
n
- T
ransl
oca
tio
n o
f al
l
cora
l co
lonie
s fo
und
w
ithin
the
recl
am
atio
n a
reas
- T
emp
ora
ry:
10
.7 h
a so
ft
bo
tto
m b
enth
ic &
sub
tid
al
hab
itat
& 8
50
m a
rtif
icia
l in
tert
idal
hab
itat
- M
itig
atio
n m
easu
res
to c
ontr
ol
wat
er
qual
ity
Chan
ges
in w
ater
qual
ity
- M
ore
than
30
% i
ncr
ease
of
SS
at
the
imm
edia
te v
icin
ity
outs
ide
recl
am
ati
on a
rea
- In
sign
ific
ant
elevat
ion o
f S
S
at f
ar-f
ield
sensi
tive
rece
iver
s
- L
evel
of
TIN
is
pre
dic
ted
to
b
e sl
ightl
y h
igher
than
WQ
O s
tand
ard
at
sever
al
loca
tio
ns
imm
edia
tely
o
uts
ide
recl
am
ati
on a
rea
- M
inim
um
dep
th-a
ver
aged
D
O a
t H
KC
EC
is
pre
dic
ted
to
be
slig
htl
y l
ow
er t
han
4.0
m
g/L
(See
wat
er q
ual
ity
asse
ssm
ent)
(See
wat
er q
ual
ity
asse
ssm
ent)
- M
itig
atio
n m
easu
res
to a
vo
id d
istu
rban
ce
imp
act
to n
earb
y
wat
erb
ird
po
pula
tio
n
Oth
er M
easu
res
- C
onst
ruct
ion o
f ab
out
1 k
m n
ew
ver
tica
l w
ave
abso
rbin
g
seaw
all
to r
eco
ver
lo
ss o
f ar
tifi
cial
in
tert
idal
hab
itat
![Page 14: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/14.jpg)
Wan C
hai D
evelo
pm
ent
Ph
ase I
I
EIA
Report
and C
entr
al-W
an C
hai B
ypass
Volu
me 1
9
71
03
_E
IA9
(D
ec0
7)
15-1
4
Maunsell
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
Dis
turb
ance
im
pac
t N
ot
app
lica
ble
N
ot
app
lica
ble
Dis
turb
ance
im
pac
t N
ot
app
lica
ble
N
ot
app
lica
ble
O
per
atio
nal
P
has
e E
colo
gic
al
reso
urc
es i
n t
he
asse
ssm
ent
area
P
ote
nti
al c
hange
in w
ater
qual
ity
in V
icto
ria
Har
bo
ur
duri
ng
op
erat
ion o
f W
DII
and
CW
B
cause
d b
y c
han
ge
in t
idal
flo
w
(See
wat
er q
ual
ity
asse
ssm
ent)
(S
ee w
ater
qual
ity
asse
ssm
ent)
Mit
igat
ion m
easu
res
are
no
t re
quir
ed a
s no
ad
ver
se
imp
act
is p
red
icte
d.
Nil
La
nd
sca
pe
an
d V
isu
al
Imp
act
Co
nst
ruct
ion
Phas
e A
ll L
and
scap
e R
eso
urc
es
/ L
and
scap
e C
har
acte
r A
reas
an
d V
isual
S
ensi
tive
Rec
eiver
s w
ithin
the
stud
y
area
Ap
pro
xim
atel
y 5
71
tre
es w
ill
be
affe
cted
. N
one
of
these
are
L
CS
D C
ham
pio
n T
rees
or
Reg
iste
red
Old
and
Val
uab
le
Tre
es.
Ther
e ar
e no
rar
e sp
ecie
s o
r en
dan
ger
ed s
pec
ie b
ut
com
mo
n s
pec
ies.
1.
ET
WB
TC
W N
o.
29
/20
04
-
Reg
istr
atio
n o
f O
ld a
nd
Val
uab
le
Tre
es,
and
G
uid
elin
es f
or
thei
r P
rese
rvat
ion
2.
ET
WB
TC
W N
o.
3/2
00
6 -
Tre
e P
rese
rvat
ion
No
t ap
pli
cab
le
- E
xis
tin
g t
rees
to
be
reta
ined
on s
ite
sho
uld
be
care
full
y
pro
tect
ed d
uri
ng
const
ructi
on.
- T
rees
unav
oid
ably
af
fect
ed b
y t
he
wo
rks
sho
uld
be
tran
spla
nte
d w
her
e p
ract
ical
.
- C
om
pen
sato
ry t
ree
pla
nti
ng s
ho
uld
be
pro
vid
ed t
o
com
pen
sate
fo
r fe
lled
tr
ees.
La
nd
sca
pe I
mpa
cts
Wit
h m
itig
atio
n m
easu
res,
th
e p
roje
ct w
ill
no
t cr
eate
ad
ver
se i
mp
act
to o
pen
sp
ace
fram
ew
ork
but
have
po
siti
ve
sub
stanti
al
imp
act
to t
he
wat
erfr
ont
fro
m C
entr
al t
o N
ort
h
Po
int.
Ap
pro
xim
atel
y 5
71
tre
es
wil
l b
e af
fect
ed.
Ther
e w
ill
be
mo
der
ate
resi
dual
im
pac
t o
n
Vic
tori
a H
arb
our
and
V
icto
ria
Par
k.
- C
ontr
ol
of
nig
ht-
tim
e li
ghti
ng.
![Page 15: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/15.jpg)
EIA
Report
W
an C
hai D
evelo
pm
ent
Ph
ase I
I
Volu
me 1
and C
entr
al-W
an C
hai B
ypass
97
10
3_
EIA
9 (
De
c0
7)
Maunsell
15-1
5
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
- E
rect
ion o
f d
eco
rati
ve
scre
en
ho
ard
ing c
om
pat
ible
w
ith t
he
surr
ound
ing
sett
ing.
Vis
ua
l Im
pa
cts
Wit
h i
mp
lem
enta
tio
n o
f m
itig
atio
n m
easu
res,
ther
e w
ill
stil
l b
e so
me
mo
der
ate
neg
ativ
e vis
ual
im
pac
t o
n t
he
VS
Rs
in t
he
fro
nt
row
of
hig
h r
ise
buil
din
gs
alo
ng t
he
wat
erfr
ont
fro
m C
entr
al t
o
No
rth P
oin
t.
Res
idual
im
pac
ts V
SR
s fu
rther
aw
ay t
he
Vic
tori
a har
bo
ur
wil
l b
eco
me
slig
ht.
Op
erat
ional
P
has
e A
ll L
and
scap
e R
eso
urc
es
/ L
and
scap
e C
har
acte
r A
reas
an
d V
isual
S
ensi
tive
Rec
eiver
s w
ithin
the
stud
y
area
1
. E
IAO
and
TM
, p
arti
cula
rly
An
nex
es
10
and
1
8
2.
EIA
O G
uid
ance
N
ote
8/2
002
No
t ap
pli
cab
le
- A
est
heti
c d
esig
n o
f b
uil
din
gs
and
ro
ad-
rela
ted
str
uct
ure
s,
incl
ud
ing v
iad
uct
s,
ven
t b
uil
din
gs,
su
bw
ays,
fo
otb
rid
ges
an
d n
ois
e b
arri
ers
and
en
clo
sure
.
La
nd
sca
pe I
mpa
cts
Wit
h i
mp
lem
enta
tio
n o
f m
itig
atio
n m
easu
res,
the
resi
dual
im
pac
ts o
n
Vic
tori
a H
arb
our
are
slig
ht.
![Page 16: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/16.jpg)
Wan C
hai D
evelo
pm
ent
Ph
ase I
I
EIA
Report
and C
entr
al-W
an C
hai B
ypass
Volu
me 1
9
71
03
_E
IA9
(D
ec0
7)
15-1
6
Maunsell
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
Ther
e ar
e sl
ight
neg
ativ
e im
pac
ts o
n V
icto
ria
Har
bo
ur
and
Vic
tori
a P
ark.
The
exis
tin
g
land
scap
e ch
arac
ters
al
ong t
he
wat
erfr
ont
wil
l b
e fu
rther
enhance
d b
y
the
pro
po
sed
op
en s
pac
e.
Sp
ecif
ic t
hem
es f
or
the
op
en s
pac
es w
ill
be
pro
po
sed
to
the
wat
erfr
ont
fro
m C
entr
al t
o N
ort
h
Po
int.
