TOUCH UP PROCEDURE FOR BOLTS & NUTS COATING. Process This procedure is to be applied in-site (offshore platform) without opening the corroded stud bolts and nuts due to handling problem during transportation or installation. Wire Brush Degreasing Water Rinsing Drying Paint Grease Wire Brush Remove rust and scale with wire brush and make sure all corroded surface are clean and free from particles. Degreasing (1/2 kg R-Cleaner + 1/2kg Water) Apply degreasing solution with a cloth on the are surface that we have already been clean-up with wire brush, leave it to react of hour Water Rinsing Upon completion of degreasing process rinsing with water thoroughly Drying Use a dry cloth to dry the article, then air blow to ensure no moisture is strap in the thread. Painting ( Xylan 1424 ) Apply a thin layer of top coat (Green or Blue) Xylan with a fine brush . Let it dry for 3 hours in the sun. When the paint is finger touch dry, apply the same manner for second layer of Xylan paint. Paint should be cure after 3 days.
Note: If there is no rust at the Bolts and nuts, you may skip all and proceed to Painting
SBN INDUSTRIES SDN BHD (Company No: 070659-P)
No 6 Jalan Penaga , Kawasan Perindustrian Kota Puteri , 817500 Masai , Johor , West Malaysia .
Tel No. 607 388 2521 Fax No. 607 388 2523 Website: www.sbnbiz.com Email: [email protected]