3.
To
wn P
lan
nin
g
Ord
inan
ce (
Cap
1
31
)
4.
ET
WB
TC
W N
o.
2/2
00
4 -
M
ainte
nan
ce o
f V
eget
atio
n a
nd
H
ard
Lan
dsc
ape
Fea
ture
s
5.
ET
WB
TC
W N
o.
29
/20
04
-
Reg
istr
atio
n o
f O
ld a
nd
Val
uab
le
Tre
es,
and
G
uid
elin
es f
or
thei
r P
rese
rvat
ion
6.
ET
WB
TC
W N
o.
3/2
00
6 -
Tre
e P
rese
rvat
ion
- S
hru
b a
nd
Cli
mb
ing
Pla
nts
to
so
ften
pro
po
sed
str
uct
ure
s
- B
uff
er T
ree
and
S
hru
b P
lanti
ng t
o
scre
en p
rop
ose
d
road
s an
d a
sso
ciat
ed
stru
cture
s.
- A
est
heti
c d
esig
n o
f p
ropo
sed
wat
erfr
ont
pro
menad
e.
- A
est
heti
c st
reet
scap
e d
esig
n.
- A
est
heti
c d
esig
n o
f ro
adsi
de
amenit
y
area
s.
Vis
ua
l Im
pa
cts
Ther
e w
ill
be
sub
stan
tial
to
mo
der
ate
po
siti
ve
vis
ual
im
pac
t o
n V
SR
s al
ong t
he
new
wat
erfr
ont
as t
he
land
scap
e an
d
vis
ual
am
enit
y a
re
gen
eral
ly e
nhance
d a
nd
st
ren
gth
en b
y t
he
pro
po
sed
pro
ject
.
![Page 17: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/17.jpg)
EIA
Report
W
an C
hai D
evelo
pm
ent
Ph
ase I
I
Volu
me 1
and C
entr
al-W
an C
hai B
ypass
97
10
3_
EIA
9 (
De
c0
7)
Maunsell
15-1
7
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
Cu
ltu
ral
Her
ita
ge
Imp
act
Co
nst
ruct
ion
Phas
e M
arin
e ar
chae
olo
gic
al
reso
urc
es i
n
Vic
tori
a H
arb
our
Sin
ce t
her
e is
no
arc
hae
olo
gic
al
mat
eria
l p
rese
nt
wit
hin
the
stu
dy
area
, no
ad
ver
se c
ult
ura
l her
itag
e im
pac
t is
exp
ecte
d.
1. A
nti
quit
ies
and
M
onu
ments
O
rdin
ance
(C
ap.5
3)
2. E
nvir
on
menta
l Im
pac
t A
ssess
ment
Ord
inan
ce (
EIA
O)
(Cap
. 4
99
, S
.16
)
No
t ap
pli
cab
le
No
furt
her
arc
hae
olo
gic
al
inves
tigat
ion o
r m
itig
atio
n
mea
sure
s is
req
uir
ed
Nil
3
. Tec
hnic
al
Mem
ora
nd
um
on
the
En
vir
on
menta
l Im
pac
t A
ssess
ment
Pro
cess
(E
IAO
-T
M)
4
. Guid
ance
No
tes
on
Ass
essm
ent
of
Imp
act
on S
ites
of
Cult
ura
l H
erit
age
in E
nvir
on
menta
l Im
pac
t A
ssess
ment
Stu
die
s (G
N-C
H)
5
. Ho
ng K
ong
Pla
nnin
g S
tand
ard
s an
d G
uid
elin
es
(HK
PS
G)
![Page 18: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/18.jpg)
Wan C
hai D
evelo
pm
ent
Ph
ase I
I
EIA
Report
and C
entr
al-W
an C
hai B
ypass
Volu
me 1
9
71
03
_E
IA9
(D
ec0
7)
15-1
8
Maunsell
En
vir
on
men
tal
Issu
e S
ensi
tiv
e R
ecei
ver
s/
Ass
essm
en
t P
oin
ts
Imp
act
Pre
dic
tio
n R
esu
lts
Rel
eva
nt
Sta
nd
ard
s/
Cri
teri
a
Exte
nts
of
Exce
ed
an
ces
Imp
act
Av
oid
an
ce
Mea
sure
s/ M
itig
ati
on
M
easu
res
Res
idu
al
Imp
act
s
6
. Mar
ine
Arc
hae
olo
gic
al
Invest
igat
ion
Guid
elin
es.
![Page 19: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/19.jpg)
EIA Report Wan Chai Development Phase II
Volume 1 and Central-Wan Chai Bypass
97103_EIA9 (Dec07)
Maunsell 15-19
15.2 Environmental Outcomes
15.2.1 A summary of the key environmental outcomes arising from the EIA study and environmental
benefits of the environmental protection measures recommended are presented in Table 15.2
below.
Table 15.2 Summary of Key Environmental Outcomes/ Benefits
Issue Environmental Outcomes/Benefits
The Project Requirements:
• The Project is driven by the need for the implementation of the
Trunk Road, which is defined as the section of road extending from
Rumsey Street Flyover Extension to the IEC, comprising the CWB
and the IECL. The Trunk Road will form an east-west strategic
route through Central and Wan Chai and is an essential element of
Government’s strategic transportation planning for Hong Kong that
is required to provide relief to the existing main east-west corridor
(that is, Connaught Road - Harcourt Road - Gloucester Road).
• The Project can create a coherent pattern of land use and for the
development of an appropriate waterfront ‘edge’ to the existing
urban area. The Project will therefore consider imaginative
measures to develop a high quality waterfront for the enjoyment of
the public and tourists.
Benefits:
• The Project provides essential land for the construction of the Trunk
Road, the NIL, the SCL and other key transport infrastructure so as
to relieve congestion on the strategic east-west routes through
Central, Wan Chai and Causeway Bay and on the public transport
system, and their implementation is a core element of Government's
transport planning strategy.
• The Project provides opportunity to create an attractive waterfront
for the enjoyment of the public. The land formed through this
Project will be used to regenerate the waterfront into an attractive
public resource that could be used for a wide range of recreational
and tourism-related uses and functions, with easy access from the
urban hinterland. In so doing, the waterfront will become, as it
should, an integral element of the public asset currently provided by
the harbour.
Potential consequences without the Project:
(i) Not able to relieve traffic congestion
• Without the Trunk Road, the east-west strategic corridors of the
hinterland such as Gloucester Road, Harcourt Road and Connaught
Road Central will be severely affected. At the eastern end of the
Trunk Road, long queues would be anticipated along the IEC as
Victoria Park Road between Causeway Bay Flyover and Canal
Road, already very congested, will become a bottleneck. At the
western end, Connaught Road Central will be severely congested.
Road connections from the hinterland will also not be able to
operate due to congestion.
![Page 20: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/20.jpg)
Wan Chai Development Phase II EIA Report
and Central-Wan Chai Bypass Volume 1
97103_EIA9 (Dec07)
15-20 Maunsell
Issue Environmental Outcomes/Benefits
• From traffic point of view, given that the existing east-west corridor
along the north shore is already overloaded at present, the future
increase in general traffic growth on the Island due to territory-wide
population and employment growth will exert additional pressure on
the existing road network, thus causing further congestion and likely
‘gridlock’ situations to the north shore of Hong Kong Island, which
may also have far reaching impacts to the harbour crossings.
• A district traffic study has confirmed that a dual 3-lane Trunk Road
(or Central-Wan Chai Bypass), together with intermediate slip
roads, is required to divert traffic away from the existing east-west
corridor and to provide adequate relief to the corridor and the local
road network. The need for the Trunk Road has also been
confirmed by the Expert Panel on Sustainable Transport Planning
and Central-Wan Chai Bypass (‘Expert Panel’), which consists of
independent local and overseas experts in the relevant fields.
(ii) Not able to provide land for NIL and SCL
• Land formed under the Project, in addition to providing for the
construction of the Trunk Road, also provides for the construction
of the NIL and the SCL. Should the Project not proceed,
implementation of these rail routes will be severely constrained.
This will have consequential adverse impacts on the planning and
provision of public transport infrastructure.
(iii) No improvement of the waterfront
• Should the Trunk Road not be implemented the requirement for
land formation is likely to fall away and opportunities to improve
the existing waterfront would be limited.
(iv) Likely environmental conditions
• The existing odour nuisance at the CBTS would persist and no
improvement of the situation would be expected. The Project will
provide opportunities to remove the potential sources of odour
nuisance within the CBTS so as to alleviate this existing
environmental problem as well as to provide an acceptable
environment for the future land uses within the project area.
• In the absence of project, similar air quality conditions along the
northshore areas of Wan Chai, Causeway Bay and North Point as
currently exist would be expected to continue. There would be no
opportunity to improve air quality condition by diverting traffic
underground. With the project, air quality at the east tunnel portal
area of the proposed Trunk Road would be enhanced by the
introduction of an electrostatic precipitator system into the tunnel
ventilation exhaust system and zero portal emission design of the
East Tunnel Portal.
![Page 21: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/21.jpg)
EIA Report Wan Chai Development Phase II
Volume 1 and Central-Wan Chai Bypass
97103_EIA9 (Dec07)
Maunsell 15-21
Issue Environmental Outcomes/Benefits
• In the absence of the project, the noise environment of the project
area would be increased due to the natural growth of traffic. In the
presence of the project, it would help lessen the traffic burden on
Gloucester Road by diverting traffic to the proposed Trunk Road
tunnel. There would be an improvement of the noise environment
alongside Gloucester Road. Besides, the project would provide an
opportunity to alleviate the noise impact at noise sensitive receivers
along IEC at North Point area by installing the proposed landscaped
deck at the east tunnel portal area of the Trunk Road and direct
noise mitigation measures on the reconstructed IEC. In this regard,
it is anticipated that the future noise environment would be
improved in the presence of the project.
• No improvement of the existing landscape and visual conditions of
the waterfront would be expected. With the implementation of the
Project, there will be substantial to moderate positive landscape and
visual impact along the new waterfront as the landscape and visual
amenity are generally enhanced and strengthened.
• Water quality at Victoria Harbour would be similar for both the
situations with and without the Project.
Development Alternatives Factors such as engineering, social, and environmental aspects have
been considered in the light of different alternatives and construction
methods. The following outcomes are found:
• A “foreshore” alignment of Trunk Road is considered the most
reasonable and practical Trunk Road routeing, while “offshore” and
“inland” alignments are found not feasible due to conflict with
existing development and infrastructure.
• Tunnel Option is selected in preference to Flyover Option, as it
would serve better to protect and preserve the Harbour.
• Trunk Road Tunnel Variation 1 scheme is selected as the preferred
scheme in that it provides the necessary functional requirements of
the Trunk Road in meeting the overriding need and results in the
least affected area of the Harbour in conformance with the PHO.
Environmentally Friendly
Designs Recommended
The following environmental-friendly designs have been incorporated
into the current project designs:
� The extent of reclamation under the current scheme has been
minimized. Compared to original scheme in the previous approved
EIA report, the reclamation area is substantially reduced by
approximately 15.8 ha.
� The length of elevated road section from east portal ramp of Trunk
Road to existing IEC is approximately 1.2 km under the original
scheme. In the current scheme, the Trunk Road will run in tunnel
and connect directly to the existing IEC beyond the tunnel section.
Open new road sections are greatly reduced.
� The section of Trunk Road passing across RHKYC will be in the
form of tunnel. Hence, RHKYC will not be affected.
![Page 22: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/22.jpg)
Wan Chai Development Phase II EIA Report
and Central-Wan Chai Bypass Volume 1
97103_EIA9 (Dec07)
15-22 Maunsell
Issue Environmental Outcomes/Benefits
� A landscaped deck has been proposed over the east tunnel portal
area of the Trunk Road. This landscaped deck provides visual and
noise screening effect to the nearby sensitive receivers.
� Smooth curves have been adopted at indented areas rather than
sharp corners along the shoreline. This smoothing of the shoreline
will enhance flows and prevent accumulation of pollutants or
floating refuse.
� The current ventilation system proposed for the Trunk Road
consists of three extraction fans for the East Tunnel Portal. Two
fans will be adequate to extract all polluted air from the upstream
tunnel section of the exit portal. The third fan will be used as
standby in case one fan is under maintenance or out of order.
Airflow direction sensors will be installed at the location of the exit
portal to monitor the airflow direction of the tunnel. This sensor
will be used to control the operation of tunnel portal extraction
system to ensure that the target of “zero portal emission” will be
met.
� The polluted tunnel air extracted from the East Tunnel Portal will
be filtered by electrostatic precipitator installed at the East
Ventilation Building to filter about 80% of the emitted RSP. The
filtered tunnel air will then be conveyed to the exhaust vent shaft
proposed at the East Breakwater of the Causeway Bay Typhoon
Shelter. The proposed ventilation scheme aims at enhancing the air
quality of the tunnel portal areas.
Environmental Problems
Avoided
The environmental problems avoided/minimized due to the current
scheme include:
• As a result of the tunnel design of the Trunk Road, potential vehicle
emissions and road traffic noise impacts from the proposed Trunk
Road on the air and noise sensitive receivers at Wan Chai and
Causeway Bay would be avoided/minimized.
• Noonday Gun at CBTS would not be affected and would be
retained at the same location.
• Kellett Island Archaeological Site at RHKYC would not be
affected.
• Potential environmental impacts including construction dust, water
quality and marine ecology would be reduced compared to the
original scheme in the approved EIA report due to the decrease in
the extent of reclamation.
• As there is no longer any development on reclaimed land formed
with marine sediments in place within CBTS, potential biogas
problem would be avoided in the current scheme.
• Since the section of Trunk Road across RHKYC under the current
scheme is more than 20m below ground level, land contamination
impact associated with the construction of Trunk Road section at
RHKYC would be avoided.
![Page 23: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/23.jpg)
EIA Report Wan Chai Development Phase II
Volume 1 and Central-Wan Chai Bypass
97103_EIA9 (Dec07)
Maunsell 15-23
Issue Environmental Outcomes/Benefits
• With the zero portal emission design of the East Tunnel Portal,
potential air quality impact from the portal emission would be
avoided. In addition, the air quality of the East Tunnel Portal area
would be enhanced by locating the exhaust vent shaft proposed at
the East Breakwater of the CBTS and the electrostatic precipitator
system at the East Ventilation Building.
Population and
Environmentally Sensitive
Areas Protected
The major environmentally sensitive areas within the study area include
residential buildings, commercial buildings, hotels, recreational areas,
and educational institutions at Wan Chai, Causeway Bay and North
Point areas, and WSD flushing water intakes and cooling water intakes
at the waterfront of Victoria Harbour. The population within the study
area is approximately 125,000. With the implementation of the
proposed control and mitigation measures, the air, noise and water
quality sensitive receivers within the study area would be protected
from adverse environmental impacts arising from the Project during
both construction and operational phases. The population and
environmental sensitive receivers protected, compensation areas
included, and the environmental benefits of environmental protection
measures recommended with respect to each environmental issue are
summarized below.
Construction Air Quality
Impact
Environmental benefits of environmental protection measures
recommended:
During construction phase, potential air quality impacts include dust
nuisance and gaseous emissions from the construction plant and
vehicles and dredgers and odour impact from contaminated sediment
during dredging in the vicinity of Police Officers’ Club.
Mitigation measures for dust impact include four times watering a day
on the active work areas and implementation of the Air Pollution
Control (Construction Dust) Regulation and good site practices.
For the dredging activities carried out in the vicinity of Police Officers’
Club, the dredging operation will be restricted to only 1 small close
grab dredger to minimise the odour impact during the dredging activity.
The dredging rate should be reduced as much as practicable for area in
close proximity to the Police Officers’ Club.
With the implementation of the recommended control and mitigation
measures, no adverse air quality impacts are anticipated.
Compensation areas included:
Not required
Population and environmental sensitive receivers protected:
Existing air sensitive receivers within 500m of the project boundary.
![Page 24: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/24.jpg)
Wan Chai Development Phase II EIA Report
and Central-Wan Chai Bypass Volume 1
97103_EIA9 (Dec07)
15-24 Maunsell
Issue Environmental Outcomes/Benefits
Operational Air Quality
Impact
Environmental benefits of environmental protection measures
recommended:
No unacceptable residual traffic emission impacts are anticipated at the
existing and future ASRs.
Air quality inside CWB Tunnel and deckover for planned HKCEC
Atrium Link would comply with standards of EPD Tunnel Air Quality
Guidelines.
Potential odour impacts are identified at the corner of CBTS near the
Police Officers’ Club and the area in the vicinity of Outfall Q. With the
removal of seabed sediments at the corner of CBTS and removal of
slime attached on the CBTS seawall during construction phase, as well
as rectification of expedient connections to CBTS and the
implementation of Enhancement Package for existing identified odour
sources at CBTS, odour impact will be significantly reduced. Although
modelling results indicate that some residual impact is still predicted at
the nearest planned ASRs (open space at CBTS Breakwater and Water
Sports Centre), this impact would occur infrequently and mainly under
a combination of extreme weather and tidal conditions.
Monthly monitoring (from July to September) of odour impacts, for a
period of 5 years, is proposed during the operational phase of the
Project to ascertain the effectiveness of the Enhancement Package over
time, and to monitor any on-going odour impacts at the ASRs.
Air quality monitoring for the operation performance of the East
Ventilation Building and the East Vent Shaft will be conducted.
Compensation areas included:
Not required
Population and environmental sensitive receivers protected:
Existing and planned air sensitive receivers within 500m of the project
boundary.
Construction Noise Impact Environmental benefits of environmental protection measures
recommended:
The predicted mitigated noise levels would range from 44 to 85 dB(A)
at the representative NSRs. With the implementation of quiet PME,
movable barriers, temporary barriers, PME grouping and good site
practices for construction tasks under the Project and implementation of
the noise mitigation measures proposed in the CRIII Reports, the
predicted noise levels at the NSRs selected for construction noise
impact assessment except N11, N17, N18 and N20 would comply with
the construction noise standard.
Compensation areas included:
Not required.
Population and environmental sensitive receivers protected:
Noise sensitive receivers within 300m of the project boundary.
![Page 25: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/25.jpg)
EIA Report Wan Chai Development Phase II
Volume 1 and Central-Wan Chai Bypass
97103_EIA9 (Dec07)
Maunsell 15-25
Issue Environmental Outcomes/Benefits
Road Traffic Noise Impact Environmental benefits of environmental protection measures
recommended:
The following mitigation measures would be recommended:
• about 500m length of noise semi-enclosure with transparent panel
covering the westbound slip road from the IEC;
• about 230m length of noise semi-enclosure with transparent panel
covering the main carriageways (eastbound and westbound) of the
CWB and IEC;
• about 135m length of 5.5m high cantilevered noise barrier with 3m
cantilever inclined at 45° with transparent panel on the eastbound
slip road to the IEC;
• about 95m length of 5.5m high cantilevered noise barrier with 1m
cantilever inclined at 45° with transparent panel on the eastbound
slip road to the IEC;
• about 350m length of 3.5m high vertical noise barrier with
transparent panel on the eastbound slip road to the IEC;
• low noise road surfacing for the trunk road (except tunnel section
and beneath the landscaped deck at the eastern portal area) with
speed limit of 70 km/hour; and
• the openable windows of the re-provisioned Tin Hau Temple, if
any, should be orientated so as to avoid direct line of sight to the
existing Victoria Park Road as far as practicable.
Predicted mitigated noise levels would be in the range of 60 dB(A) to
87 dB(A). Noise exceedances at the representative NSRs are due to the
existing roads. The ‘new’ road noise contributions to the overall noise
levels at all representative NSRs would be less than 1.0 dB(A) and the
‘new’ road noise levels would all be below the relevant noise criteria.
No adverse noise impacts arising from the ‘new’ roads are predicted at
any of the representative NSRs.
In general, the noise environment for the NSRs would be improved by
the Project and the direct noise mitigation measures. As compared with
the prevailing noise environment, the predicted road traffic noise levels
at the existing NSRs in year 2031 would be reduced by:
• 1-10 dB(A) at N2 to N5 (Wan Chai area)
• 1-3 dB(A) at N6 to N8 (Causeway Bay area)
• 1-27 dB(A) at N12 to N17 (Tin Hau area)
• 1-27 dB(A) at N18 to N21 (North Point area)
Compensation areas included:
Not required.
Population and environmental sensitive receivers protected:
Existing and planned NSRs within 300m of the project boundary.
Fixed Plant Noise Impact Environmental benefits of environmental protection measures
recommended:
Operation of the proposed permanent helipad, ventilation buildings and
PTI will not impose adverse noise impacts on the existing and planned
NSRs.
![Page 26: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/26.jpg)
Wan Chai Development Phase II EIA Report
and Central-Wan Chai Bypass Volume 1
97103_EIA9 (Dec07)
15-26 Maunsell
Issue Environmental Outcomes/Benefits
Compensation areas included:
Not required.
Population and environmental sensitive receivers protected:
Noise sensitive receivers within 300m of the proposed helipad,
ventilation buildings and PTI.
Water Quality Impact Environmental benefits of environmental protection measures
recommended:
Implementation of the proposed mitigation measures including use of
closed grab dredging, the deployment of silt curtains at appropriate
dredging areas, and installation of silt screens at selected seawater
intakes along the water front of Victoria Harbour would reduce the
predicted water quality impact to an acceptable level.
Compensation areas included:
Not required.
Population and environmental sensitive receivers protected:
Seawater intakes along the waterfront of Victoria Harbour and corals
identified in Junk Bay, Green Island and Cape Collinson.
Waste Management
Implications
Environmental benefits of environmental protection measures
recommended:
With the implementation of the recommended mitigation measures and
practices (refer to Section 6.7 for details), potential air, odour, noise,
water quality for the handling, transportation and disposal of the
identified waste arisings, no adverse environmental impacts are
expected.
Limited amount of refuse and debris may be unintentionally brought
from the site into the harbour during heavy rains or typhoons. Given
that the Project would not worsen the shoreline configuration and the
implementation of appropriate control measures during construction
phase, it is considered that the future quantity of refuse to be found
along the shoreline would be similar if not better than the existing
situation. With the implementation of a refuse collection system within
the project area, no insurmountable environmental impact with regard
to floating refuse would be anticipated during the construction phase, or
after completion of the Project.
Compensation areas included:
Not required.
Population and environmental sensitive receivers protected:
Water quality, air, and noise sensitive receivers at or near the Project
site, the waste transportation routes and the waste disposal site.
![Page 27: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/27.jpg)
EIA Report Wan Chai Development Phase II
Volume 1 and Central-Wan Chai Bypass
97103_EIA9 (Dec07)
Maunsell 15-27
Issue Environmental Outcomes/Benefits
Land Contamination
Impact
Environmental benefits of environmental protection measures
recommended:
Based on the review of the previous WDIICFS EIA Report and
investigation on the historical/current land uses, the proposed re-
development of A King Marine might pose potential land
contamination impacts during the construction phase of the Project. Site
investigation (SI) was carried out in accordance with the endorsed CAP.
Based on the analytical results, exceedances in relevant criteria of
heavy metals and total petroleum hydrocarbons (TPH) were identified
and an estimated 633 m3 of contaminated soil (mainly heavy metals)
were found to require remediation. Landfill disposal and cement
solidification / stabilisation were proposed as the soil remediation
method.
The land contamination impacts associated with A King Marine would
be the handling of contaminated soil by construction works during the
remediation works. If the proposed mitigation measures (refer to
Section 7.10 for details) were properly implemented, adverse land
contamination impacts are not anticipated.
Compensation areas included:
Not required.
Population and environmental sensitive receivers protected:
Construction workers at A King Marine Shipyard.
Marine Ecological Impact Environmental benefits of environmental protection measures
recommended:
The benthic, intertidal and subtidal habitats within the affected area are
of very low ecological value and direct impact on some small and
isolated coral colonies attached to movable boulders at the coastlines
within ex-PCWA Basin and along seawall at North Point would be
avoided by translocation to a nearby suitable habitat such as Junk Bay.
Hence, no adverse direct ecological impact is expected. Water quality
and noise control measures (as described above) would minimise
indirect impact on marine habitats and associated flora and fauna due to
change in water quality and noise environment during the construction
phase.
Compensation areas included:
Construction of about 1 km vertical wave absorbing seawall along the
coastlines of the newly reclamated land would provide large area of
hard substrata for settlement and recruitment of similar intertidal fauna.
Population and environmental sensitive receivers protected:
Ecological resources in the assessment area.
![Page 28: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/28.jpg)
Wan Chai Development Phase II EIA Report
and Central-Wan Chai Bypass Volume 1
97103_EIA9 (Dec07)
15-28 Maunsell
Issue Environmental Outcomes/Benefits
Landscape and Visual
Impact • Environmental benefits of environmental protection measures
recommended:
• Under the proposed development, approximately 13.8 ha of new
waterfront open space and nine new pedestrian links to the new
harbour-front will be provided. This will strengthen the existing
waterfront character from Wan Chai to North Point and enhance the
connectivity between the waterfront and the hinterland. The overall
urban landscape framework will be strengthened and enhanced by
the proposed project.
• Approximately 12.7 ha (1.8% of total 700ha harbour area) of
Victoria Harbour will be permanently lost. Causeway Bay Typhoon
Shelter will be temporarily alienated. A temporary typhoon shelter
of approximately 6ha will be constructed outside existing typhoon
shelter.
• The bowling greens will be temporarily affected by the construction
of Slip Road 8 and will be reprovisioned within the Victoria Park
during the operation phase.
• Under the proposed development, Fenwick Pier Street Public Open
Space will be temporarily affected during the construction stage.
However, this open space will be replaced by the new district open
space at the site of the Hong Kong Academy of Performing Arts
Extension in the future.
• Approximately 571 trees will be affected. None of these are LCSD
Champion Trees, Registered Old and Valuable Trees, rare or
endangered specie, all trees are common species. Approximately
1500 new trees and other proposed planting will be planted in the
new waterfront and along roadside amenity areas after the new open
space is built to compensate the felled trees.
• During construction, substantial negative impacts on the Fenwick
Pier Street Public Open Space landscape character and the CBTS
landscape character, and moderate residual impact on Victoria
Harbour and Victoria Park.
• During operation, slight negative impacts on Victoria Harbour due
to the loss of harbour area. There are slight negative impacts on the
Victoria Park due to the slight reduction in park area.
• There will still be slight residual visual impact due to the provision
of noise barriers/screening/semi-enclosures in North Point.
However, there will be significant area of new waterfront open
space from Tin Hau to Oil Street with at-grade pedestrian to North
Point.
• With implementation of mitigation measures during construction,
there will still be some moderate negative visual impact on the
VSRs in the front row of high rise buildings along the waterfront
from Central to North Point. Residual impacts on VSRs further
away the Victoria Harbour will become slight.
• During operation, there will be substantial to moderate positive
visual impact on VSRs along the new waterfront as the landscape
and visual amenity are generally enhanced and strengthened by the
Project.
![Page 29: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/29.jpg)
EIA Report Wan Chai Development Phase II
Volume 1 and Central-Wan Chai Bypass
97103_EIA9 (Dec07)
Maunsell 15-29
Issue Environmental Outcomes/Benefits
Compensation areas included: Approximately 13.8 ha of new waterfront open space and nine new
pedestrian links to the new harbour-front will be provided
Population and environmental sensitive receivers protected:
Existing and planned Landscape Resources , Landscape Character Area
and VSR at and near the project site.
Cultural Heritage Impact Environmental benefits of environmental protection measures
recommended:
Since there are no marine archaeological resources within the study
area that would be affected by the project, marine archaeological impact
due to the construction activities is not expected. The current project
design would avoid the potential impact on the Kellett Island
Archaeological Site at RHKYC and Noonday Gun at CBTS. No
environmental protection measure is required.
Compensation areas included:
Not required.
Population and environmental sensitive receivers protected:
Potential archaeological resources, and historical buildings and
structures within the project area.
15.3 Air Quality Impact
Construction Phase
15.3.1 During construction, reclamation, filling and surcharging were identified as the major dust
sources. Trunk Road tunnel works would also generate dust. Due to the complex sequencing of
the construction activities, six worst case scenarios of the construction schedules have been
identified and assessed. The findings of the construction phase air quality assessment indicate
that no exceedance of the 1-hour and 24-hour total TSP criteria are predicted at ASRs in the
vicinity of the construction sites. In order to ensure complicance with the TSP criteria at the
ASRs at all times, the dust suppression measures and requirements of the Air Pollution Control
(Construction Dust) Regulation should be adhered to during the construction period. In addition,
a comprehensive dust monitoring and audit programme are recommended to ensure the effective
implementation of dust suppression measures.
![Page 30: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/30.jpg)
Wan Chai Development Phase II EIA Report
and Central-Wan Chai Bypass Volume 1
97103_EIA9 (Dec07)
15-30 Maunsell
Operational Phase
15.3.2 The cumulative effect arising from the background pollutant levels within and adjacent to the
WDII, vehicle emissions from open road networks, tunnel portal and ventilation building
emissions from the Trunk Road, tunnel portal emissions from the CHT and portal emissions from
existing underpasses and planned deckovers have been assessed. Results show that the predicted
air quality at the ASRs would comply with the AQO criteria. No mitigation measures are
required. The air quality inside the tunnel section of Trunk Road and planned deckovers at the
HKCEC Atrium Link, Road P2 and Expo Drive would also comply with EPD in-tunnel air
quality standards.
15.3.3 With the Trunk Road tunnel ventilation system designed for zero portal emission at the eastern
portal, at North Point, potential air quality impacts from the tunnel portal emission would be
avoided. In addition, the air quality at the eastern portal area would be enhanced by locating the
vent shaft at the end of the eastern breakwater of the CBTS and by the introduction of an
electrostatic precipitator system at the East Ventilation Building to screen RSPs from the tunnel
emissions.
15.3.4 During operational phase, this Project will not create any new odour source. However, odour
nuisance associated with the CBTS is an existing environmental problem. In order to improve
the environment, this Project will take the opportunity to mitigate the potential sources of odour
nuisance within the Project area so as to alleviate this existing environmental problem, as well as
to provide an acceptable environment for the future land uses within the project area.
Enhancement measures have been formulated to alleviate this existing odour problem. These
include rectification of expedient connections, regular collection of floating debris, dredging to
remove the polluted and odourous sediments at the corner of CBTS and clean up the slime
attached on CBTS seawall. With the implementation of these enhancement measures, the
predicted odour levels in the vicinity of CBTS would be reduced significantly. In other words,
this Project will alleviate the existing odour problems in the vicinity of CBTS to a large extent by
implementing the proposed enhancement measures. However, some exceedances of the odour
criterion are still predicted at two planned ASRs A100 and A101 under the worst case condition.
Nevertheless, the residual odour impact at these planned ASRs is not persistent, with a time of
exceedance of the odour criterion expected to be less than 0.2% of time in a year. In view of this
infrequent likelihood of occurrence, no unacceptable adverse odour impact would be expected at
the planned ASRs within the study area.
15.3.5 Monthly monitoring (from July to September) of odour impacts, for a period of 5 years, is
proposed during the operational phase of the Project to ascertain the effectiveness of the
Enhancement Package over time, and to monitor any on-going odour impacts at the ASRs. If
residual odour impact is still found at the end of the odour monitoring programme, further
investigation would be carried out to review the odour problem and to identify the parties
responsible for further remedial action.
![Page 31: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/31.jpg)
EIA Report Wan Chai Development Phase II
Volume 1 and Central-Wan Chai Bypass
97103_EIA9 (Dec07)
Maunsell 15-31
15.4 Noise Impact
Construction Phase
15.4.1 This assessment has predicted the construction noise impacts of the Project during normal
daytime working hours, taking into account other concurrent projects including the CRIII and
HKCEC ALE projects. The predicted unmitigated noise levels would range from 57 to 101 dB(A)
at the representative NSRs. With the use of quiet PME, movable barriers, temporary barriers and
PME grouping for construction tasks under the Project and implementation of the noise
mitigation measures proposed in the CRIII Reports, the noise levels at the NSRs selected for
construction noise impact assessment except N11, N17, N18 and N20 would comply with the
construction noise standard.
15.4.2 Having exhausted practicable noise mitigation measures, the predicted noise level at N11 (i.e.
Mayson Garden) would exceed the noise standard of 75 dB(A) for 1 month by 10 dB(A) with
Group 2 PME. For N17 (i.e.Harbour Heights), the predicted noise level would exceed the noise
standard of 75 dB(A) by up to 5 dB(A) with Group 1 or Group 2 PME for a total of 8 weeks. For
N18 (i.e. City Garden), the predicted noise level would exceed the noise standard of 75 dB(A) by
up to 9 dB(A) with Group 1 or Group 2 PME for a total of 16 weeks. For N20 (i.e. Hong Kong
Baptist Church Henrietta Secondary School), the predicted noise level with Group 1 or Group 2
PME would exceed the noise standard of 65 dB(A) by up to 12 dB(A) for Group 1 or Group 2
PME during examination periods for a total of 28 weeks in 2009, 2013 and 2015. For the normal
teaching period, the noise level would exceed the noise standard of 70 dB(A) by 7 dB(A) with
Group 1 or Group 2 PME for 13.5 weeks. However, the school has been noise insulated with air
conditioners and, by keeping the windows closed during construction activities, noise impacts at
the indoor environment can be avoided. Notwithstanding this, it is recommended that the
particularly noisy construction activities be scheduled to avoid examination period as far as
practicable.
15.4.3 Whilst this impact assessment does indicate some noise exceedances for limited periods of time,
even with the consideration of all practicable mitigation measures, during the actual construction
period as much as practically possible will be done to reduce construction noise still further, and
there will be on-going liaison with all concerned parties and site monitoring to deal with and
minimise any exceedances.
15.4.4 The proposed cross harbour water mains will extend from Wan Chai near the HKCEC Extension
to connect to the existing system near the Museum of Arts at the Tsim Sha Tsui promenade.
Insignificant construction noise impacts are expected on the indoor environment of the NSRs
such as the HKCEC Extension, the Hong Kong Space Museum and the Museum of Arts, which
are close to the construction sites at Wan Chai and Tsim Sha Tsui, as they have blank façades /
fixed windows and are provided with central air conditioning, and therefore do not rely on
openable windows for ventilation.
15.4.5 An indicative assessment has been undertaken for possible construction activities during
restricted hours (1900 to 2300) associated with the reclamation works of the Project. With the
adoption of quite PME and movable noise barriers, the predicted noise levels at the NSRs
selected for noise impact assessment except NSR N2 would comply with construction noise
criterion of 65 dB(A). It should be noted that the results of the construction noise impact
assessment for restricted hours (1900 to 2300) are for indicative purposes, the Noise Control
Authority will process any CNP application based on the NCO and the relevant technical
memoranda in addition to considering the contemporary situations / conditions.
15.4.6 A construction noise EM&A programme is recommended to check the compliance of the noise
criteria during normal daytime working hours.
![Page 32: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/32.jpg)
Wan Chai Development Phase II EIA Report
and Central-Wan Chai Bypass Volume 1
97103_EIA9 (Dec07)
15-32 Maunsell
Operational Phase
15.4.7 The potential road traffic noise impacts have been assessed based on the worst case traffic flows
in 2031. The noise levels at most of the NSRs in the areas of Wanchai, Causeway Bay, Tin Hau
and North Point are predicted to exceed the EIAO-TM traffic noise criteria due to the existing
roads. Without the noise mitigation measures in place, the predicted noise levels at the NSRs
would range from 60 to 87 dB(A). As a result, direct mitigation measures have been proposed to
mitigate the noise impacts at NSRs N16, N17, N17-A, N18, N18-A, N18-B, N19, N19-A, N20,
P2 and P3 where ‘New’ road noise levels would exceed the relevant noise criteria and ‘New’
road noise contributions to the overall noise levels would be more than 1.0 dB(A).
15.4.8 With the proposed noise semi-enclosure, cantilevered noise barrier and vertical noise barrier in
place, the predicted overall noise levels at N17, N17-A, N18, N18-A, N18-B, N19, N19-A, P2
and P3 would be in the range of 51 to 66 dB(A) which comply with the noise limit of 70 dB(A).
For all other affected NSRs, the ‘New’ road noise contributions to the overall noise levels would
be less than 1.0 dB(A) and the ‘New’ road noise levels would all be below the relevant noise
criteria, although the overall noise levels would still exceed the relevant noise criteria. However,
it should be noted that such noise exceedances at the representative NSRs are due to the existing
roads. Nevertheless, there will be an overall reduction of noise brought about by the project,
which may be considered an environmental benefit.
15.4.9 A section of the noise semi-enclosure (~265m long) located in between the Electric Centre and
CDA(1) site would only be required to be constructed before the occupation of future/planned
NSRs (i.e. P2 – A land zoned as “CDA(1)” near Oil Street and P3 – A land zoned as CDA near
Oil Street), while the remaining sections of noise semi-enclosure and vertical noise barrier shall
be implemented before commencement of operation of the proposed road project.
15.4.10 For noise mitigation at the proposed site of the reprovisioned floating Tin Hau Temple, at the
south-east corner of the CBTS, a 2.5m high boundary wall along the southern and eastern
boundary of re-provisioned Tin Hau Temple has been examined for its noise reduction
effectiveness. However, in view of the traditional design of a Tin Hau Temple, it would not be
considered desirable to erect a boundary wall along the western boundary of the temple, as this
will block the seaview. With the southern and eastern boundary wall in place but without the
western boundary wall, the predicted noise levels at the temple would still exceed EIAO-TM
noise limit of 65 dB(A) by 4 dB(A) due to the existing roads. Instead of a western boundary wall,
the openable windows of the temple should rather be orientated so as to avoid direct line of sight
to the existing Victoria Park Road as far as practicable. An indicative layout for the temple has
demonstrated that the traffic noise criterion would be met with proper orientation of the sensitive
façade. The project proponent of the temple will need to take into account such environmental
requirements/constraints and review the mitigation measures during the detailed design of the
temple with a view to eliminating the need for the boundary wall.
15.4.11 No adverse impacts in respect of the NCO and the EIAO-TM noise criteria arising from the
operation of the proposed permanent helipad and fixed noise sources including ventilation
buildings and the reprovisioned Wan Chai North PTI are anticipated at existing and planned
NSRs.
15.4.12 Monitoring of road traffic noise is recommended to verify the effectiveness of the mitigation
schemes during the first year after road opening. Besides, as part of the design process,
monitoring of operation noise from proposed EVB during the testing and commissioning stage
would be recommended to verify the maximum sound power levels as assumed in the noise
assessment in this EIA.
![Page 33: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/33.jpg)
EIA Report Wan Chai Development Phase II
Volume 1 and Central-Wan Chai Bypass
97103_EIA9 (Dec07)
Maunsell 15-33
15.5 Water Quality Impacts
Construction Phase
Marine-based Impact
15.5.1 The water quality impacts during the reclamation of WDII and CWB have been quantitatively
assessed by numerical modelling. Suspended sediment is identified as the most significant water
quality parameter during the reclamation. The worst-case scenarios during reclamation, taking
into account the anticipated reclamation stages and possible overlapping dredging and filling
activities, have been assessed. The assessment also takes into account the cumulative effects that
arise from other concurrent marine works in the Harbour. It is predicted that potential water
quality impacts could occur at seawater intakes along the Central and Wan Chai shorelines and in
the CBTS. However, the water quality impacts at the seawater intakes can be effectively
minimised with the implementation of proposed mitigation measures, which include silt curtains
around the dredging operations, silt screens at the intakes, restricted dredging rates and bulk
filling behind constructed seawalls. With the implementation of these mitigation measures, there
would be no unacceptable residual water quality impacts due to the WDII and CWB reclamation
and due to the cumulative effects from other concurrent reclamation activities. A water quality
monitoring and audit programme will be implemented to ensure the effectiveness of the proposed
water quality mitigation measures.
Land-based Impact
15.5.2 Water quality impacts from land-based construction, including road works, waterfront facilities
and public utilities, are associated with surface runoff and effluent discharge from the site.
Impacts can be controlled to comply with statutory standards by implementing mitigation
measures such as on-site drainage and sediment traps to control run-off. No unacceptable
residual impact on water quality is anticipated.
Operational Phase
15.5.3 An assessment of the hydrodynamic and water quality impacts due to the Project has been carried
out by numerical modelling, taking into consideration all other concurrent developments and
water pollution sources. For both hydrodynamics and water quality, the baseline (without the
WDII and CWB reclamation) and operational phase (with the WDII reclamation) simulations
have been compared. The model results indicate that the WDII and CWB reclamation would
have minimal impact on the hydrodynamic regime of the study area. The model results also
suggest that the levels of pollutants near Wan Chai and the neighbouring areas are similar under
both baseline and operational scenarios. No unacceptable impacts associated with the operation
of the WDII project upon the water quality in Victoria Harbour are therefore anticipated.
15.5.4 The key water quality issue in relation to the operation of the CWB would be the potential oil-
contaminated surface road runoff and tunnel seepage. However, the CWB will be designed with
adequate drainage systems and appropriate oil interceptors, as required, and no adverse water
quality impact is therefore expected.
![Page 34: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/34.jpg)
Wan Chai Development Phase II EIA Report
and Central-Wan Chai Bypass Volume 1
97103_EIA9 (Dec07)
15-34 Maunsell
15.6 Waste Management Implications
15.6.1 A review of the sediment quality data from the marine ground investigation indicated that the
majority of marine sediments to be dredged for the WDII and CWB reclamation were classified
as contaminated. The total dredged volume was estimated as approximately 1.15 Mm3, of which
0.7 Mm3 was classified as contaminated (Category M and H) requiring Type 2 confined marine
disposal, and 0.4 Mm3 was classified as Category L and would be suitable for Type 1 open sea
disposal. With the implementation of the recommended mitigation measures in accordance with
the requirements of ETWB TCW No. 34/2002, no adverse residual impact was predicted. Since
the dredging activities are marine based activities and negligible dust impacts on nearby air
sensitive receivers would be expected. The findings of the noise impact assessment in Section 4
of this report indicated that adverse noise impact would not be expected during the course of the
dredging activities.
15.6.2 Based on the results of the biological screening, approximately 0.05 Mm3 of highly contaminated
sediment from the CBTS would require Type 3 special disposal arrangements. A review of
possible disposal arrangements has recommended the use of a geosynthetic container system
with negligible loss of material to the marine environment during disposal. It is proposed that
the dredged sediments are sealed in geosynthetic containers and, at the disposal site, the
containers would be dropped into the designated contaminated mud pit where they would be
covered by further mud disposal and later by the mud pit capping, thereby meeting the
requirements for fully confined mud disposal. Field trials undertaken during the WDII D&C
consultancy using uncontaminated mud established the optimum handling methodology for the
proposed special disposal method.
15.6.3 Wastes generated by the construction activities will include C&D material (including excavated
material and demolition material), general refuse from the workforce and chemical waste from
the maintenance of construction plant and equipment. The quantity of C&D materials generated
is estimated to be approximately 2.915 Mm3 of which around 1.17 Mm
3 will be reused on-site
and the remaining surplus of around 1.745 Mm3 will be disposed off-site. By reducing the
quantity of C&D material requiring off-site disposal, the potential impacts from the
transportation of material by road will be reduced (such as noise impacts, possible congestion
due to increased traffic flows, and dust and exhaust emissions from the haul vehicles). Provided
that these identified waste arisings are handled, transported and disposed of using approved
methods and that recommended good site practice are strictly followed, adverse environmental
impacts of air and odour emissions, noise, potential hazards, wastewater discharge and transport
would not be expected during the construction phase.
15.6.4 Floating refuse is an existing waste and the Project itself is not designed to generate floating
refuse. Owing to the project area in close proximity to or within Victoria Harbour, limited
amount of refuse and debris may be unintentionally brought from the site into the harbour during
heavy rains or typhoons. Given that the Project would not worsen the shoreline configuration and
the implementation of appropriate control measures during construction phase, it is considered
that the future quantity of refuse to be found along the shoreline would be similar if not better
than the existing situation.
15.6.5 With the implementation of the refuse collection system properly within the project area, no
insurmountable environmental impact with regard to floating refuse would be anticipated during
the construction phase, or after completion of the Project.
![Page 35: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/35.jpg)
EIA Report Wan Chai Development Phase II
Volume 1 and Central-Wan Chai Bypass
97103_EIA9 (Dec07)
Maunsell 15-35
15.7 Land Contamination Impact
15.7.1 The potential environmental issues associated with land contamination for the WDII Project have
been reviewed and any implication for the proposed development has been assessed.
15.7.2 Based on the review of the previous WDIICFS EIA Report and investigation on the
historical/current land uses, the proposed re-development of A King Marine might pose potential
land contamination impacts during the construction phase of the Project. In order to indicate the
nature and extent of soil contamination, a Contamination Assessment Plan (CAP) (attached in
Appendix 7.1) has been prepared under this Study. The CAP discusses the details of the site
investigation requirements to be carried out.
15.7.3 Site investigation (SI) was subsequently carried out in accordance with the endorsed CAP and a
Contamination Assessment Report (CAR), presenting the results and findings of the SI works
had been compiled. Based on the analytical results, exceedances in relevant criteria of heavy
metals and total petroleum hydrocarbons (TPH) were identified and an estimated 633 m3 of
contaminated soil (mainly heavy metals) were required remediation. A Remediation Action Plan
(RAP) was thus drawn up to formulate the necessary remedial measures and landfill disposal and
cement solidification / stabilisation were proposed as the soil remediation method. The
combined CAR / RAP report is attached in Appendix 7.2.
15.7.4 The land contamination impacts associated with A King Marine would be the handling of
contaminated soil by construction works during the remediation works. If the proposed
mitigation measures are properly implemented, no adverse land contamination impacts are
anticipated.
15.7.5 No adverse residual impact in respect of land contamination is expected if the proposed
remediation actions are carried out.
15.8 Marine Ecological Impact
15.8.1 Literature reviews of existing information supplemented with the results of recently undertaken
field surveys on marine ecological resources indicated that identified marine habitats within the
Assessment Area are of low ecological value. There are no ecological sensitive receivers, such
as SSSIs, Marine Parks and / or Reserves and other areas of ecological importance or
conservation interest, in and within the immediate vicinity of the study area.
15.8.2 Direct and indirect ecological impacts arising from the Project during construction phase and
operation phase were identified and evaluated. The Project will result in the permanent loss of
approximately 12.7 hectares of soft bottom benthic and subtidal habitats. Considering that the
benthic, intertidal and subtidal habitats within affected area are of very low ecological value, and
as direct impacts on some small and isolated coral colonies attached to movable boulders would
be avoided by translocation, no adverse direct ecological impact is expected.
15.8.3 Indirect disturbance impact on the associated waterbirds and other avifaunal species of
conservation interest in the CBTS and Victoria Harbour was expected to occur during the
construction and operation phases of the Project. Considering the existing background of intense
human activities in these areas, the affected wildlife are considered already well adapted to
human disturbance and therefore no adverse indirect impact is expected to occur.
15.8.4 Other impacts arsing from the Project would be temporary and minimised with implementation
of proper mitigation measures. Overall, no adverse ecological impacts on marine resources are
anticipated.
![Page 36: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/36.jpg)
Wan Chai Development Phase II EIA Report
and Central-Wan Chai Bypass Volume 1
97103_EIA9 (Dec07)
15-36 Maunsell
15.9 Landscape and Visual Impact
15.9.1 The proposed development and associated works follow in principle the planning intentions from
the Metroplan, Visions and Goals for Victoria Harbour prepared by Town Planning Board and
the views of the public received during the engagement exercises of the HER that was carried out
under the steer of HEC Sub-committee on WDII Review. In respond to the CFA judgment on the
PHO, the extent of reclamation has been reduced to a minimum. With the new waterfront
development proposals together with enhanced connectivity to the waterfront from the hinterland
and east-west linkages along the northshore, the landscape planning framework of the waterfront
from Wan Chai to North Point is strengthened and reinforced by the proposed project.
15.9.2 Approximately 12.7 ha (1.8% of total 700ha harbour area) of Victoria Harbour will be
permanently lost under the proposed reclamation (DP3). Causeway Bay Typhoon Shelter will be
temporarily alienated for the construction of the Trunk Road tunnel. The temporary reclamation
will be removed and sea-bed reinstated after the completion of the tunnel construction. A
temporary typhoon shelter (DP4) with mooring area of approximately 4ha will be constructed in
Victoria Harbour just outside existing typhoon shelter. It is considered that the residual
landscape impacts on Victoria Harbour are moderate during construction phase but slight during
operation phase with implementation of mitigation measures.
15.9.3 Under the proposed development, Fenwick Pier Street Public Open Space will be temporarily
affected during the construction stage. In the longer term, this open space will be permanently
lost for the Hong Kong Academy of Performing Arts Extension. Approximate 0.24ha of Victoria
Park will be permanently lost for the construction of Slip Road 8 of the Trunk Road. Under the
proposed development, approximately 13.8ha of new waterfront open space will be provided to
strengthen the existing landscape framework from Central to North Point. It is considered the
proposed development with mitigation measures will not create adverse impact to open space
framework but have positive substantial impact to the waterfront from Central to North Point.
15.9.4 It is estimated that, approximately 571 trees will be affected by the construction of Road P2, Slip
Road 8, the reprovisioning of the bowling green, the landscape deck connecting Victoria Park to
the Causeway Bay waterfront, the HKAPA Extension, the HK Visual Arts Education Centre and
the helipad. None of these are LCSD Champion Trees or Registered Old and Valuable Trees.
There are no rare species or endangered species, all trees are common species. All the trees with
high amenity value which are unavoidably affected by the works will be transplanted where
possible. Detailed tree preservation, transplanting and felling including compensatory planting
proposals will be submitted to relevant government departments for approval in accordance with
ETWB TCW no. 3/2006. Based on the proposed works, new trees will be planted along roadside
amenity areas and new waterfront to compensate for the loss of existing trees.
15.9.5 The proposed Trunk Road consists primarily of a road tunnel, administration building, Central
Ventilation Building, eastern tunnel portal, East Ventilation Building and an associated exhaust
vent shaft at the eastern breakwater of CBTS. At the eastern end, the Trunk Road rises on
flyover structure to connect with the existing IEC. Most of the Trunk Road is underground or
underneath the CBTS and there will not be significant visual or landscape impacts. The eastern
tunnel portal will be covered by a landscaped deck with lush planting. The noise barriers/semi-
enclosures on the IEC will mainly compose of transparent noise barrier panels above and green
panels below. Amenity planting will provided along the eastbound and westbound of IEC with
vertical greening of noise barriers/semi-enclosures for around 3m above the planter to soften the
structures. The location of the administration building is selected at the least prominent location
along the available waterfront area; it is proposed at a location underneath the elevated IEC and
climbers will be planted on the building façade to soften the structure.
![Page 37: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/37.jpg)
EIA Report Wan Chai Development Phase II
Volume 1 and Central-Wan Chai Bypass
97103_EIA9 (Dec07)
Maunsell 15-37
15.9.6 The Central Ventilation Building, East Ventilation Building and its associated exhaust vent shaft
will be the main source of impact. These buildings will be structures with compatible disposition,
form and finishing which match with the future harbour environment to achieve visual
conformity. Tree and shrub planting is proposed to soften the Central Ventilation Building and
East Ventilation Building. The location of the East Ventilation Building at the north of the
FEHD Whitfield Depot and at the west end of the North Point reclamation area has been selected
in order to increase the distance to the nearby residents as far as practicable. The building height
has been minimised by placing some E&M equipment in a basement. The overall height of the
building will be lower than the adjacent existing IEC elevated road. The exhaust of the East
Ventilation Building has been separated from the East Ventilation Building and extended to the
tip of the eastern breakwater of CBTS to further increase the distance to the residents. The vent
shaft will be a structure with compatible disposition, form, colour and finishing to create a
harmonious visual relationship with the Harbour. Finishing materials will be sensitively
designed in form, basic color, color/tone variation, micro- and macro-texture, and
reflectivity/light absorbance to avoid glare. The maximum height of the vent shaft will be
restricted to +25mPD.
15.9.7 With implementation of mitigation measures during construction, there will still be some
moderate negative visual impact on the VSRs in the front row of high rise buildings along the
waterfront from Central to North Point. Residual impacts on VSRs further away the Victoria
Harbour and in the hinterland will become slight or insubstantial. During operation, there will be
substantial to moderate positive visual impact on VSRs along the new waterfront as the landscape
and visual amenity are generally enhanced and strengthen by the proposed project. The visual
impacts from the hinterland and the harbour will be slight or insubstantial.
15.9.8 Under the proposed scheme, there will be a significant area of new open space (13.8 ha) and a
substantial number of new trees and other proposed planting (approximately 1500 new trees will
be planted in the new waterfront and along roadside amenity areas after the new open space is
built to compensate the felled trees). The existing landscape characters along the waterfront will
be enhanced. There will still be slight residual visual impact due to the provision of noise
barriers/screening/semi-enclosures in North Point. However, there will be significant area of new
waterfront open space from Tin Hau to Oil Street with at-grade pedestrian connection to North
Point. Therefore, overall, it is considered that the residual landscape and visual impacts of the
proposed development and the associated designated projects are considered acceptable with
mitigation measures during construction, acceptable with mitigation measures during
operation up to 10 years and beneficial with mitigation in the long run after 20 to 30 years.
15.10 Cultural Heritage Impact
15.10.1 A Marine Archaeological Investigation has been carried out for the seabed that will be affected
by the reclamation required by the Project. The aim of the investigation was to locate and assess
underwater archaeological resources which may be damaged by the dredging and reclamation. In
accordance with AMO Guidelines, the MAI consisted of a Baseline Review and Geophysical
Survey.
15.10.2 The results of the MAI in 2001 (Report No. SDA8827) are applicable to the current study since
they cover the same seabed area, with the exception of North Point. There have not been any
significant changes to the seabed since 2001 which would have affected its archaeological
potential. According to the MAI in 2001, it was concluded there were no archaeological
resources within the study area of Wan Chai.
15.10.3 The baseline review indicates high archaeological potential for the North Point study area. To
ensure compliance with AMO Guidelines for MAI, it is therefore necessary to carry out a
geophysical survey for this area.
![Page 38: 15 CONCLUSION 15.1 Introduction · Maunsell 15-1 15 CONCLUSION 15.1 Introduction 15.1.1 The Project is a designated project in accordance with Item 1 of Schedule 3 of the EIAO, which](https://reader033.fdocuments.net/reader033/viewer/2022053023/60541ec2de16416bc07ef726/html5/thumbnails/38.jpg)
Wan Chai Development Phase II EIA Report
and Central-Wan Chai Bypass Volume 1
97103_EIA9 (Dec07)
15-38 Maunsell
15.10.4 The geophysical survey provided very detailed information about features on the seabed. Within
the study area, the seabed is characterised by the presence of dumped materials, trawl marks,
scars and other evidence of previous disturbance. The geophysical survey located one significant
sonar contact but its intact linear shape indicated it was a shipwreck of modern origin. There
were no other sonar contacts which merited further investigation.
15.10.5 It is therefore concluded that there are no marine archaeological resources within the study area.
It follows that there are no related constraints on the proposed development. There is no need for
any further archaeological investigation or mitigation measures.
15.11 Environmental Monitoring and Audit
15.11.1 Environmental monitoring and audit (EM&A) are recommended for construction dust monitoring,
construction and operation noise, water quality and marine ecology. Site inspection / audit is
also recommended for waste management during construction and also for implementation of
landscaping measures during operation. Details of the recommended mitigation measures,
monitoring procedures and locations will be presented in a stand-alone EM&A Manual. This
will enable the Contractor to have early warning and provide necessary action to reduce impacts
at specific areas if the assessment criteria are approached. The effectiveness of on-site control
measures could also be evaluated through the monitoring exercise. All the recommended
mitigation measures should be incorporated into the EM&A programme for implementation.
15.12 Overall Conclusion
15.12.1 The EIA has been conducted based on currently available information and has been adequately
addressed the environmental impacts of the Schedule 2 designated projects identified. No
outstanding issues were identified and hence further detailed EIA study was considered not
necessary. The findings of this EIA have provided information on the nature and extent of
environmental impacts arising from the construction and operation of the Project. The EIA has,
where appropriate, identified mitigation measures to ensure compliance with environmental
legislation and standards.
15.12.2 Overall, the EIA Report for the WDII and CWB has predicted that the Project will generally
comply with the environmental standards and legislation after the proposed construction and
operational stage mitigation measures are implemented. This EIA has also demonstrated the
general acceptability of the residual impacts from the Project and the protection of the population
and environmentally sensitive resources. Environmental monitoring and audit mechanisms have
been recommended before and during construction and operation, where necessary, to verify the
accuracy of the EIA predictions and the effectiveness of recommended mitigation measures.